Additional Requirements For Heavy Wall IP 5-1-2 Pressure Vessels, Thickness Over 2 Inches
Additional Requirements For Heavy Wall IP 5-1-2 Pressure Vessels, Thickness Over 2 Inches
Changes shown by
SCOPE
I 1.1 This practice covers additional requirements governing the design, fabrication, examination, and testing of
unfired pressure vessels having a thickness in excess of 2 in. (50 mm) and up to 6 in. (150 mm).
I 1.2 The examination and testing requirements of IP 5-1-1 are replaced in their entirety by those specified in
this practice. All other requirements are in addition to those in IP 5-1-1.
I 1.3 An asterisk () indicates that a decision by the Purchaser is required, or that additional information is
furnished by the Purchaser.
I 1.4 Additional requirements for pressure vessels having a thickness in excess of 6 in. (150 mm) will be
specified.
TABLE 1
PRACTICE
IP 5-1-1 Pressure Vessels
IP 18-10-1 Additional Requirements for Materials
STANDARDS
ASTM Standards
A 388 Ultrasonic Examination of Heavy Steel Forgings
A 578 / A 578M Straight-Beam Ultrasonic Examination of Plain and Clad Steel Plates for Special
Applications
E 94 Radiographic Testing
DESIGN
ANALYSIS
R 3.1 Thermal Stress. When thermal gradients exceed 150F (80C) in a distance equal to Rt, where R
and t are the mean radius and thickness of the vessel component in question, a thermal stress analysis
shall be performed in accordance with the applicable design code. If the design code used does not
contain procedures for thermal analysis, the procedures of the ASME Code Section VIII, Division 2 may
be used.
R 3.2 The Owner's Engineer shall specify if a fatigue analysis is required. An acceptable method for
determining the need for a fatigue analysis is contained in the ASME Code Section VIII, Division 2, Par.
AD-160. When a fatigue analysis is required, the procedures of the ASME Code Section VIII, Division 2
may be used for the analysis.
Figure Reference From Indicated Division of the ASME Code Section VIII
Nozzle NPS, in. (mm)(1)
Division 1 Division 2
4 (100) Fig. UW 16.1 (a), (b), (c), (d) or (e) (2) Fig. AD 610.1 (a), (b), (c), (d), (e), (e-1) or (f)
> 4 (100) Fig. UW 16.1 (f1), (f2), (f3) or (f4) (3) (4) Fig. AD 613.1 (a), (b), (c), (c-1) or (d) (3) (5)
Notes:
(1) In all cases, nozzle configurations that are acceptable for diameters over NPS 4 (100 mm) may be used for
smaller diameters as well.
(2) Backing strips, if used, shall be removed after welding.
(3) Proposals to use alternative design details, which will permit either 100% radiographic or ultrasonic
examination of the nozzle to shell weld, shall be submitted to the Purchaser for approval by the Owner's
Engineer.
(4) Alternatively Figure UW 16.1 (g) may be used at design temperatures below 850F (450C).
(5) Alternatively Figure AD 610.1 (g) may be used at design temperatures below 850F (450C).
R 3.7 The minimum inside corner radius for all openings shall be the lesser of the following:
a. 1/4 of the thickness of the vessel component penetrated.
b. 1/4 of the finished inside diameter of the opening.
c. 3/4 in. (19 mm).
R 3.8 No exterior radius for attachments shall be less than 1/4 in. (6 mm).
VESSEL SUPPORT
R
3.9 For skirt supported vessels with design temperatures above 500F (260C), excluding internally lined
vessels, the skirt to shell attachment shall be made by means of a forged head ring with stub, as shown
below, or weld build-up on the shell. If the weld build-up method is used, its design details shall be
approved by the Owner's Engineer.
R 3.10 For vessels with design temperatures above 500F (260C), excluding internally lined vessels, a support
skirt “hot box," as shown below, shall be provided at the vessel to skirt junction.
