0% found this document useful (0 votes)
142 views84 pages

Construction Methods (1) 1

The document discusses construction methods and provides an overview of the construction industry. It describes the five main sectors of the industry as residential, commercial, heavy civil, industrial, and environmental construction. It also outlines the design process, factors that influence project cost, ways to increase productivity and minimize costs, how construction projects are divided into activities, and the steps for preparing a work program.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
142 views84 pages

Construction Methods (1) 1

The document discusses construction methods and provides an overview of the construction industry. It describes the five main sectors of the industry as residential, commercial, heavy civil, industrial, and environmental construction. It also outlines the design process, factors that influence project cost, ways to increase productivity and minimize costs, how construction projects are divided into activities, and the steps for preparing a work program.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 84

University of Duhok

College of Engineering
Surveying Engineering Dep.

QS and Construction Methods

Introduction to Construction Methods

Yousif Y. Zaia
(MSc Quantity Surveying)
The Construction Industry The University of
Duhok
Surveying Engineering
The construction industry is essentially a service industry whose responsibility is to
convert plans and specifications into a finished product. It is exceedingly complex and
highly individual in character.

The construction industry (including design, new and renovation construction, the
manufacture and supply of building materials and equipment) is one of the largest
industries. While construction has traditionally been a very conservative industry, the
increasing rate of technological development and growing international competition in
the industry are serving to accelerate the development of new construction methods,
equipment, materials and management techniques.

2
The University of

Construction industry divisions: Duhok

Surveying Engineering

Constructing any project includes many steps and relations among owners, engineers,
contractors, companies, factories, materials and equipment providers, workers and
others.

Engineer should be aware of various methods of construction and its cost to be able to
perform the work with least cost.
Engineer should take into consideration the different methods that the project can be
done and the equipment which are going to be used.

3
The University of
Duhok
Industry Sectors:
Surveying Engineering
There are five basic sectors of the industry:
1- Residential building
2- Commercial building
3- Heavy civil construction
4- Industrial construction
5- Environmental construction
-

4
The University of

1- Residential Building Duhok


Surveying Engineering
Residential construction addresses the housing needs of a society. Housing
construction takes many forms: individual homes, apartments (flats), townhouses and
prefabricated units such as modular and manufactured homes.

2- Commercial Building
This sector of the industry primarily addresses the needs of commerce, trade and
government. This is the category that includes banks, schools, office buildings, hotels,
shopping malls, religious facilities, baseball stadiums, theatres, universities,
amusement parks, hospitals, some government buildings, and other facilities where
people gather.

5
The University of

3- Heavy Civil Construction Duhok


Surveying Engineering

This sector of the industry impacts all of society in a very big way. Often
referred to as horizontal construction, the heavy civil sector includes roadways,
bridges, tunnels, dams, airports, and railways. Or, any work that is associated
with infrastructure and transportation.

Equipment operators play a huge role in the work of a heavy civil project.
Heavy civil contractors make huge investments in equipment. Keeping the
earth movers, excavators, scrappers, and trucks rolling is the name of the game
for this sector of the industry.

6
The University of
Duhok
4- Industrial Construction Surveying Engineering

This sector of the industry is highly specialized and requires firms with vast
resources and significant construction and engineering expertise. The number
of contractors qualified to work within the industrial sector is limited.
Manufacturing plants, electrical generating facilities, oil refineries, pipelines,
steel mills, and chemical processing plants are all examples of industrial
construction projects.

7
The University of
Duhok
5- Environmental Construction Surveying Engineering

Generally, this sector of the industry is comprised of projects that improve the
environment, maintain public health, and contribute to a community’s quality
of life. Think clean water, sanitary sewers, and waste management.

The construction manager works with both the architect and the engineer on a
regular basis throughout the construction process.

8
The University of

Design process
Duhok
Surveying Engineering

There are four steps to the design process:


1. Programming and possibility
2. Schematic design
3. Design development
4. Contract documents

These steps are sequential and build on one another. As the designers work
through the process, they move the design from concept to detailed
drawings.

