DrainageDesignGuide PDF
DrainageDesignGuide PDF
TABLE OF CONTENTS
Chapter 1 Introduction
Chapter 2 Hydrology
Chapter 3 Open Channel
Chapter 4 Culvert
Chapter 5 Bridge Hydraulics
Chapter 6 Storm Drains
Chapter 7 Exfiltration Systems
Chapter 8 Optional Pipe Material
Chapter 9 Stormwater Management Facility
Chapter 10 Temporary Drainage Design
APPENDICES
Table of Contents i
January 2019
CHAPTER 1: INTRODUCTION
1. INTRODUCTION
1.1 BACKGROUND
In 1987, Florida Department of Transportation (FDOT) published the Drainage Manual as
a three volume set: Volume 1 - Policy; Volumes 2A and 2B - Procedures; Volume 3 -
Theory.
In October 1992, the FDOT revised Volume 1 - Policy to Volume 1- Standards and
designated Volumes 2A, 2B, and 3 as general reference documents.
In January 1997, the FDOT renamed Volume 1 - Standards to “Drainage Manual”. In the
years that followed, the FDOT developed numerous handbooks to replace Volumes 2A,
2B, and 3 of the original 1987 Drainage Manual. With this, the Drainage Manual was
maintained as a “standards” document while the handbooks provided guidance
addressing drainage design practice, analysis and computational methods, along with
design aids and reference material.
In 2016, the Department consolidated the handbooks into the Drainage Design Guide.
Chapters 2 through 10 of the Drainage Design Guide each represent a handbook in
previous form. The appendices of the handbooks, with a few exceptions, were
incorporated as appendices in the Drainage Design Guide. Whereas, the remaining
handbook appendices were inserted into the appropriate chapter of the Drainage Design
Guide.
1.2 PURPOSE
The Drainage Design Guide is a reference for designers, which provides guidelines for
common drainage and stormwater aspects of FDOT projects. The guidelines do not
replace the need for professional engineering judgment or preclude the use of other
information. These guidelines are suggested or preferred approaches, not requirements.
The Drainage Manual provides minimum standards and governs over the Drainage
Design Guide, when discrepancies are noted between both documents.
The technical information in these guidelines is written by Central Office Drainage and is
then reviewed and commented upon by the district drainage engineers. The district
drainage engineer has the final project specific decisions concerning the application of
these guidelines, especially given the subjective judgment required to do good drainage
design. If you have project specific questions on this material, please collaborate with
your district drainage engineer.
1.3 REVISIONS
Any comments or suggestions concerning this handbook may be made by e-mailing the
State Drainage Engineer. The FDOT will routinely make revisions to keep the Drainage
Design Guide consistent with other FDOT documents and to reflect changes and trends
in drainage design.
Darcy’s Law Darcy’s Law characterizes the flow through porous media,
assuming that the viscosity, temperature, and density of the
fluids are constant. The flow rate is a function of the
proportionality constant (coefficient of permeability), the
hydraulic gradient, and the flow area; Q = k i A.
Degradation The lowering of land or bottom elevation. In stream stability
assessment, the lowering occurs through natural erosion of
sediment without sufficient incoming sediment to replenish.
DEM Digital Elevation Model
Department Florida Department of Transportation
Depth of flow The vertical distance between the lowest point of a channel
section and the free surface.
Detention To temporarily hold back or store stormwater to control the rate
of discharge. Normally, the term “Wet Detention” is associated
with water quality treatment. Sometimes the term is used for
flood control attenuation.
Drainage Manual Refers to the current release of the Florida Department of
Transportation Drainage Manual
Diurnal tide The diurnal tide is represented by one high tide and one low
tide per day.
Diversion structure For stormwater treatment, a diversion structure may be used
to divert the “first flush” of stormwater to a facility for treatment.
Drainage basin A subdivision of a watershed.
Duration The time from beginning to end of a rain storm event used to
perform runoff calculations.
Ebb phase The period when the water level of the tide is falling.
ECB Erosion Control Blanket. A temporary degradable mat
composed of natural or polymer fibers used to reduce erosive
impact in low-velocity ditches during short periods of
construction. (See Ch. 3.)
Environmental Conceptual approval granted via an individual or general
Resource Permit permit for a surface water management system issued
(ERP) pursuant to Part IV, Chapter 373, Florida Statutes.
Froude Number (Fr) The Fr value is the dimensionless ratio of inertial forces to
gravity forces. If Fr values are less than 1, gravity forces
dominate and the open channel is said to be operating in the
sub-critical range of flow. If Fr values are greater than 1, inertial
forces dominate and the open channel is said to be operating
in the super-critical range of flow.
v
Fr = 1
2
(gL)
Full flow friction loss For pipes flowing full, the full flow friction loss is the full flow
friction slope times the pipe length.
Full flow friction The slope obtained from Manning’s Equation using an area
slope equal to the full cross sectional area of the pipe and a flow rate
equal to the design flow rate.
S = [Qn /(1.49AR2/3)] 2
Where:
Q = design flow rate
A & R = based on full cross section area of pipe
Gabions Wire mesh forms filled with stones. These include mattresses
and baskets.
Grout-filled Woven fabric forms that are filled with concrete grout. These
mattresses include Filter Point Linings and Articulating Block Mats.
Gutter drain A pipe, used along steep slopes, to convey stormwater from
shoulder gutter inlets on elevated roadways to drainage
conveyance systems below at a much lower elevation.
HEC Hydraulic Engineering Circular. Produced by the FHWA.
HGL Hydraulic grade line. In open channel flow, it is the water
surface along the channel reach. In pressure flow, it is a
theoretical line connecting hydraulic gradient points (points to
which the water would rise in a tube or inlet connecting the flow
pipe to atmospheric pressure) along the flow path.
HG Hydraulic gradient. The difference in water surface divided by
the flow distance (dimensionless value often expressed in
percent).
MLW Mean Low Water. The average height of the low waters over a
19-year period. For shorter periods of observations,
corrections are applied to eliminate known variations and
reduce the results to the equivalent of a mean 19-year value.
All low water heights are included in the average where the
type of tide is either semi-diurnal or mixed. Only lower low
water heights are included in the average where the type of
tide is diurnal. So determined, mean low water in the latter
case is the same as mean lower low water.
MLLW Mean Lower Low Water. The average of the lower low water
height of each tidal day observed over the National Tidal
Datum Epoch. For stations with shorter series, comparison of
simultaneous observations with a control tide station is made
to derive the equivalent datum of the National Tidal Datum
Epoch. For locations with diurnal tides—one high tide and one
low tide per day—this datum will be unavailable. At most
locations, there are semi-diurnal tides—the tide cycles through
a high and low water level twice each day, with one of the two
high tides being higher than the other and one of the two low
tides being lower than the other.
MSL Mean Sea Level. The arithmetic mean of hourly heights
observed over the National Tidal Datum Epoch. Shorter series
are specified in the name; i.e., monthly mean sea level and
yearly mean sea level.
MTL Mean Tide Level. The arithmetic mean of mean high water and
mean low water.
Minor losses All losses that are not due to friction. Generally, these are
energy losses due to changes or disturbances in the flow path.
Minor losses include entrance, exit, bend, and junction losses.
Neap tide Tide of decreased range occurring semi-monthly as the result
of the moon being in quadrature.
NFIP National Flood Insurance Program. Administered by the
Federal Emergency Management Agency (FEMA) pursuant to
44 Code of Federal Regulations (CFR) parts 59 through 80.
Part 65 pertains to mapping of Special Hazard Areas.
NHW Normal High Water. For bridge hydraulics, the water stage
associated with a flow that has a 43-percent chance of
recurrence (2.33-year frequency) in a given year. In some
cases, stain lines may be used to estimate NHW.
Non-uniform flow A flow condition where the depth of flow changes with respect
to distance along a channel or conduit. Non-uniform flow may
be classified as either rapidly varied or gradually varied.
Rapidly varied flow also is known as a local phenomenon,
examples of which include the hydraulic jump and hydraulic
drop. The primary example of gradually varied flow occurs
when sub-critical flow is restricted by a culvert or storage
reservoir. The water surface profile caused by such a
restriction generally is referred to as a backwater curve.
Normal depth The depth of flow in a channel determined by the channel
properties and physical slope using Manning’s Equation. The
solution is not direct because the channel depth is unknown
and, therefore, requires an iterative process using trial and
error to solve implicitly for depth.
NRCS Natural Resources Conservation Service (formerly Soil
Conservation Service)
NTDE National Tidal Datum Epoch. The specific 19-year period
adopted by the National Ocean Service as the official time
segment over which tide observations are taken and reduced
to obtain mean values (e.g., mean lower low water, etc.) for
tidal datums. It is necessary for standardization because of
periodic and apparent secular trends in sea level. The present
NTDE is 1983 through 2001 and is actively considered for
revision every 20 years to 25 years. Tidal datums in certain
regions with anomalous sea level changes (Alaska, Gulf of
Mexico) are calculated on a Modified 5-Year Epoch.
NWFWMD Northwest Florida Water Management District
Open channel flow Fluid flow in which the liquid surface is subject to atmospheric
pressure (i.e., has an open or free water surface). Open
channel conditions are the basis for most hydraulic
calculations.
Overland flow Water that travels over the ground surface to the stream
channel, usually limited to a maximum length of 100 feet.
Physical velocity The velocity in a pipe that is flowing full, but not under
pressure. This condition is sometimes called gravity full flow
and the velocity is determined from Manning's Equation.
Actual velocity may be greater than or less than physical
velocity depending on actual flow conditions.
Positive outlet As defined by Rule 14-86 F.A.C.: A point of stormwater
discharge into surface waters that, under normal conditions,
would drain by gravity through surface waters ultimately to the
Gulf of Mexico, the Atlantic Ocean, or into sinks or closed lakes
provided the receiving water body has been identified by the
appropriate Water Management District as functioning as if it
recovered from runoff by means other than transpiration,
evaporation, percolation, or infiltration.
Prismatic channel An artificial channel with non-varying cross section and
constant bottom slope.
Recovery time For stormwater facilities; the time it takes to recover the
volume of water stored above the facility control elevation.
Regression equation A statistical method that correlates peak discharge with
physical features such as watershed area and stream slope.
Retention To retain stormwater and prevent any surface water discharge.
The retained stormwater is either infiltrated into the ground or
evaporated.
Riverine flow For bridge hydraulics, those crossings with no tidal influence
during the design storm, such as (a) inland rivers, or (b)
controlled canals with a salinity structure oceanward
intercepting the design hurricane surge.
Runoff Precipitation remaining after appropriate hydrologic
abstractions have been accounted for.
Runoff coefficient Empirical parameter used to calculate rainfall excess as a fixed
percentage of precipitation; it accounts for interception,
surface storage, and infiltration.
Steady flow A flow condition where the discharge or rate of flow at any
location along a channel or conduit remains constant with
respect to time. The maintenance of steady flow in any channel
reach requires that the rates of inflow and outflow be constant
and equal.
Storm surge A long wave generated offshore that may propagate into
coastal bays and estuaries. The five components of storm
surge are: wind setup, atmospheric pressure setup, Coriolis
effect, wave setup, and the rainfall effect.
Stormwater injection Wells used for stormwater runoff disposal into pervious
wells underground soils or the water table.
Swell Wind-generated waves that have traveled out of their
generating area. Swell characteristically exhibits a more
regular and longer period and has flatter crests than waves
within their fetch.
SWFWMD Southwest Florida Water Management District
tc Time of concentration. The time required for runoff to travel
from the hydraulically most distant point of a watershed to the
design point.
Tailwater The water surface elevation at the downstream end of a
hydraulic conveyance.
Thalweg In hydraulics, the line joining the deepest points along a flow
path.
Tidally dominated For bridge hydraulics, crossings where the tidal influences are
flow dominated by the design hurricane surge. Large bays, ocean
inlets, and open sections of the Intracoastal Waterway typically
are tidally dominated so much so that even extreme rainfall
events have little influence on the design flows in these
systems.
Tidally influenced Flows in tidal creeks and rivers opening to tidally dominated
flow waterways are affected by both river flow and tidal fluctuations.
Tidally affected river crossings do not always experience flow
reversal; however, backwater effects from the downstream
tidal fluctuation can induce water surface elevation fluctuations
up through the bridge reach.
Wind set-down The vertical drop below the still water level on the windward
side of a water body due to wind stresses on the surface of the
water.
Wind setup The vertical rise above the still water level on the leeward side
of a water body due to wind stresses on the surface of the
water.
Wind wave Waves being formed and built up by the wind.
WMD Water Management District
CHAPTER 2: HYDROLOGY
2. HYDROLOGY
• Published data on precipitation, soils, land use, topography, streamflow, and flood
history
• Field investigations and surveys to:
o determine drainage areas
o identify pertinent features
o obtain high water information
o survey lateral ditch alignments
o survey bridge and culvert crossings
Information on types of data available and the sources of that data are presented in
Appendix A of this document.
Considering peak runoff rates for design conditions generally is adequate for conveyance
systems such as storm drains or open channels. However, if the design must include
flood routing (e.g., storage basins or complex conveyance networks), you typically must
create a flood hydrograph. Computer programs are available to help develop a runoff
hydrograph.
In general, you can apply procedures using streamflow analysis and unit hydrograph
theory to all watershed categories.
Table 2.2-1 shows guidelines for selecting peak runoff rate and flood hydrograph
procedures.
TABLE 2.2-1
GUIDELINES FOR SELECTING PEAK RUNOFF RATE AND FLOOD HYDROGRAPHS
Stormwater None X X
Management
a
The modified rational method is not recommended for drainage basins with tc greater than 15 minutes.
Depth-frequency data for durations of 1, 2, 4, 7, and 10 days, which depict maps of Florida
with contours of precipitation depth for return period frequencies of 2, 5, 10, 25, 50, and
100 years also are available on the Internet.
1
p= (2.2-1)
T
A 25-year storm has a 0.04 or 4-percent exceedance probability (probability of occurrence
in any given year), a 50-year storm has a 0.02 or 2-percent exceedance probability, etc.
Li
ti = (2.2-2)
60 vi
where:
ti = Travel time for velocity in segment i, in minutes
Li = Length of the flow path for segment i, in feet
vi = Average velocity for segment i, in feet/second
t c = t1 + t 2 + t 3 + ... t i (2.2-3)
where:
tc = Time of concentration, in minutes
t 1, t 2, t 3, t i = Travel time in minutes for segments 1, 2, 3, i, respectively
where:
t1 = Overland flow travel time, in minutes
L= Overland flow length, in feet (maximum 100 feet recommended by
Natural Resources Conservation Service [NRCS])
n= Manning roughness coefficient for overland flow (See Table B-1 in
Appendix B, Hydrology Design Aids)
i= Rainfall intensity, in inches/hour
S= Average slope of overland flow path, in feet/feet
V = kS 0.5 (2.2-5)
where:
V= Velocity (feet per second)
S= Longitudinal slope in feet / feet
k= Constant for different flow types. (Refer to table below Figure B-3 in
Appendix B)
You also can calculate gutter flow velocities using the following equation:
S X 1S X 2
SX = (2.2-7)
SX1 + SX 2
Evaluate average velocities for main channel flow using Manning’s Equation.
where:
V= Velocity in feet per second
n= Manning’s n value from Table B-3 (Appendix B)
R= Hydraulic Radius (A/P)
S= Longitudinal Slope in feet/feet
L0.77
t c = 0.0078 Fs (2.2-9)
S 0.385
where:
tc = Time of concentration, in minutes
L= Length of travel, in feet
S= Slope, in feet/feet
Fs = 1.0 for natural basins with well-defined channels, overland flow on bare
earth, and mowed grass roadside channels
= 2.0 for overland flow on grassed surfaces
= 0.4 for overland flow on concrete or asphaltic surfaces
= 0.2 for concrete channels
Separate the flow path into different reaches if there are breaks in the slope and changes
in the topography. Add together the times of travel in each reach to obtain the time of
concentration (see Equation 2.2-3).
where:
Q= Peak flow rate (cubic feet per second)
C= Runoff coefficient
i= Rainfall intensity (inches per hour)
A= Area (acres)
Σ C i Ai
Weighted C = (2.2-11)
ATotal
A flooding problem exists along a farm road near Zolfo Springs in Hardee County (sandy
soil, zone 8). A low water crossing is to be replaced by a culvert to improve the road safety
during rainstorms. The drainage area is shown above and has an area of 108.1 acres.
Determine the maximum flow the culvert must pass for a 25-year storm.
1. Determine the weighted "C," assuming sandy soil. From the sketch and Tables B-
4 and B-5 in Appendix B, develop a summary of "C" values, adjusted for design
storm frequency.
Σ C i Ai 37.60
Weighted C = = = 0.35
A 108.1
2. Determine intensity. To determine the intensity, the time of concentration (tc) must
first be determined.
d. Intensity is obtained from the Department’s IDF curves using a duration equal
to the time of concentration (tc). IDF curves are available on the Department’s
Internet Site.
Q25 = C x i25 x A = 0.35 x 4.8 x 108.1 = 182 cubic feet per second
The USGS equations in “Magnitude and Frequency of Floods for Rural Streams in
Florida, 2006” by Verdi (2006) supersede the information presented by Bridges (1982)
and in the USGS Water Supply Paper (WSP) No. 1674 by Pride (1958). Although not
recommended as a design procedure, you can use the method presented in WSP No.
1674 as an independent check for evaluating natural flow estimates for watershed areas
between 100 and 10,000 square miles.
The Statistical Analysis System (SAS) was used to perform multiple regression analyses
of flood peak data from 275 gagging stations in Florida and 30 in the adjacent states of
Georgia and Alabama. Tables B-10 through B-13 in Appendix B (Hydrology Design Aids)
show the USGS Regression Equations for each designated region in the State of Florida.
The natural flow regression equations for Regions 1 through 4 take the following general
form:
QT = C Aa ( ST + 1.0) b (2.2-12)
where:
QT = Peak runoff rate for return period T, in ft3/sec.
C= Regression constant (See Appendix B, B-10 through B-13)
A= Drainage area in square miles
ST = Basin storage, the percentage of the drainage basin occupied by lakes,
reservoirs, swamps, and wetland. In-channel storage of a temporary nature,
resulting from detention ponds or roadway embankments, is not included in
the computation of ST.
a, b = Regression exponents (See Appendix B, B-10 through B-13).
The standard error of prediction, in percent, is reported for each natural flow regression
equation for each of the Regions 1 through 4, Tables B-10 through B-13 (Appendix B).
The standard error of prediction is a measure of how well the regression equation
estimates flood flows when applied to ungaged basins.
The square of the multiple regression coefficient (R2), unit less, and the standard error, in
percent, are reported for each regression equation for the urban and Tampa Bay area
and Leon County, Tables B-14 through B-16 (Appendix B). The R2 value provides a
measure of the equation’s ability to account for variation in the dependent variable. The
standard error is the standard deviation of the distribution of residuals about the
regression line.
The standard error of model, in percent, is reported for each West-Central Florida
regression equation, Table B-17 (Appendix B). The standard error of model is a measure
of how well the regression equation model estimates flood flows.
When applying the regression equations, you should consider the following limitations:
1. The relationship of the regression equations for areas with basin characteristics
outside the ranges given above. Do not use the equations for watershed conditions
outside the range of applicability shown in Tables B-10 through B-13 in Appendix
B (Hydrology Design Aids).
2. In areas of karst topography for the Tampa Area and Leon County regression
equations, some basins may contain closed depressions and sinkholes, which do
not contribute to direct runoff. When you determine the drainage area from 7.5-
minute topographic maps, subtract any area containing sinkholes or depressions
(non-contributing areas) from the total drainage area.
3. Regression equations are not applicable where manmade changes have a
significant effect on the runoff. These changes may include construction of dams,
reservoirs, levees and diversion canals, strip mines, and areas with significant
urban development.
To apply the USGS regression equations, you should take the following steps:
Sauer, et al. (1983), provide two seven-parameter equations and a third set based on
three parameters. The seven-parameter equations based on lake and reservoir
(presented in Appendix B, Table B-14) are recommended. The equations account for
regional runoff variations through the use of the equivalent rural peak runoff rate (RQ).
The equations adjust RQ to an urban condition using the basin development factor (BDF),
the percentage of impervious area (IA), and other variables. These equations have the
following general form:
Basin Development Factor—Determine the BDF from drainage maps and by field
inspection of the watershed. First, divide the basin into three sections so that each sub-
area contains approximately one-third of the drainage area. Mark distances along main
streams and tributaries so that, within each third, the travel distances of two or more
streams are about equal. Generally, you can draw the lines on the drainage map by visual
estimate without the need for measurements. Complex basin shapes and drainage
patterns require more judgment when subdividing.
You will examine four drainage aspects for each subsection, assigning a code of zero or
one to each aspect for each subsection. The BDF, therefore, can range from zero for an
undeveloped watershed to 12 for a completely urbanized watershed. A code of zero does
not mean that the watershed is completely unaffected by urbanization. A basin could have
some impervious area, some improved channels and some curb and gutter streets and
still have a BDF of zero. The four drainage aspects are:
Channel Improvements
Upper third: 460 ft have been straightened and deepened
460/2,500 < 50% Code = 0
Middle third: 2,020 ft have been straightened and deepened
2,020/3,800 > 50% Code = 1
Lower third: 1,720 ft have been straightened and deepened
1,720/3,000 > 50% Code = 1
Channel Linings
Upper third: 0 ft have been lined
0/2,500 < 50% Code = 0
Middle third: 1,770 ft have been lined
1,770/3,800 < 50% Code = 0
Lower third: 1,570 ft have been lined
1,570/3,000 > 50% Code = 1
Storm Drains on Secondary Tributaries
Upper third: 1,345 ft have been converted to storm drains
1,345/5,180 < 50% Code = 0
Middle third: 2,330 ft have been converted to storm drains
2,330/3,940 > 50% Code = 1
Lower third: 1,510 ft have been converted to storm drains
1,510/2,160 > 50% Code = 1
Curb and Gutter Streets
Upper third: 690 ft of curb and gutter street
690/2,850 < 50% Code = 0
Middle third: 3,020 ft of curb and gutter street
3,020/4,700 > 50% Code = 1
Lower third: 3,180 ft of curb and gutter street
3,180/5,610 > 50% Code = 1
Total BDF = 7
You can use regression equations developed as part of a nationwide project by the USGS
(Sauer et al., 1983) to estimate peak runoff for urban watershed conditions. Regionalized
regression equations for urban watersheds in the Tampa Bay area and for Leon County
are presented by Lopez and Woodham (1983), Franklin and Losey (1984), and Hammett
and DelCharco (2001) respectively. Tables B-15, B-16, and B-17 in Appendix B show the
USGS Regionalized Regression Equations for the Tampa Bay area, Leon County, and
West-Central Florida respectively.
For urban drainage areas of less than 10 square miles in the Tampa Bay area, the general
form of the regression equations are:
where:
QT = Peak runoff rate for return period T, in cubic feet per second
C= Regression constant (See Appendix B, Table B-15)
A= Drainage area in square miles
BDF = Basin development factor (dimensionless)
SL = Channel slope (feet/mile) between points 10 percent and 85 percent of the
distance from the design point to the watershed boundary.
DTENA = Surface area of lakes, ponds, and detention and retention basins expressed
as a percent of drainage area.
B1, B2, etc. = Regression exponents (See Appendix B, Table B-15)
The equations are not to be used for watershed conditions outside the range of
applicability shown in Table B-15 (Appendix B). To apply the Tampa Bay regression
equations:
For urban drainage areas of less than 16 square miles in Leon County, Franklin and Losey
(1984) developed regression equations for areas inside and outside the Lake Lafayette
Basin.
where:
QT = Peak runoff rate for return period T, in cubic feet per second
C= Regression constant (See Appendix B, Table B-16)
A= Drainage area in square miles
IA = Impervious area, in percent of drainage area
B1, B2 = Regression exponents (See Appendix B, Table B-16)
These equations must not be used for watershed conditions outside the range of
applicability shown in Table B-16 (Appendix B). The following steps are used to apply
the Leon County regression equations:
For drainage areas in West-Central Florida, Hammett and DelCharco (2001) developed
regression equations for areas inside and outside the Southwest Florida Water
Management District. The general form of the regression equations are:
For Region 1:
QT = C AB1 ( LK + 0.6) B2 (2.2-17)
where:
QT = Peak runoff rate for return period T, in cubic feet per second
C= Regression constant (See Appendix B, Table B-17)
A= Drainage area in square miles
LK = Drainage area covered by lakes, in percent of drainage area
SL = Channel slope (feet/mile) between points 10 percent and 85 percent of the
distance from the design point to the watershed boundary
B1, B2, B3 = Regression exponents (See Appendix B, Table B-17)
These equations must not be used for watershed conditions outside the range of
applicability shown in Table B-18 (Appendix B). The following steps are used to apply the
West-Central Florida regression equations:
Some Water Management Districts (WMDs) in Florida set allowable discharge or removal
rates for specific watershed areas. WMDs also may have computer programs for surface
hydrology calculations available. Consult the appropriate WMD handbook and, if needed,
appropriate WMD or FDOT District drainage personnel for guidance. There are also local
drainage districts that control runoff amounts to particular streams or water bodies.
Example: Using a drainage area of 0.981 acres, tc of 10 minutes, CA of 0.82, and IDF
Zone 5, calculate an inflow hydrograph for the 100-year two-hour rainfall.
From the Zone 5 IDF curves, the two-hour 100-year i = 2.7 inches/hour.
Therefore, Ptotal = 5.4 inches
Three levels of antecedent moisture conditions are considered by the NRCS relationship.
Antecedent Moisture Condition I (AMC-I) is the lower limit of antecedent rainfall or the
upper limit of the maximum soil storage (S). Antecedent Moisture Condition II (AMC-II)
represents average antecedent rainfall conditions, and Antecedent Moisture Condition III
(AMC-III) is the upper limit of antecedent rainfall or the lower limit of S. Only AMC-II
generally is selected for design purposes. The curve number values in the tables in the
Appendix B (Hydrology Design Aids) are based on AMC-II.
Σ CN i Ai
CN C = (2.2-19)
AT
where:
CNC = Composite curve number
CNi = Curve number for sub-area I
Ai = Area for sub-area I
AT = Total area of watershed
The curve number tables developed by the U.S. Department of Agriculture (USDA) are
based on the assumption that all impervious areas have a CN of 98 and are hydraulically
connected. If the rain on the roof of a house runs off onto the lawn, that roof area is not
hydraulically connected. If the roof drains into a gutter, which in turn flows onto the
driveway, then on to the street, that area is hydraulically connected.
If these assumptions don't fit the project area, there is an alternate method of predicting
curve number from Department-sponsored research on estimating coefficients for
hydrologic methods used for the design of hydraulic structures. The results were reported
in "Techniques for Estimating Hydrologic Parameters for Small Basins in Florida," by
Scott Kenner, et al, FDOT Project Number 99700-3542, April 1996.
CN = 58.38 - 8.2716 ln(A) + 0.50274 HCIA + 6.22971 ln(L) + 0.68079 ln( Lc ) - 0.14986 S
(2.2-20)
where:
A= Drainage area (acres)
HCIA = Hydraulically connected impervious area (percent of A)
L= Length of main flow channel (feet)
Lc = Length to centroid (feet)
S= Main channel slope (feet/mile)
1000
S= - 10 (2.2-21)
CN
where:
S= Maximum soil storage, in inches
CN = Watershed curve number, dimensionless
When you know the maximum soil storage, you can calculate the rainfall excess using
the following NRCS relationship:
(P - 0.2S )2
R= (2.2-22)
P + 0.8S
where:
R= Accumulated rainfall excess (or runoff), in inches
P= Accumulated rainfall, in inches
S= Maximum soil storage, in inches
The South Florida Water Management District has a memorandum (dated June 25, 1993)
concerning hydrograph shape (peak rate) factors. For slopes less than 5 feet per mile, a
factor of 100 is recommended, and for slopes in South Florida greater than 5 feet per
mile, a factor of 256 is recommended.
Hal Wilkening of the St. Johns River Water Management District prepared a
memorandum for a "Procedure for Selection of SCS Peak Rate Factors for Use in MSSE
Permit Applications", dated April 25, 1990. The memorandum provides a summary of the
NRCS unit hydrograph methodology and information on research on, as well as
recommendations for the selection of, hydrograph shape (peak rate) factors. His
recommendations are outlined in the following table.
(2.2-23)
where:
A= Drainage area (acres)
HCIA = Hydraulically connected impervious area (percent)
L= Length of main flow channel (feet)
Lc = Length to centroid (feet)
S= Main channel slope (feet/mile)
The designer should consult with district drainage personnel and, if necessary, WMD
personnel before using a shape (peak rate) factor other than the standard factor of 484.
3. OPEN CHANNEL...................................................................................................3-1
3. OPEN CHANNEL
Conservation of mass
Conservation of energy
Conservation of linear momentum
3.1.1.1 Mass
You can mathematically express the conservation of mass for continuous steady flow in
the Continuity Equation as:
Q v A (3.1-1)
where:
Q= Discharge, in cubic feet per second
A= Cross-sectional area, in square feet
v= Average channel velocity, in feet per second
For continuous unsteady flow, the Continuity Equation must include time as a variable.
You can find additional information on unsteady flow from Chow (1959) or Henderson
(1966).
3.1.1.2 Energy
The total energy head at a point in an open channel is the sum of the potential and kinetic
energy of the flowing water. The potential energy is represented by the elevation of the
water surface. The water surface elevation is the depth of flow, d, defined in Section 1.4,
added to the elevation of the channel bottom, z. The water surface elevation is a measure
of the potential work that the flow can do as it transitions to a lower elevation. The kinetic
energy is the energy of motion as measured by the velocity, v.
If you insert a straight tube down into the flow, the water level in the tube will rise to the
water surface elevation in the channel. If you insert a tube with a 90-degree elbow into
the flow with the open end pointing into the flow, then the water level will rise to a level
higher than the water surface elevation in the channel—this distance is a measure of the
ability of the water velocity to do work. Using Newton’s Laws of Motion, this distance is
v2/2g, where g is the acceleration due to gravity. Therefore, the total energy head at a
point in an open channel is: d + z + v2/2g.
As water flows down a channel, the flow loses energy because of friction and turbulence.
You can set the total energy head between two points in a channel reach equal to one
another if the losses between the sections are added to the downstream total energy
head. This equality is commonly known as the Energy Equation, which is expressed as:
2 2
v1 v
d1 z1 d 2 2 z 2 hloss (3.1-2)
2g 2g
where:
d1, d2 = Depth of open channel flow at channel sections 1 and 2, respectively, in
feet
v1, v2 = Average channel velocities at channel sections 1 and 2, respectively, in
feet per second
z1, z2 = Channel elevations above an arbitrary datum at channel sections 1 and 2,
respectively, in feet
hloss = Head or energy loss between channel sections 1 and 2, in feet
g= Acceleration due to gravity, 32.174 ft/sec2
A longitudinal profile of total energy head elevations is called the energy grade line
(gradient). The longitudinal profile of water surface elevations is called the hydraulic grade
line (gradient). The energy and hydraulic grade lines for uniform open channel flow are
illustrated in Figure 3.1-1. For flow to occur in an open channel, the energy grade line
must have a negative slope in the direction of flow. A gradual decrease in the energy
grade line for a given length of channel represents the loss of energy caused by friction.
When considered together, the hydraulic and energy grade lines reflect not only the loss
of energy by friction, but also the conversion between potential and kinetic forms of
energy.
Figure 3.1-2: Definition Sketch for Specific Head and Sub-Critical and Super-
Critical Flow
For uniform flow conditions, the energy grade line is parallel to the hydraulic grade line,
which is parallel to the channel bottom (see Figure 3.1-1). Thus, for uniform flow, the
slope of the channel bottom becomes an adequate basis for the determination of
friction losses. During uniform flow, no conversions occur between kinetic and potential
forms of energy. If the flow is accelerating, the hydraulic grade line would be steeper than
the energy grade line, while decelerating flow would produce an energy grade line steeper
than the hydraulic grade line.
The Energy Equation presented in Equation 3.1-2 ignores the effect of a non-uniform
velocity distribution on the computed velocity head. The actual distribution of velocities
over a channel section are non-uniform (i.e., slow along the bottom and faster in the
middle). The velocity head for actual flow conditions generally is greater than the value
computed using the average channel velocity. Find guidance on kinetic energy
coefficients that account for non-uniform velocity conditions in Chapter 5 (Bridge
Hydraulics).
For typical prismatic channels with a fairly straight alignment, the effect of disregarding
the existence of a non-uniform velocity distribution is negligible, especially when
compared to other uncertainties involved in such calculations. Therefore, Equation 3.1-2
is appropriate for most open channel problems. However, if you know or suspect that
velocity distributions are non-typical, you should obtain additional information related to
velocity coefficients, as presented by Chow (1959) or Henderson (1966).
Equation 3.1-2 also assumes that the hydrostatic law of pressure distribution is
applicable. This law states that the distribution of pressure over the channel cross section
is the same as the distribution of hydrostatic pressure; that is, that the distribution is linear
with depth. The assumption of a hydrostatic pressure distribution for flowing water is valid
only if the flow is not accelerating or decelerating in the plane of the cross section. Thus,
restrict the use of Equation 3.1-2 to conditions of uniform or gradually varied non-uniform
flow. If you know that the flow will be varying rapidly, obtain additional information, as
presented by Chow (1959) or Henderson (1966).
3.1.1.3 Momentum
According to Newton's Second Law of Motion, the change of momentum per unit of time
is equal to all the resultant external forces applied to the moving body. Applying this
principle to open channel flow produces a relationship that is virtually the same as the
Energy Equation expressed in Equation 3.1-2. Theoretically, these principles of energy
and momentum are unique, primarily because energy is a scalar quantity (magnitude
only), while momentum is a vector quantity (magnitude and direction). In addition, the
head loss determined by the Energy Equation measures the internal energy dissipated in
a particular channel reach, while the Momentum Equation measures the losses due to
external forces exerted on the water by the walls of the channel. However, for uniform
flow, since the losses due to external forces and internal energy dissipation are equal, the
Momentum and Energy Equations give the same results.
Applying the momentum principle has certain advantages for problems involving
substantial changes of internal energy, such as a hydraulic jump. Thus, you should use
the momentum principle for evaluating rapidly varied non-uniform flow conditions.
Theoretical details of the momentum principle applied to open channel flow are presented
by Chow (1959) and Henderson (1966). Section 3.1.4.3 provides a brief presentation of
hydraulic jump fundamentals.
1.486 2 3 12
v R S (3.1-3)
n
or
1.486 2 1
Q AR 3 S 2 (3.1-4)
n
where:
v= Average channel velocity, in feet per second
Q= Discharge, in cubic feet per second
n= Manning's roughness coefficient
𝐴
R= Hydraulic radius of the channel, in feet, calculated: 𝑅 = 𝑃
P= Wetted perimeter of channel, in feet
S= Slope of the energy gradient, in feet per feet
A= Cross-sectional area of the open channel, in square feet
You can find design values for Manning’s roughness coefficient for artificial channels (i.e.,
roadside, median, interceptor, and outfall ditches) in Chapter 2 (Section 2.7) of the
Drainage Manual. You can find guidance on methods for estimate Manning’s roughness
coefficient for natural channels in Chapter 5 (Bridge Hydraulics).
1 0.6 ft 1
4 6
5 ft
*Not to scale
Note: To make things easier, try breaking the drawing into three parts: two triangles and
a rectangle.
1
A1 (4 0.6)(0.6)
2
A1 0.72 ft2
Solve for the right triangle’s area
1
A2 (6 0.6)(0.6)
2
A2 1.08 ft2
Solve for the rectangle’s area
A3 5 0.6
A3 3 ft 2
Cross-Sectional Area (A) = 0.72 1.08 3 4.8 ft2
Example 3.1-1 has a direct solution because the depth is known. The next problem will
be more difficult to solve because the discharge will be given and the normal depth must
be calculated. The equations cannot be solved directly for depth, so an iterative process
is used to solve for normal depth. You also can solve Example 3.1-1 using the charts in
Appendix C.
Use the channel cross section shape, slope, and Manning’s roughness coefficient given
in Example 3.1-1
Calculate:
Normal Depth
1 1
4 6
5 ft
Note: The solution must use trial and error since you cannot solve the equations implicitly
for depth. Perform the first trial in the steps below and the remaining trials will be shown
in a table. The initial trial depth (i.e., the first guess) should be greater than the depth
given previously in Example 3.1-1 because the discharge is greater. So we will perform
our trial with an estimated depth of flow of 0.8 ft.
A2 1.92 ft 2
Solve for the rectangle’s area
A3 5 0.8
A3 4 ft 2
Cross-Sectional Area (A) = 1.28 1.92 4 7.2 ft 2
The discharge calculated in Step 4 is still less than 9 ft3/sec, so normal depth is greater
than 0.8 feet. Use a slightly higher depth of flow for the next guess. The following table
summarizes subsequent trials. The trial-and-error process continues until you achieve the
ideal level of accuracy.