Vessel Shell
Skirt To Shell Attachment
Blend Grind (Weld Build-up Method Shown)
Toe Of Weld
Forged Head Ring Thermal 1 in. (25 mm) Radius
Insulation Minimum, Note (1)
Note:
(1) If approved by the Owner's Engineer, the radius may be reduced based on a detailed stress analysis.
R 3.11 For lug supported vessels with design temperatures above 500F (260C), excluding internally lined
vessels, a thermal stress analysis shall be performed of the lug to vessel attachment.
FABRICATION
WELDING
R 4.1 Attachment welds on the vessel, including those for platform clips, shall be full penetration.
R 4.2 All major load bearing attachments including tray support rings, catalyst bed supports, etc., shall be
welded to the base material of the shell, and have the same nominal chemistry as the base material of the
shell, if the design temperature exceeds 300F (150C).
MATERIALS TESTING
R 5.10 Chemical analysis per the applicable material specification shall be provided for base materials. Weld
metal analysis shall be performed on production test plates.
R 5.11 Tension tests. The number, orientation and location of specimens for both room temperature and hot
tension tests shall be per the applicable material specification, or weld procedure.
R 5.12 Transverse tension tests shall be per the ASME Code Section IX. Specimens from production test
plates need be tested at design temperature only.
R 5.13 Bend tests shall be per the ASME Code Section IX.
Revision Memo
9/68 Original Issue of Basic Practice
1/71 Revision 1
1/73 Revision 2
11/90 Revision 3
12/94 Revision 0 - Original Issue of International Practice
3/98 Revision 1
Complete editorial revision to rationalize this practice with the referenced standards and other IP’s. Significant changes
include: old Par. 1.4 deleted; old Par. 3.1 deleted, covered design to Div. 1 or Div. 2 of ASME Code which is covered
in IP 5-1-1; old Par. 4.1 deleted, require full penetration welding for pressure welds which is covered in IP 5-1-1; old
Par. 5.9 deleted, covered hardness testing per IP 5-1-1, now covered by IP 18-10-1. Table 3 modified hardness
testing and impact testing covered in IP 18-10-1.
TABLE 3
INSPECTION AND TESTING REQUIREMENTS
Tension -
MATERIALS TO Chemical T.S., Y.S., Charpy Bend Transverse Magnetic Liquid Hardness
BE INSPECTED Analysis EL, R.A. (3) Impact Test Tension- Radiography Ultrasonics Particle Penetrant (Brinell)
T.S.
Base Material
1) Plates (2)
5.10 5.11 5.2
2) Forgings
5.10 5.11 (2) 5.3
3) Pipe
5.10 5.11 (2) —
4) Internals
5.10 5.11 —
—
Welding
Qualification
Plates
1) Weld metal 5.10 5.11 (2) — — — — —
2) Weld metal — — (2) 5.13 5.12 5.7 5.8 (4)
and heat
affected
zone
3) Weld (1) — (1) — — — —
overlay, if —
any
Production Test
Plates (per Par.
5.10)
1) Weld metal 5.10 5.11 (2) — — —
2) Weld metal — (2) 5.13 5.12 (4)
and heat
affected
zone
All Pressure
Retaining Welds
1) Edges to be — 5.5 —
welded
2) Before 5.7 — 5.6 —
overlay
3) After — 5.8 — (4)
PWHT(3)
4) After — — 5.6 —
hydrotest
Attachment and
5.6
Temporary
Welds
Weld Overlay
1) Before (1) (1) —
PWHT
2) After PWHT — — (1)
and
hydrotest
Notes:
(1) Inspection requirements shall be per IP 19-2-1.
(2) Impact testing shall be per IP 18-10-1.
(3) Abbreviations used are: T.S. - Tensile Stress; Y.S. - Yield Stress; EL - Elongation; R.A. - Reduction of Area; PWHT -
Postweld Heat Treatment. All other numerals shown in Table 3 refer to corresponding paragraphs within this practice.
(4) Hardness testing shall be per IP 18-10-1.