9
The University of

Project Cost Duhok


Surveying Engineering
The cost of any project is a very important factor and can be divided into:
a) Material cost
b) Labour cost
c) Machine and equipment cost
d) Engineering supervision cost
e) profits
The design engineer has a strong influence over the first four points while it is
hard to control the profit.

10
The University of
Duhok
Surveying Engineering
Some ways in which productivity can be increased and costs
minimized during construction include:
1. Good work planning.
2. Carefully selecting and training workers and managers.
3. Efficiently scheduling labour, materials and equipment.
4. Properly organizing work.
5. Using laboursaving techniques such as prefabrication and
preassembly.
6. Minimizing rework through timely quality control.
7. Preventing accidents through good safety procedures.

11
The University of
Duhok
Construction Activities Surveying Engineering

Most construction projects are divided into specific activities of work, each with
a specific objective and length of time to accomplish.
Each activity generally has a specific beginning and ending point and may
require a specific trade classification.

12
Example: The construction of a reinforced concrete retaining wall can be
divided into following activities:
1. Layout (planning) of site.
2. Excavating of earth mechanically.
3. Excavating of earth manually.
4. Building and erecting of forms.
5. Erection of reinforcing steel.
6. Pouring )Casting) of concrete.
7. Curing of the concrete.
8. Removing of forms.
9. Finishing the concrete surface.
10. Clean up of the site.

13
The University of
Duhok
Surveying Engineering

The following steps should be followed before commencing the work


program:
 Preparing a list of the project activities.
 Estimating the time required to complete each activity.
 Specifying the time of performing each activity and the sequence of the
activities.

14
The University of
Duhok
Job Layout Surveying Engineering

One of the first duties of the supervisor engineer is to prepare a job layout for
the project.
On this layout a plan should draw to scale the area available for: Offices,
Warehouses, Storage of materials, Equipment, Construction forms and Work
shops for fabricating reinforcing steel.

15
The University of
Duhok
Steps should be considered when preparing the layout Surveying Engineering

1. Arrange all areas to reduce the time consumed in carrying materials from storage areas to the
project.
2. Materials that are similar in use should be stored close together.
3. The general office should be located near the main entrance in order that persons visiting the
project for business purposes will not have to travel around the construction areas to reach
the office.
4. The general warehouse should be near the entrance in order to facilitate the delivery of
materials to be stored in the warehouse.
5. If a warehouse is needed to store heavy materials, such as machines that will be incorporated
into the project, it may be desirable to consider using additional warehouses, located near the
project.

16
The figure shown below illustrates a job layout for a multistorey reinforced
concrete frame building.

17
18
The University of
Project Control Duhok
Surveying Engineering

Once the process of construction started, controlling the progress of construction


is important.
The project must be monitored from beginning to end to ensure that all of the
following targets are met.
Time

Cost Quality

Project control requires continuous monitoring and evaluation of actual


performance relative to the estimated performance for all aspects of the job that
have an impact on cost, time and quality.

19
The University of
1- Quality Control Duhok
Surveying Engineering
The plans and specifications are the primary tools used to verify project
quality. The best way to track quality performance on a project is to prepare
and implement a complete quality plan.

Quality Control Inspection

• Organization and Staffing Responsibilities


• Inspection Plan and Field Practices
• Documentation
• Material Testing

20
The University of
Duhok
Surveying Engineering
2- Controlling cost:
The original estimate used for bidding purposes is converted to a project
budget and establishes the benchmark from which project costs are
monitored. During this conversion process, which usually takes place right
after the contract award, quoted prices are confirmed with purchase orders
and subcontracts. Sometimes there are minor adjustments made in the
budget because of price fluctuations between the time when the job was bid
and when the work begins, but generally the budget contains the same work
packages developed in the estimate.

21
The University of
Duhok
Surveying Engineering

3- Time Control:
Time controlling is done through scheduling which is a time phased plan.
Schedules are used as guides during the performance of an operation in
order to control the pace of activities and to permit completion of the
operation at the desired or required time.
There are a number of different forms of schedules that may be used,
including written schedules, bar graph schedules (Gantt charts), network
schedules and others.