The normal depth for the given channel and flow rate is 0.83 feet. You should perform
intermediate calculations using more significant digits than needed, and then round in the
last step to avoid rounding errors.
The Drainage Manual recommends that, where the flow depth is greater than 0.7 feet,
reduce the roughness value to 0.042. However, the normal depth using n = 0.042 is 0.69
feet. The recommended roughness for flow depths less than 0.7 feet is 0.06. The abrupt
change in the recommended roughness values causes this anomaly. If the flow depth is
the primary concern, then using n = 0.06 will give a conservative answer. However, if the
velocity is the primary concern, then using n = 0.042 is conservative.
v2
Ed (3.1-5)
2g
where:
E= Specific energy head, in feet
d= Depth of open channel flow, in feet
v= Average channel velocity, in feet per second
g= Acceleration due to gravity, 32.174 ft/sec2
Considering the relative values of potential energy (depth) and kinetic energy (velocity
head) in an open channel can help you with the hydraulic analysis of open channel flow
problems. Usually, you will perform these analyses using a curve that shows the
relationship between the specific energy head and the depth of flow for a given discharge
in a given channel that you can place on various slopes. Generally, you will use the curve
representing specific energy head for an open channel to identify regions of super-critical
and sub-critical flow conditions. This information usually is necessary to properly perform
hydraulic capacity calculations and evaluate the suitability of channel linings and flow
transition sections.
Q 2 A3
(3.1-6)
g T
where:
Q= Discharge, in cubic feet per second
g= Acceleration due to gravity, 32.174 ft/sec2
T= Top width of water surface, in feet
A= Cross-sectional area, in square feet
You can calculate critical depth for a given channel through trial and error by using
Equation 3.1-6. Chow (1959) presents a procedure for the analysis of critical flow that
uses the Critical Flow Section Factor (Z), defined as the ratio of the cross-sectional area
and the square root of the hydraulic depth, expressed mathematically as:
A A
Z (3.1-7)
D A
T
where:
Z= Critical flow section factor
A= Cross-sectional area of the flow perpendicular to the direction of flow, in
square feet
D= Hydraulic depth, in feet
T= Top width of the channel, in feet
Using the definition of the critical section factor and a velocity distribution coefficient of
one, the equation for critical flow conditions is:
Q
Z (3.1-8)
g
where:
Z= Critical flow section factor
Q= Discharge, in cubic feet per second
g= Acceleration due to gravity, 32.174 ft/sec2
When you know the discharge, Equation 3.1-8 gives the critical section factor and, thus,
by substitution into Equation 3.1-6, the critical depth. Conversely, when you know the
critical section factor, you can calculate the discharge with Equation 3.1-8.
It is important to note that the determination of critical depth is independent of the channel
slope and roughness, since critical depth simply represents a depth for which the specific
energy head is at a minimum. According to Equation 3.1-6, the magnitude of critical depth
depends only on the discharge and the shape of the channel. Thus, for any given size
and shape of channel, there is only one critical depth for the given discharge, which is
Calculate:
Critical Depth
1 1
4 6
5 ft
Note: The solution must use trial and error since you cannot implicitly solve the equations
for depth. You can perform the first trial as shown in the steps below, with the remaining
trials shown in a table. Typically, the slope of a roadside ditch channel must exceed 2
percent to have a normal depth that is super-critical. Since the slope in Example 3.1-1
and Example 3.1-2 is 0.5 percent, the critical depth is probably much less than the normal
depth of 0.83 feet calculated in Example 3.1-2 for 9 cfs. So, we will perform our trial with
an estimated depth of flow of 0.4 ft.
The discharge calculated in Step 3 is less than 9 ft3/sec, so critical depth is greater than
0.4 feet. Use a slightly higher depth of flow for the next guess. The following table
summarizes subsequent trials. The trial-and-error process continues until you achieve the
ideal level of accuracy.
You also can solve this problem by determining the minimum specific energy, as
discussed in the previous section. The following table solves Equation 3.1-5 for depths
bracketing the critical depth determined above, and shows that the critical depth has the
minimum specific energy.
Most computer programs that solve water surface profiles for natural channels use the
minimum specific energy approach. For more information, refer to Chapter 5 (Bridge
Hydraulics).
vC gd m (3.1-9)
where:
vc = Critical velocity, in feet per second
g= Acceleration due to gravity, 32.174 ft/sec2
dm = Mean depth of flow, in feet, calculated from:
A
dm (3.1-10)
T
where:
A= Cross-sectional area, in square feet
T= Top width of water surface, in feet
as sub-critical flow. Sub-critical flow is characterized by relatively large depths with low
velocities, as shown in Figure 3.1-2 (Part C). If the natural depth of flow in an open
channel is sub-critical, a downstream control section can influence the depth of flow at
any point in the channel. The relationship of sub-critical flow to the specific energy curve
is shown in Figure 3.1-2 (Parts B and C).
Figure 3.1-3: Non-Uniform Water Surface Profile for Downstream Control Caused
by a Flow Restriction
Cross Section 1 is upstream of the pool, where uniform flow occurs in the channel. Cross
Section 2 is at the beginning of a level pool. The depth of flow between Sections 1 and 2
is changing, and the flow is non-uniform. The water surface profile between the sections
is known as a backwater curve and is characteristically very long.
Figure 3.1-4 illustrates a channel in which the slope changes from sub-critical (mild) to
super-critical (steep). The flow profile passes through critical depth near the break in slope
(Section 1). This is true whether the upstream slope is mild, as in the sketch, or the water
above Section 1 is ponded, as would be the case if Section 1 were the crest of a dam
spillway. If, at Section 2, you were to compute the total head, assuming normal depth on
the steep slope, it would plot above the elevation of total head at Section 1 (Point “a” in
Figure 3.1-4). This is physically impossible, because the total head line must slope
downward in the direction of flow. The actual total head line will take the position shown
and have a slope approximately equal to So, the slope of the channel bottom, at Section
1 and approaching So farther downstream. The drop in the total head line (hloss) between
Sections 1 and 2 represents the loss in energy due to friction.
At Section 2, the actual depth (d2) is greater than normal depth (dn) because sufficient
acceleration has not occurred, and the assumption of normal depth at this point would
clearly be in error. As you move Section 2 downstream, so that the total head for normal
depth drops below the pool elevation above Section 1, the actual depth quickly
approaches the normal depth for the steep channel. This type of water surface curve
(Section 1 to Section 2) is characteristically much shorter than the backwater curve
discussed previously.
Another common type of non-uniform flow is the drawdown curve to critical depth that
occurs upstream from Section 1 (Figure 3.1-4) where the water surface passes through
critical depth. The depth gradually increases upstream from critical depth to normal depth,
provided that the channel remains uniform over a sufficient distance. The length of the
drawdown curve is much longer than the curve from critical depth to normal depth in the
steep channel.
The losses between cross sections include friction, expansion, contraction, bend, and
other form losses. Expansion, contraction, bend, and other form losses will be neglected
in the computations presented in this design guide. Refer to Chapter 5 (Bridge Hydraulics)
for more information. Determine the remaining loss—the friction loss—which is express
as:
hf S f L (3.1-11)
where:
hf = Friction head loss, in feet
Sf = Slope of the energy grade line, in feet per feet
L= Flow length between cross sections, in feet
Calculate the slope of the energy grade line at each cross section by rearranging
Manning’s Equation (Equation 3.1-4) into the following expression:
2
Qn
S 2
(3.1-12)
1.49 AR 3
For uniform flow, the slope of the channel bed, the slope of the water surface (hydraulic
grade line), and the slope of the energy grade line are all equal. For non-uniform flow,
including gradually varied flow, each slope is different.
Use the slope determined at each cross section to estimate the average slope for the
entire flow length between the cross sections. You can use several different averaging
schemes to estimate the average slope, and these techniques are discussed in more
detail in the Chapter 5 (Bridge Hydraulics). The simplest estimate of slope of the energy
gradient between two sections is:
S1 S 2
Sf (3.1-13)
2
where:
S1, S2 = Slope of the energy gradient at Sections 1 and 2, in feet per feet
Given:
Discharge = 25 ft 3 /sec
Roughness = 0.04
Cross Section from Example 3.1-1
Slope = 0.005 ft/ft
Calculate:
Depth of flow in narrower cross section
R/W
15’
100’
15’
You can estimate the flow depths in the two cross sections using the slope conveyance
method, which solves Manning’s Equation and assumes that the ditch is flowing at normal
depth. Example C.2 (Appendix C) shows the computation of the normal depths for the
ditch in this problem using the nomographs in Appendix C. The normal depth in the
standard ditch is 1.12 feet, and the normal depth in the narrowed ditch is 1.25 feet.
The Froude Number (Fr) for normal depth flow at the first section is:
1 1
Area (1.12 5) (6 1.12)(1.12) (4 1.12)(1.12) 11.87 sq. ft.
2 2
A 11.87
T 5 (6 4)1.12 16.2 ft. D 0.733
T 16.2
Q 25
v 2.11 fps
A 11.87
v 2.11
Fr 1
1
0.43
( gD) 2 (32.174 0.733) 2
Because Fr is less than one, the flow in the channel will be sub-critical. Therefore, you
will start the analysis at the downstream cross section and proceed upstream. Assume
normal depth in the standard ditch at a point just downstream of the downstream transition
(Section 1 in the figure above). This assumes that the ditch downstream is uniform for a
sufficient distance to establish normal depth at Section 1.
The water depth at Section 1 is 1.12 feet, as determined in Example C.2 (Appendix C).
The first row of the table on the next page shows this depth, along with other geometric
and hydraulic values needed for the computations. The elevation, z, is arbitrarily taken as
zero. Next, you will determine the depth at Section 2 from a trial-and-error procedure. The
first trial depth will be the normal depth at Section 2, which is 1.25 feet. Use Equations
3.1-10, 3.1-11, 3.1-12, and 3.1-2 to back calculate the depth at Section 2. The back-
calculated depth of 1.11 feet is shown in the last column. You can assume additional trial
depths until the trial and the back-calculated depths agree at the chosen level of accuracy.
After you have calculated the depth at Section 2, then calculate the depth at Section 3
using the same trial-and-error process. Repeat the same process to solve for the depth
at Section 4.
1 2 3 4 5 6 7 8 9 10 11
Depth
XS Area Perimeter Radius Velocity V2 / 2g Z EGL Slope Loss Depth
Guess
# (ft2) (ft) (ft) (ft /s) (ft) (ft) (ft) (ft) (ft)
(ft)
1 1.12 11.872 16.43057 0.72256 2.105795 0.068912 0 1.188912 0.005
1.25 11.40625 15.0563 0.75757 2.191781 0.074655 0.075 1.399655 0.00504 0.075301 1.114558
1.1 9.295 13.66954 0.67998 2.689618 0.112421 0.075 1.287421 0.008766 0.103245 1.104737
1.104 9.348672 13.70652 0.68206 2.674177 0.111134 0.075 1.290134 0.00863 0.102228 1.105007
2 1.105 9.362113 13.71577 0.68258 2.670337 0.110815 0.075 1.290815 0.008597 0.101977 1.105075
1.25 11.40625 15.0563 0.75757 2.191781 0.074655 0.575 1.899655 0.00504 0.681854 1.323014
1.29 12.00345 15.4261 0.77812 2.082735 0.067411 0.575 1.932411 0.004392 0.649423 1.297827
1.296 12.09427 15.48157 0.78120 2.067094 0.066403 0.575 1.937403 0.004303 0.645002 1.294414
3 1.295 12.07911 15.47233 0.78069 2.069688 0.066569 0.575 1.936569 0.004318 0.645732 1.294977
1.12 11.872 16.43057 0.72256 2.105795 0.068912 0.65 1.838912 0.004955 0.069549 1.287206
1.28 14.592 18.06351 0.80781 1.713268 0.045616 0.65 1.975616 0.002827 0.053585 1.294538
1.294 14.84218 18.20639 0.81522 1.684389 0.044091 0.65 1.988091 0.002699 0.052628 1.295107
4 1.295 14.86013 18.2166 0.81575 1.682355 0.043985 0.65 1.988985 0.002691 0.052562 1.295147
Column 2. Use Area formula for trapezoid with the depth guessed in Column 1
Column 3. Use Wetted Perimeter formula for trapezoid with depth guessed in Column 1
Column 4. Column 2 ÷ Column 3
Column 5. Q ÷ Column 2
Column 8. Column 1 + Column 6 + Column 7
Column 9. Solve Equation 3.1-12 using Column 2 and Column 4 values
Column 10. Calculate Sf with Equation 3.1-13 using Column 9 from this row and last row of previous section. Calculate the loss with Equation 3.1-11
by multiplying Sf by the distance to the previous cross section.
Column 11. Back calculate Depth by calculating the Total Energy (Col. 8 of previous cross section + Col. 10) and subtracting the Datum and the
Velocity Head (Col. 7 + Col. 6).
Looking at the results of the profile analysis on the previous page, there are several things
you might not expect. First, the flow depth at Section 2 (1.105 feet) is less than the flow
depth at Section 1 (1.12 feet), which might be unexpected because the normal depth of
Section 2 is greater than Section 1. However, this is not an unusual occurrence in
contracted sections. The reason that the flow depth decreases is because the velocity,
and, therefore, the velocity head, increases. The increase in the velocity head is greater
than the losses between the sections; therefore, the depth must decrease to balance the
energy equation. The opposite can occur in an expanding reach, resulting in an
unexpected rise in the flow depth even though the normal depth decreases.
The next unusual result is that the flow depth at Section 3 is greater than the normal depth
in the narrow section. Since the flow depth is less than normal depth at Section 2, the
water surface profile should approach normal depth from below as the calculations
proceed upstream. Therefore, the flow depth at Section 3 should be less than the normal
depth. The reason that the profile jumps over the normal depth line is because of
numerical errors introduced by Equation 3.1-13. When the change in the energy gradient
between two cross sections is too large, Equation 3.1-13 does not accurately estimate
the average energy gradient between the sections. Cross sections must be added
between these cross sections to reduce the numerical errors to an acceptable amount.
This example was solved using HEC-RAS with the extra cross sections added. The
details are described below, but the results indicate that the flow depth essentially
converges to normal depth within the 100-foot distance between Sections 2 and 3. The
normal depth is 1.25 feet compared to the 1.24 feet computed by HEC-RAS at Section 3.
This Illustrates one of the primary reasons that water surface profiles are not
necessary in the typical roadside ditch design. The water depth does not significantly
vary from normal depth at any location. So, assuming that the design includes some
freeboard, the ditch will operate adequately when designed by assuming normal depth.
HEC-RAS Solution:
Four cross sections with the trapezoidal ditch shapes and slope were input into the
program. The expansion and contraction coefficients were changed to zero so that the
only the friction loss will be calculated. The friction loss method also was changed to the
Average Friction Loss to match Equation 3.1-13. The results of the analysis are shown
below.
To compare the results with the spreadsheet solution, the depth of flow must be calculated
from the water surface elevation.
Flow Depth
Section River Station Water Surface Z
(Ft.)
1 0 1.12 0 1.12
2 15 1.18 0.075 1.11
3 115 1.87 0.575 1.30
4 130 1.94 0.65 1.29
The flow depths match the solution in Section 2. However, a conveyance ratio warning at
Section 3 indicates a possible error at that location. To improve the analysis, extra cross
sections were inserted between Section 2 and 3. Four cross sections are added by
interpolation and the profile is recomputed. The results are shown below:
The new flow depth at Section 3 is 1.81 – 0.575 = 1.24 feet. The profile in the narrow
section has essentially converged to normal depth (1.25 feet). The depth of the complete
profile is shown below:
Flow Depth
Section River Station Water Surface Z
(Ft.)
1 0 1.12 0 1.12
2 15 1.18 0.075 1.11
35 1.35 0.175 1.18
55 1.48 0.275 1.21
75 1.60 0.375 1.23
95 1.71 0.475 1.24
3 115 1.81 0.575 1.24
4 130 1.90 0.65 1.25
It is important to know where a hydraulic jump will form, since the turbulent energy
released in a jump can cause extensive scour in an unlined channel. For simplicity, you
can assume that the flow in the channel is uniform except in the reach between the jump
and the break in the channel slope. The jump may occur in either the steep channel or
the mild channel, depending on whether the downstream depth is greater or less than the
depth sequent to the upstream depth.
Using the equation below, you can calculate the sequent depth:
2
d1 d 2v d
d2 1 1 1 (3.1-14)
2 4 g
where:
d2 = Depth below jump, in feet
d1 = Depth above jump, in feet
v1 = Velocity above jump, in feet per second
g= Acceleration due to gravity, 32.174 ft/sec2
If the downstream depth is greater than the sequent depth, the jump will occur in the steep
region. If the downstream depth is lower than the sequent depth, the jump will move into
the mild channel (Chow). For more discussion on the location of hydraulic jumps, refer to
Open-Channel Hydraulics, by V.T. Chow, PhD.
When you have determined the location of the jump, you can determine the length using
Figure 3.1-7. This figure plots the Froude Number of the upstream flow against the
dimensionless ratio of jump length to downstream depth. The curve was prepared by V.T.
Chow from data gathered by the Bureau of Reclamation for jumps in rectangular
channels. You also can use the curve for approximate results for jumps formed in
trapezoidal channels.
When you have determined the location and the length of the hydraulic jump, you can
determine the need for alternative channel lining, as well as the limits the alternative lining
will need to be applied.
Given:
Q = 60.23 cfs
V1 = 13.81 fps
g = 32.2 ft/s2
d1 = 0.33 ft
d2 = 6.74 ft
You calculated the depths above using Manning’s Equation. The ditch has a 12.5-foot
bottom width with 1:2 side slopes. The longitudinal slopes are 10 percent and 0.001
percent, respectively. The roughness value for the proposed rubble riprap is 0.035.
Calculate:
Hydraulic Jump and the extent of rubble needed.
Step 1: Calculate Froude Number and the Length of the Hydraulic Jump
Froude Number, F1:
V
F1 1
gd1
13.81
F1
(32.2)(0.33)
F1 4.24
d1' 1.81 ft
Since the downstream depth d2 (6.74 ft) is greater than the upstream sequent depth d1’
(1.81 ft), the hydraulic jump occurs in the steep region.
d2
d 1’
d1
Assuming a more conservative approach, you can split the length of the hydraulic jump
between the two regions and provide rubble riprap ditch protection for 20 feet
downstream.
At channel bends, the water surface elevation increases at the outside of the bend
because of the super-elevation of the water surface. Additional freeboard is necessary in
bends, and you can calculate it using the following equation:
V 2T
d (3.1-15)
gRC
where:
∆d = Additional freeboard required because of super-elevation, in feet
V= Average channel velocity, in feet per second
T= Water surface top width, in feet
g= Acceleration due to gravity, in feet per second squared
RC = Radius of curvature of the bend to the channel centerline, in feet
The channel of Example 3.1-2 takes a 45-degree bend with a radius of 30 feet. What is
the increased depth on the outside of the channel at the bend?
V 2T 1.192 2 (13.26)
d 0.02 ft
gRC 32.174(30)
The depth of flow on the outside edge of the ditch is 0.86 + 0.02 = 0.88 ft.
The super-elevation is insignificant for this example problem, as it is for many ditches in
Florida. The variable that affects water surface super-elevation the most is the velocity
because it is squared in Equation 3.1-15. Ditches with a high velocity at a bend with a
small radius will have greater super-elevations.
Roadside Ditch
Median Ditch
Interceptor Ditch
Outfall Ditch
Canals
Section 2.2 of the Drainage Manual recommends design frequencies for each of these
channel types.
The roadside ditch receives runoff from the roadway pavement and shoulders as directed
by the cross slope and shoulder slopes. The roadside ditch also may receive flow from
offsite drainage areas on adjacent properties. The roadside ditch also may intercept
ground water to protect the base of the roadway. The roadside ditch conveys the flow to
an outfall point, although the ditch may flow into other ditches or components of the
stormwater management system before reaching the ultimate outfall point from FDOT
right of way. Depressed medians will collect runoff and a median ditch will be needed to
convey runoff to an outfall point. In general, roadside and median ditches are relatively
shallow trapezoidal channels, while swales are shallow, triangular, zero-bottom-width
channels.
Interceptor ditches have various purposes. They provide a method for intercepting offsite
flow above cut slopes, thereby controlling slope erosion. They can also collect offsite flow
and keep it separate from the project stormwater. This flow can bypass the stormwater
treatment facilities, reducing their size and cost.
Design outfall ditches, in most cases, to receive runoff from numerous secondary
drainage facilities, such as roadside ditches or storm drains. The delineation between a
roadside ditch and an outfall ditch can become blurred. If the discharge from a stormwater
management facility is brought back to the roadside ditch to convey the flow to another
point on the project for ultimate discharge, then consider the roadside ditch to be an outfall
ditch for the purpose of selecting the design frequency. If you combine considerable flows
from offsite areas and onsite project flows together in the roadside ditch to become a
significant discharge, then consider the roadside ditch to be an outfall ditch for the
purpose of selecting the design frequency. It is unwise to use a roadside ditch as an outfall
ditch, since its probable depth and size could create a potential hazard.
Canals, like outfalls, also are large artificial channels that accept flows from other
drainage components. The added connotation of a canal is that there is always water in
the channel, unlike many outfalls that only flow immediately after a rainfall event. If the
canal, which always has water, is close to the road, then it can be a potential hazard. For
the purpose of identifying a hazard, the FDM defines a canal as an open ditch parallel to
the roadway for a minimum distance of 1,000 feet, and with a seasonal water depth in
excess of three feet for extended periods of time (24 hours or more). Water Management
Districts and local agencies may have a different definition for canals when determining
regulatory jurisdiction.
Other FDOT publications mention other types of ditches. Right-of-way ditches are
mentioned in the Standard Specifications and a detail is given on Standard Plans, Index
524-001. The right-of-way ditch often functions as a type of relief ditch, handling drainage
needs other than those for the roadway and thus freeing roadside ditches from carrying
anything except roadway runoff. You usually can consider right-of-way ditches as
interceptor ditches when selecting the design frequency.
The term “lateral ditch” is used in the FDM and the Standard Specifications. The term is
used to determine:
A lateral ditch generally is perpendicular to the roadway and can flow either toward or
away from the road. However, a lateral ditch also can run parallel to the road right of way
if the ditch or channel is separate from the roadway template. Refer to the FDM for
guidance on selecting the excavation pay item. Consider the purpose of the lateral ditch
and associate it with one of the ditch types listed above to select the design frequency.
Several FDOT publications use the term roadway ditch rather than roadside ditch. These
two terms are interchangeable. Other FDOT publications or engineers performing work
for the Department also may use many other terms to refer to open channels. The
definitions of most of these terms are self-explanatory because of their descriptive names.
Some examples are:
Drainage ditch
Stormwater ditch
Bypass ditch
Diversion ditch
Conveyance channel
Agricultural ditch
Treatment swale
A swale is a special kind of artificial ditch that has become important in Florida. The
following legal definition of a swale as it relates to the regulation and treatment of
stormwater discharge is from Chapter 62-25.020, Florida Administrative Code (FAC):
Most projects will have stormwater management facilities, so the roadside ditches will
connect with the conveyance components to the various facilities. Not all portions of the
roadside ditch can physically be directed to a stormwater management facility, so short
segments may need to discharge to other points, such as streams or ditches near cross
drains and bridges, or other points along the roadway.
When determining initial ditch grades, provide a ditch slope with sufficient grade to
minimize ponding and sediment accumulation. The Drainage Manual requires a minimum
physical slope of 0.0005 feet/feet for ditches where positive flow is required. These flat
slopes are difficult to grade during construction and clumps of grass left behind by mowers
easily impede the flow.
Existing utilities also may control the grade of the ditch to maintain minimum cover over
the utility.
Step 2—Select Standard Ditch Components. The standard roadside ditch will be
shown in the plans on the typical section. You can find standard ditch sections in the FDM
for several roadway types, and in Figures 3.2-1 and 3.2-2, below. You may need to adjust
the standard ditch due to peculiarities that are consistent throughout the project. An
example might be a narrow border width and limited right of way.
The typical ditch shown in Figure 3.2-1 for two-lane roads is narrower than most mitered
end sections. In some situations, you can use a wider typical ditch section. If the wider
ditch is not used, then check the right of way at each mitered end to be sure the right of
way will be adequate to accommodate a wider ditch at the mitered end section.
If the ditch size needs to be reduced due to right-of-way limitations, you can consider the
following options:
The front slope must remain 1:6 in the clear zone, but can break over to 1:4 at the
clear zone
You can narrow the bottom width. Five feet is an ideal minimum, but Maintenance
and Construction may have equipment to build and maintain a two-foot bottom
width. Avoid V-bottomed ditches with steep side slopes. Refer to Chapter 2 of the
Drainage Manual for criteria regarding V-bottomed ditches. Avoid using a bottom
width narrower than the side drain endwalls.
You can steepen the back slope if the following is considered:
o Steeper slopes are harder to maintain, especially 1:3 and steeper
o Check the soils for stability
o Significant offsite drainage down a steep back slope will cause erosion on
the slope
You can reduce the depth to the shoulder point if the following is considered:
o Check the ditch capacity
o Consider the type of facility and base clearance needs
You also can enclose the ditch with a pipe system, although a ditch or swale
usually still is needed to collect the roadway runoff into inlets. Enclosing the
system will increase construction costs, but may be less expensive than
obtaining more right of way.
Step 3—Check for locations where the standard ditch will not work. A good way to
check is to plot the standard ditch on the cross sections. Look for places where the ditch
extends beyond the right of way or conflicts with utilities and other obstructions. Also look
in the Plan View to check for obstructions between the cross sections.
You can adjust the size of the ditch while also considering the same issues identified in
the previous step. If the grade of the ditch must be adjusted, then you must develop a
special ditch profile and plot it in the plans. Some locations where the ditch grade may
need to be adjusted include:
Outfall locations—The grade of the standard ditch will follow the grade of the road.
If the outfall location is not at the lowest point in the roadway profile, then you need
to develop a special ditch profile.
Locations of high water table—These areas may require feedback to the roadway
designer to raise the roadway grade.
Cross drains, median drains, and side drains—These structures may need to be
at a lower elevation than the standard ditch elevation. If the entrance end of the
culvert is depressed below the stream bed, more head is exerted on the inlet for
the same headwater elevation. Usually, the sump is paved, but for small
depressions, an unpaved excavation may be adequate.
Locations where the top of the back slope creates a ditch that is too shallow—
Sometimes, you can use a berm to contain the ditch instead of changing the grade.
Be careful that offsite drainage is not blocked. If you use a berm, provide an
adequate top width and side slopes for ease of maintenance. A suggested
minimum top width is three feet, but five feet is ideal.
You will need to develop special ditch profiles if the profile grade is less than the minimum
ditch slope. Refer to the Drainage Manual for minimum ditch slope criteria. At vertical
curve crests, the ditch grade will be less than the minimum ditch grade criteria given in
the Drainage Manual. (In fact, the ditch grade will go to zero at the high point.) A special
ditch grade is not necessary at a vertical curve crest.
Step 4—Compute the Flow Depths and Velocities. Although some designers check
the ditch at regular intervals, it is not necessary. Checking at critical locations is adequate.
Check the ditch at the outfall point. The discharge will be greatest at this location, so it
may represent the worst-case conditions for the entire ditch. Other critical locations to
check are:
Determine the maximum allowable depth of the ditch at these sections, including
freeboard. Section 2.4.5 of the Drainage Manual provides freeboard requirements. If the
actual depth exceeds the maximum allowable depth in the ditch, then the ditch does not
have enough capacity. Possible ways to increase the ditch capacity include:
Step 5—Check Lining Requirements. When the ditch geometry components are set
and the depth of flow is determined to be adequate, then the ditch needs to be checked
to determine if you need a ditch lining. Check the maximum velocity in the ditch against
the allowable velocities for bare earth shown in Table 2.3 of the Drainage Manual. If these
velocities are met, then you can use the standard treatment of grassing and mulching.
If the maximum ditch velocity exceeds the allowable velocity for bare earth, then you
should provide sodding, ditch paving, or other forms of ditch lining. See Section 3.3 for
more discussion of ditch linings.
When the width of the median ditch is established, locate outfall points from the median.
If the travel lanes slope to the outside and the median is impervious, then the median
runoff may not need to be conveyed to a stormwater treatment facility. The median may
be able to discharge directly into cross drains via inlets.
Median cross overs, bridge piers, or other structures often interrupt continuous flow in
medians. Decide whether to convey around the obstruction or to one side of the roadway.
Consider the flow depth in the median, feasible means to convey the flow around the
obstruction, the size of pipe to convey the flow to the outside, the cover available, and the
elevation of the roadside ditch to which the flow will be conveyed. Also consider the actual
low point of the median ditch, which is usually at the low point of the roadway grade. This
may be affected by guardrail, turn lanes, etc. Turn lanes and other non-typical roadway
configurations also may create a depressed gore area. You will need to analyze these
areas with methods similar to those used for roadside ditches.
Step 2—Select Standard Ditch Components. The standard median ditch will be shown
in the Plans on the Typical Section. Standard ditch sections are given in the FDM for
several roadway types, and one is shown in Figure 3.2-2.
Step 3—Compute the Flow Depths and Velocities. Determine critical locations to
check depth of flow and velocities, as outlined above. In addition to the critical areas for
the roadside ditch, you also should evaluate the median ditch in gore areas caused by
turn lanes or additional pavement. If the actual depth exceeds the maximum allowable
depth, then you will need to increase the capacity of the ditch. Use methods similar to
those for increasing the capacity of a roadside ditch. Be mindful of the additional clear
zone requirements for median ditches.
Step 4—Check Lining Requirements. After you establish the section of the ditch, check
the maximum velocities against the allowable velocities for bare soil. If those velocities
are exceeded, then you need to research further to determine the appropriate lining for
the ditch. See Section 3.3 of this design guide for further discussion.
Interceptor ditches along the edge of the right of way are commonly referred to as right-
of-way ditches.
The interceptor ditch generally will follow the grade of the natural ground adjacent to the
project, not the profile grade of the road. If possible, locate the high points in an interceptor
ditch at the drainage divides of the adjacent property to maintain existing drainage
patterns. Low points also typically follow the adjacent terrain, allowing the interceptor ditch
to discharge to points such as streams near cross drains and bridges.
Most projects will have stormwater management facilities. These facilities often are set
off from the project area, so it is important to consider conflicts that may arise where the
outfall ditch intersects the interceptor ditch.
The design steps for interceptor ditches are the same as those for the roadside ditch. See
Section 3.2.2 for the design procedure.
The drainage area that flows into the outfall ditch by overland flow. Designers often
forget to include this area in the total drainage area when determining the design
flow rates for the outfall ditch. Another concern is erosion down the side slope from
the sheet flow from these areas. You can use spoil from the ditch construction to
create berms to block and collect the flow in inlets to prevent this erosion.
Check for existing outfall easements. Some easements may require a specific type
of conveyance, such as a ditch or a pipe system.
3.2.6 Hydrology
As stated in Section 2.3 of the Drainage Manual, hydrologic data used for the design of
open channels will be based on one of the following methods, as appropriate for the
particular site:
For a more detailed discussion on procedure selection and method for calculating runoff
rates, refer to Chapter 2 (Hydrology).
3.2.6.1 Frequency
Roadside or median ditches or swales, including bypass and interceptor ditches, usually
are designed to convey a 10-year frequency storm without damage; outfall ditches or
canals should convey a 25-year frequency storm without damage. However, because the
risks and drainage requirements for each project are unique, site-specific factors may
warrant the use of an atypical design frequency. Regardless of the frequency selected,
you should always consider the potential for flooding that exceeds standard criteria. Pre-
development stages for all frequencies up to and including the 100-year event must not
be exceeded unless flood rights are obtained or the flow is contained within the ditch.
Design temporary open channel facilities for use during construction to handle flood flows
commensurate with risks. The recommended minimum frequency for temporary facilities
and the temporary lining of permanent facilities is 20 percent of the standard frequency
for permanent facilities, which extrapolates as a two-year frequency for roadside ditches
and a five-year frequency for outfall ditches.
Tw
Tw
To summarize the water surface approximation, the water surface elevation at any point
in the ditch is the higher of the normal depth elevation or the tailwater elevation. You can
determine the frequency of the design tailwater elevation using the same
recommendations for storm drains in Section 3.4 of the Drainage Manual.
The same water surface profile assumptions illustrated above also apply to other
backwater conditions in the ditch. Side drains are an example. The water surface
elevation in the ditch at any point upstream of a side drain should be the greater of the
normal depth elevation or the headwater elevation of the culvert. The normal depth in the
ditch changes if the ditch slope, cross section, or roughness changes. If the downstream
normal depth is greater, then the assumed water surface is shown in Figure 3.2-5.
dn
400’ V.C.
1,500’ V.C.
Pond
Step 1—Drainage Plan. On the left side of the roadway near Station 3125+00A, there is
a stormwater pond to treat and attenuate the roadway runoff. Roadside ditches will collect
the runoff from the roadway and convey it to the cross drain, which empties into the pond.
The offsite drainage area is small; therefore, dual ditches are not needed to reduce the
size of the pond.
The left roadside ditch will discharge into a mitered end section at Station 3126+50. The
design frequency for the ditch will be 10 years (refer to the Drainage Manual for the design
frequency). The pipe system and the pond may have different design frequencies than
the ditch, but you can determine a 10-year elevation in the pond and the 10-year hydraulic
grade line for the pipe system at the mitered end section. The hydraulic grade line of the
pipe system at this headwall will be the tailwater elevation for the ditch.
The design of the overall drainage system may be iterative. The design of one component,
such as the pond, can affect the design of other components, such as the left and right
roadside ditches, the cross drain, and even the median ditch. To simplify this example,
the tailwater elevation for the ditch will be given as 76.52 feet.
Step 2—Standard Ditch Components. The standard ditch shown in Figure 3.2-2 will be
used. The vertical distance from the profile grade line (PGL) to the ditch bottom elevation
of the standard ditch will be:
Elevation Difference = (24 ft. x 0.02) + (12 ft. x 0.06) + 3.5 ft. = 4.7 ft.
Step 3—Check for locations where the standard ditch will not work. Three reasons
why the standard ditch will not work are:
The backslope tie in to natural ground extends beyond the right-of-way line and
acquiring additional right of way is not prudent.
The natural ground elevation is lower than the standard ditch bottom elevation, or
low enough that the standard ditch is too shallow.
The profile grade is less than the minimum ditch slope.
Plotting the standard ditch on the roadway cross sections is a good way to look for
locations where the standard ditch will not work. Also, starting at the downstream end of
the ditch and working upstream will afford an orderly approach to design the ditch. For
this example, the profile grade elevation will be 79.00 and the bottom of the standard ditch
will be 74.3 feet at Station 3127+00, as shown in the figure below.
El. 79.00
The PGL is flat (0.000 percent) between this cross section and the end section at Station
3126+50. The minimum slope of the ditch is 0.05 percent, and the ideal slope is at least
0.1 percent. Therefore, you will need a special ditch grade between these stations. If the
flowline at the headwall (Station 3126+50) is set at 74.2 feet, the ditch grade between
these stations will be 0.1/50 = 0.002, or 0.2 percent.
At this point in the design process, you would calculate the discharge at the downstream
end of the ditch. For this example, the discharge will be given as 12.7 cfs at the end
section. Refer to the Chapter 2 (Hydrology) for an explanation of how to calculate the
discharge. Solving Manning’s Equation with the standard ditch shape (five-foot bottom
width, 1:6 front slope, 1:4 back slope), the slope of 0.2 percent, n = 0.042, and the
discharge of 12.7 cfs gives a flow depth in the ditch of 1.03 feet. At the headwall, the
normal depth elevation would be 74.2 + 1.03 = 75.23 feet. This elevation is less than the
tailwater elevation. Therefore, the flow depth in the ditch is the tailwater elevation of 76.52
feet. The outside edge of the shoulder elevation is lower than the back of the ditch
elevation at this location and will, therefore, control the allowable flow depth in the ditch.
Since the tailwater elevation is lower than the allowable flow depth, the ditch depth is
adequate.
Proceed upstream to continue the design. Looking at the cross sections between Stations
3133+00 and 3136+00, the standard ditch bottom elevation will be higher than the natural
ground elevation for several hundred feet, as typified by the cross section shown below
for Station 3134+00.
El. 87.08
El.
81.3
Sta.
3134+00
The standard ditch could be used if a berm was constructed. However, there are at least
two reasons not to construct the berm. First, some offsite flow to the ditch would be
blocked. Second, the cost of constructing the berm is unnecessary since you can use a
special ditch profile to lower the ditch into the natural ground.
The discharge needs to be determined at this point to continue the design. A conservative
assumption would be to use the discharge at the downstream end of the ditch. In this
case, the designer judges that the discharge might be significantly different and calculates
the discharge at this point. To simplify the example, the discharge at this location is given
as 10.2 cfs.
