Brickwork Work Order
Brickwork Work Order
WORK ORDER
To,
ABC
A/P: Pune,
PAN:
Contact No-
Subject: Work Order for Masonry Work on Item Rate Basis at Our Project
Dear Sir,
With reference to the discussions and negotiations with you for Masonry Work on Item
Rate Basis at Our Project We are glad to issue this work order.
Quality and timely completion of work with safety is the essence of this contract. If it is
found at any time, any negligence or violation to quality and time, the work may get
terminated with immediate effect. This site should be totally accident free and safety
precautions must be followed. If any accident or death occurs on site, it will be all your
responsibility and the work may be terminated.
All other terms and conditions are applicable as an annexure.
You are advised to Mobilize Manpower to start the work within 7 days of letter of intent
and follow the schedule.
Thanking you,
Received& Accepted
Total
Sr.No. Particular. QTY Unit Amount
Rate
Providing and constructing at all levels with
specified thickness walls with fly ash bricks of
approved quality and make confirming to IS:12894-
1989 with a crushing strength of not less than 50
Kgs/Sqcms in CM 1:4 with River sand and 100mm
RCC band for and below 150 mm thk wall shall be
provided with reinforced with 2 nos. Tor 8
longitudinal bars and Tor 8 at 200c/c transverse
reinforcement scrap steel anchored in RCC
1 420.40 sqm 1853.08 779033.98
structure using anchoring grout at every 1.5 meter
with M20 concrete mix for the full length of the
wall including all scaffolding, ladders, platforms and
staging, packing the junction of wall with ceiling
with antishrinkage compound and plant required
for the execution of the work. Bearing blocks of
concrete or bricks in mortar courses will have to be
introduced where required.
A) CONTRACTOR’S SCOPE :
Required tools& tackles for masonry work required should be of good quality
and will be arranged by contractor at his own cost.
Day to day cleaning/housekeeping is contractor responsibility.
Any fallen mortar should be collected at the end of the day and reused after
proper screening on next day.
Shifting of material should be as per requirement, if any material in excess
should be shifted to next floor or stock yard after the completion of Work.
Wetting the surface of Masonry work at least 12 hrs before plaster works.
Wastage of material will be debited and recovered from his RA Bills.
Work should be executed in line and level and as per quality checklist at site and should
be verified by the engg. In-charge, without which payment will not be released.
No extra payment will be paid for Re-work due to bad workmanship.
All the company machineries and assets would be handled carefully by the contractor.
If any damage, theft the same would be recovered from the contractors RA bills.
On completion of work, floor should be cleaned with required chipping on floor and
material should be shifted as per instruction of site engg.
The Procedure of works should be understood by the contractor from site engg. Before
starting of work.
All the quantities will be finalized as per actual site measurements. All openings above
10sqft will be deducted.
If contractor wish to terminate the contract or discontinue the work he should inform
the project in charge/manager before hand writing at least 30 working days, stating the
reasons to do so. If the work is stopped without written intimation to project In
charge/manager, dues to contractors shall be withheld and will not be given until
another contractor is not finalized and mobilized.
B) COMPANY’S SCOPE :--
Providing Labor Hutments, with drinking water and sanitation facility at suitable
locations.
Providing arrangement for Water Supply & Electric supply at place of work.
Safety PPE set would be provided by company to contractor on returnable basis.
If not returned, the same would be recovered from RA Bills.
For Night Work, required Metal Halide Lamps/Halogen Lamps along with
cables/wires would be provided.
Company will provide material list, material mixing pan, farma, scaffolding
material.
1) CONTRACTOR’S FUNCTIONS
1.1 The Contractor will mobilize his active manpower within seven days of Letter of
Intent/Labour Work Order and the work shall commence immediately. He shall construct
necessary site office at his own cost.
1.2 All works shall be carried out as per approved drawings and will be paid at unit rate
indicated in the BOQ Rate shall be valid for any variation in quantity. No escalation in the
rates is applicable during the period of the contract.
