LT PANEL Testing Procedure

This document outlines the testing procedure for low voltage (LT) panels, including infrared (IR) testing, high voltage testing, and electrical and mechanical testing. It describes the steps to isolate and ground the panels, measure insulation resistance and inject test voltages phase-to-phase and phase-to-ground. It also lists the main resources needed, including equipment, materials and personnel, as well as health, safety and environmental measures to follow during testing. The procedure is to ensure the stability and compliance of the LT panels according to applicable installation standards.

Uploaded by

aslam shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
70% found this document useful (10 votes)
24K views

LT PANEL Testing Procedure

This document outlines the testing procedure for low voltage (LT) panels, including infrared (IR) testing, high voltage testing, and electrical and mechanical testing. It describes the steps to isolate and ground the panels, measure insulation resistance and inject test voltages phase-to-phase and phase-to-ground. It also lists the main resources needed, including equipment, materials and personnel, as well as health, safety and environmental measures to follow during testing. The procedure is to ensure the stability and compliance of the LT panels according to applicable installation standards.

Uploaded by

aslam shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

LT Panel Testing Procedure

Prepared By Reviewed By Reviewed By Approved By


Construction Manager Engineering Manager Safety Manager Project Manager

Introduction
Contents
PREAMBLE : Design Principle
1
 Scope of work.

 Testing Procedure.

 Specification Compliance Statement.

 List of Main Resources.

 Health, Safety and Environment Measures.

 Reference Documents.

 Attachments.

PREAMBLE : Design Principle:


Approach: Provision of proper LT Panels Testing as per standard Installation
guidelines.

1. Scope of Work

1.1 This Statement Covers the LT Panels Testing Procedure and the
details check to be carried out.

1.2 This procedure is to be read in conjunction with relevant ITP


(Inspection and Test Plan) . This also outlines the responsibilities
and quality verification to be done by Blue Star, Samsung and Client
as per relevant ITP.

1.3 This procedure also defines the method of testing to be done to ensure the
stability to an acceptable level as per applicable Installation Standards.

2. LT Panels Testing Procedure


Following Test will be carried Out
1. IR Test.
2. High Voltage Test.
3. Electrical & Mechanical Test.

LT Panel IR Test

1. Switch power supply breaker to "Open" or "Off" position.

2. De-energize load side connections

3. Isolate all loads associated with bus to be tested.

2
4. Disconnect high-voltage sensitive devices and potential transformers from buss to be tested.

5. Record leads lifted and fuses removed on Verification Sheet. Verify that information is correct

6. Megger busswork phase-to-phase then phase-to-ground for one minute, until readings are stable

Phase To Phase R–Y,Y–B,B–R,

Phase To Nutral R–N,Y–N,B–N,

Phase To Earth R – E ,Y – E , B – E ,

Nutral To Earth N –E

7. Ground and discharge each phase tested.

8. Connect high voltage sensitive devices and potential transformers.

High Voltage Test of LT Panels

1. After IR Test Hi Pot Test is carried on panel.

2. De-energize load side connections .

3. Isolate all loads associated with bus to be tested.

4. Disconnect high-voltage sensitive devices and potential transformers from buss to be tested.

5. Record leads lifted and fuses removed on Verification Sheet. Verify that information is correct.

6. Inject 2.5 KV AC voltage to phase-to-phase then phase-to-ground for one minute, until readings are stable

7. Phase To Phase R–Y,Y–B,B–R,

8. Phase To Nutral R–N,Y–N,B–N,

9. Phase To Earth R – E ,Y – E , B – E ,

10. Nutral To Earth N –E

11. Record the leakage current of each test

12. Ground and discharge each phase tested.

13. Connect high voltage sensitive devices and potential transformers.

Electrical & Mechanical Test

1. Equipment Installation Position & Condition.

2. Panel flanges & Chamber Cover.

3. Door Locks & Gasket.

4. Panel coupling and fish-plate.


3
5. Busbar Connection & its supports.

6. Earthing Connection & Continuity.

7. Nuts / bolts / screws / fasteners are Tight.

8. Incoming & Outgoing Cable Connection.

9. Power & Control Wiring Connections.

10. Indication Lamp, Push Button,Selector Switch.

11. Electrical / Mechanical Interlock Check.

12. Meter & CT / PT Connection.

13. Relay / Protective Devices.

14. On/Off Operation of Breaker.

4. List of Main Resources


Materials
Approved Material submittals for LT Panels.

Equipment
The following tools and instruments will be used:
 Megger (1 KV)
 TPN MCB (63 A)- 2 Nos
 Hand Gloves
 Multimeter
 Mini Clamp Meter
 HV Tester (Up to 5KV)

Personnel
 Site Engineer/Site supervisor
 Safety Officer
 QA/QC Engineer
 Electrician
 Helper

4
5. Health, Safety and Environment Measures
Work will commence as per safety regulations laid down in the contract specification
and project safety plan.
Proper safety harness will be used and secured while working at heights, as required.
All personal protective equipment will be used appropriately according to the nature
of the job.

6. Reference Documents
Approved Materials Submittals (Latest)
Specification Reference No. 262413
Test Report
Approved Method statement for LT Panel Installation