22
A simple bar graph The University of
Duhok
Surveying Engineering

23
The University of
Duhok
Surveying Engineering

24
The University of
Duhok
Surveying Engineering
The University of
Duhok
Surveying Engineering

26
The University of
Duhok
Surveying Engineering

Soil Compaction and Stabilization

27
The University of

Soil compaction and stabilization Duhok


Surveying Engineering

Compaction is the process of increasing the density of a soil by mechanically


forcing the soil particles closer together, thereby expelling air from the void
spaces in the soil.

Compaction has been employed for centuries to improve the engineering


properties of soil. Improvements include increased bearing strength, reduced
compressibility, improved volume-change characteristics, and reduced
permeability.

28
The University of
Duhok
Surveying Engineering

Compaction can be done by the following basic


methods:

1- Kneading Action
2- Impact
3- Vibration
4- Static Weight

29
The University of
Duhok
Surveying Engineering
Types of Compacting Equipment:
Equipment manufacturers have developed a variety of compactors that
incorporate at least one of the compaction methods, and in some cases
more than one, into their performance capabilities.

There are many types of compaction equipment such as:

30
The University of
Duhok

1 – Tamping Rollers Surveying Engineering

A- Sheep’s foot rollers


1- These rollers are either self-propelled or towed drums.
2- These rollers have steel wheels equipped with cylindrical pads or feet.
3- It utilizes static weight and kneading to achieve compaction.
4- Suitable for compacting all fined-grained materials, but is generally not
suitable for use on cohesion less granular materials.

31
The University of
Duhok
Surveying Engineering

32
The University of
Duhok
Surveying Engineering
B- Modified Tamping rollers:

1- Self propelled no vibratory rollers

2- The pads are tapered with an oval or rectangular face


3- The pad face is smaller than the base of the pad at the drum
4- Effective on all soils except pure sand.

33
The University of
Duhok
Surveying Engineering

34
The University of

2 – Smooth wheel Rollers:


Duhok
Surveying Engineering
These rollers can be classified according to its type or weight.

a- By type:

• Three wheel & two axle rollers


• Two wheel tandem rollers
• Three wheel tandem rollers.
• The three wheel & two axle rollers are used for granular & granular
plastic material.
• The two & three wheel tandem used for sandy soil granular material
with clay binder.

35
The University of
Duhok
Surveying Engineering

36
The University of
Duhok
b- By weight: Surveying Engineering

For example 10 ton, 20 ton ……etc.

The compacting drums are empty and can be filled with sand or
water. When it says that a smooth wheel roller with (14 – 20) ton,
that means the weight of the smooth wheel roller is 14 tons and can
be increased to 20 tons.

37
The University of
Duhok

3 – Pneumatic-tired rollers : Surveying Engineering

These are rubber tire rollers filled with air.


Types: -
i)- Small types used for sandy silt , sandy clay , gravely sand. Asphalt
(4-9) tires on one axle.
ii) - Large type used for all types of soil & all depths.
With (15-200) ton.

There are other types called


Pneumatic rubber roller with variable air pressing which
enables the operator to change the pressure of the tires without
stopping.

38
The University of
Duhok
Surveying Engineering

39
The University of
Vibrating Compactors Duhok
Surveying Engineering

Vibration creates impact forces, and these forces result in greater compacting
energy than an equivalent static load. This fact is the economics behind a
vibratory compactor.
The impact forces are higher than the static forces because the vibrating drum
converts potential energy into kinetic energy.
Certain types of soils such as sand, gravel, and relatively large shot rock
respond quite well to compaction produced by a combination of pressure and
vibration. When these materials are vibrated, the particles shift their positions
and nestle more closely with adjacent particles to increase the density of the
mass.
40
The University of
Duhok
Surveying Engineering
Types of vibratory compacters

1 – Sheep's foot vibratory compactors


2 – Steel drum vibratory compactors.
3 – Pad type vibratory compactors.
4 – Manually operated vibrating compactors
- Used in confined areas where large compactors
- could not operate
- Can be operated either manually as a walk behind unit or by
remote control.