1.3 The contractor shall give all reasonable facilities of access, use of road, etc. to the other
contractors at site and shall keep the roads; drains and building area clear of heaps. As per
direction of site In charge, material should be stacked properly and shifted wherever
directed. The Labour contractor shall return all empty bags of cement to store keeper before
demanding further cement for any work on that/ next day’s work.
2) SAFETY AT SITE
2.1 The contractor will observe all statutory and legal requirements by Central and state
Government applicable to the work as well as any local regulations applicable to the site
issued by the Owner/ Consultant or other authority, and collaborate with the owner /
Consultant in all matters connected with safety. The Contractor shall in particular observe
and comply with safety procedures, work permit systems and any other such regulation of
the owner, in force from time to time. Contractor shall work safely and provide his
people/staff with all safely appliances at work. Work will be carried out as per best safety
standards and practice. Client will specify the safety standards from time to time.
2.2 Night work will be permitted only with prior approval of Owner/ Consultant. Owner
may also require contractor to operate extra shifts over and above normal day shift to ensure
completion of contract on schedule, if in his opinion such work is required. Permission for
such work can be given only after providing adequate supervision by contractor to Owner/
Consultant’s satisfaction. Also, the Contractor will ensure that no disturbance is caused to
neighboring people.
2.3 The Contactor shall observe and comply with safety procedures, work permit systems
and any other such regulations/ procedures of Owner and also ensure that children of
workers are not allowed within the working area. All necessary personal protection
equipment’s to workers and staffs as per safety rules such as safety belts, helmets, safety
shoes etc. shall be provided during construction. The Contractor will install a safely net all
around the building for the safety of people working on the ground.
2.4 If at any time Contractor’s methods, materials or equipment’s appear to Owner/
Consultant to be unsafe, inefficient or inadequate for securing safety of workmen or the
public, the quality of the work or the rate of progress required, he may order Contractor to
ensure therein safety, and increase their efficiency and adequacy, and Contractor shall
promptly comply with such orders.
SAFETY UNDERTAKING
To,
ABC
A/P: PUNE,
1. SAFETY AT SITE.
1.1 The contractor will observe all statutory and legal requirements by Central and state
Government applicable to the work as well as any local regulations applicable to the site issued by
the Engineer-In-Charge/ Consultant or other authority, and collaborate with the Engineer-In-Charge
/ Consultant in all matters connected with safety.
1.2 Night work will be permitted only with prior approval of Engineer-In-Charge/ Consultant.
Engineer-In-Charge may also require contractor to operate extra shifts over and above normal day
shift to ensure completion of contract on schedule, if in his opinion such work is required.
Permission for such work can be given only after providing adequate supervision by contractor to
Engineer-In-Charge/ Consultant’s satisfaction. Also, the Contractor will ensure that no disturbance
is caused to neighboring people.
1.3 The Contractor shall observe and comply with safety procedures, work permit systems and any
other such regulations/ procedures of Engineer-In-Charge and also ensure that children of workers
are not allowed within the working area. All necessary personal protection equipment’s to workers
and staffs as per safety rules such as safety belts, helmets, safety shoes etc. shall be provided during
construction. The Contractor will install a safely net all around the building for the safety of people
working on the ground.
1.4 If at any time Contractor’s methods, materials or equipment’s appear to Engineer-In-Charge/
Consultant to be unsafe, inefficient or inadequate for securing safety of workmen or the public, the
quality of the work or the rate of progress required, he may order Contractor to ensure therein
safety, and increase their efficiency and adequacy, and Contractor shall promptly comply with such
orders.
1.5 In case of any injury/incident falling of labour from any height without following above safety
norms. Also responsibility of sub ordinate working contractors labours at the time of working on
site at any level & any area of building is Contractors Responsible.
1.6 The Contractor must follow all the Safety norms as per Safety IS Codes.
1.7 As a safety Precaution, the contractor / Contractor’s Employee must not tap or tamper any of
the electrical installation provided in the room and labour camp or from common area. Such type of
mistake is risky & hazardous to life, any Contractor employee found tapping/damaging electrical
installation will be liable for action by the management against the contractor & his employee.
While making of electricity or taping of electrical connection from any common point or room
point any injury/incident happens its total responsibility of contractor.