Analysis and Investigation Results
Analysis and Investigation Results
Structural Investigation of E‐PLDT IDC VITRO BUILDING
Chapter 5: Analysis and Investigation Results
5.1 Overview
This chapter presents the results obtained from the ETABS 3D Model of the modal
analysis, wind analysis, static and dynamic seismic analysis.
The performance of each member and the global building acceptability limits were
checked against the required strength and acceptance criteria as set forth by the current
governing codes of practice.
Minor Direction (Y)
Major Direction (X)
Figure 5‐1: Principal Axes of the building
Table 5‐1: Natural Period in (sec)
Modal Participating Mass Ratios
Mode Natural Period
X (%) Y (%)
1 1.11 59.54 31.00
2 0.93 5.81 50.04
3 0.87 7.64 22.37
4 0.50 3.55 0.10
5 0.43 0.02 6.15
6 0.36 6.11 0.00
It was found that approximately 59.54% of total mass was participating in the first mode
of X‐direction (Mode 1) and 50.04% of total mass was participating in the first mode of Y‐
direction (Mode 2). From the table, it can be seen that the total mass participation
contributed from the first twelve modes were 99.63% and 99.61% in the X and Y
directions, respectively. The natural periods of the fundamental modes are generally
acceptable for this type of building height. The first two modes are translational modes
and the third mode is torsional mode, which is the preferable building response. The
mode shapes are presented in the following table.
Base Shear from the different types of analysis were compared in this section at the
ground level. For wind analysis, the resulting base shear is multiplied by a load factor of
1.6 for comparison.
Table 5‐2: Base Shears
Base Shear at Ground Level
160,000
140,000
120,000
Base Shear (kN)
100,000
Static (Inelastic)
80,000
RS (Elastic)
60,000 RS (Inelastic)
RS (Scaled Inelastic)
40,000
20,000
0
X Y
Direction
Figure 5‐4: Base Shear at Ground Level
Base Shear in terms of Seismic Weight
90%
80%
70%
60%
Base Shear (%)
50% Static (Inelastic)
40% RS (Elastic)
RS (Inelastic)
30%
RS (Scaled Inelastic)
20%
10%
0%
X Y
Direction
Figure 5‐5: Base Shear in Terms of Seismic Weight
The maximum story displacements and story drifts under seismic loadings are plotted in
the following figures (Note: Seismic Loads Govern over Wind Loads).
Table 5‐3: Building Story Height/Elevation
Table 5‐4: Inelastic Displacement at X Direction
Story Point Load UX UY UZ RX RY RZ Resultant Displacement (m)
HELIPAD 31 SPECY 0.1184 0.4143 0.0027 0.0119 0.00383 0.00549 0.3016
WT/TOP
OF ROOF 31 SPECY 0.0933 0.3419 0.0024 0.02009 0.00707 0.00473 0.2481
SLAB
RDECK 31 SPECY 0.0777 0.2951 0.002 0.00925 0.00281 0.00425 0.2136
5F 31 SPECY 0.0613 0.2358 0.0014 0.0099 0.00295 0.0034 0.1705
4F 31 SPECY 0.0428 0.1675 0.001 0.01158 0.00335 0.00245 0.1210
3F 31 SPECY 0.0246 0.0993 0.0006 0.01204 0.00331 0.00142 0.0716
2F 31 SPECY 0.0085 0.036 0.0003 0.0097 0.00255 0.00051 0.0259
BASE 31 SPECY 0 0 0 0 0 0 0.0000
Table 5‐5: Inelastic Displacement at Y Direction
Inelastic Displacement (EQ)
35
30
25
Elevation (m)
20
SPECX
15
SPECY
10
0
0.00 0.10 0.20 0.30 0.40 0.50
Displacement (m)
Figure 5‐6: Inelastic Displacement
Table 5‐6: Inelastic Story Drift at X Direction
Story Load Point X Y Z DriftX DriftY Resultant Drift
HELIPAD SPECY 33 24.45 24.45 29.8 0.006262 0.022136 0.01610
WT/TOP OF
ROOF SLAB SPECY 33 24.45 24.45 25.5 0.006285 0.019514 0.01435
RDECK SPECY 2350 36.45 47.625 22.3 0.007712 0.014131 0.01127
5F SPECY 61 48.9 77.9 17.6 0.008732 0.017161 0.01348
4F SPECY 54 36.45 77.9 12.9 0.00988 0.016642 0.01355
3F SPECY 228 0 79 8.6 0.00865 0.015942 0.01270
2F SPECY 11 0 61.35 4.3 0.004421 0.008797 0.00689
BASE SPECY 0 0 0 0 0 0 0.00000
Table 5‐7: Inelastic Story Drift at Y Direction
Inelastic Story Drift
35
DriftX
30
Drift X
25 Limit
Elevation (m)
20
15
10
0
0.000 0.005 0.010 0.015 0.020 0.025
Story Drift
Figure 5‐7: Inelastic Story Drift
Each of the existing suspended slab panels were designed as reinforced concrete
structural member on metal deck. Reinforcements were verified and checked
based on the furnished as built drawings and such reinforcements were
properly placed and provided at the critical locations of the slab.
Flexural capacity, one way and punching shear capacity as well as the
deflection of slab were checked against the demand of serviceability and design
level basis. Also, diaphragm forces were checked to ensure the force
transfer mechanism through the diaphragm. Shear reinforcements were also
checked if needed at locations with high shear demand. Refer to
tabulated summary of member stress for each individual slab for reference.
From the slab summary, majority of the slab panels have passed the allowable
capacity ratio of 1.0 except on the some slab panels 3S‐1 at third floor located at
gridlines A‐E/1‐2 and slab panel RS‐1 at roof deck located at gridlines A‐B/1‐2.
Refer to retrofitting key plans in the appendix for reference.
Each of the columns has been checked and evaluated for each individual capacity
Axial capacity check of the concrete columns was performed against the
average axial force demand (both compression and tension) at serviceability and
design level basis. The results of analysis and design showed that most columns
have passed the required axial‐flexural interaction capacity while some of the
columns did not pass the allowable axial‐flexural capacity check. Longitudinal
reinforcements for the concrete columns were adequate and have also passed
the axial capacity as well as the flexural capacity check.
In shear design check, all columns have passed the demand shear
capacity as the shear capacity of each column is within the limits of serviceability
and can resist the shear demand capacity as set forth by design level basis.
Ductility check on each of the columns was also performed and it is complying to
code requirements in all aspect especially with regards to girder to column joint
requirement. Refer to COLUMN SUMMARY for list of columns having registered
demand/capacity ratio greater than 1.0 as per design analysis. Retrofitting key
plan was also provided in the appendix for easy reference.
The foundation system was not included in the investigation due lack of essential
data for checking like the soil investigation report. In the absence of such
important data, we have conducted indeed, thorough inspection at lowest floor
level and nearby area for some signs of possible ground settlement or
deflection or heave, signs of liquefaction or deterioration and other foundation
defects, and we have found no signs of such manifestations.
Furthermore, the building is built with deep foundation using pre stressed piles
as reflected on the as built plans. The quantity of the piles installed cannot be
checked due to absence of pile capacity which normally recommended by the
soils Engineer. Thus, we assumed that the foundation is intact and rests on tuff
formation or hard strata and is likewise adequate to support the building loads.