41
The University of
Duhok
Surveying Engineering

42
The University of
Duhok
Surveying Engineering

43
The University of

Estimating Compactor Production Duhok


Surveying Engineering
The following equation may be used to calculate compactor production based
on compactor speed, lift thickness and effective width of compaction. The
accuracy of the result obtained will depend on the accuracy in estimating
speed and lift thickness.

𝟏𝟔. 𝟑 ∗ 𝑾 ∗ 𝑺 ∗ 𝑳 ∗ 𝑬
𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒗𝒊𝒕𝒚 𝑪𝑪𝒀/𝒉 =
𝑷
𝟏𝟎 ∗ 𝑾 ∗ 𝑺 ∗ 𝑳 ∗ 𝑬
𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒗𝒊𝒕𝒚 𝑪𝑪𝑴/𝒉 =
𝑷
Where P: Number of passes required
W: Width compacted per pass (ft. or m)
S: Compactor speed (mile/h or km/h)
L: Compacted lift thickness (in or cm)
44
E: Job efficiency
The University of
Example : Duhok
Surveying Engineering

45
Soil Stabilization
The University of
Duhok
Surveying Engineering

While soil stabilization technically includes all the techniques described


above, in common construction usage the term soil stabilization refers to
the improvement of the engineering properties of a soil by use of physical
or chemical admixture.

The principle physiochemical admixtures used for soil stabilization


include granular materials, Portland cement, lime and asphalt. Table 5-5
lists these materials along with the applicable soil, typical percentage
employed, and their curing time.
46
The University of
Duhok
Surveying Engineering

47
The University of

The reason of compaction is for improving soil Duhok


Surveying Engineering
properties like:

1 – Reduce or prevent settlement.


2 – Increase strength.
3 – Improve bearing capacity.
4 – Control volume changes.
5 – Lowering permeability.

48
The University of

Example:- Duhok
Surveying Engineering
For the compaction of a road of 8 km length & 10 m width use clay soil with the
thickness of the layer is 0.2m, use a smooth wheel roller.
Determine:
1 – The time required to compacting the road.
2 – Number of trucks for providing the required soil for filling of the roads.
If:
1 – Width of roller = 2.1m.
2 – Number of compactions = 9 times.
3 – Precent of stopping = 20%.
4 – Capacity of trucks = 15m3 (loose material)
5 – Over lap of layers = 10 cm.
6 – Velocity of roller = 4 km/hr.
7 – Hour of working = 50 min.
8 – Day of working = 8 hr.
9 – Density of soil = 1450 kg/m3 (loose material)
Density of soil = 1800 kg/m3 (compacted material

49
The University of

Solution: Duhok
Surveying Engineering
No. of road parts = 10/(2.1- 0.1) = 5 times the roller will move on the road.
Total compacted length (D) = 5 * 8 * 9 = 360 km
Work time (hr) = D/V =360/(4*50/60) = 108 hr. of work.

Work time (day) =108/8 = 13.5 ≈ 14 days

Duration (with stopping) = 14/(1-0.2) ≈17.5= 18 days .


Volume of compacted material (c.m.) = (8*103 )*10*0.2
= 8000*10*0.2 = 16000 m3

Volume of loose material (l.m.) = 16000*1800/1450 = 19862 m3

No. of trucks = 19862/15 = 1325 Trucks

50
The University of
Duhok
Example
Surveying Engineering

It is required to compact a road of 10 km length and 15 m width


clay soil with the thickness of the layer is 0.25m, use a smooth
wheel roller. Determine:
The Velocity of roller (V).
If
• Duration of the compacting road is 30 Days with stoping.
• Width of roller = 2.1m.
• Number of compactions = 11 times.
• Percent of stopping = 20%.
• Over lap of layers = 10 cm.
• Hour of working = 50 min.
• Day of working = 8 hr.