Assuming a ditch bottom elevation of about 79.3 ft (2 feet below natural ground), the slope
to Station 3127+00 would be (79.3 – 74.3)/700 = 0.007, or 0.07 percent. Selecting the
value of 2 feet was based on some preliminary calculations of the flow depth and including
some freeboard. Solving Manning’s Equation with the standard ditch shape, the slope of
0.7 percent, n = 0.042, and the discharge of 10.2 cfs gives a flow depth in the ditch of
0.68 feet. This would leave a freeboard of approximately 1.3 feet at this location, which is
more than needed. The flow depth of 0.68 feet is close enough to 0.7 feet that using n of
0.042 is reasonable given the amount of freeboard provided. A special ditch grade of 0.07
percent will be used between Stations 3127+00 and 3134+00.
The special ditch grade has to tie back into the standard ditch grade someplace further
upstream. The standard ditch bottom will return to an adequate depth into natural ground
to contain the flow at Station 3137+00. The PGL at Station 3137+00 is 91.17 feet. The
ditch bottom elevation for the standard ditch is 86.47 feet. The ditch grade will be (86.47
– 79.3)/300 = 0.0239, or 2.39 percent. Solving Manning’s Equation with the standard ditch
shape, the slope of 2.39 percent, n = 0.06, and the discharge of 10.2 cfs gives a flow
depth in the ditch of 0.59 feet and a velocity of 2.2 fps. Note that the roughness changes
because the flow depth is less than 0.7 feet. The velocity is low enough that ditch lining
will not be needed. However, sod will be needed, instead of seed and mulch, to establish
grass during construction.
Checking the cross sections between 3134+00 and 3137+00, the ditch depth is at least
1.5 feet, which will provide acceptable freeboard.
The standard ditch will provide an adequate depth from 3137+00 to the top of the hill.
Checking the cross section plots shows that the earthwork to construct the standard ditch
will not extend beyond the proposed right-of-way line.
Step 4—Compute the Flow Depths and Velocities. These values were calculated in
the description of the previous step. In most cases, the designer will be iterating through
Steps 3 and 4 as the ditch is designed.
Figure 3.2-6 shows the ditch checks appropriate for including in the Drainage
Documentation to prove the design.
51
HYDRAULIC WORKSHEET FOR ROADSIDE DITCHES Sheet ___1____ of ___1_______
Road: New Road__________________________________________ Prepared by: _____XXX_________ Date: ___4/1/09_______
Project Number: 1234567___________________________________________
Checked by: _____YYY_________ Date: ___4/1/09_______
Ditch Section
Side
STATION TO % Drain Q Calculated Vel Ditch
SIDE "C" Tc I10 "n" "d" "dallowed" Drain Remarks
STATION Slope Area (cfs) F.S. B.W. B.S. Freeboard (fps) Lining
Pipe Dia
3126+50 LT 0.20 2.61 0.75 15 6.5 12.7 6 5.0 4 0.042 1.03 1.2 SOD TW El. will control
3127+00 LT 0.70 12.7 6 5.0 4 0.042 0.75 1.9 SOD TW El. will control
3134+00 LT 0.70 1.79 0.75 10 7.6 10.2 6 5.0 4 0.042 0.68 1.87 SDO
Note: F.S. = Front Slope B.W. = Bottom Width B.S. = Back Slope
Manning "N" is Transitioning as the depth Approaches 0.7'
A side drain is a class of culvert pipe that can transport flow through fill placed in a
roadside ditch. A side drain is normally aligned parallel or nearly parallel to the project
roadway and along the flowline of the ditch. Side drains located under public roads
connecting to the project roadway, are identified and hydraulically sized as a cross drains
(see Chapter 4, Culverts). Side drains and cross drains are similar in many ways, but
there are some differences in design analysis requirements, materials, and end treatment.
Cross drains have to meet more rigorous criteria for some parameters.
You will normally develop the design flow for a side drain in the design calculations
spreadsheet or worksheet for the roadside ditch that contains the side drain. (Figure 2-1
of the Drainage Manual depicts such a ditch design worksheet.) The design flow and
surface water depth for the ditch section at the upstream end of the side drain are
determined in the ditch calculations, and this ditch flow is the side drain design inflow as
well. This flow typically is also the design flow for the ditch section at the downstream end
of the side drain, and must be accounted for in the calculations for the remainder of the
downstream ditch length. Of course, if additional flow enters the side drain between its
upstream and downstream ends, this additional flow also must be appropriately
accounted for in both the side drain hydraulic design and in the downstream ditch design
calculations.
Determine the tailwater elevation at the culvert outlet. Since the culvert usually is placed
through fill in the roadside ditch, the ditch calculations downstream of the culvert are used
to determine the tailwater. The culvert tailwater will be the normal depth in the
downstream ditch unless the tailwater for the ditch controls the water surface elevation at
the side drain outlet. Refer to Section 3.2.7 for more discussion on tailwater.
Then you can generate the hydraulic calculations for a side drain, using the procedure
described above to determine the pipe dimensions needed to safely pass the design flow
to the downstream ditch segment. Include these side drain calculations in the Drainage
Documentation Report as either a separate section or as part of the Ditch Calculations
section.
Note that the surface water depth computed for culvert flow at the upstream end of a side
drain generally will be larger than the depth computed for ditch flow at that location. If the
difference in this flow depth is not significant, evaluate the ditch flow depths upstream
from the side drain and adjust (if appropriate) for the “flat pool” that will be established in
the ditch by the higher of the two water surface elevations. If the difference in surface
water flow depth at the side drain is substantial and the ditch design is sensitive to actual
flow depths, a backwater analysis may be needed rather than the “flat pool” approximation
in determining the actual flow depth estimates.
Recognize that the specification of a grate could increase the required side drain
size (due to the increase in Ke).
In critical hydraulic locations, evaluate the potential debris transport prior to using
grates. Vegetated ditch grades in excess of 3 percent, pipe with less than 1.5 feet
Problem Statement:
A driveway is included in the design of the left roadside ditch for a new two-lane rural
roadway segment. Figure 3.2-1 depicts the typical section for the left side of the roadway.
The ditch extends and flows from Station 10+00 to Station 45+00, with the centerline of
the driveway located at Station 40+00. The width of the proposed driveway base at the
ditch flowline is 40 feet, and the ditch section is uniform throughout its length with a 2-foot
allowable depth below the left top-of-bank. At its upstream and downstream ends, the
ditch flowlines must match elevations of 100.0 feet and 96.0 feet, respectively. The
following sketch shows the ditch longitudinal slopes are 0.1 percent from Station 10+00
to Station 35+00, and 0.15 percent from Station 35+00 to Station 45+00. The site is
located in FDOT IDF Curve Zone 7, and the natural ground slopes away from the left top-
of-bank of the ditch section.
Design Approach:
First, develop the ditch design calculations to determine the side drain design inflow at
Station 39+80. These calculations are shown on Figure 3.2-7, and identify a side drain
design flow of 4.60 cfs.
Next, refer to Section 4.5 for the side drain hydraulic design procedure. Use either the
inlet control and outlet control nomographs from FHWA HDS-5, or software such as HY-
8, to develop the required side drain size.
El. 100
0.1% 40+00
0.15%
Culver
t
El. 96
10+00
35+00
40’
45+00
51
HYDRAULIC WORKSHEET FOR ROADSIDE DITCHES Sheet ___1____ of ___1_______
Road: New Road__________________________________________ Prepared by: _____XXX_________ Date: ___4/1/09_______
Project Number: 1234567___________________________________________
Checked by: _____YYY_________ Date: ___4/1/09_______
Ditch Section
Side
STATION TO % Drain Q Calculated Vel Ditch
SIDE "C" Tc I10 "n" "d" "dallowed" Drain Remarks
STATION Slope Area (cfs) F.S. B.W. B.S. Freeboard (fps) Lining
Pipe Dia
Note: F.S. = Front Slope B.W. = Bottom Width B.S. = Back Slope
Manning "N" is Transitioning as the depth Approaches 0.7'
1. Flexible Linings:
a. Grasses or natural vegetation
b. Rubble riprap
c. Wire-enclosed riprap (gabions)
d. Turf reinforcement (non-biodegradable)
2. Rigid Linings:
a. Cast-in-place concrete or asphaltic concrete
b. Soil cement and roller-compacted concrete
c. Grout-filled mattresses
d. Partially grouted riprap
e. Articulated concrete blocks
3.3.1.1 Vegetation
Vegetative linings consist of seeded or sodded grasses placed in and along the channel,
as well as naturally occurring vegetation. Vegetation is one of the most common and most
ideal channel linings for an artificial channel. It stabilizes the body of the channel,
consolidates the soil mass of the bed, checks erosion on the channel surface, and
controls the movement of soil particles along the channel bottom. Vegetative channel
lining also is recognized as a best management practice for stormwater quality design in
highway drainage systems. The slower flow of a vegetated channel helps the uptake of
highway runoff contaminants (particularly suspended sediments) before they leave the
highway right of way and enter streams.
There are conditions for which vegetation may not be acceptable, so you will need to
consider other linings. These conditions include, but are not limited to:
The Department operates on the premise that, with proper seeding and mulching during
construction, maintenance of most ditches on normal sections and grades can be handled
economically until a growth of grass becomes established. The use of temporary erosion
control measures in ditches with low velocities will provide time for grassing and mulching
to establish a vegetative ditch. When velocities exceed those for bare soils, seeding and
mulching should not be used.
Sodding is recommended when the design velocity exceeds the value permitted for the
bare base soil conditions, but is less than 4 feet per second. Lapped or shingle sod is
recommended when the design velocity exceeds that for sod (4 feet per second), and is
suitable with velocities up to 5.5 feet per second.
types of rubble riprap. Use ditch lining rubble riprap in standard or typical ditches or
channels. It consists of smaller stone sizes, which reduces construction costs over bank
and shore rubble. Limit bank and shore rubble riprap to uses such as revetments and
linings along stream banks and shorelines where extreme flows or wave action occurs.
Limited right of way and availability of material may restrict the use of this type of flexible
lining. Place rubble riprap on a filter blanket and prepared slope to form a well-graded
mass with a minimum of voids. Riprap and gabion linings can perform in the initial range
of hydraulic conditions where you would use rigid linings. Stones used for riprap and
gabion installations preferably have an angular shape that allow them to interlock. These
linings usually require a filter material between the stone and the underlying soil to prevent
soil washout and migration of fine grained soils. Sometimes you will need a bedding stone
layer to protect the filter fabric from larger stone.
To create soil/gravel turf reinforcement, you mix gravel mulch into on-site soils and seed
the soil-gravel layer. The rock products industry provides a variety of uniformly graded
gravels for use as mulch and soil stabilization. A gravel/soil mixture provides a non-
degradable lining that is created as part of the soil preparation and is followed by seeding.
Rigid linings are particularly vulnerable to a seasonal rise in the water table that can cause
a static uplift pressure on the lining. If you need a rigid lining in such conditions,
incorporate a reliable system of under drains and weep holes as a part of the channel
design. Evaluate the migration of fine grained soils into filter layers to ensure that the
ground water is being discharged without filter clogging or collapse of the underlying soil.
A related case is the buildup of soil pore pressure behind the lining when the flow depth
in the channel drops quickly. Using watertight joints and backflow preventers on weep
holes can help to reduce the buildup of water behind the lining.
Section 2.4.3.1.2 of the Drainage Manual states that you should consider the potential for
buoyancy due to the uplift water pressure when concrete linings are to be used where
soils may become saturated. The total upward force is equal to the weight of the water
displaced by the channel. The total weight of the lining helps to resist the uplift pressure.
When the weight of the lining is less than the uplift pressure, the channel is unstable.
Despite the non-erodible nature of concrete linings, they are susceptible to failure from
foundation instability. The major cause of failure is undermining that can occur in a
number of ways. Inadequate erosion protection at the outfall, at the channel edges, and
on bends can initiate undermining by allowing water to carry away the foundation material
and leaving the channel to break apart. Concrete linings also may break up and
deteriorate due to conditions such as a high water table or swelling soils that exert an
uplift pressure on the lining. When a rigid lining breaks and displaces upward, the lining
continues to move due to dynamic uplift and drag forces. The broken lining typically forms
large, flat slabs that are particularly susceptible to these forces.
Filter point grout-filled mattresses consist of a dual wall fabric that is injected with
concrete. This type of grout-filled mattress is characterized by a deeply cobbled surface.
The filter points woven into the fabric provide a means for groundwater to escape and to
provide release for the hydrostatic pressure. Filter point fabrics provide a higher
coefficient of friction to promote energy dissipation.
Note: As of May 2016, FDOT does not have standard specifications for grout-filled
mattresses. A technical specification will need to be prepared if grout-filled mattresses
are proposed for a project.
Stable channel design concepts provide a means of evaluating and defining channel
configurations that will perform within acceptable limits of stability. Most highway drainage
channels cannot tolerate bank instability and lateral migration. When the material forming
the channel boundary effectively resists the erosive forces of the flow, then you have
achieved stability. You can apply principles of rigid boundary hydraulics to evaluate this
type of system.
Apply both velocity and tractive force methods to help determine channel stability.
Permissible velocity procedures are empirical in nature, so they have been used to design
numerous channels in Florida and throughout the world. However, tractive force methods
consider actual physical processes occurring at the channel boundary and represent a
more realistic model of the detachment and erosion processes.
The hydrodynamic force that water flowing in a channel creates causes a shear stress on
the channel bottom. The bed material, in turn, resists this shear stress by developing a
tractive force. Tractive force theory states that the flow-induced shear stress should not
produce a force greater than the tractive resisting force of the bed material. This tractive
resisting force of the bed material creates the permissible or critical shear stress of the
bed material. In a uniform flow, the shear stress is equal to the effective component of the
gravitational force acting on the body of water parallel to the channel bottom. The average
shear stress is equal to:
=RS (3.3-1)
where:
= Average shear stress, in pounds per square feet
= Unit weight of water,62.4 lb/ft3
R= Hydraulic radius, in feet
S= Average bed slope or energy slope, in feet per feet
The maximum shear stress for a straight channel occurs on the channel bed and is less
than or equal to the shear stress at maximum depth. Compute the maximum shear stress
as follows:
d = d S (3.3-2)
where:
d = Maximum shear stress, in pounds per square feet
d= Maximum depth of flow, in feet
S= Channel bottom slope, in feet per feet
Velocity limitations for artificial open channels should be consistent with stability
requirements for the selected channel lining. As indicated above, use seed and mulch
only when the design velocity does not exceed the allowable velocity for bare soil. Table
2.3 of the Drainage Manual presents maximum shear stress values and allowable
velocities for different soils. When design velocities exceed those acceptable for bare soil,
sod, or lapped sod, consider flexible or rigid linings. Table 2.4 of the Drainage Manual
summarizes maximum velocities for these lining types.
where:
s = Side shear stress on the channel, in pounds per square feet
= Ratio of channel side to bottom shear stress
d = Shear stress in channel at maximum depth, in pounds per square feet
The value K1 depends on the size and shape of the channel. For parabolic channels, the
shear stress at any point on the side slope is related to the depth at that point and you
can calculate it using Equation 3.3-2. For trapezoidal and triangular channels, K1 is based
on the horizontal dimension 1: Z (V: H) of the side slopes.
K1 = 0.77 Z ≤ 1.5
K1 = 0.066Z + 0.67 1.5 < Z < 5
K1 = 1.0 5≤Z
Avoid using side slopes steeper than 1:3 for flexible linings other than riprap or gabions
because of the potential for erosion at the side slopes. Steep side slopes are allowable
within a channel if cohesive soil conditions exist.
Maintenance Considerations
Also consider maintenance of the channel when choosing a channel lining. The channel
will need to be accessible by mowers and trucks.
Mowing
Side slopes of vegetated channels will need to be traversable for mowing equipment and
crews. The maximum traversable slope for this equipment is 1:4.
If there is rubble riprap lining the channel and a vegetated buffer on the backside of the
channel along the right of way, the irregularity of the riprap typically prevents access. In
this situation, it may become impractical to maintain the vegetation.
DISADVANTAGES
Hauling and installation costs
Prohibits maintenance equipment from traversing channels
If hand placement is required, then labor is intensive
Vegetation growth can hinder inspections
DISADVANTAGES
Needs to be installed on a prepared slope
Not aesthetically pleasing
Easily undermined if not toed properly
(Source: http://www.fabriform1.com)
Construction Techniques, Inc.
3.3.4.3 Gabions
Types
Gabion Mats—Wire mesh mats filled with stones
Gabion Baskets—Wire mesh baskets filled with stones
DISADVANTAGES
Cost of installation
Susceptibility of the wire baskets to corrosion and abrasion damage
More difficult and expensive to repair
Less flexible than standard riprap
(Source: http://www.gabions.net/downloads.html)
Modular Gabion Systems, a division of C.E. Shepherd Company
(Source: http://www.gabions.net/downloads.html)
Modular Gabion Systems, a division of C.E. Shepherd Company
Figure 3.3-5: Erosion Control Mat in Channel Figure 3.3-6: Initial Anchor
(Downstream)
(Source: http://propexglobal.com/)
Propex Geosynthetics
If the roadside ditch is a linear treatment pond, then any reduction in the volume of the
ditch could violate the conditions of the permit obtained for the facility. The simplest way
to resolve this issue is to rework the ditch so that any volume lost as a result of the
development is replaced. This may require that the property owner donate some property
to the Department to provide an area to rework the ditch.
Even if the roadside ditch is not a linear treatment facility, you must maintain the capacity
of the ditch. Include a side drain to convey the ditch flow from one side of the turnout to
the other, unless the turnout is located at a high point in the ditch and the flow is away
from the turnout in both directions. An added turn lane may require that the roadside ditch
be relocated. The relocated portion of the ditch should have the same capacity or more
than the existing ditch. If the existing right of way is not wide enough to accommodate the
relocated ditch, then right of way may need to be donated to FDOT for the ditch. A turnout
requiring a side drain and a turn lane requiring donated right of way for the ditch relocation
are shown in Figure 3.4-1.
In some cases, the developer may need to add a left-turn lane. Widening the road to
accommodate the left-turn lane also may affect the ditch on the opposite side of the road
from the development. Often, the developer will not own the property on both sides of the
road. In this case, the roadside ditches and roadway must be redesigned to accommodate
the new turn lanes in such a way as to require donated right of way on the new
development’s side of the road.
The flow lines of the side drain should match the existing ditch. Also ensure that the flow
lines of the new side drain are higher than the next side drain downstream and lower than
the next side drain upstream to avoid temporary ponding in the ditch.
Make sure to size the side drain properly. You can make some judgments about the size
of the pipe by looking at the side drains upstream and downstream of the new drive.
Analyze the side drain to ensure the new pipe does not cause the water levels to pop out
of the ditch. In some cases, you can obtain the design discharge for the ditch from the old
plans for the roadway. Or you can calculate the flow by determining the drainage area
and performing the proper hydrologic calculations; typically, the Rational Equation. You
can find more details on these hydrology calculations in Chapter 2. Calculate the losses
through the pipe using methods given in Chapter 4. Additional sizing considerations are
discussed in Section 3.2.8.
When adding new side drains, another consideration is the proximity of other existing side
drains. If side drains are too close to each other, then the hydraulic losses can be too
large. The general requirement is that the end sections of two side drains in series should
be at least 25 feet apart. If the distance is less than 25 feet, then you should enclose the
area and add an inlet to collect the runoff from the area between the driveways.
Evaluate potential erosion at the infall point of the connection, especially for pipe
connections. Chapter 4 explains how to calculate the outlet velocity from a pipe. Refer to
Section 3.3 for channel linings. You can find outlet erosion protection criteria in the
Drainage Manual.
Unless you can place a new median opening at the high point in the median ditch, or
close enough to the high point that it is possible to regrade the ditch to flow away from
the new median opening in both directions, then the new opening will block the flow in
the ditch. Figure 3.4-2 shows a typical situation where there is an existing median opening
at the high point in the median ditch and the ditch flows to a median drain, which consists
of a ditch bottom inlet, pipe, and endwall. The median drain discharges runoff from the
median to keep the median from filling with water and spilling across the roadway.
If you add a new median opening to accommodate an adjacent development, the opening
may block the flow in the median ditch. Include a new drainage structure with the opening
to discharge the flow from the median. Figure 3.4-3 shows a side drain included to convey
the ditch flow from one side of the new median opening to the other. This often will be the
most economical method to provide adequate drainage for the median. However, in many
cases, the median ditch will be too shallow and the side drain will not have adequate
cover over the pipe. Refer to Appendix C of the Drainage Manual for the minimum cover
needed over the pipe.
Figure 3.4-4 includes a new median drain to accommodate the median flow. If you choose
to use this option, check the capacity of the roadside ditch with the added discharge from
the median. Unless you jack and bore the pipe, the existing pavement would have to be
cut and patched to install the pipe. Make sure to consider the cutting and patching
operations in maintenance of traffic plans.
Another option that might avoid the expense of jacking and boring or the concerns of
cutting and patching the existing roadway is shown in Figure 3.4-5. You could connect
the new ditch bottom inlet (DBI) to the existing median drain with a pipe beneath the new
median opening.
Adding a turn lane in the median often will reduce the size of the median ditch adjacent
to the new turn lane. Check the reduced ditch for capacity, and add extra median drainage
structures if needed. Super-elevated roadways that drain to the median can worsen the
capacity problems in areas where the ditch has been reduced.
Overland flow connections can cause bank erosion and sloughing if the flow becomes
concentrated. To avoid this problem, use point connections through pipes or ditches.
Erosion problems also can occur at the connections to an outfall ditch. Refer to Section
3.4.1.1 for guidance to protect the infall point.
Do not consider filling an open ditch if the basis for the modification is for aesthetic
purposes, for landscaping, or to benefit the abutting private property owner only. Table
3.4-1 lists criteria and other considerations for converting existing drainage ditches to
closed drainage systems.
Table 3.4-1
Capacity of Closed System
Criteria Comments
Design Storms: Primary considerations:
The more stringent of: Minimize adverse impact on
Rule 14-86, F.A.C. Storms: Department & other facility users
Original Ditch Design Storms: Maximize capacity of facility
Drainage Manual Design Storms: Maximize life of facility
o Evacuation route? o Avoid need to reconstruct
o Upstream owner constraints? for later foreseeable
Potential for flooding projects
upstream? Minimize maintenance cost
o Downstream constraints?
Tailwater
Planned work program improvements:
Pipe Size: Check various scenarios and use the
The more stringent of: criteria that most satisfies the
Rule 14-86, F.A.C. Criteria: Department’s interests.
Original Ditch Design Criteria:
Drainage Manual Criteria:
Future Work Program Requirements:
Erosion Control
Considerations: May result in failure of the pipe outfall
Erosion at outlet system.
Erosion when flows exceed system
capacity Possible turbid discharge downstream.
Soils
Flow velocity
Slopes
Methods:
Drainage Manual
Erosion and Sediment Control Designer
and Reviewer Manual
Protective measures
o Structural solutions
o Non-structural methods
Maintenance
Responsibility: Define this carefully in the agreement.
Applicant (local government)
responsible
o When concession needed from
Department in negotiation
o When special structures require
more maintenance attention or
expense
DOT responsible
o At DOT discretion
In some cases, there may be enough right of way available to reconstruct the ditch to
standards. More frequently, though, right of way is not sufficient to provide these
upgrades. Then, it may be practical to purchase additional right of way or drainage
easements in which to upgrade the current ditch system. If additional right of way proves
to be too costly, consider a closed system with a series of inlets and storm drain pipes.
The least ideal but often unavoidable option will consist of obtaining exceptions or
variances of the current standards for the existing ditch.
CHAPTER 4: CULVERT
4.6 Specific Standards Relating To All Cross Drains Except Bridges................ 4-27
4.6.1 Culvert Materials .......................................................................................... 4-27
4.6.2 Scour Estimates ........................................................................................... 4-27
4. CULVERT
4.1 GENERAL
4.1.1 Cross Drain Design
Section 4.2 of the Drainage Manual states, "All cross drains shall be designed to have
sufficient hydraulic capacity to convey the selected design frequency flood without
damage to the structure and approach embankments, with due consideration to the
effects of greater floods." This requires evaluation of the following:
Backwater
Refer to Section 4.3 of this design guide and Section 4.4 of the Drainage Manual.
Tailwater
Refer to Section 4.4 of this design guide and Section 4.5 of the Drainage Manual.
Scour
Refer to Sections 4.1.2 and 4.6.2 of this design guide and Section 4.9.2 of the
Drainage Manual.
You may need to perform a risk analysis to evaluate damage to structures and/or
embankments caused by backwater and/or scour. Refer to Appendix G, Risk Evaluations.
To use bridge culverts with no bottom slab and toe wall, you need to get the following
approval/evaluation:
b) An analysis of the degradation that could take place through the bridge culvert.
This would require you to recommend the toe wall depths of the bridge culvert and
the need for scour protection for the design-year frequency, 100-year frequency,
and 500-year frequency.
Base Flood
The “base flood” (100-year frequency flood event) is defined as the flood or storm
surge having a 1-percent chance of being exceeded in any given year. The base
flood is the standard in Federal Emergency Management Agency (FEMA) flood
insurance studies and many agencies have adopted it to comply with regulatory
requirements.
Greatest Flood
The “greatest flood” (500-year frequency flood event) is defined as the flood or
storm surge having a 0.2-percent chance of being exceeded in any given year.
This event is used to define the possible consequences of a flood occurrence
significantly greater than the 1-percent flood event. While it is seldom possible to
compute the discharge for the 500-year frequency flood with the same accuracy
that you would compute the discharge for the base flood, it serves to draw attention
to the fact that floods greater than the base flood can occur. In some cases, FEMA
and other agencies compute the 500-year frequency flood.
Overtopping Flood
The “overtopping flood” is described by the probability of exceedance and water
surface elevation at which water begins to flow over the highway, a watershed
divide, or through structure(s) providing for emergency relief.
The overtopping flood is of particular interest because it will indicate one of the
following:
2. The limit (stage) at which the highway, ditch, or some other control point will
act as a significant flood relief for the structure of interest
Carefully compare roadside ditch elevations with respect to the water surface
elevation for the structure being designed or analyzed. There may be instances
where the ditch elevation will provide significant relief to the structure for a certain
flood. This ditch elevation will define the overtopping flood stage.
Given the information below, determine the discharge and frequency for the overtopping
flood.
Solution
Step 1:
Step 2:
c. Knowing the overtopping discharge from Step 1c, you can determine
the probability of the overtopping flood being exceeded in any year.
In this case, the probability is 0.65 percent. This corresponds to a
frequency of 154 years (i.e., 100/0.65).
For culverts other than bridge culverts, include hydraulic data in a Flood Data
Summary Box similar to the example shown in Figure 4.1-3. Include these data for
those conditions discussed in FDM 305.
STRUCTURE
OVERTOPPING GREATEST
FLOOD FLOOD
NO.
Note: The hydraulic data are shown for informational purposes only, to indicate the flood discharges and water
surface elevations that may be anticipated in any given year. These data were generated using highly variable
factors determined by a study of the watershed. Many judgments and assumptions are required to establish
these factors. The resultant hydraulic data are sensitive to changes, particularly of antecedent conditions,
urbanization, channelization, and land use. Users of these data are cautioned against the assumption of
precision, which cannot be attained. Discharges are in cubic feet per second and stages are in feet.
Definitions:
Design Flood The flood selected by FDOT to be utilized to assure a standard level of hydraulic
performance
Base Flood: The flood having a 1-percent chance of being exceeded in any given year (100-year
frequency)
Overtopping Flood: The flood that causes water to flow over the highway, over a watershed divide, or through
emergency relief structures
Greatest Flood: The most severe flood that can be predicted, where overtopping is not practicable;
normally, one with a 0.2-percent chance of being exceeded in any given year (500-year
frequency)
Fill out the hydraulic flood data sheet according to the Federal Aid Policy Guide (23 CFR
650A). You can find this policy guide at
http://www.fhwa.dot.gov/legsregs/directives/fapg/cfr0650a.htm. In general, the following
applies.
a. If the overtopping flood is less than the standard design frequency, perform a
risk assessment to define the design flood as the overtopping flood. Fill out the
information for the design flood, base flood, and overtopping flood.
b. If the overtopping flood is between the standard design frequency and the base
flood (100-year flood), then fill out the information for the design flood, base
flood, and overtopping flood.
c. If the overtopping flood is between the base flood (100-year flood) and the
greatest flood (500-year flood), then fill out the information for the design flood,
base flood, and overtopping flood.
d. If the overtopping flood is larger than the greatest flood (500-year flood), then
fill out the information for the design flood, base flood, and greatest flood.
Example 4.1-2 shows you how to complete the Flood Data Summary Box when the
overtopping flood is less than the greatest flood (500-year flood).
Example 4.1-3 shows you how to complete the Flood Data Summary Box when the
overtopping flood occurs at a 10-year frequency.
Referring back to Example 4.1-1, assume the design flood is the 25-year frequency. Fill
out the Flood Data Summary Box.
Solution
Since the overtopping flood is between the base flood (100-year flood) and the greatest
flood (500-year flood), then fill out the information for the design flood, base flood, and
overtopping flood.
Q (25) = 31 ft3/sec
Stage (25) = 134.3 ft.
Q (100) = 44 ft3/sec
Stage (100) = 136.4 ft.
Q (Overtopping) = 64 ft3/sec
Stage (Overtopping) = 140.9 ft.
Put these values in the corresponding column, as shown in Figure 4.1-4. From Example
4.1-1, the overtopping flood was found to have a 0.65 percent chance of being exceeded
in any year, or a frequency of 154 years.
STRUCTURE
OVERTOPPING GREATEST
FLOOD FLOOD
NO.
4% PROB. 1% PROB.
25-YR FREQ 100-YR FREQ
PROB FREQ. PROB FREQ
DISCHARGE STAGE DISCHARGE STAGE DISCHARGE STAGE DISCHARGE STAGE
% YR % YR
Note: The hydraulic data are shown for informational purposes only, to indicate the flood discharges and water
surface elevations that may be anticipated in any given year. These data were generated using highly variable
factors determined by a study of the watershed. Many judgments and assumptions are required to establish
these factors. The resultant hydraulic data are sensitive to changes, particularly of antecedent conditions,
urbanization, channelization, and land use. Users of these data are cautioned against the assumption of
precision, which cannot be attained. Discharges are in cubic feet per second and stages are in feet.
Definitions:
Design Flood: The flood selected by FDOT to be utilized to assure a standard level of hydraulic
performance
Base Flood: The flood having a 1-percent chance of being exceeded in any given year (100-year
frequency)
Overtopping Flood: The flood that causes water to flow over the highway, over a watershed divide, or through
emergency relief structures
Greatest Flood: The most severe flood that can be predicted, where overtopping is not practicable;
normally, one with a 0.2-percent chance of being exceeded in any given year (500-year
frequency)
Given the information below, fill out the Hydraulic Flood Data Sheet.
The standard frequency for Structure 1 is 50 years, based on the criteria from
Section 4.3 of the Drainage Manual.
Perform a risk assessment to define the design flood as the overtopping flood.
Q (Overtopping) = 20 ft3/sec
Stage (Overtopping) = 45 ft.
Q (100) = 37 ft3/sec
Stage (100) = 50.5 ft.
Solution
Since the overtopping flood is less than the standard design frequency and you performed
a risk assessment to define the design flood as the overtopping flood, fill out the
information for the design (overtopping) flood, base flood, and overtopping flood. Put
these values in the corresponding columns, as shown in Figure 4.1-5.
Q (Overtopping) = 20 ft3/sec
Stage (Overtopping) = 45 ft.
Q (100) = 37 ft3/sec
Stage (100) = 50.5 ft.
Note: The hydraulic data are shown for informational purposes only, to indicate the flood discharges and water
surface elevations that may be anticipated in any given year. These data were generated using highly variable
factors determined by a study of the watershed. Many judgments and assumptions are required to establish
these factors. The resultant hydraulic data are sensitive to changes, particularly of antecedent conditions,
urbanization, channelization, and land use. Users of these data are cautioned against the assumption of
precision, which cannot be attained. Discharges are in cubic feet per second and stages are in feet.
Definitions:
Design Flood: The flood selected by FDOT to be utilized to assure a standard level of hydraulic
performance
Base Flood: The flood having a 1-percent chance of being exceeded in any given year (100-year
frequency)
Overtopping Flood: The flood that causes water to flow over the highway, over a watershed divide, or through
emergency relief structures
Greatest Flood: The most severe flood that can be predicted, where overtopping is not practicable;
normally, one with a 0.2-percent chance of being exceeded in any given year (500-year
frequency)
Under certain conditions, it may be appropriate to establish a level of risk allowable for a
site and to design to that level. When the risks associated with a particular project are
significant for floods of greater magnitude than the standard design flood, evaluate a
greater return interval design flood by using a risk analysis. Risk analysis procedures are
provided in FHWA’s HEC 17 and discussed briefly in Appendix G, Risk Evaluations. In
addition, consider incorporating or addressing design standards of other agencies that
have control or jurisdiction over the waterway or facility of concern in the design.
4.3 BACKWATER
Backwater is defined as the increase of water surface elevation induced upstream from
a bridge, culvert, dike, dam, another stream at a higher stage, or other similar structures;
or conditions that obstruct or constrict a channel relative to the elevation occurring under
natural channel and floodplain conditions.
Backwater effects are important to consider in the design/analysis of cross drains in rural
and urban areas.
In rural areas, the concern centers on increased flood stages. The degree and duration
of an increased flood stage could affect present and future land uses. You certainly must
evaluate agricultural land use for increased risks due to flooding. As an example,
inundation may impact crops or livestock.
In urban areas, the effects of increased flood stages or increased velocities become an
important consideration. In addition to the impact on future land use, the existing property
may suffer extensive physical damage. Many urban areas have stream or watershed
management regulations or are part of the National Flood Insurance Program (NFIP).
These regulations may dictate limits on changes that can be made to flow characteristics
of a watershed.
You may need to perform a risk evaluation to determine damage to surrounding property.
Refer to Appendix G, Risk Evaluations.
The Department does not encourage obtaining flood rights; however, it is recognized that,
in some instances, it may be necessary. Evaluate all possible alternatives before
recommending that the Department obtains flood rights.
Consider performing a risk analysis for situations where you are evaluating acquiring flood
rights. Appendix G briefly discusses risk analysis, whereas the topic is extensively
covered in HEC 17 (USDOT, FHWA, 1981).
Further discussion about obtaining flood rights is included in Appendix B of the Drainage
Manual.
4.4 TAILWATER
Section 4.5 of the Drainage Manual states: "For the sizing of cross drains and the
determination of headwater and backwater elevations, use the highest tailwater elevation
that can reasonably be expected to occur coincident with the design storm event."
Additional guidelines for tailwater elevations are provided in Section 4.5. For cross drains
subject to tidal conditions, include in the tailwater determination a sea-level rise analysis,
as described in Section 3.4.1 of the Drainage Manual.
Guidelines that pertain to the hydraulic analysis of bridge culverts and other culverts are
presented below.
• Allowable Headwater
You can determine the allowable headwater elevation by evaluating land use
upstream of the culvert and the proposed or existing roadway elevation. The
criteria in Section 4.4 of the Drainage Manual apply, but other factors that may limit
the allowable headwater are:
In general, the constraint that gives the lowest allowable headwater elevation
should establish the basis for hydraulic calculations.
• Inlet Control
Nomographs
You can determine the headwater elevation for inlet control by taking the culvert invert
elevation at the entrance and adding the headwater depth.
• Outlet Control
Nomographs
Outlet control nomographs have been developed and are shown in FHWA HDS-5
to provide graphical solutions to the head loss equations for various culvert
materials, cross sections, and inlet combinations.
Appendix F, Applications Guide for Pipe End Treatments presents culvert entrance
loss coefficients (ke) for the end treatments. For other types of end treatments,
refer to FHWA HDS-5.
Critical Depth
Use FHWA HDS-5 or other suitable methods to determine the critical depth for
various sizes and types of culverts.
For culverts flowing partially full, the distance from the invert of the culvert outlet to
the equivalent hydraulic grade line is termed the equivalent hydraulic elevation and
is expressed as:
D+ dc
ho = (Equation 4.5-1)
2
where:
ho = Equivalent hydraulic elevation, in feet, for an unsubmerged outlet condition
D = Depth of the culvert, in feet
dc = Critical depth at the culvert outlet, in feet
If the value for dc from the figures of FHWA HDS-5 is greater than D, then ho will
equal D.
The equivalent hydraulic elevation is valid as long as the headwater is not less
than 0.75D. For headwaters lower than 0.75D, perform backwater calculations to
obtain headwater elevations.
Tailwater
Tailwater (TW) is the depth of water measured from the invert of the culvert at the
outlet to the water surface elevation due to downstream conditions. Evaluate the
hydraulic conditions downstream of the culvert site to determine a tailwater depth
for the discharge and frequency under consideration. Determine tailwater as
follows:
b. For culverts that discharge to an open channel, the tailwater may be equal to
the normal depth of flow in that channel. Calculate normal depth using a trial-
and-error solution of the Manning’s equation. The known inputs are channel
roughness, slope, and geometry.
For bridge culverts that discharge to an open channel, you may have to
determine the tailwater by performing a standard backwater calculation.
