LT PANEL Testing Procedure
LT PANEL Testing Procedure
Introduction
Contents
PREAMBLE : Design Principle
1
Scope of work.
Testing Procedure.
Reference Documents.
Attachments.
1. Scope of Work
1.1 This Statement Covers the LT Panels Testing Procedure and the
details check to be carried out.
1.3 This procedure also defines the method of testing to be done to ensure the
stability to an acceptable level as per applicable Installation Standards.
LT Panel IR Test
2
4. Disconnect high-voltage sensitive devices and potential transformers from buss to be tested.
5. Record leads lifted and fuses removed on Verification Sheet. Verify that information is correct
6. Megger busswork phase-to-phase then phase-to-ground for one minute, until readings are stable
Phase To Earth R – E ,Y – E , B – E ,
Nutral To Earth N –E
4. Disconnect high-voltage sensitive devices and potential transformers from buss to be tested.
5. Record leads lifted and fuses removed on Verification Sheet. Verify that information is correct.
6. Inject 2.5 KV AC voltage to phase-to-phase then phase-to-ground for one minute, until readings are stable
9. Phase To Earth R – E ,Y – E , B – E ,
Equipment
The following tools and instruments will be used:
Megger (1 KV)
TPN MCB (63 A)- 2 Nos
Hand Gloves
Multimeter
Mini Clamp Meter
HV Tester (Up to 5KV)
Personnel
Site Engineer/Site supervisor
Safety Officer
QA/QC Engineer
Electrician
Helper
4
5. Health, Safety and Environment Measures
Work will commence as per safety regulations laid down in the contract specification
and project safety plan.
Proper safety harness will be used and secured while working at heights, as required.
All personal protective equipment will be used appropriately according to the nature
of the job.
6. Reference Documents
Approved Materials Submittals (Latest)
Specification Reference No. 262413
Test Report
Approved Method statement for LT Panel Installation