51
The University of
Solution: Duhok
Surveying Engineering

No. of road parts (strips) = 15/(2.1- 0.1) = 8 part or roller will


move eight times on the road.

Speed =) Distance /Time(


Total compacted length (D) = 8*10*11 = 880 km
Duration (without stopping, day) = 30*(1-0.2) ≈ 24 days
Work time (hours ) = 24*8 = 192 hours.

Work time =) D/S.E(

S = (880/(192*50/60) = 5.5 km/hr.

52
The University of
Duhok
Surveying Engineering

Earthwork and Equipment

53
The University of
Duhok

Excavating Equipment Surveying Engineering

The selection of the appropriate type and size of construction


equipment often affects the required time and effort and thus the
job-site productivity of a project. It is therefore important for site
managers and construction planners to be familiar with the
characteristics of the major types of equipment that most
commonly used in the construction.

54
The University of
Duhok

Excavating Equipment Surveying Engineering

An excavator is defined as a power-driven digging machine. The


major types of excavators used in earthmoving operations include
hydraulic excavators and the members of the cable-operated crane-
shovel family (shovels, draglines, hoes and clamshells). Dozers,
loaders and scrapers can also serve as excavators.

55
Hydraulic Excavators The University of
Duhok

Backhoe
Surveying Engineering

A backhoe is an excavator designed primarily for excavation below grade.


It digs by pulling the dipper back toward the machine. This machine is
also called hydraulic hoe or hydraulic excavator-backhoe.

56
The University of
Duhok
Surveying Engineering

57
The University of
Duhok
Production Estimating Surveying Engineering

Production (LCY/H) = C * S * V * B * E
Where ,
C = Cycles/h (Table 3-3)
S = Swing-depth factor (Table 3-4)
V = heaped bucket Volume (LCY or LCM, Loose Cubic Yard or metre)
B = Bucket fill factor (Table 3-2) ,
E = job Efficiency

58
The University of

Example: Duhok
Surveying Engineering
Find the expected production in loose cubic yards per hours of a small hydraulic
excavator. Heaped bucket capacity is 0.75 CY (0.57 CM). The material is sand
and gravel with a bucket fill factor of 0.95. Job efficiency is 50 min/h. Average
depth of cut is 14 ft (4.3 m). Maximum depth of cut is 20 ft (6.1 m) and average
swing angle is 90.

Solution:
Cycle output = 250 cycles/60 min (Table 3-3)
Swing-depth factor = 1.00 (Table 3-4), Bucket Volume= 0.75 LCY
Bucket fill factor = 0.95, Job efficiency= 50/60 = 0.833
Production = 250 * 1.00 * 0.75 * 0.95 * 0.833 = 148 LCY/h
Or = 250 * 1.00 * 0.57 * 0.95 * 0.833 = 113 LCM/h 59
The University of
Duhok
Surveying Engineering

60
The University of
Power shovel Duhok
Surveying Engineering
Power shovel is used to excavate & load the earth into trucks or tractor-pulled
wagons or conveyor belts. Capable of excavating all classes of earth except solid
rock. Can be operated on soft ground.
May be mounted on rubber-
tired wheels. It is useful for
small jobs where considerable
traveling is necessary &
where the road surfaces
and ground are firm.

61
The University of
Duhok
Surveying Engineering

62
The University of
Duhok
Size of a power shovel: Surveying Engineering

Size of power shovel indicated by the size of dipper (bucket) in m3.


Due to the swelling of soil the bank measure volume of a dipper will be less
than the loose volume.