Consider this analysis if the open channel does not have constant channel
roughness, slope, and geometry or if there is a control structure downstream
that could cause backwater.
c. If the culvert discharges to a lake, pond, or other major water body, the
expected high-water elevation of the particular water body may establish the
culvert tailwater. However, it is probably not appropriate to use a 25-year lake
stage for a cross drain that uses a 25-year design frequency, due to the
difference in time relationship between occurrences. Usually, the mean annual
stage would be appropriate.
d. If tidal conditions occur at the outlet, the mean high water, as determined by
sources such as the National Oceanic and Atmospheric Administration
(NOAA), usually establishes the initial basis for tailwater conditions. Adjust the
mean high water for sea level rise as described in Section 3.4.1 of the Drainage
Manual.
Design Tailwater
The tailwater condition that prevails during the design event is called the design
tailwater (DTW). The design tailwater may be a function of either downstream or
culvert outlet conditions.
b. For the unsubmerged outlet shown in Figure 4.5-2, TW is less than ho, so
the ho elevation becomes DTW.
Headwater Depth
Having established the total head loss (H) and the design tailwater depth (DTW),
compute the headwater depth (HW), as follows:
where:
HW = Headwater depth for outlet control, in feet
H = Total head, in feet
DTW = Design tailwater depth, in feet
L = Length of culvert barrel, in feet
So = Barrel slope, in feet/feet
The difference in elevation between the culvert inlet and the culvert outlet is equal
to LSo. You may use it directly in Equation 4.5-2.
Determine the headwater elevation for outlet control by taking the culvert invert
elevation at the entrance and adding the headwater depth.
• Outlet Velocity
Inlet Control
In inlet control, you may need to make backwater calculations to determine the
outlet velocity. These calculations begin at the culvert entrance and proceed
downstream to the exit. Obtain the flow velocity from the flow and the cross
sectional area at the exit:
Q
V= (Equation 4.5-3)
A
where:
V = Average velocity in the culvert, in feet per second
Q = Flow rate, in cubic feet per second
A = Cross sectional area of the flow, in square feet
Calculate normal depth using a trial-and-error solution of the Manning equation. The
known inputs are barrel resistance, slope, and geometry. Then, determine the area of
flow prism based on the culvert barrel geometry and depth equal to normal depth. You
also can determine normal depth and area of flow using the charts for various pipe cross
section shapes in Appendix E.
Given the information below, determine the outlet velocity for inlet control.
where:
Qdesign = 18 ft3/sec
Diameter of Pipe (D) = 24 in.
Slope of Pipe (S) = 0.01 ft./ft.
Roughness Coefficient (n) = 0.012
Solution
Step 1: Determine area, wetted perimeter, and hydraulic radius of the pipe flowing
full.
Step 2: Using Manning's Equation, determine the discharge and velocity of the pipe
flowing full.
1.49
Q Full = A R 2/3 S 1/2
n
1.49
Q Full = (3.14 ft 2 ) (0.5 ft. )2/3 (0.01 ft./ft. )1/2 = 24.56 ft 3 /s (say 25 ft 3 /s)
0.012
3 2
V Full = Q Full / AFull = 25 ft /s / 3.14 ft = 7.96 ft/s (say 8.0 ft/s)
Step 3: Using Figure 4.5-4, determine the area of flow for the design discharge
using the following relationship:
Q Design 18 ft 3 /s
= = 0.72 or 72 % of value for section
Q Full 25 ft 3 /s
ADesign
= 0.66 ; ADesign = 0.66 × 3.14 ft 2 = 2.07 ft 2
AFull
Q Design 18 ft 3 /s
V Design = = = 8.70 ft/s
ADesign 2.07 ft 2
Outlet Control:
In outlet control, the cross sectional area of the flow (Ap) is defined by the geometry of
the outlet and either critical depth, tailwater depth, or the height of the culvert (see Figure
4.5-5).
Use critical depth when the tailwater is less than critical depth; use the tailwater depth
when tailwater is greater than critical depth but below the top of the barrel. The total barrel
area is used when the tailwater exceeds the top of the barrel.
Q
V= (Equation 4.5-4)
Ap
where:
V = Average velocity in the culvert, in feet per second
Q = Flow rate, in cubic feet per second
Ap = Cross sectional area of the flow defined by the geometry of the outlet and either
critical depth, tailwater depth, or the height of the culvert, in square feet
You can determine the area of flow prism based on barrel geometry and depth of flow (d)
using the charts for various pipe cross section shapes in Appendix E.
Given the information below, determine the outlet velocity for outlet control.
where:
QDesign = 18 ft3/s
Diameter of Pipe = 36 in.
Slope of Pipe = 0.01 ft./ft.
Roughness Coefficient (n) = 0.012
Critical Depth (dc) = 1.4 ft. (determined from FHWA HDS-5, for QDesign = 18 ft3/s)
Tailwater (TW) = 2.0 ft.
Solution
Step 1: Determine the area of the pipe flowing full:
Step 3: Using Figure 4.5-6 determine the depth of flow to full depth flow (TW/D) or
2 ft./3 ft. = 0.67, or 67 percent of the full depth.
3. Project vertically down from the area of flow curve and read from the
horizontal axis a value of 0.73, or 73 percent for full section.
ADesign
= 0.73 ; ADesign = 0.73 × 7.07 ft 2 = 5.61 ft 2
AFull
18 ft 3 /s
V Design = Q Design / ADesign = = 3.2 ft/s
5.61 ft 2
b. Computer programs
FHWA’s HY-8 computer program is only one of several programs that are capable of
culvert capacity calculations. The Department has accepted the computer program for
use and it is available through FHWA’s website
(http://www.fhwa.dot.gov/engineering/hydraulics/software/hy8/). Before you use other
computer programs in the design of a Department project, the District Drainage Engineer
should approve them.
When the vertical distance from invert to roadway is limited, arch culverts may be
appropriate. When the rise of a culvert exceeds four feet, consider the use of box culverts
since they may offer cost advantages.
A method for estimating the dimensions of a scour hole at a culvert outlet is available in
HEC 14, Chapter 5, linked below:
http://www.fhwa.dot.gov/engineering/hydraulics/pubs/06086/hec14ch05.cfm.
A good guide in estimating potential scour at the outlet of proposed culverts is to look for
scour developed at the outlet of similar existing culverts. Scour does not develop at all
suspected locations because the susceptibility of the stream to scour is difficult to assess
and the flow conditions that will cause scour do not occur at all flow rates. At locations
where you expect scour to develop only during relatively rare flood events, the most
economical solution may be to repair or retrofit the damage after it occurs.
When the outlet velocity is greater than or equal to 12 ft/sec, consider energy dissipation
devices, such as those shown in the Standard Plans.
The design procedures below do not account for structures within regulatory floodways;
therefore, you may need to deviate from these procedures to satisfy regulatory agencies.
Evaluate and determine the level of effort needed to produce an acceptable design.
Design procedures for three categories of cross drains are provided, including:
Review Checklist
Date: _________________________________
Project: _________________________________
___________________________________________________________________
___________________________________________________________________
Erosion/Sedimentation: ________________________________________________
___________________________________________________________
___________________________________________________________
___________________________________________________________
___________________________________________________________
If there are no signs of undesirable scour at inlet and outlet ends, no excessive
sedimentation, and no history of problems, you may extend the existing culvert.
The hydrologic and hydraulic analysis would follow the procedure shown below:
General Concerns
Make sure enough right of way exists beyond the ends of the extended culvert to
tie in the roadside ditches and provide for outlet treatment if necessary. There is a
detail in the Standard Plans for ditch transitions at culvert locations. If right of way
is inadequate, consider adjusting the ditch cross-section. If there is not enough
room for the transition shown in the Standard Plans, you may design a sharper
transition, but evaluate the need for channel lining to prevent erosion of the ditch
side slopes. Example 4.7-1 illustrates this method.
Spoke with Mr. Steve Smith from the FDOT Maintenance Office on November 18,
1993. From our discussion, we found that there has been no history of problems
in overtopping of the roadway and no complaints of flooding from upstream
property owners have been found.
We performed a field review with Mr. Smith on November 21, 1993. From our
review, we determined the culvert was in good condition, with no signs of
sedimentation or scour.
Since this roadway has an ADT > 1,500, the design frequency is 50 years
(determined from the Drainage Manual). To determine the 50-year
discharge, a procedure similar to that used in Example 4.1-1 is appropriate.
For this example, the Q(50) is 50 ft3/sec.
For this example, the 50-year tailwater elevation to be used will be:
For this example, only the hydraulic analysis for the 50-year frequency will be
computed. However, you also would need to compute an analysis for the other
frequencies. The analysis is for the proposed conditions. Figure 4.7-1
summarizes the following calculations.
• Inlet Control
Nomographs:
Determine the headwater elevation by taking the culvert invert at the entrance
and adding the headwater depth:
• Outlet Control
Nomographs:
Using Chart 5 in FHWA HDS 5 with a pipe length of 67 feet (existing 59 ft. + 8
ft. of extension) and an entrance loss coefficient of 0.2 feet (as determined
below), the headwater (H) for the 50-year discharge is 1.55.
Culvert entrance loss is 0.2 as determined from the Application Guidelines for
Pipe End Treatment, Appendix F, based on the structure having a standard
end wall treatment.
Using Chart 4 in FHWA HDS 5, the critical depth was found to be 2.3 feet.
D + d c 3 ft + 2.3 ft
ho = = = 2.65 ft.
2 2
Having established the total head loss (H) and the design tailwater depth
(DTW) as described above, compute the headwater depth (HW), as follows:
HW = H + DTW - LSo
HW = 1.55 ft. + 2.70 ft. - (0.4 ft.)
HW = 3.85 ft., say 3.9 ft.
Determine the headwater elevation by taking the culvert invert at the entrance
and adding the headwater depth:
Since the HW depth or elevation for outlet control (HW Elevation = 104.0 feet)
is greater than that of inlet control (HW Elevation = 103.9 feet), then the
controlling HW Elevation is 104.0 feet.
• Outlet Velocity
Outlet velocity for a culvert for this type of problem does not need to be
computed since the discharges were estimated using a 25-year velocity of 6
ft/sec.
General Considerations
The ditch transition concerns in the previous section also apply here. In addition,
any problems such as scour, sedimentation, etc., should be limited to within the
right of way or not extend any further outside the right of way than they currently
extend. Example 4.7-2 illustrates this procedure.
Spoke with Mr. Steve Smith from the FDOT Maintenance Office on November 18,
1993. We found that there has been history of overtopping of the roadway.
We performed a field review with Mr. Smith on November 21, 1993. From our
review, we discovered that the area around the outlet end of the culvert showed
signs of scouring.
From the field review and hydrologic calculations, the following design
information is known:
Q(50) = 35 ft3/sec
Q(100) = 52 ft3/sec
Q(500) = 88 ft3/sec
For this example, the 50-year tailwater elevation to be used will be TW (50
year) = 2.5 ft.
For this example, only a hydraulic analysis for the 50-year frequency will be
computed. The other frequencies also would need to be analyzed for an actual
project. The analysis is for the existing conditions. Figure 4.7-2 summarizes the
following calculations.
• Inlet Control
Nomographs
Using Chart 8 in FHWA HDS 5, Q/B = (35 ft3/sec)/2 ft. = 17.5 ft3/sec.
Therefore, HW/D = 2.4 and HW = 2.4 ft. x D = 2.4 ft. x 2 ft = 4.8 ft.
• Outlet Control
Nomographs
Using Chart 15 in FHWA HDS 5, the headwater (H) for the 50-year
discharge is 2.2 feet based on the pipe length of 50 feet and entrance loss
coefficient of 0.2, as determined below.
Using Chart 14 in FHWA HDS 5, the critical depth was found to be 2 feet.
D + d c 2 ft. + 2 ft.
ho = = = 2 ft.
2 2
Having established the total head loss (H) and the design tailwater depth
(DTW) as described above, compute the headwater depth (HW), as follows:
HW = H + DTW - LSo
HW = 2.2 ft. + 2.5 ft. - (0.2 ft.)
HW = 4.5 ft.
Since the HW depth or elevation for inlet control (HW elevation = 104.8 feet)
is greater than that of outlet control (HW elevation = 104.5 feet), then the
controlling HW elevation is 104.8 feet.
• Outlet Velocity
Since the existing structure was found to be inlet control, the outlet velocity
was determined as discussed earlier in this section.
Review of Figure 4.7-2 indicates that the roadway is overtopped for a 50-year
design frequency. Therefore, recommend replacing the structure. It is
anticipated that a cross drain no larger than a 48-inch diameter would be
appropriate for this location. The procedure in Section 4.7.2, following, could
be used. Example 4.7-3 illustrates this using the information from this example.
A = Q/V
Where:
A = Culvert area (square feet)
Q = Design discharge (e.g., 50 year)
V = Average velocity (feet per second); use an average velocity of four feet per second
• Estimate tailwater. If the outlet is in a free-flowing condition, the crown of the pipe
at the outlet may be assumed.
• Check hydraulic results against design standards for backwater, minimum size,
and scour. If these standards are satisfied, the trial culvert size is acceptable.
• Determine the most economical culvert size that satisfies all standards. If the
trial selected size does not satisfy all design standards, obtain a variance.
Referring back to Example 4.7-2, you determined that the two-foot x two-foot concrete
box culvert should be replaced. A design frequency of 50 years was determined as the
minimum for this roadway. The existing length of the two-foot x two-foot concrete box
culvert was 50 feet. However, since the structure will have to be extended four feet on
each side, the design length of the proposed structure will be 58 feet.
Q(50) = 35 ft3/sec
Q(100) = 52 ft3/sec
Q(500) = 88 ft3/sec
Q 35 ft 3 /s
A= = = 8.8 ft 2
V 4 ft/s
The hydraulic analysis would be similar to what was done in Example 4.7-1 and
Example 4.7-2. A worksheet of the calculations for the 50-year frequency is shown
in Figure 4.7-3. The other frequencies also would need to be analyzed for an actual
project. The analysis shown in Figure 4.7-3 is for the proposed conditions.
Review of the worksheet in Figure 4.7-3 indicates that the roadway will not overtop
for the 50-year frequency for either culvert size. There is very little difference
between the 36-inch and 42 inch pipe as far as controlling headwater. Therefore,
either pipe size would be adequate. However, it is recommended that the 36-inch
pipe be installed since it would be slightly less in cost than the 42-inch pipe. In
addition, it would be recommended that a rubble ditch lining design be installed at
the outlet end due to velocities exceeding six feet per second.
• If design does not meet standards or if you can use more economical culvert size
that satisfies the standards, then perform new computations for that design.
The remaining steps are the same as those identified in Section 4.7.2 for small cross
drains.
5. BRIDGE HYDRAULICS.........................................................................................5-1
5. BRIDGE HYDRAULICS
Most bridge projects in Florida receive funding from FHWA. Even if the project is not
planned to receive federal funding, the funding situation may change before the project
is complete. As a result, much of the hydraulic analyses and documentation required by
the Department’s standards are tailored to satisfy federal regulations and requirements.
FHWA 23 CFR 650A outlines the principal hydraulic analysis and design requirements
that you must satisfy to qualify bridge projects (as well as any other project involving
floodplain encroachments) for Federal Aid. The requirements in 23 CFR 650A are very
comprehensive, so you, as the drainage engineer, should become familiar with them. The
document is available at: (http://www.fhwa.dot.gov/legsregs/directives/fapg/cfr0650a.htm).
1. Riverine flow—Crossings with no tidal influence during the design storm, such as:
(a) inland rivers, or (b) controlled canals with a salinity structure oceanward
intercepting the design hurricane surge. Bridges identified as riverine dominated
require only examination of design runoff conditions.
2. Tidally dominated flow—Crossings where the tidal influences are dominated by the
design hurricane surge. Flows in tidal inlets, bays, estuaries, and interconnected
waterways are characterized by tide propagation evidenced by flow reversal
(Zevenbergen et al., 2004). Large bays, ocean inlets, and open sections of the
Intracoastal Waterway typically are tidally dominated, so much so that even
extreme rainfall events have little influence on the design flows in these systems.
Tidally dominated areas with negligible upland influx require only examination of
design storm surge conditions.
3. Tidally influenced flow—Both river flow and tidal fluctuations affect flows in tidally
influenced crossings, such as tidal creeks and rivers opening to tidally dominated
waterways. Tidally affected river crossings do not always experience flow reversal;
however, backwater effects from the downstream tidal fluctuation can induce water
surface elevation fluctuations up through the bridge reach. Tidally influenced
bridges require you to examine both design runoff and surge conditions to
determine which hydraulic (and scour) parameter will dictate design. For example,
a bridge located near the mouth of a river that discharges into a tidal bay (see
Figure 5.1-2) may experience a high stage during a storm surge event. However,
high losses through the bridge and a relatively small storage area upstream may
limit the flow (and velocities) through the bridge. In fact, the design flow parameters
(and thus scour) may occur during the design runoff event while the design stage
(for clearance) and wave climate occurs during the storm surge event. Given that
tidally influenced crossings may require both types of analyses, you should plan to
include a coastal engineer for these bridge projects.
The level of tidal influence is a function of several parameters, including distance from the
open coast, size of the upstream watershed, elevation at the bridge site, conveyance
between the bridge and the open coast, upstream storage, and tidal range.
By far, the best indicator is distance from the coast. Comparisons of gage data or tidal
benchmarks with distance from the coast will illustrate the decrease in tidal influence with
increasing distance (see Figure 5.1-2). The figure shows that with increasing distance,
the tidal range decreases, the flow no longer reverses, and, eventually, the tidal signal
dies out completely. This illustrates the transition from tidally controlled (gage 2323592),
to tidally influenced (gages 2323590, and 2323567, and 2323500), and finally to a riverine
dominant system (gage 2323000).
5
2323592 (7 miles from coast)
4 2323590 (13 miles from coast)
2323567 (20 miles from coast)
2323500 (28 miles from coast)
Stage in ft-NGVD
3
2323000 (47 miles from coast)
-1
-2
10/31/2010 11/2/2010 11/4/2010 11/6/2010 11/8/2010 11/10/2010
Date
Figure 5.1-1: USGS Gage Data from the Suwannee River with Increasing Distance
from the Coast
US 90 over the
US-90
Escambia River
Escambia Bay
Figure 5.1-2: Example of a Bridge Requiring both Riverine and Tidal Analyses
(US-90 over Escambia Bay)
For the purposes of Department work, a coastal engineer is an engineer who holds a
Master of Science or doctoral degree in coastal engineering or a related engineering field
and/or has extensive experience (as demonstrated by publications in technical journals
with peer review) in coastal hydrodynamics and sediment transport processes.
Refer to the PD&E or environmental documents and the Location Hydraulic Report for
commitments made during the PD&E phase. Refer to Part 2, Chapter 24 of the FDOT
Project Development and Environment Manual for more information on floodplain
assessment during PD&E.
Flood maps for the bridge site, if available, to determine if the floodplain has been
established by approximate methods or by a detailed study, and if a floodway has
been established.
Community Status Book Report to determine the status of the community’s
participation in the NFIP.
Both the flood maps and the Status Book are available at the Federal Emergency
Management Agency (FEMA) website: http://www.fema.gov/.
The Special Flood Hazard Area (SFHA) is the area within the 100-year floodplain (refer
to Figure 5.1-3). If a floodway has been defined, it will include the main channel of the
stream or river, and usually a portion of the floodplain. The remaining floodplain within the
SFHA is called the floodway fringe. The floodway is established by including simulated
encroachments in the floodplain that will cause the 100-year flood elevation to increase
one foot (refer to Figure 5.1-4).
Figure 5.1-5 shows an example of a floodway on the flood map. The floodway, as well as
other map features, may have a different appearance on different community flood maps.
Each map will have a legend for the various features on the map.
Floodway
The cross-hatched area. Includes
the most conveyance and highest
velocities.
Zone X (shaded)
Subject to flooding by the 500-
year flood. Zone B on some maps.
Zone X (unshaded)
Outside 500-year floodplain.
The simplest way to be consistent with the NFIP standards for an established floodway
is to design the bridge and approach roadways so that you exclude their components
from the floodway. If a project element encroaches on the floodway but has a very minor
effect on the floodway water surface elevation (such as piers in the floodway), the project
may be considered consistent with the standards if hydraulic conditions can be improved
so that no water surface elevation increase is reflected in the computer printout for the
new conditions. You will prepare a No-Rise Certification and support it by technical data.
Base the data on the original model used to establish the floodway. The FEMA website
has contact information to obtain the original model.
A Flood Insurance Study (FIS) documents methods and results of the detailed hydraulic
study. The report includes the following information:
Name of community
Hydrologic analysis methods
Hydraulic analysis methods
Floodway data, including areas, widths, average velocities, base flood elevations,
and regulatory elevations
Water surface profile plots
The FIS can be obtained from the FEMA website. Note that the report does not include
the original hydraulic model.
For some rivers and streams, a detailed study was performed, but a floodway was not
established (refer to Figure 5.1-6). In this case, the bridge and roadway approaches may
be designed to allow no more than a one-foot increase in the base flood elevation
depending on local regulations and if offsite land use values will not be significantly
impacted (see Section 4.4 of the Drainage Manual). Use information from the FIS and the
original hydraulic model to model the bridge, and submit technical data to the local
community and FEMA.
Zone AE
Subject to flooding by the 100-year flood as
determined by a detailed study.
Zone A
Flooding area determined by approximate
methods.
If the encroachment is in an area without a detailed study (Zone A on Figure 5.1-5 and
Figure 5.1-6), then generate technical data for the project. You should give base flood
information to the local community. Pursuant to NFIP regulations in CFR 60.3(c)(10), no
more than a foot of increase in base flood elevation is allowed for cumulative development
within the floodplain.
Many of these agencies also have implemented mitigation requirements for fill within the
floodplain, because it reduces the storage capacity in the floodplain and may increase
discharges downstream. Therefore, other agencies may require a compensation area that
creates the amount of storage lost due to the roadway approach fill.
The bridge must convey the design frequency without damage (Section 4.2 of the
Drainage Manual).
Backwater for the design frequency must be at or below the travel lanes (Section
4.4 of the Drainage Manual).
The bridge must have adequate debris clearance.
Figure 5.1-7 showsthe relationship between these design frequency criteria and the
geometric design. These criteria tend to create a crest curve on the bridge, with the profile
of the approach roadway lower than the bridge profile. This is a desirable profile because
the roadway will overtop before the bridge is inundated. Losing the roadway is preferable
to losing the bridge.
Backwater criteria also apply for floods other than the design flood:
When the risks associated with a particular project are significant for floods of greater
magnitude than the standard design flood, a greater return interval design flood should
be evaluated by use of a risk analysis. Risk analysis procedures are provided in FHWA
HEC 17 and discussed briefly in Appendix G, Risk Evaluations. Discuss changing the
design frequency with the District Drainage Engineer before making a final decision. In
addition, incorporate or address in the design hydraulic design frequency standards of
other agencies that have control or jurisdiction over the waterway or facility.
Scour analysis and design has a separate design frequency, discussed in Section 4.9 of
the Drainage Manual. You will find national standards for scour design in FHWA HEC 18,
Evaluating Scour at Bridges.
The worst-case condition for scour usually will occur at overtopping of the approach
roadway or another basin boundary. Overtopping flow at the bridge often provides flow
relief, and scour conditions will be a maximum at overtopping.
For more guidance on scour computation and design, refer to Section 5.5 of this
document and the FDOT Bridge Scour Manual.
5.1.4 Clearances
The span lengths of a bridge affect the cost of the bridge, with longer spans generally
increasing the cost. Increased height above the ground increases the cost of the
foundations and the earthen fill of the approach roadways. However, minimum vertical
and horizontal clearance requirements must be maintained to ensure the hydraulic
crossing functions in conformance with the design criteria. Minimum clearances are
addressed in the FDM 210.
5.1.4.1 Debris
The two-foot minimum debris drift clearance used by the Department traditionally has
provided an acceptable level of service. Though this clearance usually is adequate for
facilities of all types, review bridge maintenance records for the size and type of debris
that may be expected. For example, if the watershed is a forested area subject to
timbering activities, anticipate sizeable logs and trees among the debris. Meandering
rivers also will tend to fell trees along the banks, carrying them toward downstream bridge
crossings. On the other hand, bridges immediately downstream from a pump station may
have little opportunity to encounter debris. Also, manmade canals tend to be stable
laterally and will fell many fewer trees than sinuous, moving natural rivers. In such low
debris cases, if a reduced vertical clearance is economically ideal, the hydraulic designer
should approach the District Drainage Engineer to reduce the debris drift clearance.
For new bridges, you should advocate for aligning the piers normal to the flow if there is
a possibility of debris being lodged between the pilings. The debris drift clearance is
shown on the Bridge Hydraulics Recommendation Sheet (BHRS).
5.1.4.2 Navigation
For crossings subject to small boat traffic, the minimum vertical navigation clearance is
set as six feet above the mean high water, normal high water, or control elevation.
Notably, other agencies may require different navigational clearances.
For tidally controlled or tidally influenced bridges, the BHR should document the tidal
datums for the bridge location. This includes not only the Mean High Water (MHW) for
use in navigational clearances, but also any other tidal datums available for the site. If
taken from a tidal bench mark, the BHR should document the bench mark ID as well as
the tidal epoch referenced.
Normal High Water is considered to be equivalent to the mean annual flood. The mean
annual flood is the average of the highest flood stage for each year. For gaged sites, you
can obtain this information from the U.S. Geological Survey (USGS). Statistically, the
mean annual flood is equivalent to the 2.33-year frequency interval (recurrence interval).
Therefore, if you use a synthetic hydrologic method to determine the Normal High Water,
use the 2.33-year event. In some cases, stain lines at the site indicating the normal flood
levels can be used to estimate the Normal High Water.
Obtaincontrol elevations from the regulating agency (Water Management Districts, water
control districts, U.S. Army Corps of Engineers, etc.).
5.1.4.3 Waves
Elevate coastal bridges one foot above the design wave crest, as required in the FDM
210. If the clearance is less than one foot, which often occurs near the bridge approaches,
you must design the bridge according to the Guide Specifications for Bridges Vulnerable
to Coastal Storms, a publication from the American Association of State Highway and
Transportation Officials (AASHTO).
The BHR should demonstrate clearly that the proposed structure length and configuration
are justified for the crossing. Use historical records from the life of the bridge, along with
hydrologic and hydraulic calculations, to make recommendations. Using the same length
as an existing structure that may have been in place for many years is not justification to
use the same bridge length, given that the existing structure may not be hydraulically
appropriate and may not have experienced a significant flooding event.
The most effective way to justify the length of a proposed structure is with the analysis of
alternate structure lengths. Typical alternative bridge lengths that might be appropriate
include:
As the analysis proceeds, the need to analyze another length may become apparent, and
that may turn out to be the proposed structure length.
As stated in Section 4.9 of the Drainage Manual, you must determine the horizontal limit
of protection using the methods in HEC 23. However, a 10-foot width between the top of
the main channel and the toe of spill-through abutment slopes is considered the minimum
width necessary to address the above concerns. For stable banks, make the horizontal
10-foot measurement from the top edge of the main channel. The use of the minimum
berm width does not excuse the drainage engineer from conducting sufficient site analysis
to determine the existence of unusual conditions. If the natural channel banks are very
steep, unstable, and/or if the channel is very deep, or channel migration exists, additional
berm width may be necessary for proper stability. For these conditions, you should make
the horizontal 10-foot measurement from the point where an imaginary 1V:2H slope from
the bottom of the channel intersects the ground line in the floodplain.
In most situations, the structure that provides the minimum berm width often will be the
shortest bridge length considered as a design alternative.
The minimum abutment protection is stated in Section 4.9 of the Drainage Manual. The
standard rubble riprap was sized in accordance with HEC 23 for flow velocities (average)
not exceeding 9 fps, or wave heights not exceeding 3 feet. Determine the horizontal and
Figure 5.1-8 is a plan view that defines the limit of rubble riprap protection. Refer to the
FDOT Structures Detailing Manual for the recommended minimum distance.
In contrast, controlled canals in developed areas typically have very low velocities, no
stability problems, no overbank flow contracting into the bridge opening, and few
abutment maintenance problems. In such cases, the abutment slope usually drops
steeply from the abutment directly into the canal.
Use rubble with a specific gravity of 2.65 or other extra heavy revetment where large wave
attack is expected, typically in coastal applications. Avoid corrodible metal cabling or
baskets in coastal environments; even if coated, the coating may be marred and allow
corrosion. Follow the USACE Shore Protection Manual for design of coastal revetment.
Use bedding stone on all bank and shore rubble installations to guard against tearing of
the filter fabric during placement of the rubble. The bedding stone also helps dissipate
wave impacts on the revetment.
For revetment installations where wave attack is not expected to be significant, include
all options (e.g., fabric-formed concrete, standard rubble, or cabled interlocking block,
etc.) that are appropriate based on site conditions. All options shown to be inappropriate
for the site should be documented in the BHR. Write a technical specification based on
the use of the most desirable revetment material, with the option to substitute the other
allowable materials at no additional expense to the Department. This recommendation
will help in eliminating revetment Cost Savings Initiative Proposals (CSIPs) during
construction.
No matter what options are allowed, match the bedding (filter fabric and bedding stone)
to the abutment material. Some of the options are not self-healing, and a major failure
can occur if loss of the embankment material beneath the protection takes place.
Scour estimates must consider the combined effects of both bridges. Ideally, the
foundation of the new or replacement bridge will be the same type as the other foundation
and will be aligned with the other foundation. In such cases, the scour calculations will be
similar to that of a single bridge.
In some cases, it may not be reasonable to match and align the foundations of both
bridges because of such things as economics, geotechnical considerations, and channel
migration, etc. If the foundation designs are not the same, or are not aligned, or both, the
scour estimates must consider the combined obstruction of both foundations to the flow.
The techniques of HEC 18 do not specifically address this situation. If another approach
is not available, assume a single foundation configuration that accounts for the
obstruction of both foundations and use the techniques of HEC 18. You can develop a
conservative configuration by assuming each downstream pile group is moved upstream
(parallel to flow) a sufficient distance to bring it in line with the adjacent upstream pile
group. Figure 5.1-9 shows some configurations.
For minor widening (defined in Chapter 6 of the FDOT Structures Design Guidelines) of
bridges that have been through the Statewide Bridge Scour Evaluation Process and have
not been identified as scour critical, it is acceptable to leave the existing foundation
without modification. The foundation under the widened portion must be properly
designed to accommodate the predicted scour.
Widening existing bridges often will result in a minor violation of vertical clearances due
to the extension of the cross slope of the bridge deck. Consult the District Drainage
Engineer in documenting justification for deviating from criteria.
Dolphins and fender systems are two structural systems designed to protect piers,
bents, and other bridge structural members from damage due to collision by marine
traffic. Dolphins are large structures with types ranging from simple pile clusters to
massive concrete structures that can either absorb or deflect a vessel collision.
Typically, they are located on both sides of the structure being protected, as shown in
Figure 5.1-10. Fender system types are less variable, consisting usually of pile-
supported wales, as shown in Figure 5.1-11. Fender systems typically wrap around the
protected piers and run along the main navigation channel.
Dolphins
Fender System
For design purposes, you can calculate scour around dolphins in the same manner as
bridge piers. Typically, dolphins are located sufficiently far from the piers so that you can
calculate local scour independently. However, check to ensure there is sufficient spacing
(greater than 10 effective diameters).
Scour at fender systems typically is taken as equal to that of the pier it is protecting. In
some cases, fender systems may “shield” bridge piers, reducing velocities and scour at
the pier. However, this shielding effect can vanish or be modified if the fender system is
lost due to collision or unforeseen scour problems, or if the flow attack angle is skewed
so that the pier is not in the hydraulic shadow of the fender system. Piers and fender
systems introduced into relatively narrow rivers may cause contraction scour between the
fender systems. This scour usually is greatest near the downstream end of the system.
1. Determine the model domain. The geometric data must extend far enough
upstream, downstream, and laterally to provide an accurate representation of the
terrain within the domain. Refer to Section 5.2.4 for guidance.
2. Locate available geometric data within the model domain. You can use liberally
estimated boundaries of the domain when the cost of collecting existing data is
low.
3. Order survey for those portions of the model domain that do not have adequate
coverage from existing geometric data. Survey will be expensive, so estimate the
domain boundaries conservatively.
USGS
o Quadrangle maps
o A public source in both scanned and vector formats is the FDEP Land Boundary
Information System (LABINS) located at: http://www.labins.org/
o Digital Elevation Models (DEMs)
DEMs are essentially x, y, z coordinate points on a 90-meter grid. They were
derived from the Quadrangle Maps. DEMs also are available at LABINS.
o LiDAR
Coverage in Florida is not yet complete. Available data can be downloaded at:
https://lta.cr.usgs.gov/lidar_digitalelevation
U.S. Army Corps of Engineers
o USACE performs hydrographic surveys on navigable waterways, which can provide
main channel information.
o Mobile District: http://navigation.sam.usace.army.mil/surveys/index.asp
o Jacksonville District:
http://www.saj.usace.army.mil/Missions/CivilWorks/Navigation/HydroSurveys.aspx
Florida Department of Emergency Management
o Data for the Florida Coastal LiDAR project and links to other compatible data:
http://www.floridadisaster.org/gis/lidar/
Water Management Districts
Cities and counties
Old plans and BHRs
FEMA studies
o Refer to Section 5.2.1.1 for more information on how to determine if a detailed study
is available.
USGS Quadrangle Maps and DEMs are available for the entire state of Florida. They may
be useful for preliminary analysis and, in some circumstances, you may use them to fill in
gaps farther away from the site.
The remaining data sources usually will have a level of accuracy that was adequate for
hydraulic modeling at the time of collection. However, consider the age of the data. If the
terrain within the model domain has changed significantly, then you must find newer
existing data sources or you will need to order survey.
You may need data from different sources to cover the entire model terrain. Sometimes,
one source will have data within the overbank and floodplain areas, and a different source
will have hydrographic data within the channel. Be sure to convert all data to a common
datum and projection.
Survey can be in either cross section or Digital Terrain Model (DTM) format for one-
dimensional models. Although you can use cross sections to develop two-dimensional
models, a DTM format is preferable. Discuss the survey format with the surveyor to
determine which format is most appropriate.
Always order survey in the immediate vicinity of the proposed bridge. The accuracy needs
in this area are greater than the accuracy needs of the hydraulic model, for two reasons:
2. The approach roadway and bridge abutment, including abutment protection, must
fit within the right of way.
The typical roadway survey will be a DTM within the proposed right of way, and may
extend a minimal distance outside of the proposed right of way. Coordinate with the
roadway design engineer.
Determine the location of the approach and exit cross sections for the model and extend
survey information in the main channel to these locations. Additional survey information
in the adjacent floodplain and farther upstream and downstream of these extents will
depend upon the other available geometric data.
Provide a sketch to the surveyor on a topographic map or aerial showing the limits of the
DTM or the location, orientation, and length of cross sections. Also ask the surveyor for:
When ordering survey, remember that most floodplains in Florida often have dense
vegetation. Surveying in these areas will be difficult. Not all cross sections need to be
surveyed at the actual location used in the hydraulic model. Surveyed cross sections can
be reasonably manipulated into model cross sections, so look for areas that would be
easier to survey, such as along power lines and open fields.
For bridges with foundations in cohesionless sediments (sands and silts), include sieve
analyses in the geotechnical data collection to characterize the size of the bed sediments.
Obtain a sufficient number of samples to confidently characterize the sediment size, both
over the length of the bridge as well as over the thickness of the expected scour layer.
The parameter from the sieve analyses necessary for scour calculation is the median
grain size (D50). NRCS soil surveys can provide an estimated median grain size for
preliminary scour estimates.
For bridges with foundations in cohesive sediments (rock or clay), establish the bed
material’s scour resistance. For rock, the FHWA provides guidelines for scourability of
rock formations in HEC 18 (refer to Chapter 4).
Additionally, the Department has developed a Rock Scour Protocol, which you can find
at:
http://www.fdot.gov/roadway/Drainage/Bridgescour/Bridge-Rock-Scour-Analysis-Protocol-Jan2008.pdf.
The referenced protocol recommends obtaining core borings at each pier for testing at
the State Materials Office. It is your responsibility to follow the protocol procedure when
encountering soils of this type.
For smaller streams where a bridge culvert may be an appropriate hydraulic option,
consider obtaining a preliminary soil boring to determine if increased foundation costs for
the culvert need to be included in the alternatives cost comparisons.
Speak with local residents, business owners and employees, and local officials—
including fire and emergency services—to obtain anecdotal information about past floods.
This information can be very important in the absence of other historical data.
Gage Measurements
In bridge hydraulics analysis, you can use gage data in a number of ways:
To determine the peak flow rates, although the Department usually relies upon
agencies, such as the USGS, to perform statistical analysis of the stream flow data.
Refer to Section 2.2 (Hydrology) for more information.
To provide starting water surface elevations, or boundary conditions, for the model
if the gage is downstream of the bridge. Refer to Section 5.2.4.9 for more
information.
To calibrate the model. Refer to Section 5.2.5.1 for more information.
If the gage is located at a distance from the bridge site, the gage flow rates may not be
the same as the bridge flow rates. However, the gage data still may be useful if the flow
rates can be adjusted. Refer to Section 4.5, Peak Flow Transposition in FHWA Highway
Hydrology, Hydraulic Design Series 2 (HDS-2), for more information.
Gage data also may be available from the Water Management Districts and other local
agencies.
Recent and current aerial photographs can be found at many Internet sites. Be careful of
copyright infringements when using these aerials in the Bridge Hydraulics Report. For this
reason, it is probably best to obtain the photographs from government sites that give free
access.
Older aerial photographs can be obtained from the Aerial Photography Archive Collection
(APAC), maintained by the FDOT Surveying and Mapping Office. APAC archives aerials
dating back to the 1940s. Ordering information is available at the following link:
http://www.dot.state.fl.us/surveyingandmapping/aerialmain.shtm
http://ufdc.ufl.edu/aerials
Another useful site to obtain aerial photography is the FDEP Land Boundary Information
System (LABINS), which can be accessed at the following link:
http://www.labins.org/
Channel profiles usually are created by taking soundings from the bridge deck. Soundings
are measurements taken using a weighted tape measure to keep the tape vertical. The
measurements are the distance from a consistent point on the bridge (usually the bridge
rail) to the stream bed. The measurements are made on both sides of the bridge at each
bridge pier and often at mid-span.
You may be able to find the Phase 1 Scour Evaluation Report for existing bridges. This
report will plot some of the bridge inspection profiles against the cross section from the
original construction, assuming that old plans or pile driving records were available to
obtain the original cross section. The example bridge shown in Figures 5.2-1 and 5.2-2
has a very wide excavated cross section beneath the bridge. This was a common bridge
design practice before dredge and fill permitting requirements brought the practice to an
end unless the required wetland impact was justified and mitigated. In the example, the
widened channel has filled back in and narrowed since the initial construction in 1963.
You can use the channel profiles to determine long-term bed changes at the bridge site.
Figure 5.2-1: Example Bridge Profile from a Bridge Inspection Report (cont.)
Previous Studies
If the project replaces or widens an existing bridge, obtain the BHR or other hydraulic
calculations for the existing bridge, if possible. Other BHRs for bridges over the same
water body also may provide useful information.
If a detailed study was performed by FEMA, then obtain the Flood Insurance Study, the
NFIP Maps, and the original model (refer to Section 5.2.1.5).
Additional sources of existing studies can include the Water Management Districts, the
Florida Department of Environmental Regulation, county offices, and the U.S. Army Corps
of Engineers.
Maintenance Records
Contact the local district or local agency maintenance staff for bridge inspection reports,
historical overtopping, and/or maintenance issues at the bridge site.
You also should gather information on other structures on the river upstream and
downstream of the proposed bridge site, including the size and type of structure for
comparison with the proposed structure.
Backup and supporting data for a detailed study, if the area has a detailed study, also can
be obtained from FEMA. At the time of this writing, this information cannot be ordered
through the website. A data request form must be completed and sent to FEMA. Call the
FEMA Map Service Center for ordering information.
https://www.fema.gov/media-library/assets/documents/7320
Look for channel changes and new tributaries compared to the latest aerial
photographs or maps from the office data collection
Look for evidence of scour in the area of the existing structure and check the
adequacy of existing abutment protection
Check for recent repairs to the existing abutment protection (as compared with
the age of the bridge)
Check for local evidence of overflow or breaching of the approaches
Search the site for evidence of high flood levels, debris, or stains on the structure
that may indicate flood levels
Search for local evidence of wave-induced erosion along the banks
Note the velocity direction through the bridge and estimate the velocities (note
the date and time of these observations)
Photograph the channel and adjacent areas
Seek evidence of the main overflow routes and flood relief channels
Search for hydraulic control points upstream and downstream of the structure
Assess the roughness or flow capacity of the floodplain areas
Consider visiting other structures across the stream or river upstream and downstream
of the proposed bridge site.
5.2.2 Hydrology
In most riverine analyses, you can assume steady-state conditions and perform the
hydraulic analysis using the peak discharge for each frequency analyzed. The peak
discharge may vary at different locations on the stream if there are tributaries within the
reach, but each discharge will be assumed to remain constant with respect to time.
Section 4.7.1 of the Drainage Manual gives criteria for selecting discharges used for
riverine analysis. Further guidance is given in Chapter 2 (Hydrology).
Generally, the length of the structure does not control the hydrology. That is, in general,
a longer structure will not significantly increase the discharge downstream. When
considering the inaccuracies associated with the hydrology, the effect of the structure
length and the resulting backwater (or reduction of backwater) usually will not significantly
affect the amount of water going downstream. However, if you or the regulatory agency
are significantly concerned about this effect, then you should conduct an analysis to verify
the concern. You can calculate the pre- and post-water surface profiles and route them
with an unsteady flow model.
Mild stream slopes less than two feet per mile. If the slope is greater than five feet
per mile, steady flow can be used. For slopes between these values, consider the
cost and complexity of an unsteady model versus the cost importance of the
bridge.
Situations with rapid changes in flow and stage. Models of dam breaks are the
primary example of this situation.
Bifurcated streams (streams where the flow divides into one or more channels and
recombines downstream).
You can find more information on these situations in USACE Manual EM 1110-2-1416
(15 October 1993), River Hydraulics.
HEC-RAS and WSPRO both are suitable to analyze one-dimensional, gradually varied,
steady flow in open channels, and you also can use them to analyze flow through bridges
and culverts, embankment overflow, and multiple-opening stream crossings. HEC-RAS
has the additional capability of analyzing unsteady flow.
The WSPRO program analyzes unconstricted valley sections using the standard step
method, and incorporates research for losses across a bridge constriction. HEC-RAS
allows the user to select the method used to analyze the bridge losses, including energy
(standard step), momentum, Yarnell, and WSPRO methods. Both programs allow you to
readily analyze alternate bridge openings. The output provides water surface elevations,
bridge losses, and velocities for both the constricted (with bridge) and the unconstricted
(with no bridge) condition. You can use this information to estimate the backwater effects
of the structure and provide input information for scour analysis.
The most commonly used two-dimensional models are FESWMS and RMA 2. The Finite
Element Surface Water Modeling System (FESWMS) was developed originally for FHWA
and the USGS. The FHWA has continued to maintain and sponsor development of
subsequent versions, which continue to incorporate features specifically designed for
modeling highway structures in complex hydraulic environments. As such, it includes
many features that other available two-dimensional models do not have, such as pressure
flow under bridge decks, flow resistance from bridge piers, local scour at bridge piers,
live-bed and clear-water contraction scour at bridges, bridge pier riprap sizing, flow over
roadway embankments, flow through culverts, flow through gate structures, and flow
through drop-inlet spillways. FESWMS can perform either steady-state or unsteady flow
modeling.
Geometric data
Flow data (upstream boundary)
Loss coefficients
Starting water surface elevations (downstream boundary)
Geotechnical data (D50 soils information)
Upstream
At a minimum, the upstream boundary should be set far enough upstream of the bridge
to encompass the point of maximum backwater caused by the bridge. If a point of concern
where the water surface elevation must be known is farther upstream, then the model
must be extended to that point. An example would be upstream houses or buildings
because the 100-year water surface elevation must be kept below their floor elevation.
Check with permitting agencies, including cities and counties, as some have limits on the
amount of backwater allowed at a given distance upstream.
The following equation can be used to determine how far upstream data collection and
analysis needs to be performed.
where:
Lu = Upstream study length (along main channel), in feet for normal depth starting
conditions
HD = Average reach hydraulic depth (1-percent chance flow area divided by cross
section top width), in feet
S = Average reach slope, in feet per mile
HL = Head loss, ranging between 0.5 feet and 5.0 feet at the channel crossing
structure for the 1-percent chance flow
The values of HD and HL may not be known precisely since the model has not yet been
run to determine these values. They can be estimated from FEMA maps, USGS
Quadrangle Maps (or other topographic information).
Downstream
Open channel hydraulics programs must have a starting water surface elevation specified
by the user at the downstream boundary of the model.
The programs allow for one or more of the following methods of specifying the starting
water surface elevation:
The modeler must decide which method to use, and the decision will affect the distance
to the downstream boundary of the model.
For the storm frequency being modeled, if a point of known water surface elevation is
within a reasonable distance downstream, extend the model to that point. Refer to the
section below on convergence for guidance on determining if the point is within a
reasonable distance.
Gages are points with a known relationship between the discharge and the water surface
elevation. Lakes and sea level also can be points of known elevation. Other locations
where you can calculate the water surface elevation from the discharge can include weirs,
dams, and culverts if these locations are not significantly influenced by their tailwater.
When the downstream channel and overbank are nearly uniform, use the normal depth
assumption to determine the starting water surface elevation, both in cross section and
slope, for a long reach downstream. The length of uniform channel that will be adequate
will vary with the slope and properties of the channel. This reach should not be subject to
significant backwater from farther downstream. The following equation can be used to
determine how far downstream data collection and analysis needs to be performed.
where:
Ldn = Downstream study length (along main channel), in feet for normal depth starting
conditions
HD = Average reach hydraulic depth (1-percent chance flow area divided by cross
section top width), in feet
S = Average reach slope, in feet per mile
Make some sound engineering judgment when determining the variables HD, S, and HL.
Guidelines are presented below:
a. Average reach hydraulic depth (HD): If limited existing data are available, an
estimate can be made using FEMA maps and quadrangle maps. Using the FEMA
map, outline on the Quadrangle Map the boundary of the 1-percent chance flow.
Select a representative location and plot a cross section using the Quadrangle
Map. Plotting several cross sections may improve the estimate. The area (A), top
width (TW), and, thus, the hydraulic depth (A/TW) for these cross sections are now
determined. Average these hydraulic depths to determine an average reach
hydraulic depth. Use survey data or other existing geometric data that are more
accurate than the Quadrangle Maps if available.
b. Average reach slope (S): Using the Quadrangle Maps, determine and average
the slope of the main channel, left overbank, and right overbank.
c. Head loss (HL): This term also is known as the "backwater.” Backwater is defined
as the difference in the water surface elevation between the constricted (bridge)
flow condition and the unconstricted (no bridge) flow condition at a point of interest
upstream of the structure crossing. Make an educated guess at the anticipated
head loss. For a new bridge, the allowable head loss would be a reasonable
estimate. In most cases, a maximum head loss of one foot would be expected for
Florida.
Lateral Extents
Extend the model laterally on both sides of the floodplain to an elevation that is above the
highest water surface elevation that will be modeled. Often, this water surface elevation
will be unknown until the model is complete. But you must collect data to complete the
model. So, you must estimate the water surface elevation and lateral extent for the data-
gathering effort. You can estimate the elevation or the lateral extent from FEMA maps
and other historical studies of the site. In some cases, it is appropriate to set up a
preliminary model based on limited data to estimate the water surface elevations.
Whichever method you use to estimate the lateral extent of the model, consider making
a conservative estimate to avoid additional data gathering at a later time, especially
survey data.
1. Guide for Selecting Manning’s Roughness Coefficients for Natural Channels and
Flood Plains, USGS Water-Supply Paper 2339 (replaces Report Number FHWA-
TS-84-204), which can be accessed at the following link:
http://www.fhwa.dot.gov/bridge/wsp2339.pdf
2. Estimating Manning's Roughness Coefficients for Natural and Man-Made Streams
in Illinois, USGS and Illinois Department of Natural Resources.
http://il.water.usgs.gov/proj/nvalues/
Roughness values from previous models or studies can be useful. However, you should
verify these roughness values because conditions may have changed.
Roughness values can be varied within reasonable limits representative of the physical
conditions of the site to calibrate the hydraulic model.
One-Dimensional Models
One-dimensional models use cross sections to define the geometry of the channel and
floodplain. There are several good references you can use as guidelines to locate and
subdivide the cross sections. One good source is Computation of Water-Surface Profiles
in Open Channels, by Jacob Davidian: USGS—Techniques of Water-Resources
Investigations Reports, Book 3, Chapter A15, 1984. This publication can be downloaded
from: http://pubs.usgs.gov/twri/twri3-a15/pdf/twri_3-A15_b.pdf.
d. Take cross sections normal to the flood flow lines. In some cases, you may need
to “dog leg” cross sections. Figure 5.2-5 illustrates this procedure.
e. Place cross sections at closer intervals in reaches where the conveyance changes
greatly as a result of changes in width, depth, or roughness. The relation between
upstream conveyance, K1, and downstream conveyance, K2, should satisfy the
criterion: 0.7<(K1/K2)<1.4.
f. Avoid areas with dead flow, eddies, or flow reversals.
g. Extend cross section ends higher than the expected water surface elevation of the
largest flood that is to be considered in the sub-reach.
h. Place cross sections between sections that change radically in shape, even if the
two areas and the two conveyances are nearly the same.
i. Place cross sections at shorter intervals in reaches where the lateral distribution
of conveyance in a cross section changes radically from one end of the reach to
the other, even though the total areas, total conveyance, and cross sectional shape
do not change drastically. Increasing the number of subdivisions generally will
increase the value of alpha, and, therefore, increase the velocity head. Spacing
the cross sections closer together will help prevent drastic changes in the velocity
head.
Subdivisions of cross sections should be done primarily for major breaks in cross-
sectional geometry. Major changes in the roughness coefficient also may call for more
subdivisions.
(A) Conveyance
Conveyance is a measure of the ability of a channel to transport flow. In streams of
irregular cross section, it is necessary to divide the water area into smaller but more or
less regular subsections, assigning an appropriate roughness coefficient to each, and
computing the discharge for each subsection separately. By rearranging the Manning’s
Equation, the following relationship is derived:
q 1.49 2/3
k= 1/2
= ar (Equation 1)
S n
where:
k= Channel subsection conveyance
q= Subsection discharge, in cubic feet per second
S = Channel bottom slope, in feet/feet
n= Manning's roughness coefficient
a= Subsection cross-sectional area, in square feet
r= Subsection hydraulic radius, in feet
Solution:
Step 1: Compute the area, hydraulic radius, and conveyance for each of
the subareas:
Subarea 1:
a1 = 10 ft. * 2 ft = 20 ft2
wp1 = 10 ft. + 2 ft. = 12 ft.
r1 = a1/wp1 = 20 ft2/12 ft. = 1.67 ft.
1.49 1.49
k1=
2/3
a1 r 1 = (20 ft .2 ) (1.67 ft. )2/3 = 419.5
n1 0.1
Subarea 2:
1.49 1.49
k2=
2/3
a2 r 2 = (280 ft .2 ) (5.60 ft. )2/3 = 32890.9
n2 0.04
Subarea 3:
1.49 1.49
k3 =
2/3
a3 r 3 = (20 ft .2 ) (1.67 ft. )2/3 = 419.5
n3 0.1
b. Assuming the total discharge for the water surface elevation of 107.0 feet in part
(a) is 4,000 cubic feet per second, determine the discharge distribution for each
subarea.
Solution:
Subarea 1:
k1 419.5
Q1 = * Qtotal = ( )* 4000 ft 3 /s = 49.8 ft 3 /s
k total 33729.9
Subarea 2:
k2 32890.9
Q2 = * Qtotal = ( )* 4000 ft 3 /s = 3900.5 ft 3 /s
k total 33729.9
Subarea 3:
k3 419.5
Q3 = * Qtotal = ( )* 4000 ft 3 /s = 49.8 ft 3 /s
k total 33729.9
Q2
hv =
2g A2
where:
As the velocity distribution in a river varies from a maximum at the deeper portion of the
channel to essentially zero along banks, the average velocity head, computed as
(Q/A1)2/2g, does not a give a true measure of the kinetic energy of the flow. You can
obtain a weighted average value of the kinetic energy by multiplying the average velocity
head above by a kinetic energy coefficient (1) defined as:
(qv 2)
1 = 2
Qv1
where:
1 = Kinetic energy coefficient, before the bridge
q= Discharge in a subsection, in cubic feet per second
v= Average velocity in same subsection, in feet per second
Q = Total river discharge, in cubic feet per second
v1 = Average velocity in river at Section 1, or Q/A1, in feet per second
In general, the more subdivisions in a cross section, the higher the alpha (α) value.
The energy equation for flow along a channel includes a term for the kinetic energy or
velocity head, V2/2g. Use the average velocity, V, for the entire cross section in the
equation. In reality the velocity is not a constant value. It is highest in the middle of the
channel near the water surface and lowest at the edges of the channel near the channel
bottom. Using the average velocity in the equation means that the sum of the differing
velocities in the cross section is being squared, (v1 + v2 + … + vn)2. However, to correctly
determine the kinetic energy, you should first square the differing velocities and then sum
them, v12 + v22 + … + vn2. Since the sum of the squares is greater than the square of the
sum, you will need to use the kinetic energy correction factor. This factor usually is
represented by the Greek letter alpha in the energy equation, and is, therefore, referred
to as alpha for short.
Alpha values are calculated and reported for each cross section in both HEC-RAS and
WSPRO. However, neither program provides warnings when alpha values are out of
range. Incorrect alpha values can cause significant errors. Check the alpha values to be
sure they are appropriate.
Alpha values typically should stay in the ranges shown in Table 5.2-1. In general, the
more subdivisions in a cross section, the larger alpha will become. Alpha values greater
than 3 should be checked. If adjacent cross sections have comparable values, or if the
changes are not sudden between cross sections, such values can be accepted. But if the
change is sudden, some attempt should be made to obtain uniformity. Consider the
following:
The following examples illustrate the importance of proper subdivision, as well as the
effects of improper subdivision.
Given:
K = 1.49/n (AR2/3)
n is constant over cross section
Factor out 1.49 and compare AR2/3 = K feet
Method 1: Consider K1 feet as one section encompassing subareas “A,” “B,” and “C.”
2/3
2/3 (6x10) + (50x0.2) + (50x0.15)
K 1 '= AR ; K 1 ' = [(6x10) + (50x0.2) + (50x0.15)] = 57.3
(0.1 50 50 5.8 10 6)
Method 2: Consider K2 feet as two sections, “A” and “B” combined and “C.”
2/3
2/3 (50x0.2) + (50x0.15)
K 2 = [(6x10) (60/21.8) ] + [(50x0.2) + (50x0.15)] = 117.8 + 5.5 = 123.3
100.1
Method 3: Consider K3 feet as section “C” and ignore sections “A” and “B.”
2/3
60
K 3 (6 10) 117.8
5.8 10 6
Method 4: Consider K4 feet with “A,” “B,” and “C” treated as independent sections.
K 4 [(6 10)(60 / 21.8) 2 / 3 ] [(50 0.2)(10 / 50) 2 / 3 ] [(50 0.15)(7.5 / 50.1) 2 / 3 ]
K 4 117.8 3.4 2.1 123.3
Method 1 is incorrect. The problem is the method neglects the impact the hydraulic radii
of the shallow areas have on the overall flow calculation. This can be seen by looking at
method 3, which shows conveyance in just the main channel as being greater. Two
reasons why method 1 is incorrect are:
Method 2 is correct. It combines subareas of the channel cross section that have similar
hydraulic properties to yield a reasonable answer of total conveyance. If n values between
section “A” and “B” were significantly different, combining them to determine conveyance
might not provide the desired accuracy.
Method 3 is incorrect but exemplifies how easily you can underestimate total conveyance
by not considering the conveyance from the other subareas. Obviously, the total
conveyance cannot be less than that contained in one section.
Method 4 is correct. This may be considered overkill, but technically it is the most accurate
solution. If n values were significantly different between section “A” and “B,” this type of
subdivision for determining conveyance would be essential.
hf = L Sf
where:
L= Flow length, in feet
Sf = Average friction slope, in feet/feet
You can calculate the average friction slope using either the geometric mean slope
method, the average conveyance method, the average friction slope method, or the
harmonic mean friction slope method. WSPRO uses the geometric mean slope method
as the default option. The geometric mean slope is computed as:
2
[0.5 (Q1 + Q2)]
Sf =
K1 K 2
where:
Sf = Average friction slope, in feet/feet
Q1 = Discharge at Section 1, in cubic feet per second
Q2 = Discharge at Section 2, in cubic feet per second
K1 = Conveyance at Section 1
K2 = Conveyance at Section 2
he = k e (hv 2 - hv1)
where:
kc = Expansion loss coefficient
hV1 = Velocity Head in Section 1, in feet
hV2 = Velocity Head in Section 2, in feet
The expansion loss coefficient varies from 0.0 to 1.0 from ideal transitions to abrupt
transitions. HEC-RAS uses an expansion value of 0.3 as its default. WSPRO uses an
expansion value of 0.5 as its default. Brater and King’s Handbook of Hydraulics provides
additional guidance for selection of expansion coefficients.
Contraction Losses
Compute the contraction loss as follows:
hc = k c (hv 2 - hv1)
where:
kc = Contraction loss coefficient
hV1 = Velocity Head in Section 1, in feet
hV2 = Velocity Head in Section 2, in feet
The contraction loss coefficient varies from 0.0 to 0.5 from ideal transitions to abrupt
transitions. HEC-RAS uses a contraction value of 0.1 as its default. WSPRO uses a
contraction value of 0.0 as its default. Brater and King’s Handbook of Hydraulics provides
additional guidance for selection of contraction coefficients.
Energy Equation
Write the energy equation between two adjacent cross sections as follows:
h1 + hv1 = h2 + hv 2 + hf + he + hc
where:
h1 = Water surface elevation in Section 1, in feet
hV1 = Velocity head in Section 1, in feet
h2 = Water surface elevation in Section 2, in feet
hV2 = Velocity head in Section 2, in feet
hf = Friction loss between Sections 1 and 2, in feet
he = Expansion loss between Sections 1 and 2, in feet
hc = Contraction loss between Sections 1 and 2, in feet
It is not possible to find a direct solution of the above equation when either h1 or h2 is
unknown, since the associated velocity head and the energy loss terms also are then
unknown. Therefore, an iterative procedure must be used to determine the unknown
elevation. The WSPRO model computes the difference in total energy between two
sections, H, as:
Use successive estimates of unknown elevations to compute the unknown velocity head
and the energy loss terms until the equation yields an absolute value of ∆H that is within
an acceptable tolerance. Generally, a tolerance between 0.01 and 0.05 is sufficient to
obtain satisfactory results. Slightly higher results may be satisfactory for some higher-
velocity situations. However, if a tolerance value exceeding 0.1 is required to obtain a
satisfactory solution, then there would be reason to suspect data inadequacies (example:
insufficient cross sections).
Computational Procedure
Given: Discharge Q and WSE at one cross section and the fact that the flow is
subcritical. We want to compute the WSE at the next upstream cross section.
Step 1: Calculate all the geometric and hydraulic properties of the downstream most
station using the known flows and WSE at that location.
Step 4: Determine energy losses that correspond to estimated water surface elevation.
Step 5: Calculate water surface elevation using energy equation and energy losses
determined in Step 4.
Step 7: If the computed and estimated elevations do not agree within some
predetermined limit of error, try another value and start the procedure again
beginning with Step 2.
a) b) c)
Figure 5.2-10: Example of (a) Cartesian, (b) Rectilinear, and (c) Curvilinear Grids
Resolution specification for finite difference models is more challenging than with finite
element models. For models that can employ curvilinear or rectilinear grids, resolution
can be increased in a few select locations. By nature of the grids, however, this resolution
propagates in both ordinal directions from the area of interest through the remainder of
the grid. For Cartesian grids, the resolution of a grid is uniform throughout the domain.
Thus, the resolution at the bridge location will dictate the resolution for the remaining
domain. For large domains requiring fine resolution at the bridge location, a common
technique is to employ a nested grid scheme.
After specifying the model resolution, the final step in preparing the model geometry
involves specifying the elevations at the model element nodes. Again, this is typically
performed with automated mesh generation programs that interpolate a survey data set
onto the prepared grid or mesh. This step can sometimes lead to interpolation errors
depending upon the relative resolution of the survey data and the model grid/mesh as
well as the quality of the TIN (triangular irregular network) representing the survey data.
Careful examination of how well the grid/mesh represents the elevations of the model
domain is an important part of the model calibration process.
Downstream Stage
Specify the stage at the downstream cross section. Known water surface elevations are
the first choice. These can be lake levels, sea levels, or control sections such as a gage,
studies (e.g., FEMA), or critical depth sections.
You can use normal depth in many cases when the stream channel is nearly uniform for
a fairly long reach. You can use HEC-RAS or WSPRO to compute the normal depth by
providing an energy slope equal to the channel slope. This method also is known as
“slope conveyance.” Determine the channel slope using a USGS Quadrangle Map.
Determine the slope below the last downstream cross section where contour lines cross
the stream channel. You can use other estimates of energy slope; however, the resulting
water surface elevation would not be “normal depth.”
When there is no gage information available and when normal depth flow (slope
conveyance) cannot be assumed at the bridge site, you should use “convergence.”
Convergence
Water surface profiles will converge to a single profile if given enough distance to
converge. The distance depends on the channel and overbank properties and the slope
of the river. Estimate the distance as the downstream study length described in Section
5.2.4.1.
should represent the range outside of which the water surface is unlikely to be.
Refer to Figure 5.2-13.
c. The computed profiles will converge toward the true profile. The profiles should
converge within an acceptable tolerance by the first section of interest in the reach
(see Figure 5.2-13). If the profiles do not adequately converge, then you should
obtain additional geometric data downstream.
Constriction of the flow causes a loss of energy, with the greater portion occurring in the
re-expansion downstream. This loss of energy is reflected in a rise in the water surface
and in the energy line upstream of the bridge. This is best illustrated by a profile along the
center of the stream, as shown in Figure 5.2-15 (Part A). The dashed line labeled "normal
water surface" represents the normal stage of the stream for a given discharge before
constricting the channel. The solid line labeled "actual water surface" represents the
nature of the water surface after constriction of the channel. Note that the water surface
starts out above normal stage at Section 1, passes through normal stage close to Section
2, reaches minimum depth in the vicinity of Section 3, and then returns to normal stage a
considerable distance downstream, at Section 4. Determination of the rise in water
surface at Section 1 is denoted by the symbol h1* and referred to as the bridge backwater.
Roughness
The roughness around and under the bridge can be significantly different than the
roughness upstream and downstream due to rubble riprap protection and clearing of trees
and underbrush. The main channel roughness often is the same through the bridge from
upstream to downstream. The most common reason that the roughness will change is if
there is a significant extent of rubble riprap protecting the piers or channel banks.
Many Florida floodplains are heavily vegetated. Many riverine bridges span a significant
length across the floodplain. The area beneath the bridge often is cleared of the trees and
underbrush, and is maintained that way. This will reduce the roughness. However, rubble
protection of the abutment will increase the roughness. The guidelines for subdivision
(refer to Section 5.2.4.3) usually would recommend against subdividing at the toe of the
abutment, so a weighted roughness should be determined.
Nodes and elements in two-dimensional models can be placed such that abrupt
roughness changes do not bisect elements.
Bridge Routine
Refer to HEC-RAS documentation for cross section location information. However, if you
are using the WSPRO bridge routine when modeling in HEC-RAS, don’t follow the
documentation; instead, use the following recommendations.
The bridge routine in WSPRO uses the Standard Step Backwater Method, only with more
complexity. The bridge hydraulics is based on the reach from the exit section to the
approach section, as defined in the WSPRO Manual. Although the manual specifies "one
bridge length,” this does not mean the exit section must be exactly one bridge length
downstream from the full-valley section or that the approach section must be exactly one
bridge length (plus roadway width) upstream from the Full-Valley section. The locations
of these sections can vary as follows.
Exit Section:
The exit section can be located no less than, but as much as 10 percent greater than,
one bridge length from the full-valley section. See Figure 5.2-16.
Approach Section:
The approach section can be located as much as 15 percent less than or greater than
one bridge length plus the roadway width from the upstream face of the bridge. See Figure
5.2-17.
If, for some reason, it is impossible to follow the cross section requirements, you may
need to analyze the site without using the bridge routine.
Piers
You can model single-row pile-bent bridges without modeling the piles and the hydraulic
results will be the same as if they were included. However, regulatory agencies may want
to see the piles included in the model. As the blockage becomes greater for more complex
piers, the hydraulic results will change.
5.2.5 Simulations
5.2.5.1 Calibration
Calibration involves changing the value of coefficients until the model results match
observed field conditions for one or more known events. When the model has been
calibrated to known events, then you can model an unknown event, such as the design
frequency event, with more confidence.
Generally, the most reliable source of information is gage data. Most gages used in
riverine situations measure the water surface elevation. Figure 5.2-18 shows a simple
staff gage that you must observe and record manually. More complex gaging stations will
record stages automatically and either store the records for later download or transmit the
data using telemetry.
You can determine discharges indirectly from the water surface elevations. Traditionally,
you would use a velocity meter to take measurements at intervals across the stream and
then determine the discharge, as shown in Figure 5.2-19. When you have determined the
discharge at enough different water surface elevations, you can establish a stage versus
discharge relationship for the gage.
More recently, discharges have been measured on some larger rivers with an Acoustic
Doppler Current Profiler mounted on a boat (see Figure 5.2-20).
The primary benefit of a gage is to establish the discharge for an observed flood. If a gage
is located within the model reach, then the gage also can supply stage and velocity
information at one point in the model.
Occasionally, the Department and agencies such as USGS, FEMA, DEM, or the Water
Management Districts may have surveyed or collected high water marks following a flood.
Contacting them is an avenue to pursue.
If a gage is not available to determine the discharge of the known event, then estimating
the discharge associated with the various high water marks will be difficult or impossible.
Obtaining rain gage information for the flood and estimating the runoff from the rainfall is
an option, assuming data from a suitable rain gage are available. Otherwise, the high
water marks can only be compared to the computed design frequency profiles from the
model to check the magnitudes for reasonableness.
Figure 5.2-22: Local Resident indicating Flood Level on the Caloosahatchee River near
LaBelle in 1913
After you obtain available gage data and/or high water mark elevations, the next step is
to develop the hydraulic model for the existing site conditions. In some situations, this
might entail creating multiple existing-condition models if the site conditions have
changed since some of the calibration floods. Develop the model using standard guidance
for the coefficients used in the model. Then compare the initial model results to the high
water marks and adjust the coefficients. The common coefficients to adjust are:
Manning’s roughness coefficient is the basic adjustment tool for unobstructed reaches.
Considerable uncertainty exists when estimating roughness values. Estimates by
experienced hydraulics engineers often vary by ± 20 percent (from USACE EM 1110-2-
1416). If you hold the channel roughness constant and vary the overbank roughness, you
should be well served.
Also, remember that Manning’s roughness varies with depth, which can affect calibration
as follows:
Do not adjust the calibration coefficients outside of their normal ranges. If the calibration
attempts are not acceptable, re-examine the model. Common model parameters to
review if calibration is a problem include:
Note that calibration problems can be caused by different issues. Use your best judgment
in the calibration process. There is no universally accepted procedure or criterion for
calibration.
Calibrating unsteady flow models is more difficult than calibrating steady flow models.
Adjust to steady flow conditions first, if possible. Unsteady flow models need to be
calibrated over a wider range of flows than steady-state models. Storage in the system is
an important parameter for unsteady flow, and essentially can be used as an adjustment
parameter. For more detail on techniques for unsteady flow calibration, refer to USACE
Manual EM 1110-2-1416, River Hydraulics.
Two-dimensional models have eddy viscosity, or turbulent loss coefficient, that becomes
another calibration parameter. This term in essence replaces expansion and contraction
losses in a one-dimensional model. However, there is not an established correlation
between the two losses. The best way to calibrate eddy viscosity is with measured
velocities. Remember that the two-dimensional velocity is depth-averaged, so you must
convert the measured velocity to a depth-averaged velocity for comparison. Set the value
high first, and then lower it until you obtain the ideal velocity distribution. The general
order of calibration for two-dimensional models would be to calibrate roughness values
to observed water surface elevations, and then adjust eddy viscosity to observed
velocities.
When using both velocities and stages for calibration, check for internal consistency of
the observed data. The velocity times the area for the stage should be approximately
equal to the discharge.
Usually, you will evaluate and select the length of the bridge and the location of the
abutments in the Bridge Hydraulics Report. Traditionally, at least three lengths are
analyzed. One is the minimum hydraulic structure, the bridge that creates no more than
one foot of backwater and does not violate other allowable water surface conditions.
Another bridge length examined is the bridge that spans all wetlands. Other potential
bridge lengths to investigate include:
Other considerations when designing and modeling the proposed conditions are:
Place the bridge in a crest vertical curve, if possible. Allowing the approach
roadways to overtop more frequently than the bridge will provide relief for the
bridge, and reduce the possibility of damage to the structure. If a portion of the
roadway is damaged, it usually can be repaired more easily than the bridge.
Try to center the bridge over the main channel of the flow. At a minimum, set the
toe of the abutments 10 feet back from the top of the channel bank.
Consider skewing the abutments and intermediate bents to align with the flood flow
direction to reduce scour potential.
Bathymetric and topographic data from the National Geophysical Data Center
(http://www.ngdc.noaa.gov/mgg/bathymetry/relief.html, Example: Figure 5.3-1
Digital Elevation Models from the FDEP Land Boundary Information System
website (http://www.labins.org/mapping_data/dem/dem.cfm)
Be careful when combining data from several sources. There can be wide ranges in
accuracy due to differing measurement techniques and survey dates. Pay close attention
to conversion between different horizontal and vertical coordinate systems. Examine
boundaries between survey data sets for inconsistencies and corrections.
The accuracy and density of survey data become more important near the site of interest.
This is especially true of bathymetry for wave modeling when you expect depth limitation
to govern wave conditions.
Several other tidal datums are available, and you should document them for each tidally
controlled or influenced project.
The east coast of Florida experiences semi-diurnal tides and the panhandle experiences
diurnal tides. The coastline from the tip of the peninsula to Apalachicola experiences
mixed tides—tides characterized by a conspicuous diurnal inequality in the higher high
and lower high waters and/or higher low and lower low waters. Figure 5.3-2 and Table
5.3-1 display an example of tidal bench mark information and gage data (with tidal
datums) for Key West, Florida.
Table 5.3-1: Elevations of Tidal Datums in ft-NAVD88 for NOAA Tidal Bench Mark
#8724580 (Key West, FL) for the 1983-2001 Tidal Epoch
1
Spring Tides
0.5
0 MHHW
MHW
Elevation (ft-NAVD)
-0.5
MSL
-1 MTL
-1.5 MLW
MLLW
-2
Neap Tides
-2.5
-3
6/26 7/16 8/5 8/25 9/14 10/4
Date
Gage Measurements
Gage measurements provide information both for model calibration and model boundary
conditions. Several sources of gage data are available to the public. The types of gage
measurements typically employed in tidal analyses include:
Data sources of streamflow and river stage records are the same as those discussed for
riverine analyses.
You also can employ tide gage data for development of model boundary conditions, as
well as for model calibration. Tide gages record stages at a fixed location in tidally
influenced areas. NOAA maintains gages throughout the state. You can access both
recent and historic data online at http://www.co-ops.nos.noaa.gov/. In Florida, the site
provides data at 29 active stations (Figure 5.3-3) and historic data at 722 locations.
Used to calibrate data for wave models, wave gage data typically is much more rare than
either streamflow or stage records. The National Data Buoy Center (NDBC)—a part of
the National Weather Service (NWS)—designs, develops, operates, and maintains a
network of data-collecting buoys and coastal stations. Several of these stations measure
wave parameters, including significant wave height, swell height, swell period, wind wave
height, wind wave period, swell wave direction, wind wave direction, wave steepness,
and average wave period. The NDBC website (http://www.ndbc.noaa.gov/) provides both
recent and historical observations at several locations around Florida (Figure 5.3-4).
Figure 5.3-5 provides an example of these data as time series of significant wave heights.
Sources of wave gage data for interior waters (such as bays, estuaries, intracoastal
waterways, etc.) are much harder to locate. Possible sources may include previous
studies and academic institutions.
10
Significant Wave Height (m)
0
8/16/2005 9/5/2005
Date
Figure 5.3-5: Example of Wave Gage Data at NDBC Station 42039 during Passage
of Hurricane Katrina
You often can find high water marks near each other and they can vary widely in elevation.
Surge-only high water marks occur only where the structure is at a location sheltered from
waves. As waves propagate inland during a surge, the high water conditions on structures
and land can vary widely. When the crest of the wave rides on the surge, this creates
coastal wave height flooding. Thus, differences will occur between high water marks
measured on the interior and exterior walls of a structure. Finally, wave run-up high water
marks include the effects of waves breaking on sloping surfaces. After a wave breaks on
a beach or sloping surface, a portion of the remaining energy will propel a bore that will
run up the face of the slope. The vertical distance the bore travels above the still water
level is termed the wave run-up. Wave run-up often pushes debris to its maximum limit,
where it is left as a wrack line (a line of debris illustrating the extent of the wave run-up).