If a dipper of 2 m3 is used for excavating a soil with 25 % swelling, therefore


the bank measure volume is equal 2.0/1.25 = 1.6 m3

Power shovel are commonly available in the following sizes


(0.3-2.0) m3

63
The University of
Output of power shovels Duhok
Surveying Engineering
The out put of power shovel is affected by the following factors
1- Class of material.
2- Depth of cut.
3- Angle of swing
4- Job condition.
5- Management conditions
6- Size of hauling units.
7- Skill of the operators.
8- Physical condition of the shovel.
9- handling of oversize material .
10- cleanup of loading area.
11- hauling -unit exchange
64
The University of
Output of power shovels Duhok
Surveying Engineering

Actual out put = optimum out put * depth-swing factor * job


management factor * time factor

Actual depth of cut


Optimum depth % = * 100
Optimum depth of cut

65
The University of
Duhok
Surveying Engineering

66
The University of
Duhok
Surveying Engineering

67
The University of
Duhok
Surveying Engineering

68
The University of
Example – 1 Duhok
Surveying Engineering
Determine the out put of power shovel if;
Size of shovel (dipper) =1.6m3
Type of soil is good common earth, Depth of cut (actual) = 3.6m
Average angle of swing of 60˚.
Solution:
from Table 8.2
Optimum out put =229
Optimum depth = 3.1
The percent of optimum depth = (3.6/3.1) * 100 = 116%
From table 8.3 the depth swing factor is 1.12 by interpolation
The probable out put = 229 * 1.12 = 257 m3/hr.
69
The University of
Duhok
Example -2: Surveying Engineering

Determine the probable out put in m3 for a power shovel which have the
following properties
Size of the shovel (Dipper)= 0.8 m3, Type of soil is Stiff & hard soil,
Depth of cut (Actual) = 2.25m, Average angle of swing is 75˚
Job condition is fair & Management is good.
Efficiency = 50/60

70
The University of
Duhok
Solution: Surveying Engineering

Optimum out put = 111m3/hr and Optimum depth is = 2.7m


Percent of optimum depth = 2.25/2.7 * 100 = 83.3%
Depth- swing factor = 1.05 (by interpolation)
Job management factor = 0.69
Probable out put = 111*1.05*0.69 = 80.4 m3/hr
If consider the working hours (Efficiency =50/60)
The probable out put = 80.4*(50/60) = 67 m3

71
The University of

Example-3: Duhok
Surveying Engineering
Determine the number of power shovels to excavate 400,000 m3 of
sand & gravel material in 4 months.
If :
Size of power shovel = 1.2 m3
Depth of cut ( actual ) = 3 m
working minutes /hour = 55 min.
Angle of swing = 110˚
working hours /one day = 8hr.
Percent of stopping = 15%
Job conditions is Good.
Management conditions is Fair
72
The University of
Solution Duhok
Time factor = 55/60 = 0.92 Surveying Engineering

Job-management factor = 0.71


Optimum depth factor = 2.1 m and Optimum out put = 206 m3/hr
Optimum depth % = 3/2.1 * 100 = 142.86 %
Depth –swing factor = 0.834
Actual out put = 206*0.92*0.71*0.834= 112.22 m3/hr
= 112.22* 8 = 897.78 m3/day
Actual working day = ( Duration * ( 1-stoping ) )
= (4*30)*(1-0.15 ) = 102 days
Out put /4month = 897.78*102 = 91573.56 m3/4month
No. of power shovel = Quantity of soil/output of shovel
= 400000/91573.56 = 4.4shovels
Use 4 shovels for 102 days & 1 shovel for 41 days (0.4*102 = 41) 73
The University of
DRAGLINES Duhok
Surveying Engineering
The dragline is a versatile machine capable of wide range of operations.
It can handle materials that range from soft to medium hard. The
greatest advantage of a dragline over other machines is its long reach
for digging and dumping.

74
The University of
Duhok
Surveying Engineering

75
The University of
Duhok
Surveying Engineering

76
The University of

Clamshell Duhok
Surveying Engineering

77
Chain Trencher The University of
Duhok
Surveying Engineering

78
Cranes The University of
Duhok
Surveying Engineering

79
Dozers The University of
Duhok
Surveying Engineering

80
The University of
Duhok
Surveying Engineering

Loader

81
The University of

Grader Duhok
Surveying Engineering

82
The University of

Scraper Duhok
Surveying Engineering

83
Trucks
The University of
Duhok
Surveying Engineering

84

You might also like