Hurricane History
The hurricane history of the project location characterizes the hurricane frequency at the
project, as well as the historical impacts to the site location. Including this information in
the Bridge Hydraulics Report elevates the importance of examining hurricane surge and
wave impacts, providing a qualitative examination of the frequency of hurricane influences
at the bridge site. Additionally, it can provide a tool for comparing the selected calibration
hurricane to the overall activity for the area. The BHR should include the historical
hurricane paths, historical storm year, and category, as well as discussion of significant
storms to impact the area. An example of the hurricane paths and listing of the historical
hurricanes is displayed in Figure 5.3-6 and Table 5.3-2 (from
https://coast.noaa.gov/hurricanes/).
Figure 5.3-6: Hurricane and Tropical Storm Tracks Passing within 50 Nautical
Miles (nmi) of Miami (Source: NHC)
Figure 5.3-7: Heckscher Drive (SR-A1A) near Ft. George Inlet in 1969
Figure 5.3-8: Heckscher Drive (SR-A1A) near Ft. George Inlet in 2000
Previous Studies
Previously performed studies of a waterway can provide additional sources of data. Refer
to Section 5.2.1.3 for sources and discussion of previous studies.
The USACE reference, Engineering and Design Storm Surge Analysis EM 1110-2-1412
(1986), provides a methodology for estimating rainfall associated with landfalling
hurricanes. The methodology applies to the area within 25 miles of the coast. It provides
graphs of point rainfall depth for a given frequency and a given distance from the left or
right of the storm track. The rainfall varies uniformly along the coast for any given storm.
Also, the rainfall depths are uniform along any line parallel to the storm track extending
across the 25-mile-wide zone. The reference provides point rainfall graphs (Figure 5.3-
10) for selected frequency levels at either 6-hour or 12-hour intervals before landfall and
after landfall. The reference provides techniques for estimating rainfall associated with
hurricanes traveling at high, moderate, and slow speeds by multiplying the rainfall from
the graphs by a ratio coefficient that is a function of area.
Alternatively, as a rule of thumb, you may assume a steady 10-year discharge over the
duration of the surge. This is likely to be conservative in light of a recent examination of
hurricane rainfall in North Carolina that suggests that a two-year rainfall well represented
historical storms in that state (OEA, 2011). Bridges over streams with short times of
concentration (< four hours) are more likely to have coincidence between the storm surge
passage and high runoff values. Historical review of the timing and magnitude of runoff
at gaged locations near the project site can provide additional insight into the appropriate
return period flow rates for boundary conditions. At a minimum, you should perform a
sensitivity study to characterize the influence of the runoff magnitude on the flow
properties at a subject bridge during a surge event.
Figure 5.3-10: Rainfall for Selected Frequency Levels for Six Hours before
Landfall (Source: USACE 1986)
Weigh all the factors mentioned above and select the appropriate model for the
application. NCHRP Web-Only Document 106: Criteria for Selecting Hydraulic Models
(Gosselin et al., 2006) provides a decision analysis tool and guidelines for selecting the
most appropriate numerical model for analyzing bridge openings in riverine and tidal
systems. The decision tool takes the form of a decision matrix that incorporates all the
factors that influence model selection, including site conditions, design elements,
available resources, and project constraints. The utility of the decision tool is that it
presents a formal procedure to apply for the selection of the appropriate model rather
than an intuitive process.
Figure 5.3-11 presents an example where an engineer is selecting between one- and two-
dimensional models. The figure shows the scoring and weighting of different aspects of
the project, with the final selection of the one-dimensional model based largely on
advantages in scheduling. The selection procedure provides an easy-to-understand and
defensible method for presentation to non-technical readers or policy makers. Also,
through its application, it clearly identifies which features of the project are most important
in the model selection for a specific application.
For tidal analyses, in general, one-dimensional modeling works well for waterways with
well-defined channels in areas that are not subject to lateral overtopping. An example
would include rivers or canals that discharge directly to the open coast (e.g., Suwannee
River, Florida Barge Canal). More complex waterways and flow circulation will require
two-dimensional modeling. Examples requiring two-dimensional flow modeling include:
For wave models, there is not currently a similar selection procedure available. Selecting
the appropriate model is left to your experience and discretion after carefully weighing the
required design criteria and model features. Confirm your final model selection with the
District Drainage Engineer.
ACES
MIKE 21 Flexible Mesh Spectral Wave Model
MIKE 21 Nearshore Spectral Wave Model (NSW)
RCPWAVE
Simulating Waves Nearshore (SWAN)
Steady-State Spectral Wave (STWAVE)
With one-way coupling, input results (water elevations and currents) from the surge model
into the wave model. This leads to more accurate prediction of the wave climate. With
two-way coupling, transmit results from each model between the models at regular
intervals. The wave model receives the simulated surge elevations and currents as an
input, and the surge model receives the wave radiation stresses (a source term in the
momentum equations that gives rise to wave setup) as an input. In general, two-way
coupling provides the most accurate predictions.
boundary conditions can be well described. For storm surge studies, this is generally the
open coast. Application of storm surge hydrograph boundary conditions, developed for
the open coast, at upland locations (e.g., at river entrances on estuaries or bays) will
result in overly conservative estimates of both surge elevation and flow rate at the bridge
location. If the model involves wind and pressure boundary conditions rather than a
hydrograph, the model should extend far enough offshore to accurately describe the
coastal effects (wind and wave setup) that contribute to the storm surge.
At a bridge, the accuracy of the surge hydrograph will be a function of the model resolution
between the open coast and the bridge location. Definition of the major tidal waterways
between the ocean and the bridge is recommended. Often, this includes extending the
model not only from the closest tidal inlet to the bridge, but also to nearby inlets as well.
This is particularly true for bridges located on or near intracoastal waterways.
Flow through the bridge is a function of the storage upstream (inland) of the bridge. The
model domain should extend far enough upstream and upland to accurately describe the
flow prism during the surge event. Underestimating the storage area upstream of a bridge
will result in underestimation of flow and scour at the site.
Definition of wave model extents will depend on the purpose of the wave model. If the
modeling results will provide wave radiation stresses for the surge model, then the wave
model should include similar offshore and lateral extents as the surge model as well as
the interior waters. If the purpose of the wave model is only to provide local wave
conditions at the site, then the model should extend from the bridge to the shoreline in all
directions so that the fetch (distance that the wind blows over a water body) is adequately
described in all directions.
Roughness values through developed areas, inundated during the surge, are especially
difficult to predict. The density of buildings is a key influence on roughness in these areas.
Calibration data are helpful in targeting the proper roughness value.
One-Dimensional Models
Specification of one-dimensional model geometry for tidal analyses follows the same
recommendations as for riverine analyses (Section 5.2.4.3.1). In general, the only
difference is the size of the model domain, which is discussed in Section 5.3.4.1.
Two-Dimensional Models
Specification of two-dimensional model geometry for tidal analyses follows the same
recommendations as for riverine analyses (Section 5.2.4.3.2). Again, the only difference
is the size of the model domain, discussed in Section 4.4.1, which can extend into the
offshore area. Adequate resolution should be incorporated into the model to resolve tidal
inlet and offshore features (such as flood and ebb shoals, or coastal structures) that affect
the flow properties of the inlets.
This section describes several of the possible model boundary conditions for coastal
bridge hydraulics analyses.
The hydrology for the boundary condition should be developed for the bridge location
rather than at the location where the boundary condition is applied. Hurricane hydrology
is discussed in Section 5.3.2.
The above guidance and supporting report are available at the following website:
http://www.dot.state.fl.us/rddesign/Drainage/FCHC.shtm
Hurricane-Generated Winds
For bridges located near the ends of bays and estuaries, wind setup can be a major
contributor to the surge elevation. Figure 5.3-14 illustrates the effects that local wind setup
can have on surge elevations. It displays results of a hindcast of the 1852 Unnamed
Hurricane in Tampa, Florida, at the Courtney Campbell Bridge near the northern end of
Old Tampa Bay. Hindcasts were performed with meteorological (spatially and temporally
varying wind and pressure fields) boundary conditions and tidal constituent forcing on the
offshore boundary. The line labeled Surge and Wind includes the “real” hindcast. For the
simulation represented by line labeled Surge Only, the wind speeds in the boundary
condition file were set to zero only at inland locations. Thus, this line represents the case
where surge at the bridge is only created from propagation of the surge hydrograph
inland.
3.5
2.0
1.5
1.0
0.5
0.0
-0.5
-1.0
10 30 50 70 90 110
Simulation Time (hrs)
Figure 5.3-14: Surge Elevations at the Courtney Campbell Bridge Location during
the 1852 Unnamed Hurricane both with and without Local Wind Effects
Another example of how bridge location affects the importance of wind setup is seen in
the hindcast of Hurricane Ivan in 2004 that made landfall near Pensacola, Florida. Figure
5.3-15 displays the calculated storm surge elevation time series at the Interstate 10 (I-10)
Bridge over Escambia Bay (red line) and at the Pensacola Bay Bridge (blue line). Located
near the back of Escambia Bay, the I-10 Bridge experienced a significantly higher storm
surge than did the Pensacola Bay Bridge even though the Pensacola Bay Bridge was
located nearer to the inlet. This is directly attributable to the wind setup that occurred near
the back of Escambia Bay.
3.5
3
Water Surface Elevation (m-MSL)
2.5
1.5
0.5
0
Pensacola Bay Bridge
-0.5
I-10 Bridge
-1
0 20 40 60 80 100 120 140
Simulation Time (hr)
Figure 5.3-15: Hindcasted Surge Elevations at the I-10 over Escambia Bay Bridge
and Pensacola Bay Bridge during Hurricane Ivan 2004.
Figure 5.3-15 shows that hurricane winds can play a major role in describing surge
propagation. The reference AASHTO Guide Specifications for Bridges Vulnerable to
Coastal Storms (AASHTO 2008) provides a methodology for determining peak design
wind speeds for a number of mean recurrence intervals. It references ASCE Standard 7-
05 as the source for determining design wind speeds throughout the country. The
AASHTO Specification also states that if design coastal storm wind speeds exist at a site,
then these values should be used.
In Florida, Dr. Michel Ochi at the University of Florida (Ochi, 2004) presents a
methodology for predicting the hurricane landfall wind speeds along the Florida coast. He
examined tropical cyclones (including hurricanes) that landed on or passed nearby the
Florida coast from the NOAA hurricane database HURDAT. He divided the Florida coast
into 15 districts (Figure 5.3-16), and developed expected extreme values for different
return periods. Table 5.3-3 gives the expected maximum sustained (1-min average) wind
speed for landfalling hurricanes calculated from Ochi’s methodology.
Table 5.3-3: Example of Extreme Landfall Wind Speeds for Florida using the Ochi
Methodology
Most Probable Maximum
Sustained Wind Speed (mph)
50- 100- 500-
District* year year year
K 130.9 141.4 162.3
1 110.5 120.5 140.5
2 107.0 116.6 135.7
3 97.5 107.5 127.5
4 82.9 88.8 100.3
5 104.0 115.3 138.4
6 89.7 101.3 125.1
7 96.8 112.4 144.9
8 127.1 137.9 159.4
9 136.5 148.0 171.2
10 140.2 147.7 162.8
11 104.0 112.0 127.6
* Districts 12-14 did not have enough storm impacts to generate a confident statistical analysis.
Hurricane Hindcasts
Hurricane hindcasts simulate the wave and surge climate associated with a unique
historical hurricane (Section 5.3.5). These types of simulations are performed primarily
with two-dimensional models. Boundary conditions typically take the form of temporally
and spatially variable wind and pressure fields (meteorological boundary conditions)
applied over the entire model domain. Additional boundary conditions include an offshore
stage boundary condition equal to the daily tidal fluctuation at the condition locations. This
can take the form of either specified tidal elevation time series (e.g., tidal hydrographs) or
be a feature of the model as selected tidal constituents (e.g., ADCIRC). The best source
for tidal hydrographs is NOAA’s Center for Operational Oceanographic Products and
Services (http://www.co-ops.nos.noaa.gov/) for real-time and measured tidal gage data,
as well as tidal prediction.
Hurricane wind and pressure fields can be developed in a number of ways. They range
from simple analytic models (e.g., Holland, 1980) to three-dimensional modeling. Several
agencies—including FEMA, NOAA, and USACE—have performed hindcasts of specific
storms. These hindcasts are available sometimes upon request. Additionally, several
commercially available sources of hindcast data also exist.
5.3.4.5 Bridge
When constructing a model to simulate hurricane surge propagation and wave climate,
you will need an accurate representation of the bridge and its influence on the
hydrodynamic processes. In general, the same techniques employed for riverine analyses
also apply to the analysis of coastal bridges during storm surges.
Roughness
Roughness specification at bridge cross sections for tidal analyses follows the same
recommendations as for riverine analysis (Section 5.2.4.2).
Bridge Routine
Selection of the appropriate bridge routines for tidal analyses follows the same
recommendations as for riverine analysis (Section 5.2.4.5).
Piers
Incorporating the effects of bridge piers into the hydraulic model for analysis of coastal
bridges follows the same procedure as for riverine bridges (Section 5.2.4.5). For two-
dimensional modeling, typically, you would not model piers directly because their
planform areas are significantly smaller than the areas of elements that resolve the bridge
openings. However, there are several options for including the effects of bridge piers.
Several models incorporate the loss effects into the hydraulic computation routines. An
example is FST2DH (part of FESWMS). FST2DH contains an automatic routine that
accounts for the effect of piers or piles on flow by increasing the bed friction coefficient
within elements that contain them (Froelich 2002). ADCIRC also contains routines for
incorporating the effects of bridge piers through a loss term in the momentum equations
due to the pier drag (http://adcirc.org/home/documentation/special-features/).
Gosselin et al. (2006) examined the effects of resolving bridge piers through element
elimination in cases where the pier width was a large percentage (5 percent to 35 percent)
of the overall bridge cross section top width. The piers were incorporated by deleting
elements within the mesh occupied by the piers. The authors compared results of the
two-dimensional modeling with one-dimensional modeling results for the same geometry
and flow conditions. The results compared well at the bridge cross section, but compared
poorly downstream of the piers. The authors concluded that whereas the one-dimensional
model incorporates the frictional losses from the piers through an increase in the wetted
perimeter, by modeling the piers through element deletion, the two-dimensional model
does not account for frictional losses if using a slip boundary condition along the model
edges. Rather, you can attribute losses from the piers to the momentum losses
associated with the creation of the secondary flows around the piers and in the wake
region.
Regarding wave models, most publicly available software does not include effects of
bridge piers on wave propagation.
5.3.5 Simulations
Following construction of the surge and wave model domains, development of the
boundary conditions, and specification of the input model parameters, you can begin
running the model simulations. This section describes the model simulations typically
performed as part of the hydraulic analysis of a coastal bridge.
Table 5.3-4: Suggestions for Model Calibration (Source: Zevenbergen et al. (2005))
If a model fails to execute, The causes of numerical Model calibration will be
check: instability are: affected by:
• Program output • Computational time • Appropriate model
error messages step too long extents
• Missing input data • Lack of geometric • Accuracy of model
• Incorrect input data refinement bathymetry
• Missing input files • Wetting and drying • Correct datum
• Inconsistent input problems conversions for
data • Weir flow bathymetry
• Correct datum
conversions for tide
gages
• Inclusion of wind
effects
Inclusion of
appropriate
upstream inflow
Calibration to known storm events is significantly more complex than tidal calibration.
Ideally, the calibration would include accurate measurements of both the model inputs
(surge hydrograph or wind and pressure fields), as well as accurate surge measurements
at locations throughout the model domain (gage measurements or high water marks).
This is seldom the case. In fact, high water marks provide one of the more difficult data
sources to calibrate to since they often contain effects of local wave climate and can vary
significantly in close proximity to each other. If reliable information is available, calibration
to a known storm event is ideal. Comparison of model results with gage data or high water
marks helps identify problems with domain extents, model resolution, grid resolution, or
friction assignment.
Calibration of wave models also is difficult because calibration data are rarely available.
If you can acquire the data, then the calibration process should involve qualitative and
quantitative comparisons of measured and simulated wave height, period, and direction.
However, if measurements are unavailable, then the coastal engineer should
demonstrate that the wave model simulations provide reasonable results, were performed
employing accepted standards for input parameters, and incorporate an appropriate level
of conservatism.
Figure 5.3-17 displays an example of water surface elevation and velocity time series
during the 100-year return period hurricane through Wiggins Pass near Naples, Florida.
The figure is typical of storm surge propagation through coastal waters. A peak in velocity
magnitude precedes the peak in water surface elevation as the surge propagates inland.
A second peak in velocity magnitude occurs as the surge recedes. The magnitude, phase,
and duration of the velocity magnitude peaks are a function of the shape of the surge
hydrograph and the response of the interior waterways.
18
Velocity (ft/s)
16 Water Surface Elevation (ft-NAVD88)
Water Surface Elevation (ft-NAVD88)
14
Velocity Magnitude (ft/s),
12
10
-2
0 5 10 15 20 25 30 35 40
Simulation Time (hr)
Figure 5.3-17: Example of Water Surface Elevation and Velocity Time Series
during the 100-year Return Period Hurricane through Wiggins Pass near Naples,
FL
velocity for tidal flows requires a separate simulation of the spring tidal flows. The average
current velocity should correspond to the peak velocity occurring over this simulation.
Time-dependent (unsteady) wave modeling gives more accurate design wave conditions
at the bridge location. As an alternative, steady-state modeling of the wave conditions
during the peak storm surge provides sufficient, though conservative, design conditions.
Inputs to the wave modeling will include design wind speeds, water surface elevations,
bathymetry/topography, and wind direction. If the wind direction is unknown, the wave
modeling should include, at a minimum, steady-state simulations of the wind field along
the direction of the longest fetches (Figure 5.3-18).
Wave models typically provide the significant wave height and the peak period. The
significant wave height is a statistical parameter representing the average of the highest
one-third of the waves in a wave spectrum. The peak period is the wave period
corresponding to the maximum of the wave energy spectrum. For design of bridge
superstructures, AASHTO recommends employing the maximum wave height rather than
the significant wave height. The AASHTO equation for converting between the two is Hmax
= 1.80 Hsignificant.
Figure 5.3-18: Example of Significant Wave Height Contours from Wave Modeling
chord must have a minimum one-foot vertical clearance above the 100-year design wave
crest elevation. If this clearance cannot be met, the bridge superstructure should be
raised as high as feasible and the bridge superstructure designed to resist storm wave
forces. For these bridges, the design strategy depends on the importance/criticalness of
the bridge when considering the consequences of bridge damage caused by wave forces.
If you judge a bridge to be extremely critical, you would design it to resist wave forces.
Bridges that you might judge to be non-critical do not require evaluation for wave forces.
Figure 5.3-19: Damage to the I-10 Bridge over Escambia Bay during Hurricane
Ivan (2004)
Figure 5.3-20 defines the parameters involved in estimating wave forces and moments
on bridge superstructures from the AASHTO Specifications. The interaction between the
wave and bridge superstructure produces vertical (uplift) forces, horizontal forces, and
over-turning moments. Computing design surge/wave-induced forces and moments on
bridge superstructures requires knowledge of the meteorological and oceanographic
(met/ocean) design conditions and the proper force and moment equations. The AASHTO
Specifications provide methods to determine both.
The AASHTO Specifications provide a series of parametric equations for calculating the
wave forces. There are two sets of equations—one corresponds to the time of the
maximum vertical force and one corresponding to the time of the maximum horizontal
force. For example, for the maximum vertical force, the vertical force is the maximum
value experienced by the structure during passage of the design wave and the horizontal
force and moment are the values at the time of maximum vertical force.
They will have some type of downstream control structure, such as salt water
intrusion barriers, flood control weir, and/or pumps that will regulate the discharge.
They will not normally flood out of bank, even in a 100-year storm.
They have low design velocities—typically 1 fps to 3 fps—and often are subject to
aggradation requiring periodic dredging to maintain the needed cross section
Their abutments typically do not encroach into the cross section of the canal;
therefore, there will be no contraction of flow and little backwater caused by the
bridge.
Even if there are piles in the flow of the canal, the design discharge will not create
substantial scour around the piles because the velocity is low and the pile size
typically is small.
Usually, the canal owner can provide the hydraulic design discharge and stage.
Given the typically innocuous hydraulic and scour conditions at controlled canal bridges,
you will find that the prudent level of effort required to perform the bridge hydraulics
analysis is considerably less than for the typical bridge. In fact, you can abbreviate the
traditional Bridge Hydraulics Report. Use the following outline for topics that should be
included for controlled canals:
5.4.1 Introduction
Bridge Location Map
Waterway owner (LWDD, SFWMD, CBDD, etc.)
Description of waterway: manmade, straight, controlled canal, etc.
Use of canal: navigation, recreation, flood protection, irrigation, etc.
Other unusual details
Engineer. Also, if the design discharge and stage are not available, then a full
bridge hydraulics analysis is needed.)
Testimony from Bridge Inspection records: aggradation/degradation, condition of
revetment, debris problems, etc.
5.4.7 Appendix
Correspondence with owner regarding canal design parameters and requirements
Pictures from Bridge Inspection Reports, if significant
Evidence of field review
For new bridge design, bridge widenings, and evaluation of existing structures, develop
scour elevation estimates for each pier/bent for the following conditions:
Include the components discussed in the following sections in your scour estimates.
Changes upstream and downstream affect stability at the bridge crossing. Natural and
manmade disturbances may change sediment load and flow dynamics, resulting in
adverse changes in the stream channel at the bridge crossing. These changes may
include channel bank migration, aggradation, or degradation of the channel bed. During
aggradation or degradation of a channel, the channel bed and thalweg tend to accrete or
erode.
Channel Migration
Lateral channel migration is an important factor to consider when deciding on a bridge’s
location. Factors affecting lateral channel migration include stream geomorphology,
bridge crossing location, flood characteristics, characteristics of the bed and bank
material, and wash load (Richardson and Davis, 2001).
There are techniques to address channel migration in the FHWA document HEC 20
(Legasse et al., 2001). These techniques generally include critical examination/
comparison of historical measurements/records combined with field observations to
forecast future trends. Sources of historical records include bridge inspection records,
historical maps, historical aerial photography, and historical surveys. In general, at
bridges where the waterway exhibits a history of meandering, the hydraulics engineer
should consider assuming that the elevation of the thalweg could occur at any point within
the bridge cross section, including along the floodplain. If this conservative approach is
excessively costly, it may be more cost-effective to mitigate potential future meander by
river training or armoring.
Chapter 6 of HEC 20 (Legasse et al., 2001) provides procedures for predicting and
evaluating lateral channel migration through aerial photograph analysis. See Section
5.2.1.3 for sources of aerial photographs.
A special case of migration found in coastal zones is inlet migration. Inlets either migrate
along the coast or remain fixed in one location. This is due to a complex interaction
between the tidal prism (volume of water transported through the inlet during tides), open
coast wave energy, and sediment supply. Although many of Florida’s inlets are improved
through jetty construction and bank stabilization, several inlets are not—particularly along
the southwest coast. New bridge construction and evaluation of existing structures over
unimproved inlets should include a thorough investigation of the historical behavior of the
inlet (through examination of historical aerial photographs and charts) to discern the
Updrift migration
Downdrift migration
Fluctuations in inlet width and depth
Spit growth and breaching (resulting in oscillation of inlet location)
A coastal engineer should perform the analysis of coastal hydraulics for the design and
evaluation of bridges over tidal inlets. References and aids in design/evaluation include
the USACE’s EM 1110-2-1810 Engineering and Design—Coastal Geology (1995) and
EM 1110-2-1100 Coastal Engineering Manual (2006).
Aggradation/Degradation
Aggradation and degradation relate to the overall vertical stability of the bed. Long-term
aggradation and degradation refers to the change in the bed elevation over time over an
entire reach of the water body. Aggradation refers to the deposition of sediments eroded
from the channel or watershed upstream of the bridge resulting in a gradual rise in bed
elevation. Degradation refers to the gradual lowering of the bed elevation due to a deficit
in sediment supply from upstream.
Given the potential influence of changes in the watershed on stability at a bridge location,
you must not only evaluate the current stability of the stream and watershed, but also the
potential future changes in the river system (within reason). Examples of this include
incorporation of watershed management plans or known planned projects (bridge/culvert
replacements, dams, planned dredging, etc.) into evaluation of the vertical stability at the
bridge location. As such, it is important that you perform the necessary data collection
(including contacting local agencies) to become aware of future projects/plans and
incorporate them appropriately into the analysis.
For existing bridge locations, the most common evaluation of a channel’s vertical stability
is through examination of Bridge Inspection Reports. The reports (available upon request
from the individual Districts) typically contain recent and historical inspection survey
information. These surveys (typically lead-line surveys at each pier location on both sides
of the bridge) are an excellent source of data on long-term aggradation or degradation
trends. Additionally, inspection reports from bridges crossing streams in the same area
or region also can provide information on the behavior of the overall waterway if
Estimate long-term vertical stability trends over the lifetime (for new projects) or remaining
lifetime (for evaluations of existing bridge or widening projects) of the subject bridge. If
the result is degradation, add the estimate at the end of the project life to the total scour.
If the result is aggradation, then document the estimate in the BHR. However, do not
include this estimate in the estimate of total scour. Rather, the existing ground elevation
should serve as the starting elevation for contraction and local scour.
As with channel migration, inlet stability is a special case of vertical stability. Examining
long-term trends through available historical information provides indicators of the inlet
behavior over time. Additionally, inlet stability analyses can provide information on the
evolutionary trends at the subject project. A qualified coastal engineer should perform
these analyses. The references USACE’s EM 1110-2-1810 Engineering and Design—
Coastal Geology (1995) and EM 1110-2-1100 Coastal Engineering Manual (2006)
provide additional resources.
Chann Chann
Piers
el el
Roadwa
Figure 5.5-1: Examples of Contractions at Bridge Crossings
A brief summary of the HEC 18 equations are presented below. Refer to HEC 18 for more
information.
where:
y1 = Average depth in the upstream channel, ft
y2 = Average depth in the contracted section after scour, ft
y0 = Average depth in the contracted section before scour, ft
Q1 = Discharge in the upstream channel transporting sediment, ft3/sec
Q2 = Discharge in the contracted channel, ft3/sec
W1 = Bottom width of the main upstream channel that is transporting bed material, ft
W2 = Bottom width of the main channel in the contracted section less pier widths, ft
K1 = Exponent listed in Table 5.5-1
where:
V* = (τo/ρ)0.5, Shear velocity in the upstream section, ft/sec
ω= Fall velocity of bed material based on the D50, ft/sec (Figure 5.5-3)
g= Acceleration of gravity, 32.17 ft/sec2 (9.81 m/s2)
τo = Shear stress on the bed, lbf /ft2 (Pa (N/m2))
ρ= Density of water, 1.94 slugs/ft3 (1,000 kg/m3)
Figure 5.5-3: Fall Velocity of Sediment Particles with Diameter Ds and Specific
Gravity of 2.65 (Source: HEC 18, 2001)
HEC 18 provides guidance for selecting upstream cross section locations, as well as the
widths at the bridge and upstream cross sections. Notably, separate contraction scour
calculations should be performed for the channel and left and right overbank areas
(assuming they extend through the bridge). For cross sections that include multiple
openings (including causeway bridges), upstream width selection involves delineating the
flow patterns upstream of the bridge to properly identify the division of the flow from the
upstream sections to the bridge.
where:
y2 = Average equilibrium depth in the contracted section after contraction scour, ft
Q = Discharge through the bridge or on the set-back overbank area at the bridge
associated with the width W, ft3/sec
Dm = Diameter of the smallest non-transportable particle in the bed material (1.25 D50)
in the contracted section, ft
D50 = Median diameter of bed material, ft
W = Bottom width of the contracted section less pier widths, ft
yo = Average existing depth in the contracted section, ft
Ku = 0.0077 (English units) or 0.025 (SI units)
For a more detailed discussion of these equations, the reader is referred to HEC 18.
at the bed and free surface due to stagnation pressure variations along the face of the
structure and flow separation at the edge of the scour hole.
You can divide local scour into two different scour regimes that depend on the flow and
sediment conditions upstream of the structure. Clear-water scour refers to the local scour
that takes place under the conditions where sediment is not in motion on a flat bed
upstream of the structure. If sediment upstream of the structure is in motion, then the local
scour is called live-bed scour.
For work in Florida, calculation of local pier scour must involve application of the Sheppard
Pier Scour Equations detailed in the FDOT Bridge Scour Manual (Sheppard, 2005) rather
than the CSU Pier Scour Equation when the total scour (long-term channel conditions,
contraction scour, and pier scour) is greater than five feet. The Florida Complex Pier
Scour Procedure is described in HEC 18, Fifth Edition. The Florida Complex Pier Scour
Calculator and Procedure can be downloaded at:
http://www.fdot.gov/roadway/Drainage/Bridge-Scour-Policy-Guidance.shtm .
A brief overview of Sheppard’s Pier Scour Equation and the Florida Complex Pier Scour
Procedure are presented below. Refer to the FDOT Bridge Scour Manual for detailed
guidelines and examples.
ys
= 2.5 f1 f2 f3
D*
V Vlp V
-1 -
ys Vc Vc Vc
= f 2.2 + 2.5 f
D*
1
Vlp 3
Vlp
V -1 V -1
c c
ys
= 2.2 f1 ,
D*
where:
y 0 0.4
f1 tanh * ,
D
V
2
f2 1-1.2 ln ,
Vc
D*
D50 , and
f3 1.2 -0.13
0.4 D +10.6 D
* *
D
50 D
50
V1 = 5Vc
V2 = 0.6 g y 0
V for V1 > V2
Vl p = live bed peak velocity = 1
V2 for V2 > V1
where:
ys = Equilibrium scour depth, ft
D* = Effective diameter of the pier, ft
yo = Water depth adjusted for general scour, aggradation/degradation, and contraction
scour, ft
V = Mean depth-averaged velocity, ft/sec
Vc = Critical depth-averaged velocity, ft/sec
Vlp = Depth-averaged velocity at the live-bed peak scour depth, ft/sec
D50 = Median sediment diameter, ft
The methodology is based on the assumption that a complex pier can be represented (for
the purposes of scour depth estimation) by a single circular pile with an “effective
diameter” denoted by D*. The magnitude of the effective diameter is such that the scour
depth at this circular pile is the same as that at the complex pier for the same sediment
and flow conditions. The problem of computing equilibrium scour depth at the complex
pier is, therefore, reduced to one of determining the value of D* for that pier and applying
Sheppard’s Pier Scour Equation to the circular pile for the sediment and flow conditions
of interest. The methodology to determine the total D* for the complex structure can be
approximated by the sum of the effective diameters of the components making up the
structure, that is:
where:
D* = Effective diameter of the complex structure
D*col = Effective diameter of the column
D*pc = Effective diameter of the pile cap
D*pg = Effective diameter of the pile group
The procedure for computing local scour depth for complex piers is further divided into
three cases, as illustrated in Figure 5.5-5 below:
Case 1 complex pier with pile cap above the sediment bed
Case 2 complex pier with pile cap partially buried
Case 3 complex pier with pile cap completely buried
Figure 5.5-5: Three Cases of Local Scour Depth for Complex Pier Computations
Refer to the FDOT Bridge Scour Manual for a more detailed discussion on the procedure
and the application of the equations.
HEC 18 also provides equations for calculating local scour at abutments. However, as
stated in the Drainage Manual, abutment scour estimates are not required when the
design provides the minimum abutment protection. Where you have significantly wide
floodplains with high-velocity flow around abutment, consider analyzing abutment spatial
requirements using HEC 23.
Many bridges in coastal environments incorporate seawalls into the design of abutment
protection. Scour at vertical walls occurs when waves either break on or near the wall or
reflect off the wall, thus increasing the shear stress at the bottom of the wall. This is known
as toe scour. Toe scour decreases the effective embedment of the wall and can threaten
the stability of the structure. Current USACE guidance (CEM, 2001) indicates that, as a
rule of thumb, the depth of scour experienced in front of a vertical wall structure is on the
same order of magnitude as the incident maximum wave height. Methodologies for
designing toe scour protection are presented in Section 5.5.4.
Figure 5.5-6: East Approach to the I-10 WB Bridge over Escambia Bay
After Hurricane Ivan (2004)
Regarding the impacts of waves on scour at bridge piers, laboratory modeling indicates
that vertical piles subject to both waves and currents experience an increase in the
effective shear stress at the bed. Additionally, there is an increase in the amount of
suspended sediment and, thus, the sediment transport in the vicinity of the pile as
compared with the transport associated with currents or waves alone. No current
analytical methods are available for design purposes. However, some sediment transport
models (e.g., SED2D) include methodologies for calculating the shear stress due to
combined waves and currents.
For bridge replacements, parallel bridges, major widenings, etc., Bridge Inspection
Reports and the design survey should be the primary basis for determining normal
everyday scour. If the proposed piers are the same as the existing piers, the normal,
everyday scour elevation should be reflected in the inspection reports and the design
survey (Figures 5.5-7 and 5.5-8). Slight differences in scour will likely exist between
inspection reports and between the reports and the design survey. In these cases, an
average scour elevation will be a reasonable estimate of normal, everyday scour. If there
is a large difference, an extreme storm event may have occurred just before the inspection
or survey. Investigate this and address it on a case-by-case basis.
0
Distance from Top of Rail, (ft)
-5
-10
1992
-15 1994
2010
-20
-25
1 2 3 4
Bent
Figure 5.5-8: Example of Normal, Everyday Scour Holes from Survey Data
For structures in which the proposed piers will be a different size or shape than the
existing or for new bridges/new alignments where there are no historical records
available, base estimates of the normal everyday scour on hydraulic modeling results of
expected daily flows. For riverine bridges, this should correspond to flows equal to the
normal high water. For tidal flows, everyday flows correspond to the maximum flows
experienced during spring tides.
The test methods establish the shear stress response of soils and the procedure
integrates that response over the lifetime of expected flows at the bridge site. The
procedure involves establishing the shear stress response of a site-specific sample using
the RETA (Rotating Erosion Test Apparatus) and SERF (Sediment Erosion Recirculating
Flume) devices, shown below in Figures 5.5-9 and 5.5-10, respectively, and then
integrating that response over the flows expected in the life of the bridge to predict
contraction or local scour at the bridge.
Spill-Through Abutments
Where flow velocities do not exceed 9 fps, and/or wave heights do not exceed 3 feet,
minimum protection consists of one of the following protection methods placed on a
1V:2H or gentler slope:
Rubble riprap (Bank and Shore), bedding stone, and filter fabric—Rubble riprap
(Bank and Shore) is defined in the FDOT Standard Specifications for Road and
Bridge Construction, Section 530
Articulated concrete block (cabled and anchored)—Articulating concrete block also
is defined in Section 530
Grout-filled mattress (articulating with cabling throughout the mattress)
You must create site-specific designs when using articulated concrete block or grout-filled
mattress abutment protection. As of May 2016, the Department does not have standard
specifications for grout-filled mattresses. You will need to prepare a technical specification
if grout-filled mattresses are proposed for a project. The FDOT Structures Detailing
Manual provides typical details for standard revetment protection of abutments and extent
of coverage. Determine the horizontal limits of protection using HEC 23. Provide a
minimum distance of 10 feet if HEC 23 calculations show less than 10 feet. Notably,
neither grouted sand-cement bag abutment protection nor slope paving is considered
adequate protection for bridges spanning waterways. Slope paving can develop cracks
or upheaved slabs where loss of fill can occur. Grouted sand-cement bags often fail when
cracks form around the individual bags and sediment is lost through cracks or displaced
elements (Figure 5.5-11). Additionally, these systems are prone to failure due to
undermining (erosion at the toe of the protection) or flanking (erosion at the edges of the
protection) when the edges of the protection are not sufficiently buried.
Determine the horizontal and vertical extents, regardless of protection type, using the
design guidelines contained in HEC 23. If the results from the HEC 23 calculations show
that a horizontal extent less than 10 feet is acceptable, you should still provide a minimum
of 10 feet. Review the limits of right of way to ensure the minimum apron width at the toe
of the abutment slope both beneath and around the bridge abutments along the entire
length of the protection. If calculations from HEC 23 result in a horizontal extent outside
the right of way limits, do the following:
Make additional considerations regarding extents in coastal areas subject to wave attack.
Prolonged exposure to hurricane-generated waves on unprotected approaches may lead
to damage to the approach slabs (Figure 5.5-6) as well as the approach roadways.
Consider extending the limits of protection to include the approach spans in wave-
vulnerable areas.
When bridges are to be widened, you may not be able to simply recommend using
standard rubble riprap, as defined in Section 4.9 of the Drainage Manual. Constructability
issues may arise at existing bridges where the low chord elevations may prevent uniform
riprap placement due to height constrictions. If this case arises, you can do the following:
a. Rather than simply employing the minimum FDOT Bank and Shore Rubble Riprap,
size the rubble according to the design average velocities determined at the
abutment using HEC 23. This may result in smaller armor stone sizes, thus
enabling easier placement.
b. Provide an alternate material in the plans that should be approved prior to
installation.
Allow abutment protection to extend beyond the bridge along embankments that may be
vulnerable during a hurricane surge. You need to consider wave attack above the peak
design surge elevation and wave-induced toe scour at the foot of bulkheads. In such
cases, consult a qualified coastal engineer to determine the size and coverage of the toe
scour protection. The choice of cabling material for interlocking block or concrete
mattresses must consider the corrosiveness of the waterway. Avoid using steel cabling
in salt or brackish waters (stainless steel is permissible).
Rubble riprap abutment protection is the preferred protection type for new bridges. Rubble
riprap has several advantages (HEC 11), including:
A drawback to rubble riprap is that it can be more sensitive than some other bank-
protection schemes to local economic factors. For example, transport costs can
significantly affect the construction costs. For an illustration of bridge abutment slope
protection adjacent to streams, refer to the FDOT Structures Detailing Manual at the
following link:
http://www.fdot.gov/structures/structuresmanual/currentrelease/vol2sdm.pdf
Where velocities do not exceed 9 fps and waves do not exceed three feet on a 1V:2H
slope, protection should consist of a 2.5-foot-thick armor layer comprised of FDOT
Standard Bank and Shore Rubble Riprap over a one-foot thick layer of bedding stone
over filter fabric. Size the filter fabric appropriately to prevent loss of the fill sediments.
The purpose of the bedding stone is to ensure consistent contact between the filter fabric
and the soil; and to prevent the armor stone from damaging the filter fabric during
construction; and to inhibit movement during design events. Ensure the riprap has a well-
graded distribution to promote interlocking between the individual units, which improves
performance of the protection. For riverine applications, compare these minimums to the
guidance presented in HEC 23 (Design Guideline No. 14) to ensure proper design. A
notable feature of the slope protection cross-sections, illustrated in the FDOT Structures
Detailing Manual’s link above, is the sand cement bags located between the revetment
and the abutment. This detail was added to the Standard following field inspection
observations that the protection/abutment interface often was a point of failure. Shifting
of the stones during a minor event would cause a gap to open at the top of the slope,
allowing erosion to take place. This addition ensures that the filter fabric remains in
contact with the abutment so that any settlement will not produce a gap between the
structure and the stones.
For locations subject to wave impacts with wave heights greater than three feet, you must
also design the revetment to resist hurricane-generated waves. Design of abutment
protection should follow the same procedures and methodologies as design of rubble
riprap protection that serves as shore protection. The U.S. Army Corps of Engineers
provides guidance in the references (USACE, 2006, and USACE, 1995). USACE
Engineering Manual 1110-2-1614 (USACE 1995), in particular, provides multiple
methodologies for properly sizing armor stone as well as designing the revetment extents,
toe geometry, bedding stone, and armor layer distribution.
Often, this analysis will result in an armor stone size greater than that provided by the
FDOT Standard Bank and Shore Rubble Riprap. When this occurs, use the more
conservative (larger stone size) design. For these designs, develop a modified special
provision for the non-standard rubble riprap. The provision must specify the new riprap
distribution developed employing the techniques located in USACE (1995) or a similar
procedure. Develop a well-graded distribution to the armor stone to ensure optimal
performance. Additionally, for large armor stone, it may become necessary to include
additional intermediate stone layers into the design to prevent loss of bedding stone
between gaps in the armor stone. The USACE (1995) reference presents guidelines for
design of granular filter layers as a function of the armor stone size.
For toe scour protection, the USACE (1995) reference provides guidance on sizing stones
and designing the apron width. Toe apron width will depend on both geotechnical and
hydraulic factors. For a sheet-pile wall, you must protect the passive earth pressure zone.
The minimum width from a hydraulic perspective should be at least twice the incident
wave height for sheet-pile walls and equal to the incident wave height for gravity walls.
Additionally, the apron should be at least 40 percent of the depth at the structure.
Compare this apron width to that required by geotechnical factors and adjust it
appropriately. Regarding size of the armor stone, the reference provides a method
developed by Brebner and Donnelly. USACE (2006) also provides guidance for toe scour
protection in front of vertical wall structures in Section VI-5-6 of the Coastal Engineering
Manual.
For revetment installations where you don’t expect significant wave attack, include all
options that are appropriate based on site conditions (e.g., fabric-formed concrete,
standard rubble, cabled interlocking block, etc.; see Figure 5.5-13 through Figure 5.5-15).
HEC 23 provides guidance for design of these protection systems, as follows:
Document options shown to be appropriate for the site in the BHR. You may write a
technical specification based on the use of the most ideal revetment material, with the
option to substitute the other allowable materials at no additional expense to the
Department. This recommendation would help to eliminate revetment CSIPs (Cost
Savings Initiative Proposals) during construction. No matter what options are allowed,
match the bedding (filter fabric and bedding stone) to the abutment material. Some of the
options are not self-healing (i.e., not rubble riprap), and a major failure can occur if loss
of the embankment material beneath the protection takes place.
As a final note, coastal bridges often incorporate seawalls into the abutment protection
design. The caps of these structures often have a low elevation (below the design surge
elevation) to tie into neighboring structures. Address the design of these structures as
containing elements of both spill-through and vertical wall abutments. The area in front of
the seawall should include a toe scour apron designed in the same manner as for vertical
wall abutments. Design areas between the seawall and the abutment using the same
procedures as spill-through abutments. These designs should ensure encapsulation of
the fill behind the seawall (Figure 5.5-16) to prevent loss of fill and potential failure of the
anchoring system (Figure 5.5-17).
You will see several similarities between the procedures. All guidelines recommend
ensuring that the top of the protection remain level with the bed of the approach.
Suggestions for achieving this include placing sand-filled geotextile containers within the
scour hole to raise the bed elevation and serve as a filter for the overlaying protection.
The guidelines all also recommend that the horizontal extent of the protection extend a
distance equal to twice the effective diameter of the pier in all directions. For the non-
riprap options, the guidelines recommend that the protection slope away from the pier
with the edges of the protection buried below the maximum scour depth for the overall
cross section (i.e., depth of contraction scour and long-term degradation). A common
failure point of the non-riprap protection schemes is at the edges of the protection if the
mattress becomes undermined. Thus, it is important to incorporate trenching of the edges
and use of anchoring systems (if appropriate) into the protection design. Another common
failure point is at the pier/protection interface. The guidelines suggest grouting this
interface to prevent loss of fill for both the articulating concrete block and gabion
protection systems. You should review disadvantages and advantages of each system,
including construction feasibility and cost.
1. Rely on the longitudinal grade of the bridge to convey the deck runoff to the end
of the bridge.
2. Use freely discharging scuppers or inlets to drain the deck runoff to the area
directly below the bridge. These sometimes are referred to as open systems.
3. Collect the discharge from the scuppers or inlets in a pipe system. The pipe
system can discharge down a pier or at the ends of the bridge. These systems
sometimes are referred to as closed systems.
Spread criteria will control the need to eliminate option 1 and use either option 2 or 3. The
inability to discharge to the area below the bridge will control the need to eliminate option
2 and use option 3.
For rural roadways, shoulder gutter is typically used to convey the bridge flow to a
shoulder gutter inlet (See Standard Plans, Index 425-040, Gutter Inlet Type S). This inlet,
including its 5-foot-long gutter transition, is usually located about 35 feet from the end of
the approach slab to provide space for the guardrail’s Approach Transition Connection to
Rigid Barrier, including its curb transition to shoulder gutter (See Standard Plans, Index
536-001, Guardrail). Additionally, check the spread at the shoulder gutter inlet for the 10-
year flow to ensure that runoff does not overtop the shoulder, causing erosion of the
embankment (refer to Chapter 6 and Appendix H for more information).
If the profile grade is sloping onto the bridge for rural roadways, then the calculations for
the deck drainage may need to include roadway runoff flowing onto the bridge. The
shoulder gutter transition directs the rainwater from the bridge into the inlet (refer to Figure
5.6-1). For standard cross slopes of 0.02 ft/ft for bridge shoulders and 0.06 ft/ft for
roadway shoulders, with a 10-foot wide shoulder, the longitudinal slope of the gutter due
to the transition is 2.1 percent. For this situation, the roadway grade would need to be
greater than 2.1 percent for roadway runoff to flow onto the bridge. Appendix H shows
how this slope was determined, and the same method can be used to calculate the slope
for other situations.
For urban locations, if there is not a barrier wall between the sidewalk and the travel lanes,
or if there is no sidewalk, a curb inlet can be placed at the end of the approach slab.
The Drainage Manual does not require bridge sidewalk runoff to be collected on the
bridge. Scuppers or drains are not necessary to control the runoff on the bridge sidewalk
unless the runoff becomes great enough to overwhelm the collection system at the end
of the bridge. Scuppers used to drain the sidewalk must be ADA compliant.
In handling runoff from the sidewalk at the end of the bridge, the best option is to transition
the sidewalk slope toward the roadway immediately downstream of the bridge. The flow
then can be picked up in the first curb inlet or barrier wall inlet off of the bridge.
Where the barrier wall or curb ends at the edge of the approach slab
At the first inlet off of the bridge
Calculate spread based on the Gutter Flow Equation in Section 6.3.2 of this document.
Spread criteria are given in Chapter 3.9 of the Drainage Manual. If the spread exceeds
the allowable spread criteria, then you may need scuppers or inlets on the bridge to
reduce the spread. If the spread exceeds the criteria, consider adjusting the profile grade
to reduce the spread before adding scuppers or inlets on the bridge. Reduce spread by:
After determining grades that would eliminate the need for scuppers or inlets, talk with
the roadway designer to determine the feasibility of adjusting the profile grade.
Example 5.6-1
A bridge for a two-lane rural roadway has the following characteristics:
200-foot length
30-foot approach slabs
A longitudinal slope of 0.3 percent
Shoulder gutter inlets located 30 feet from the uphill approach slab
The bridge typical section has two 12-foot travel lanes, 10-foot outside shoulders,
1.5-foot barriers, 0.02 ft/ft cross slopes, and is crowned in the middle.
Solution:
Determine the drainage area to the end of the downhill approach slab. On the uphill end
of the bridge, the shoulder gutter transition will cause the runoff from the area between
the shoulder gutter inlet and the end of the approach slab to flow back to the shoulder
gutter inlet. Therefore, the drainage area contributing to the downhill side will include the
bridge deck and the approach slabs:
where:
C = Rational runoff coefficient
i= Rainfall intensity, inches per hour
(4 in/hr, refer to Chapter 6 for explanation)
A = Drainage area, acres
3 3
Qn 8
(0.53)(0.016) 8
Spread 5 / 3 1/ 2
5/3 1/ 2
7.1 ft.
0.56 S X S 0.56(0.02) (0.003)
Since the spread at the end of the downhill approach slab is less than 10 feet, with 10
feet being the width of the shoulder, scuppers are not necessary.
You also can check the spread at the shoulder gutter inlet on the downhill side of the
bridge. There will be an additional drainage area from the end of the approach slab that
needs to be added to the drainage on the bridge. The drainage area to the shoulder gutter
inlet is:
Assuming that the bridge is in Zone 1 for the IDF curves, the flow to the inlet is:
where:
i= The 10-year, 10-minute rainfall intensity = 7.0 inches per hour
(Refer to Chapter 6 for explanation)
Note that this value is slightly conservative. The one-foot unpaved strip behind the
guardrail was assumed to be paved in this calculation.
The allowable conveyance in the shoulder gutter is K = 28 cfs. Refer to Section 6.3.2.3 of
this document for further explanation of this value. The allowable flow at the shoulder
gutter inlet is:
Since the gutter flow just uphill of the shoulder gutter inlet is less than the allowable flow,
the deck drainage design is acceptable.
Avoid placing scuppers over certain areas due to the direct discharge. These areas
include:
As stated in Section 4.9.4 of the Drainage Manual, the standard scupper drain is four
inches in diameter and spaced on 10-foot centers, unless spread calculations indicate
closer spacing is required. Typically, the 10-foot spacing will provide adequate drainage
for most bridges. You can evaluate the intercepted flow for four-inch bridge scuppers on
a grade using the capacity curves in Figure 5.6-3 and Figure 5.6-4. The curves were
derived from laboratory studies performed at the University of South Florida (Anderson,
1973).
Grated scuppers or inlets, as shown in Figure 5.6-5, are more uncommon, especially as
free-draining scuppers. Although grated inlets can be used with open systems, they are
normally used with closed systems. You might use this type of grated scupper, or perhaps
one with a smaller grate, to drain a bridge sidewalk or if you expect significant bicycle or
pedestrian traffic on the shoulder. The four-inch ungrated scuppers will not meet ADA
requirements.
The Department does not have standard grated scuppers or inlets; therefore, it does not
have capacity charts as with other standard Department inlets. Section 6.3.1.5 provides
references to documents that you can use to derive inlet capacities. Manufacturers may
publish capacity charts for their inlets. Keep in mind that the pipe opening at the bottom
of the inlet may control the capacity rather than the inlet opening.
The length, width, and depth of the grated inlet will be limited by the reinforcement in the
deck of the bridge. You will need to coordinate the dimensions and locations of the inlets
with the structural engineer. Use standard prefabricated inlets whenever possible. Refer
to Section 7.4 for more information on grated scuppers.
Example 5.6-2
A bridge deck grated scupper is located where the shoulder width is 10 feet and the cross
slope is 0.02 ft/ft. The longitudinal grade of the bridge is 1.5%. The dimensions of the
grated scupper as defined in Figure 5.6-5 are:
W = 5 feet
L = 1 foot
D = 7 inches
Outlet Pipe Diameter = 8 inches
The flow along the barrier wall at the scupper is 1.65 cfs. Determine the intercepted flow.
Solution:
3 3
Qn 8
(1.65)(0.016) 8
Spread 5 / 3 1/ 2
5/3 1/ 2
8.06 ft.
0.56 S X S 0.56(0.02) (0.015)
Calculate the intercepted flow using the method presented in FHWA Hydraulic
Engineering Circular No. 12, Drainage of Highway Pavements, March 1984 (HEC 12).
The flow directly over the grate is called the frontal flow. The frontal flow can be
determined using Equation 7 from HEC 12:
8 8
Q W 3
5 3
E 0 W 1 1 1 1 0.924
Q T 8.06
where:
E0 = Ratio of flow in width, W, to the total flow, Q
QW = Flow in width, W, less than T, in cfs
Q = Total flow, in cfs
W = Width of flow, W, in feet
T= Total width of flow (also called the spread), in feet
The inlet will intercept all of the frontal flow unless the velocity is great enough to cause
the flow to skip over the grate. This velocity is called the splash-over velocity. Use Chart
7 of HEC 12 to determine the splash-over velocity. Figures 8 through 13 of HEC 12 show
the dimensions of the grates in Chart 7. If the grate dimensions do not match one of the
grates shown on Chart 7, then the reticuline grate usually will provide a conservative
assumption for the splash-over velocity.
S X T 2 0.028.062
Flow Area 0.650 ft.
2 2
The splash-over velocity is estimated conservatively as 2.4 fps from Chart 7, HEC 12.
Using Equation 9 from HEC 12, the flow in width, W, that is intercepted can be
determined:
where:
RF = Ratio of the frontal flow intercepted to the total frontal flow
V = Velocity of flow in the gutter, in fps
V0 = Splash-over velocity, in fps
The gutter flow that does not flow directly over the grate is called the side flow, QS. You
can determine the side flow by subtracting the frontal flow from the total gutter flow.
Momentum can carry the side flow past the inlet before all of the flow can turn into the
side of the inlet. The amount of flow that turns into the inlet and is intercepted can be
calculated using Equation 10 from HEC 12:
RS is the ratio of the side flow intercepted to the total side flow. The intercepted side flow
is: RS * QS = 0.0245(0.13) = 0.00 cfs. Therefore, the total flow intercepted, which is the
sum of the frontal and side flows intercepted, is conservatively estimated as 1.50 cfs.
You also must check the capacity of the outlet pipe in the bottom of the scupper inlet. You
can do this using the orifice equation.
Q CA2gh
1
2
where:
C = Orifice coefficient = 0.6
A = Area of the orifice opening, in square feet
g= Gravitational force (32.17 ft/sec2)
h= Head on the orifice opening, in feet
Assuming that the orifice will not impact the intercepted flow unless the head is equal to
the distance from the outlet pipe opening to the top of the grate, D, the outlet pipe capacity
is:
D 2 (8 / 12) 2
A 0.349 ft 2
4 4
This flow is less than the capacity of the grate, and, therefore, the outlet pipe controls the
interception capacity of the inlet. The actual capacity of the outlet pipe will be slightly
greater because the actual head on the pipe will be slightly greater than the top of the
grate. However, this value is a conservative estimate of the intercepted flow.
Example 5.6-3
Constant Grade
Scupper flow on bridges with a constant grade will reach an equilibrium state if the bridge
is long enough. The equilibrium state occurs when the runoff from the area between
scuppers is equal to the flow intercepted by the scuppers.
The spread at scuppers prior to reaching equilibrium will be less than the equilibrium
spread. Therefore, equilibrium spread is a conservative estimate for scuppers on a
constant grade.
Determine the equilibrium spread for standard scuppers on a bridge with the following
characteristics:
The longitudinal grade is a constant 0.2 percent. (Normally, the minimum gutter
grade of 0.3 percent also should be applied to a bridge with flow along its barrier
wall. However, older bridges with flatter slopes are sometimes widened rather than
replaced. Occasionally, even flat-grade bridges are widened.)
Solution:
Since clogging can be a problem for scuppers, it is common to assume that every other
scupper is clogged. This assumption doubles the length between functioning scuppers
from 10 feet to 20 feet. Using this assumption, the deck runoff generated between each
scupper is:
If the bridge is long enough, the equilibrium flow intercepted by the last scupper also will
be equal to this flow rate. Using 0.096 cfs as the intercepted flow, you can use Figure 5.6-
4 to determine the bridge deck flow just upstream of a scupper. Entering the y-axis with
the equilibrium intercepted flow of 0.096, an equilibrium flow just upstream of the scupper
of 0.61 cfs is read from the x-axis.
3 3
Qn 8
(0.61)(0.016) 8
Spread 5 / 3 1/ 2
5/3 1/ 2
8.1 ft.
0.56 S X S 0.56(0.02) (0.002)
This is the equilibrium spread. Since this value is less than 10 feet, the width of the
shoulder, the standard scuppers will be adequate for this bridge.
Usually, you will omit scuppers near the end of a bridge due to potential soil erosion near
the abutments. Add the runoff from this area and the approach slab to the bypass at the
last scupper and the combined Q used to check the spread at the end of the approach
slab.
Example 5.6-4
For this example, use the information for the bridge in Example 5.6-3, with the following
substitutions:
Solution:
If a bridge has scuppers continuously from the crest of the bridge, then a conservative
estimate of the bypass from the last scupper is the equilibrium bypass. From Example
5.6-3, the equilibrium bypass is:
Equilibrium bypass
Equilibrium scupper interception
Equilibrium flow just upstream of scupper
The runoff from the area between the last scupper and the end of the approach slab is:
The total flow at the end of the approach slab can be conservatively estimated as:
3 3
Qn 8
(0.89)(0.016) 8
Spread 5 / 3 1/ 2
5/3 1/ 2
9.3 ft.
0.56 S X S 0.56(0.02) (0.002)
Since the spread is less than 10 feet, the scupper design is acceptable.
If this estimate exceeded the allowable spread, the bridge deck drainage design does not
necessarily need to be changed. The spread can be checked with a more accurate
approach that accounts for the flow at each scupper, as described in Section 5.6.4.
Example 5.6-5
Flat Grade
You can determine the capacity of a scupper on a bridge with 0-percent longitudinal grade
from the figure shown below:
Using the bridge from Example 5.6-3, except with a 0-percent grade, determine if
standard scuppers are adequate.
Solution:
Assuming that every other scupper is clogged, each scupper would need to take the flow
from a strip of the bridge deck that is 20 feet wide. You determined the runoff from this
area in Example 5.6-3 to be 0.096 cfs. Entering the above figure with this discharge, the
scupper flow will be in the transitional range between weir and orifice flow. The flow
conditions are imprecise because of this transition. However, the depth of water above
the orifice can be conservatively estimated as 0.11 feet. The spread is:
Since the spread is less than the width of the shoulder, which is 10 feet, standard
scuppers meet the criteria.
Vertical Curves
Vertical curves complicate the analysis of scupper interception and spacing. However,
you can check scuppers on crest curves at various locations by assuming the grade at
that location is a constant grade. This will be conservative for crest vertical curves, but
also can be overly conservative. Consider using a more detailed analysis procedure, as
described in Section 5.6.4, before using scupper spacing that deviates from the standard.
At the crest of a vertical curve, there is a point where the slope is zero, and—depending
on the length of the curve—there can be a significant portion where the slope is almost
flat. The flow depth in this area is not well represented by the gutter flow equation because
this equation is a normal depth equation. The flow at the crest will not be at normal depth
because it will be experiencing a drawdown due to the combination of steeper slopes and
scupper interception downhill. Checking the spread near the crest with the gutter flow
equation will be conservative. For slopes less than 0.002 ft/ft, check the spread with the
flat grade assumptions if the spread criteria is violated using the gutter flow equation. This
is true for both the equilibrium analysis of this section and the more detailed analysis of
Section 5.6.4.
Avoid sag vertical curves. If this is not possible, then use the more detailed analysis
procedure described in Section 5.6.4.
Example 5.6-6
Use the bridge from Example 5.6-3, except with the following roadway profile information:
107+40
Station
+ 0.5%
Begin Bridge
- 0.75%
Begin Appr.
End Bridge
End Appr.
100+00
100+30
107+30
107+60
The ground beneath the bridge is less than 25 feet below the bottom of the bridge deck
for a distance of 50 feet from each bridge end. Determine the required deck drainage
features.
Solution:
Determine the location of the high point on the bridge:
Therefore, the high point is located at Station 103+80. The drainage area at the edge of
the approach slab at Station 100+00 is:
where:
C = Rational runoff coefficient
i= Rainfall intensity, inches per hour
(Refer to Chapter 6 for explanation to use 4 in/hr)
A = Drainage area, acres
Solving the gutter flow equation for spread:
3 3
Qn 8
(1.82)(0.016) 8
Spread 5 / 3 1/ 2
5/3 1/ 2
10.3 ft.
0.56S X S 0.56(0.02) (0.005)
The spread exceeds the allowable spread of 10 feet. Minor changes to the roadway and
bridge profile would reduce the spread to an acceptable amount, which is less than 10
feet. However, after discussions with the roadway and the bridge engineers, if you cannot
adjust the roadway grade, then consider using standard scuppers. For this example, we
will assume the roadway grade cannot be adjusted.
The drainage area and flow are the same at the other bridge end at Station 107+60. The
spread is:
3 3
Qn 8
(1.82)(0.016) 8
Spread 5 / 3 1/ 2
5/3 1/ 2
9.5 ft.
0.56 S X S 0.56(0.02) (0.0075)
Since this spread is less than 10 feet, scuppers are not needed from the high point of the
bridge at Station 103+80 to the bridge end at Station 107+30.
Omitting scuppers within 50 feet of the bridge end, place standard scuppers every 10 feet
starting at Station 100+80 and ending at Station 103+70. The next step is to determine if
this design meets spread criteria. The previous examples show this design will work:
Example 5.6-5 shows that standard scuppers on this bridge will meet the spread
criteria for flat grades. Therefore, scuppers at the top of the vertical curve where
the longitudinal slope is less than 0.002 ft/ft will meet the spread criteria.
Example 5.6-3 shows that standard scuppers on this bridge will meet the spread
criteria for grades equal to or greater than 0.002 ft/ft.
Example 5.6-4 shows that the spread at the end of the approach slab also will
meet the spread criteria.
Therefore, the deck drainage design for this bridge is standard scuppers starting at
Station 100+80 and ending at Station 103+70.
The evaluation above uses simplified, but conservative, assumptions of equilibrium flow.
If the design failed to meet criteria under the conservative assumptions, then you can
perform a more-detailed analysis to evaluate the design. The following will illustrate the
detailed analysis procedure and explain how a spreadsheet can be used to automate the
analysis.
Enter the values of the cells in Row 1 through Row 8 of the spreadsheet as shown; i.e.,
none of these cells have formulae.
Although the scupper spacing is 10 feet, the spacing was entered as 20 feet to
conservatively assume that every other scupper was clogged.
The vertical curve data are not entered in the same manner as listed on the profile sheets
in the Plans or in Geopak. For the formulation in this spreadsheet, the peak of the vertical
curve must be determined, and all distances referenced from the peak. The slopes must
be entered so that the calculated slopes always have a positive value. G1 should be the
slope at the uphill end, and G2 the slope at the downhill end.
Column A: =A8+$B$1
Column B: =(A9-A8)*$B$4/43560
Column C: =G8+0.95*4*B9
Column D: =($E$3-$E$2)*A9/$E$4+$E$2
Column E: =(C9*$B$3/0.56/$B$2^(5/3)/D9^0.5)^(3/8)
Column F: =IF(D9<0.002,J9,(IF(D9>0.005,K9,(J9+(K9-J9)*(D9-0.002)/0.003))))
Column G: =C9-F9
Column J: =IF(C9>1,Chart!$B$15,PERCENTILE(Chart!$B$4:$B$15,
PERCENTRANK(Chart!$A$4:$A$15,C9,20)))
Column K: =IF(C9>1,Chart!$E$15,PERCENTILE(Chart!$E$4:$E$15,
PERCENTRANK(Chart!$D$4:$D$15,C9,20)))
Column B determines the drainage area between the current scupper and the previous
scupper uphill. This spreadsheet assumes that the bridge has a constant width along the
length of the bridge being analyzed.
Column C determines the flow immediately upstream of the current scupper using the
Rational Equation. The rainfall intensity is assumed to be four inches per hour and the
Runoff Coefficient is assumed to be 0.95. The bypass from the previous scupper is
combined with the runoff from the area between the scuppers.
Column D determines the slope of the profile grade at the current scupper.
Column F determines the intercepted flow rate based on Figure 5.6-4. If the slope is less
than 0.002, the curve labeled “0.2%” is used. If the slope is greater than 0.005, the curve
labeled “0.5, 1, 2%” is used. If the slope is between 0.002 ft/ft and 0.005 ft/ft, a value is
interpolated between the two curves. Values for these two curves are determined in
Column J and Column K.
Column J and Column K read the flows for the two curves of Figure 5.6-4. In the
formulation of this spreadsheet, the curves are represented on another sheet named
“Chart.” The values for the chart are presented on the next page.
At the end of the vertical curve (or, in this case, at the Begin Vertical Curve Station, since
the flow is in the opposite direction of the stationing), the profile grade slope becomes a
constant value. The formula in Column D is changed to the constant of 0.005 ft/ft, as
shown below.
The last scupper is at Station 100+80, which is 300 feet from the crest. The final row, Row
24, checks the spread at the edge of the approach slab. Since the spread at each scupper
and at the edge of the approach slab is less than the shoulder width of 10 feet, the design
meets the spread criteria.
As noted above, a separate sheet named “Chart” is included to represent the two curves
in Figure 5.6-4. The values entered on “Chart” are shown below:
Use grated inlets in closed systems to minimize debris in the piping system. Refer back
to Section 5.6.3 for guidance on determining the interception capacity of grated inlets.
You will need to coordinate the dimensions and locations of the inlets with the structural
designer. Analyze the above-deck design (i.e., size and location of the grated inlets) using
a more detailed procedure rather than the equilibrium assumptions from the previous
sections. Table 5.6-1 illustrates a typical procedure.
Station 1
Station 2
...
Station n
The below-deck system will have a network of pipes to convey the discharge collected by
the inlets to an outlet location. There are two types of systems. One type discharges
downward at the piers or bents. You will find this type of system more commonly for
overpasses. Typically, you will locate the inlets near the pier, so there are few horizontal
segments of pipe and flow is not combined from multiple inlets. Therefore, the controlling
point hydraulically typically will be the entrance to the piping system at the inlet.
The other type of system discharges at the bridge ends. The system will require
longitudinal pipes along the bridge that will carry the combined flow of multiple inlets.
Design the below-deck piping system using a procedure similar to the procedure in
Chapter 6 of this document. The procedure may be modified to use the driver visibility-
limiting rainfall intensity of four inches per hour.
Beside the hydraulic capacity of the piping system, the layout of the system also should
consider:
You can find optional material for bridge collection pipes in Chapter 22 of the Structures
Detailing Manual. No matter what type of pipe is used, give attention to the design of a
hanger system, which the bridge design engineer should design, or you can design in
coordination with the bridge design engineer. If the collection system is connected to a
roadway structure, you may need to call for a resilient connector. For proper design, it is
critical that you coordinate with the structures engineer.
The introduction to Section 4.11.2 has a concise set of rules to guide production of all
sections in the BHR. Reviewing this brief paragraph before compiling the documentation
can help focus the BHR. Additional general guidance to follow while preparing the BHR
is:
Present the BHR in clear and concise language, without redundant information or
unsubstantiated comments.
Make sure graphics address the technical aspects of the project with the public’s
point of view in mind.
Use a consistent report format, as well as consistent units with alternative units
presented where appropriate.
Executive Summary
Introduction
FEMA/Regulatory Requirements
Hydrology
Hydraulics
Scour
Deck Drainage
Appendices
The objective of the Executive Summary is to provide the findings in an opening statement
so that when the reviewer assesses the report in the future, the reviewer would
immediately understand the reasons for choosing the particular bridge. Include a brief
conclusion recounting why you selected the proposed bridge length. The discussion
should include other bridge considerations that were pertinent or had an important
influence on this project. (For bridge widening, this discussion is not necessary.) The
important influences might include the following:
Costs
Maintenance of traffic
Roadway geometrics that affect bridge length
Hydrology
Hydraulics
Scour
Stream geomorphology
Constructability
Environmental concerns
Wildlife shelf requirements
Other unique concerns particular to the site
Include a discussion of any variations from policies in the Drainage Manual, FDM, or
Structures Manual.
5.7.1.2 Introduction
The introduction should describe the location of the bridge briefly, including the name of
the water body being crossed. Giving the latitude and longitude and/or the township,
range, and section will enhance the location description. Include a figure showing a
location map.
Describe the waterway and floodplain at the proposed crossing. Describe the existing
crossing, if any, including the bridge, relief bridges, and roadway embankment within the
floodplain. The description of bridges should include only details that affect the hydraulics:
Bridge length
Span lengths
Foundation type and sizes
Low member elevations
Deck and beam heights
Other details that affect the hydraulics
Describe the land use in the area potentially affected by backwater from the crossing.
Discuss any nearby buildings or other structures that potentially will control the allowable
backwater from the crossing.
State the date of the site visit, and include photographs as figures.
Describe any pertinent information from the Bridge Inspection Report (BIR), and consider
including a copy of the report in an appendix. Discuss any information obtained from
contact with Department Maintenance.
State the associated datums for each data source and provide datum conversions needed
to convert elevations between differing datums.
5.7.1.4 Hydrology
Discuss the methods used to determine and check the flow rates applied in the analysis.
Include a summary table of frequencies and discharges used in the final analysis.
The hydrologic calculations, computer input and output, or documentation obtained from
others used to establish the design flow rates should be included in an appendix.
5.7.1.5 Hydraulics
One-Dimensional Model Setup
Identify and briefly describe the computer program used to calculate the water surface
elevations. Include a figure showing the location of the cross sections used in one-
dimensional models. Figures 5.7-1(1) and 5.7-2 are examples of cross section location
figures. Describe the following aspects of the model development:
How the data for all the cross sections were obtained and how cross section
locations were selected
How the starting water surface elevations (tailwater conditions) were determined
How the Manning’s roughness coefficients were selected
If warning messages remain in the final output, describe any attempts to eliminate the
warnings and the reasoning for not resolving them. Input and output from the computer
programs used to analyze the crossing should be included in the appendixes. Electronic
copies of the input files also will be provided to the Department.
In some cases, such as bridge widenings that do not affect the water surface profiles,
calculations may not be performed. However, you must still include the flood data at the
site in the plans, per FHWA requirements. If you do not calculate the flood data, then you
must obtain them from another source. Typical sources that can be used are hydraulic
reports for the existing crossing or FEMA Flood Insurance Studies. Document the source
in the report.
Compare water surface elevations for the existing and proposed alternative bridges. The
location of the approach section may vary between the existing bridge and each of the
alternative bridges. For the comparison to be valid, perform the water surface elevation
comparisons at a section that is at a common location in each model. As illustrated in
Figure 5.7-3, make the comparison at the location of the approach section that is farthest
upstream.
Approach
Section
Section
Alternative 1
Exit
Flow
Comparison
Approach
Section
Section
Section
Alternative 2 Flow
Exit
Include a table that summarizes the water surface elevations for the existing and
alternative bridges. Table 5.7-1 is an example of a table comparing water surface
elevations.
Examples of qualitative descriptions are provided in Figure 5.7-7 and Figure 5.7-8, which
show comparisons between measured and modeled water surface elevations and flow
rates.
FayTropical Storm
Tropical Storm
Fay
GustavHurricane
IkeHurricane
Hurricane
Hurricane
Gustav
Ike
Figure 5.7-7: Model Calibration Plot for the US 90 Bridge over Macavis Bayou
Replacement Project at the River Run Marina
80000
60000
40000
Flow Rate (cfs)
20000
Measured
0
Modeled
-20000
-40000
-60000
-80000
4/5/2001 9:00
4/5/2001 12:00
4/5/2001 15:00
4/5/2001 18:00
4/5/2001 21:00
Date Time
Figure 5.7-9: Velocity Magnitude Contours and Velocity Vectors at the Time of
Maximum Velocity during the 100-Year Storm Surge Event at the SR-A1A Bridge
over the Loxahatchee River
50000
40000
30000
20000
10000
Flow Rate (cfs)
-10000
-20000
-30000
-40000
-50000
0 10 20 30 40 50 60
Simulation Time (Hrs.)
100-year 500-year
Figure 5.7-10: Flow Rate Time Series during the Design and Check Event at the
SR-A1A Bridge over the Loxahatchee River
12
10
8
Water Surface Elevation (ft-NAVD88)
-2
-4
15 20 25 30 35 40 45 50 55 60
Simulation Time (Hrs.)
100-year 500-year
Figure 5.7-11: Water Surface Elevation Time Series during the Design and Check
Event at the SR-A1A Bridge over the Loxahatchee River
4
Velocity Magnitude (ft/s)
0
0 10 20 30 40 50 60
Simulation Time (Hrs.)
100-year 500-year
Figure 5.7-12: Velocity Magnitude Time Series during the Design and Check Event
at the SR-A1A Bridge over the Loxahatchee River
Alternatives Analysis
You will not need this section for bridge-widening projects. For new and replacement
bridges, this section should document the cost analysis, environmental impacts, and other
impacts on adjacent properties. Each alternative still should meet the design standards,
but if exceptions must be made for an alternative, then the exception should be included
in the comparisons. This section must document the reasons for selecting the
recommended alternative.
5.7.1.6 Scour
You should plan to include a discussion of the stream geomorphology, the scour history,
the long-term aggradation or degradation, and the scour values, including information on
the methods used to determine each of these items. Plot scour depths in a figure.
Discuss the proposed abutment protection. If you use one of the standard abutment
protection designs given in Section 4.9.3.2 of the Drainage Manual, abutment scour need
not be calculated and plotted. You may use other abutment protection designs in certain
circumstances, but not without prior approval from the District Drainage Office.
5.7.1.8 Appendices
Include calculations and other backup documentation as appendixes to the BHR to avoid
disrupting the flow of the main body of the report. Items to consider including in the
appendixes are:
Hydrology calculations
Hydrology reports from other sources
Hydraulic calculations
Hydraulic reports from other sources
FEMA report excerpts and maps
Scour computations
Cost calculations for alternatives
Deck drainage calculations
Regulatory requirements and permits
Memos, meeting minutes, and phone notes
the Bridge Development Report and preliminary Structures Plans. Figure 250.2.1 of the
FDM outlines a flow chart for the Structural Plans Development Process.
The process flow chart in Figure 5.7-13 shows the general sequence of events necessary
to prepare a Bridge Hydraulics Report. You also may need to perform additional
coordination, especially for projects involving floodways or for other complex elements.
After you have a relatively good idea of the approximate structure length and location,
you should conduct a field review. Then, submit the preliminary structure length and
location, along with preliminary scour depths and low member elevations to the Structures
Design Office for their preliminary evaluation. After you have developed the proposed
bridge configuration and foundation type and submitted them back for review, perform the
final hydraulic and scour analyses and submit them to the Structures and Geotechnical
Departments.
Have the BHR and BHRS reviewed internally (or by an outside consultant, if necessary).
After you have addressed all comments, approve the BHR and BHRS and submit them
to the Department for concurrence. After the BHR and BHRS receive concurrence from
the Department, the final BHR and BHRS should be submitted to the structural and
geotechnical engineers so that they can complete the BDR and geotechnical reports.
2
Hydraulics Engineer starts hydraulic
calcs to establish the minimum
hydraulic structure to avoid high Survey data to
Yes velocities and/or adverse upstream Hydraulics
effects and to establish the minimum Engineer
low member elevation for drift
clearance
Geotechnical
Finalize scour calculations
Information
Does scour
calculated dictate a
Yes
structure different
than assumed?
No
* BHRS prepared
*Hydraulics Engineer completes BHR
and furnishes needed information to
Structures
Plan View
Profile View
Location Map and Drainage Area
Existing Structures, Hydraulic Design Data, and Hydraulic Recommendations
FDM 305 gives the minimum requirements of the first three sections. In addition, consider
the following items:
In the Plan View, the FDM requires that the limits of riprap be shown. However,
abutment protection other than riprap may be proposed. Show the horizontal
extents and label the protection type in either the plan or profile view.
Plot and label the profile of the existing natural ground in the Profile View, and note
the existing elevation at each end.
When practical, you should show the profile of the expected design scour
(contraction and long-term scour along the entire unprotected cross section and
the local scour at the intermediate piers/bents). Display local scour holes as
beginning at the foundation element edges at the design scour depth and
extending up at a 1V:2H slope to meet the profile, illustrating the contraction/long-
term scour profile.
Although the profile grade line must be plotted in the Profile View, you do not need
to show percent of grade. Plot the PC, PI, and PT of vertical curves using their
respective standard symbols; however, there is no need to note data (station,
elevation, length of curve). Flag begin and end bridge stations.
Figure 5.7-14 shows a larger view of the section of the BHRS that includes Existing
Structures, Hydraulic Design Data, and Hydraulic Recommendations. The hydraulic
design data and hydraulic recommendations are for the proposed structure. The required
data are identified by bold numbers in parentheses and a brief description is provided on
the following pages.
(50)
(1) Existing Structures: Structure 1 refers to the structure being replaced or modified.
Structures 2, 3, and 4 refer to relief structures, immediate upstream and
downstream structures, and those structures that affect the hydraulics of the
proposed structure.
(2) Proposed Structure: This column should have information pertaining to the
proposed structure.
(3) Foundation: This row should have information describing the type of foundation
(e.g., timber piles, concrete piles, etc.).
(4) Overall Length (ft): This row should give the total length of the structure in feet.
The length should be measured from the top of the abutments. For the proposed
structure, this length should match the total length shown in the final plans.
(5) Span Length (ft): This row should give the span length of the structure in feet.
This length should be based on the length at the main span.
(6) Type of Construction: This row should have information describing the
material(s) used for construction of the structure (e.g., steel, concrete, steel and
concrete, etc.).
(7) Area of Opening (ft2) @ D.F.: This row should have the area of opening in square
feet below the design flood elevation less the assumed pile area, if significant, at
the bridge section.
(8) Bridge Width (ft): The bridge width should be from rail to rail, including the rails,
in feet.
(9) Elev. Low Member (ft): This elevation in feet should be the lowest point along the
low member of the structure.
(10) N.H.W. (Non-Tidal) (ft): The Normal High Water at the bridge. This water surface
elevation in feet only applies to non-tidal areas.
(11) Control (Non-Tidal) (ft): The water surface elevation in feet controlled by the
operation of pump stations, dams, or other hydraulic structures.
(12) M.H.W. (Tidal) (ft): The Mean High Water elevation in feet at the bridge. This
water surface elevation only applies to tidal areas.
(13) M.L.W. (Tidal) (ft): The Mean Low Water elevation in feet at the bridge. This water
surface elevation only applies to tidal areas.
(14) Max. Event of Record: This column provides information related to the maximum
event recorded based on historical information (if available).
(15) Design Flood: This column provides information related to the design flood.
(16) Base Flood: This column provides information related to the base flood.
(17) Overtopping Flood/Greatest Flood: If the overtopping flood has a lower return
period than the greatest flood, then the block indicating overtopping flood is
checked and the information related to the overtopping flood is shown.
Otherwise, the block indicating greatest flood is checked and the information
related to the greatest flood is shown.
(18) Stage Elev. NAVD 88 or NGVD 29 (ft): For freshwater flow, the elevation in feet
typically taken from the hydraulic model at the approach section for the design
flood and/or base flood, overtopping flood, greatest flood. Proper engineering
judgment is required for long bridges since it may not be realistic to use the
elevation at the approach section because the losses between the bridge and
approach section are large.
For tidal flow, the maximum elevation during the flood or ebb storm surge at the
bridge for the design flood and/or base flood, overtopping flood, greatest flood.
Add a remark that stage, discharge, and the velocity described in the flood data
do not occur at the same time.
(19) Discharge (cfs): For freshwater flow, the total discharge in cubic feet per second
used in the simulations for the design flood, base flood, overtopping flood, and/or
greatest flood.
For tidal flow, the maximum discharge during the flood or ebb storm surge at the
bridge for the design flood, base flood, overtopping flood and/or greatest flood.
Add a remark that stage, discharge, and the velocity described in the flood data
do not occur at the same time.
(20) Average Velocity (fps): For freshwater flow, the average velocity in feet per
second taken from the computer simulations at the Bridge Section for the design
flood, base flood, overtopping flood and/or greatest flood.
For tidal flow, the maximum average velocity at the bridge section during the
flood or ebb storm surge for the design flood, base flood, overtopping flood and/or
greatest flood.
(21) Exceedance Prob. (%): The probability that the conditions are exceeded.
Determined as 100% times unity over the return interval (e.g., 100%*(1/100) =
1%).
(23) Frequency (yr): The frequency (return period) in years of the worst case scour
condition up through the design return period flow conditions.
(24) Frequency (yr): The frequency (return period) in years of the worst case scour
condition up through the design check period flow conditions.
(25) Pier No.: The pier number or range of pier numbers that correspond to the pier
size and type in Column 26 and the scour elevations in Columns 27, 28, and 29.
(26) Pier Size and Type: The proposed pier size and type that produces the greatest
scour. If necessary for clarity, place a reference to the appropriate details of the
bridge plans. If the space provided is not adequate, place the information in the
plan or profile view.
(27) Long-Term Scour (ft): Applicable only to structures required to meet extreme
event vessel collision load. See Section 6.2 for the definition of long-term scour.
If it is not applicable, state so.
(28) Total Scour Elevation (< 100-year) (ft): The predicted total scour elevation in feet
for the worst-case scour condition up through the scour design flood frequency.
This includes aggradation or degradation, channel migration, local scour (pier
and abutment), and contraction scour.
(29) Total Scour Elevation (< 500-year) (ft): The predicted total scour elevation in feet
for the worst-case scour condition up through the scour design check flood
frequency. This includes aggradation or degradation, channel migration, local
scour (pier and abutment), and contraction scour.
(30) Begin Bridge Station: The station for the beginning of the bridge.
(31) End Bridge Station: The station for the end of the bridge.
(32) Skew Angle (degrees): The angle in degrees at which the structure is skewed
from the centerline of construction. See Standard Plans, Index 400-289, Sheet
1, Schematic “B” for further explanation.
(33) Navigation Clearance (Horiz.) (ft): The actual horizontal navigation clearance in
feet provided between fenders or piers.
(34) Navigation Clearance (Vert.) (ft): The actual vertical navigational clearance in
feet provided between fenders or piers.
(35) Navigation Clearance (Above El.) (ft): For freshwater flow, the elevation (NAVD
88 or NGVD 29, ft) at the normal high water (NHW) elevation or control elevation.
For tidal flow, this is the elevation at mean high water (MHW).
(36) Drift Clearance (Horiz.) (ft): The actual minimum horizontal clearance in feet
provided.
(37) Drift Clearance (Vert.) (ft): The actual minimum vertical clearance in feet provided
above the design flood.
(38) Drift Clearance (Above El.) (ft): For freshwater flow, this is the design flood
elevation (NAVD 88 or NGVD 29, ft) and either of two values is appropriate. In
many cases, it is reasonable to use the elevation at the approach section,
realizing that this will be slightly higher than actual elevation at the bridge.
For tidal flow, use the maximum stage associated with an average velocity of 3.3
fps through the bridge section during the flood or ebb for the storm surge for the
design flood. If the maximum velocity due to the storm surge is less than 3.3 fps,
use the stage associated with the maximum velocity through the bridge section.
If either of these stages causes the profile to be higher than the profile of the
bridge approaches, consider other alternatives. One alternative is to discuss with
personnel in the Structures Design Office the potential of having less drift
clearance and designing the structure for debris loads. Another alternative is to
do a more rigorous and site-specific analysis to set the stage above which to
provide the standard drift clearance. Investigate and address these situations on
a site-specific basis.
(39) Navigation Clearance (Horiz.) (ft): The minimum horizontal navigation clearance
in feet required. See the FDM 210 for the minimum requirements. Other agencies
may have minimum clearance requirements.
(40) Navigation Clearance (Vert.) (ft): The minimum vertical navigation clearance in
feet required. The Department minimum clearances are given in the FDM 210.
Other agencies may have minimum clearance requirements.
(41) Drift Clearance (Horiz.) (ft): The minimum horizontal debris drift clearance in feet
required. The Department minimum clearances are given in the FDM 210.
(42) Drift Clearance (Vert.) (ft): The minimum vertical debris drift clearance in feet
required above the design flood. The Department minimum clearances are given
in FDM 210.
(43) Rubble Grade: Grade of rubble (e.g., Riprap (Bank & Shore), etc.) to be
constructed at the begin and end bridge abutments. References can be made to
details sheets if non-standard riprap is employed.
(44) Slope: Slope of the abutments at the begin and end bridge (e.g., 1H:2V, etc.).
(45) Non-buried or Buried Horiz. Toe: Indicate whether the toe of the abutment will be
non-buried or buried when extended horizontally from the bridge. See Section
5.5.4 of this document for details.
(46) Toe Horizontal Distance (ft): Horizontal extent in feet of the rubble protection
measured from the toe of the abutment. See Section 5.5.4 of this document for
details.
(47) Limit of Protection (ft): Distance measured parallel to the stationing in feet, from
the edge of the rubble protection to the bridge begin/end station. If the distance
is different on each side, indicate both distances with their corresponding sides.
(48) Deck Drainage: Type of deck drainage to be used for the proposed structure
(e.g., scuppers, storm drain system, etc.)
(50) Wave Crest Elevation (ft): The 100-year design wave crest elevation in feet,
including the storm surge elevation and wind setup. The vertical clearance of the
superstructure must be a minimum of 1 foot above the wave crest elevation. The
Department minimum clearances are given in FDM 210.
6. STORM DRAINS
6.1 FDOT STORM DRAIN TABULATION FORM
The primary means of documenting storm drain design is the Department’s storm drain
tabulation form shown in Figure 6.1-1. On this form, record items identified by numbers in
parentheses on Figure 6.1-1. These items are discussed in the description following the
form. This information also is available on the FDOT Drainage web site.
ACTUAL VELOCITY
PIPE NOTES
DRAINAGE HYDRAULIC
STRUCTURE NO.
SIZE SLOPE (%) AND
LOCATION AREA (Acres) GRADIENT
NUMBER OF BARRELS *
HYD. GRAD.
(fps)
INLET ELEVATION (ft.)
TYPE OF STRUCTURE
C= (1) ** FLOWLINE RISE FREQUENCY (Yrs): (39)
INTENSITY (in/hr)
ELEVATION (ft.)
ELEVATION (ft.)
DISTANCE (ft.)
LOWER END
TOTAL (C*A)
LENGTH (ft.)
UPPER END
INCREMENT
SUB-TOTAL
PHYSICAL
VELOCITY
STATION LOWER SPAN MIN. PHYS.
TOTAL
FALL
(C*A)
SIDE
(fps)
(ft.)
(2) (6) (9) (10) (11) (21) (22) (27) (30) (32) (35)
(7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20) (23) (24) (29) (33) (37) (42)
(3) (4) (5) (6) (28) (31) (36)
(9) (10) (11) (25) (26) (34)
32. Slope (%) (Hydraulic Gradient): For 39. Frequency (Yrs): The Storm Drain
pipes under pressure flow, this is the Design Frequency according to
full-flow friction slope. For pipes Section 3.3 of the Drainage Manual.
flowing partially full, this is: [Upper 40. Manning’s “n”: For storm drains, this
End HG (21) – Lower End HG (22)] value should be 0.012 according to
/Hydraulic Length (8). Show this Section 3.6.4 of the Drainage
number to one hundredth of a Manual. Document any other
percent. Manning’s “n” values used in the
Remarks Column (42).
33. Slope (%) (Physical): Determined
from Physical Fall (28)/Hydraulic 41. Tailwater EL (ft): The water elevation
Length (8). Show this number to one coincident with the outlet pipe and
hundredth of a percent. established by Section 3.4 of the
Drainage Manual. Some districts may
34. Slope (%) (Minimum Physical): The have more stringent criteria.
flattest physical slope to maintain a 42. Remarks: Include such things as:
velocity of 2.5 FPS flowing full, area adjustments, partial flow
obtained from rearranging Manning’s depths, existing pipe connections, or
equation: anything unusual.
S MIN = [Vn / (1.49R2/3)] 2
6.2 HYDROLOGY
The rational method is used for pipe sizing, inlet capacity, and spread calculations.
Q=CiA
where:
Q = Runoff, in cubic feet per second (cfs)
C = Runoff Coefficient (see Table B-4, Appendix B)
i = Rainfall intensity, in inches per hour
A = Area, in acres
The first reason is conservatism within the storm drain design procedure. The flow rate
calculated for each pipe section is the peak flow rate. This is conservative because we
calculate the hydraulic gradient assuming that peak flow rates exist in all of the pipe
sections simultaneously. In reality, when one pipe section is at peak flow, usually one or
more of the other pipe sections have flow rates less than peak. This is most evident
when considering the differences between the upper and lower parts of a long system.
For example, consider a system where the outlet pipe’s flow is calculated based on a
Time of Concentration of 35 minutes. The flow rates of the first several pipes were based
on Times of Concentration of 10 minutes to 15 minutes. If a 35-minute storm and its
associated intensity is applied to the entire system, the flow rates in the first several
pipes would be less than the flow rate we calculated based on Times of Concentration
= 10 minutes to 15 minutes. Therefore, the friction losses in these pipes actually are less
than we calculated. Conversely, during short, intense storms, the upper pipes could
reach their design flow rates, but the downstream portion of the system does not have
the entire area contributing, so downstream pipes do not see the design flows. This
conservatism exists to some degree throughout all pipe systems, but has a minimal
effect on short systems where the differences in Times of Concentration are small.
Another reason an urban typical section can handle storms of greater magnitude is that
the roadway itself can convey substantial flow. A standard pavement section of 0.02 ft/ft
cross slope on a 0.3-percent longitudinal grade can convey approximately 7 cfs 1 with
the depth of the flow at the top of the curb.
The last reason, although less significant, is that when the flow in the road reaches the
height of the curb, there is more pressure on the piping system, thus forcing more flow
through the pipes.
Considering these reasons, look at the system to see if there are any places where the
water elevations or discharge rates could be increased.
● Are there sags in the profile? If so, could the pond water leave the right of way
at these locations? Would water have gone that direction in the pre-developed
condition?
• Is the roadway blocking overland flow in any areas? If so, would the blocked
water substantially change land use values?
• Where back-of-sidewalk inlets are used, should check valves or flap gates be
used to prevent the water in the pipes from backing off of the right of way?
• Would the inlets at the ends of the system bypass flow during a more severe
storm event? If so, would water have gone that direction in the pre-developed
condition?
If you have concerns after considering these factors, it may be appropriate to do a more
detailed evaluation. Perhaps check the operation of the storm drain system with higher
frequency (less frequent) storm. Perhaps the storage in the road and the pipes could be
modeled. You may need a more detailed model of the pre-developed conditions.
If, after evaluating these situations, it is evident there would be increased discharge or
increases over pre-developed stages that would significantly change land use values,
document this conclusion. Then change the storm drain design as necessary to bring
the stages down or to reduce the discharge. This is not saying use a higher design
frequency for the storm drain system. Instead, use larger pipes where necessary.
Increasing pipe size to prevent the adverse impacts to adjacent properties is different
than using a higher design frequency and maintaining the standard hydraulic gradient
clearance.
The Department encourages that this check be made at apparent junctions or inlets in a
storm drain system. It is acceptable but not necessary to check every pipe section for
peak flow from reduced area. Some computer programs may do this automatically.
Scott Street
Figure 6.2-2
Find:
● The design flow rate for pipe section P31-32.
S30
TC = 11 min.
3.7 Ac @ C =0.95
0.3 Ac @ C =0.20
T sect (P30-31) = 1 min
First, calculate the flow rate using the total drainage area (maximum tc).
The tc is the time it takes for the entire drainage area to contribute. It is the longer
of:
(tc)S-29 + Time of Flow in Section P29-31 = 26 + 2 = 28 min
(tc)S-30 + Time of Flow in Section P30-31 = 11 + 1 = 12 min
Therefore, (tc)S-31 = 28 min.
Now, check for a larger flow from part of the drainage area (peak flow from
reduced area).
6. Estimate the area that will contribute from S-29 during a 12-minute storm.
One approach is to reduce the area from the pipes having long times of
concentration by the ratio of the times of concentrations. Ratio = (Short tc)/(tc of
the associated pipe).
7. Add the areas that will contribute to S-31 during a 12-minute storm.
For pipe sections downstream of P31-32, add the incremental drainage areas to the
reduced areas recorded for P31-32. Then, add the time of flow in downstream sections
to the reduced time of concentration for P31-32.
Table 6.2-1 shows a way of presenting these approaches on the Tabulation form.
Table 6.2-1
NOTES
NUMBER
Example Approach
RE
(ac.)
INTENSITY (IPH )
REMARKS
TOTAL FLOW
C•A—TOTAL
(MINUTES)
(MINUTES)
C = 0.95 SUB- Zone:
(cfs )
TOTAL
C= C•A Frequency (Yrs):
UPPER
C = 0.2 Manning’s “n”:
Tailwater EL (ft):
LOWER INCREMENT TOTAL
31 0 0.7 0.14
n/a 3.7 3.52
30 J1 11 1 3.58
31 n/a 0.3 0.06
Area from S-29 reduced
0.2 4.26 4.05
by 12/28. Intensity based
31 MH 0.0 12 - 6.0 4.17 25.0 on System Time from S-
30
32 0.6 0.12
The Department realizes that current design software does not use the approach of
ignoring time of flow in section. As such, some districts may not require that time of flow
be ignored through submerged pipes.
6.3.1.2 Sags
Normally, one inlet at the low point in combination with inlets on each of the approaching
grades is sufficient to meet spread criteria.
Use flanking inlets for sags that have no outlet other than the storm drain system—for
instance, underpasses, barrier wall sections, or depressed sections where the roadway
is much lower than the surrounding ground. Flanking inlets are those placed on one or
both sides of and fairly close to the sag inlet. They provide backup capacity for the sag
inlet if it becomes clogged. The flanking inlets must be located to satisfy spread criteria
when the sag inlet is blocked. Figure 6.3-1 shows a representation of this location
pattern. Figure 6.3-9 provides vertical curve formulae to help determine the flanking inlet
locations.
Figure 6.3-1
The piping system layout may affect the locations of curb and gutter inlets. As you lay
out the piping system, you may need a manhole to redirect the flow, to provide
maintenance access, or merely to connect stub pipes. If you use an inlet rather than a
manhole, you get the benefit of an additional hydraulic opening for little or no additional
cost. Section 6.4, below, discusses piping system layout.
In instances where you may need numerous back-of-sidewalk inlets, check with the
roadway designer about modifying the roadway profile grade to better accommodate
overland flow.
Standard Plans, Index 425-060 contains the standard back-of-sidewalk drainage inlets.
Use yard drains and the double four-inch pipes under the sidewalk to correct small
existing flooding problems. For any other back-of-sidewalk drainage, obtain right of way
as necessary to construct a ditch bottom inlet or other substantial back-of-sidewalk
drainage conveyance.
Where the Department’s storm drain system connects to back-of-sidewalk inlets, check
the hydraulic grade line elevation at these inlets to see if water would back up or cause
the system to create adverse impacts to adjacent properties. If so, first consider
increasing the size of some downstream pipe sections. If avoiding adverse impacts by
increasing pipe sizes is not feasible, consider using check valves or flap gates in the
pipe connected to the back-of-sidewalk inlet (see Figure 6.3-2). Flap gates and check
valves are not ideal because they require maintenance; nevertheless, they may be the
most practical option for some situations.
Flap Gate
(Designer to specify)
Yard Drain
(Index 282)
or DBI
To Storm Drain
Figure 6.3-2
The Department uses four inches per hour (iph) as the intensity that reduces the driver’s
sight distance to less than the minimum stopping sight distance. This is based on
information summarized in FHWA HEC 21.
0.56 5 3 1 2 8 3
Q= S x SL T
n
where:
Q = Gutter flow rate, in cubic feet per second (cfs)
n = Manning’s roughness coefficient (see Table B-2, Appendix B)
Sx = Pavement Cross Slope, in feet per feet (ft/ft)
SL = Longitudinal Slope, in feet per feet (ft/ft)
T = Spread, in feet (ft)
Figure 6.3-8 provides a nomograph for solving this equation, which is intended for use
with triangular gutter sections. The standard Type F curb forms a composite section
when combined with the pavement cross slope. In most cases, it is reasonable to ignore
the gutter depression and treat the flow section as a simple gutter formed by the cross
slope of the road and the curb. Ignoring the gutter depression is conservative2, but
allows for debris buildup in the gutter. If you need to determine the additional capacity
of the gutter depression, use Figure 6.3-10 or the procedures provided in FHWA’s HEC
12 or HEC 22.
2 The gutter depression can add approximately 31% to the conveyance of the flow section in cases
where the pavement cross slope is 0.02 and the spread width is 7.5 feet.
To provide adequate drainage in sag vertical curves, maintain a minimum gutter grade
of 0.3 percent down to the inlet at the low point. Without this minimum grade, the flat
longitudinal grade near the low point would cause the spread to be greater than
allowable. Maintaining the minimum gutter grade up to the inlet increases the cross
slope at the low point, thus providing additional drainage. To maintain the minimum
gutter grade, develop and show special gutter grades in the plans.
½ Typ. Section
Find:
● The limits of the special gutter grade
● The theoretical gutter elevation at the low point
● The cross slope at the low point
1. Determine the rate of change of longitudinal slope. (Formula from Fig. 6.3-9)
2. Find the location of the low point and the location where the longitudinal slope on
the curve is -0.3 percent and +0.3 percent. Use the equation for longitudinal slope
at any point and rearrange to solve for X.
3. Find the elevation of the profile grade line at Sta. 48+45.45 and Sta. 49+81.82.
Both are equal distance from the center, so we only need to find one elevation.
4. Find the elevation at the gutter at Sta. 48+45.45. (This equals the elevation of the
gutter at Sta. 49+81.82.)
The edge of pavement is 0.56 ft. (28 ft. x 0.02) lower than profile grade line and
the gutter is 1.5 inches (0.125 ft.) below the edge of pavement, so:
ElevGUTTER = Elev PGLSta. 48+45.45 – 0.56 – 0.125 = 35.204 ft. – 0.56 ft. – 0.125 ft.
= 34.519'
This elevation would be used to check the hydraulic grade line clearance below
the sag inlet.
The elevation of the profile grade line at the low point is:
This would be used to check the spread of the inlet at the low. Interpolate
between the values in Appendix I, Figures I-17 through I-19, where the cross
slope value is between the values of the figures.
The Drainage Manual gives two spread criteria for sections with shoulder gutter. One is
related to driver visibility (rainfall intensity of four inches per hour) and the other is related
to erosion protection of the fill slope (10-year design storm). Both criteria need to be
met. Consider the potential for future additional lanes in the median when determining
the flow rates in shoulder gutter.
In a typical situation where standard cross slopes and shoulder widths exist, the criterion
for protecting the fill slope has a higher intensity and less allowable spread than the
criterion for driver safety. Thus, the criterion for protecting the fill slope will set the inlet
spacing.
Given the typical situation where both the shoulder and the miscellaneous asphalt
behind the gutter slope upward at 0.06 ft/ft from the gutter, the spread across the gutter
and pavement section should not exceed six feet for the 10-year storm. This section has
a conveyance of approximately 28 cubic feet per second [K = Q/SL½ = 28 cfs]. You can
use the conveyance to determine maximum allowable flow rates for various longitudinal
slopes. Another approach is to treat the shoulder gutter and pavement section as a
triangular gutter with a cross slope of 0.05 ft/ft, designing for 10-year flows, and limiting
the spread to six feet (see Figure 6.3-4).
3. Consider placing two gutter inlets at the down gradient shoulder gutter terminus
to provide 100-percent interception, unless 100-percent interception by one inlet
(K = 15 cfs) is demonstrated by appropriate calculation.
4. Inlet spacing must meet spread criteria (Drainage Manual, Section 3.9),
maximum pipe length criteria (Drainage Manual, Section 3.10.1), and 10-year
frequency gutter capacity criteria. In most cases, the 10-year frequency storm
may govern inlet spacing.
5. Where applicable, design inlet spacing to accommodate the additional runoff from
future widening.
6. Place gutter inlet(s) at the down gradient end of all shoulder gutter, in lieu of
concrete spillways or flumes, to reduce the potential for erosion.
Traffic Lane
Edge of
Figure 6.3-4
Start at the upper-most inlet and work to the low point, then start at the opposite high
side and work back to the low.
1. Determine the drainage area and runoff coefficient of the overland runoff. Record
the product of the area and runoff coefficient (C*A) in column 2.
2. Calculate the overland runoff by multiplying the product of C*A in column 2 by the
appropriate intensity (four inches per hour or 10-year storm design).
Q = C • A • i.
3. Calculate the total flow to the inlet by adding the overland runoff in column 3 to
the bypass from the upstream inlets.
4. Record the cross slope and longitudinal slope in column 6 and column 7,
respectively.
5. Calculate the spread and compare it to the allowable spread, keeping in mind
that allowable spread can vary along the project due to super-elevation slope
toward the median, turn lanes, and design speed. If it is within the standards,
record the number in column 8 and go to the next step. If it is not, move the inlet
(and add and move inlets as necessary) to make the spread acceptable and
repeat Step 1 through Step 5.
6. Calculate intercepted flow and bypass flow. (The figures in Appendix I can be
used in lieu of calculations to determine intercepted flow. Record these numbers
in column 9 and column 10, respectively.
7. Proceed to the next downstream inlet and repeat Step 1 through Step 6.
Manning's n = _______
Bypass to
Inlet No. Cross Long Allowable Inlet No.
or C•A Overland Previous Spread or
Runoff By-pass Total Flow Slope Slope Spread Intercepted Bypass
Location (ft/ft) (%) Flow Flow to Inlet @
(1) (2) (3) (4) (5) (6) (7) (8) (8a) (9) (10) (11)
900' 900'
320' V.C.
42'
Typical Section
Cross Slope = 0.02 ft / ft
Find:
● Inlet spacing necessary to meet the spread criterion
1. For the first try, place the inlets at the maximum 300-foot spacing out from the
low point. So, the inlets will be placed at Station 44+00, Station 47+00, Station
50+00, Station 53+00, and Station 56+00.
2. Determine the spread, the intercepted flow, and the bypass (if any) for the
uppermost inlets. (Sta. 44 & 56)
3. Determine total flow to the next downstream inlets. (Sta. 47 & 53)
5. Determine the spread approaching the sag inlet from either side.
6. Determine the spread approaching the sag inlet. The longitudinal slope is 0.3
percent approaching the sag. For this example, the cross slope at the low point
is 0.021 ft./ft. due to maintaining 0.3-percent gutter grade to the sag inlet. This
was calculated using the approach in Example 6.3-1.
44+00 0.70 2.8 -- 2.8 0.02 2.0 9.3 2.1 0.7 47+00
47+00 0.70 2.8 0.7 3.5 0.02 2.0 10.2 2.3 1.2 50+00
56+00 0.70 2.8 -- 2.8 0.02 2.0 9.3 2.1 0.7 53+00
53+00 0.70 2.8 0.7 3.5 0.02 2.0 10.2 2.3 1.2 50+00
50+00 0.70 2.8 1.2 4.0 0.021 0.3 14.7 Exceeds Standard
Approac
h
Figure 6.3-6
The inlets at stations 48+80 and 51+20 are on the vertical curve; therefore, the
longitudinal slope is flatter than 2.0 percent. Using vertical curve formulae:
For this example, the cross slope at the low point is 0.021 ft./ft. due to maintaining 0.3-
percent gutter grade down to the sag inlet. You can calculate this using the approach in
Example 6.3-1. Using Figure I-17 (cross slope = 0.02) will provide a slight conservatism.
55+70 0.77 3.1 0.0 3.1 0.02 2 9.7 2.2 0.9 53+20
53+20 0.58 2.3 0.9 3.2 0.02 2 9.8 2.2 1.0 51+20
51+20 0.47 1.9 1.0 2.9 0.02 1.5 9.9 2.4 0.5 50+00
50+00 0.28 1.1 0.5 1.6 0.021 0.3 10.5 n/a n/a n/a
50+00 0.56 2.2 1.0 3.2 0.021 n/a 6.3 n/a n/a n/a
In an actual project, the inlet location is affected by driveways and side streets.
Find:
1. The location of the shoulder gutter inlets.
Crest Curve:
Rate of change of curve (r) = (g2 – g1)/L = (-2.6 – 3.0)/14 = -0.4
Long Slope at any point X = g1 + r X = 3.0 – 0.4 X
Sag Curve:
Rate of change of curve (r) = (g2 – g1)/L = (3.0 – 0.0)/5 = 0.6
Long Slope at any point X = g1 + r X = 0.0 + 0.6 X
You should use shoulder gutter on all fill slopes greater than 10 feet long if the
roadway grade is greater than 2 percent. For this example, the fill is
approximately 10 feet at Station 67+00. The longitudinal slope at this station
67+00 is: 0.6 x (67 – 63) = 2.4 percent. Since this is steeper than 2 percent,
shoulder gutter should begin at or before Station 67+00.
4. For the first try at inlet spacing, divide the distance between Station 67+00 and
the beginning of the bridge into equal distances that are less than 300 feet.
Distance = 74+75 – 67+00 = 775 feet
This equates to three spaces at approximately 258 feet. Rounding it to 260 feet,
the first inlet will be located at 74+75 – 260 feet = 72+15. The other inlets are at
69+55 and 66+95.
@ 72+15, the longitudinal slope = 3 – 0.4 (72+15 – 70+00) = 3 – 0.4 x 2.15 = 2.14
percent
@ 69+55, the longitudinal slope = 3 percent
@ 66+95, the longitudinal slope = 0.6 x (66+95 – 63+00) = 0.6 x 3.95 = 2.37
percent
An additional lane may be added toward the median in the future, so use 36 feet
of pavement.
Width = travel lanes + shoulder + gutter + slope* under guardrail.
*Conservatively assume that all four feet sloping back to gutter is paved.
The travel time for flow along 260 feet of pavement is small, so we will use the
10-minute intensity for the 10-year storm. i = 7.4 iph
Q = CiA = 0.95 x 7.4 x 0.32 = 2.2 cfs
The intercepted flow is determined from Figure I-16. The following table
summarizes the calculations.
All flows (cfs) based on 10-year flow Allowable Spread = 6 ft Manning's n = 0.016
1 2 3 4 5 6 7 8 9 10 11
Inlet Overland Previous Cross Long Intercepte Bypass Bypass
Location C•A Runoff By-pass Total Flow Slope Slope Spread d Flow Flow to Inlet @
(Sta.) (ft/ft) (%) Station
72+15 0.30 2.2 0.2 2.4 0.05 2.14 4.9 2.4 ---
69+55 0.30 2.2 --- 2.2 0.05 3.0 4.5 2.2 ---
66+95 0.30 2.2 --- 2.2 0.05 2.37 4.7 2.2 ---
This inlet spacing meets the spread criterion for protecting the fill slopes and the last
inlet captures all the runoff coming to it. Therefore, this design is acceptable. There is
no need to check the four inches per hour criterion because the intensity would be less
and the allowable spread would be greater.
g 2 − g1
r=
1. Rate of Change of Grade: L
1
y= rX 2
2. Offset from tangent to curve: 2
1
E x = E pvc + g 1 X + ( rX 2 )
3. Elevation for any point on curve: 2
∂E x
= g1 + rX
4. Grade (longitudinal slope) at any point: ∂X
1 Lg 12
ETP = E pvc −
2 g 2 − g1
6. Elevation of turning point:
Where:
All horizontal dimensions (X) are in Stations.
All vertical dimensions (E) are in Feet.
All grades are in percent.
L = Length of vertical curve in Stations.
Epvc = Elevation of the Point of Vertical Curve.
70
60
[ K ] Conveyance Q / SL^0.5 (cfs)
50
40
Sx = 0.03
Sx = 0.02
Sx = 0.01
30
20
10
0
2 4 6 8 10 12
Spread (ft)
Example
Given: Q = 3 cfs, Sx = 0.03, SL = 0.04 ft/ft
Find Spread:
1. K = Q/SL 0.5 = 3 / 0.04 0.5 = 15
2. From Chart at K = 15 & Sx = 0.03, Spread = 6.0 ft
Figure 6.3-10: Conveyance vs. Spread for Composite Gutter Sections with Type
E or Type F Curb
There are several items to consider that can influence the piping system plan layout.
The most important issues are hydraulics, constructability, and utility conflicts.
• Avoid placing pipes that would oppose flows from other pipes, especially in high-
velocity situations. Impinging flows can be avoided by staggering the elevations of
the pipes entering a junction box.
• Consider right of way necessary to open the trench for the pipes. This is especially
important for deep pipes. You might use temporary sheet piling during installation to
reduce the trench width, but this is very costly, so you will want to explore other
alternatives (e.g., moving the trunk line).
• Use either a manhole or an inlet at changes in flow direction. This will provide
maintenance access where debris and sediment often collect.
• Preferably, place manholes in or behind the sidewalk. This allows access without
closing the travel lanes and is much safer for maintenance personnel. If you must
place manholes in the pavement, avoid putting the lids in the wheel path.
• Minimize interference with major utilities, such as fiber optic lines and sanitary and
potable water lines greater than eight inches in diameter. See the discussion in
Section 6.4.3.
• Where there is one main trunk line, place it on the side of the road constructed first.
This prevents constructing stub lines that can’t be drained.
• Where there is one main trunk line, locate it, if possible, on the low side of super-
elevated roadway sections to minimize the depth of cut.
• Where there is one main trunk line, consider connecting several inlets along the
opposite side of the road from the trunk line, and then running only one pipe laterally
across the road. This will reduce the number of cuts across the road.
• Consider using two trunk lines to minimize the number of cuts across the road and
thus simplify maintenance. In such cases, you should weight the gains in improved
maintenance against the increased cost of the additional trunk line.
Table 6.4-1 provides the minimum physical slope to produce 2.5 feet per second flowing
full for various pipe sizes with Manning’s roughness coefficient of 0.012. Note that the
velocity of 2.5 feet per second is not necessarily the actual velocity in the pipe under
design conditions. Refer to Section 6.5.5 for a discussion of flow velocity.
Table 6.4-1
For very flat systems, the minimum physical slope may not be realistic. The overall fall
across the system is based on outlet pipe depth and structural clearances at the upper
end. Most District Drainage Engineers will approve deviation from the minimum pipe
slope in these cases.
Where you cannot attain the minimum slope, try to design the system to avoid
appreciable drops in the velocity. This will help to carry sediment through the system
instead of dropping sediment at the velocity drop point in the system.
The minimum slope is 0.1 percent for systems under pressure flow.
Setting flow lines relates to the slope. Refer to FDM 300 for the accuracy level to which
you must display flow lines.
The loads placed on precast structures during shipping and handling often are greater
than the loads placed on them in their final location. Since contractors prefer precast
drainage structures and they have become the industry standard, you should consider
the potential for breakage during shipping and handling.
Where pipes are placed high in a structure, the structure has little, if any, strength above
the pipe. This can result in breakage during shipping or handling. For strength reasons,
it is best to maintain a minimum amount of precast concrete section above the pipe.
The ideal amount of precast section varies with the type of inlet and bottom
configuration. Generally, where a pipe is placed in grated inlets or in structure bottoms,
try to maintain a six-inch precast section that has full wall thickness above the pipe
opening, as shown in Figure 6.4-1. For ditch bottom inlets placed on J bottoms, the
recommended minimum precast riser section varies depending on if the unit has slots.
Refer to Structure/Pipe configuration numbers 4 & 5 in Figure 6.4-5. For ditch bottom
inlets without slots, maintain a 10-inch riser section below the grate seat. For ditch
bottom inlets with slots, maintain a 12-inch riser section below the slot.
6" Precast
Grate Seat Section
Precast
Opening*
Figure 6.4-1
Tables 6.4-4 and 6.4-5 give recommended minimum distances from inlets to pipe flow
lines for most of the Department’s standard inlets. These distances provide the precast
section discussed above and are based on concrete pipe that is centered in the precast
opening. The above discussion represents ideal values that you should try to achieve.
On occasion, you will need to use less precast section than discussed above. This is
acceptable because the contractor has the option to cast structures in place. When using
less precast section, you must add all the appropriate dimensions to assure that no
conflict will exist between pipes and the structure.
Sometimes minor changes in the storm drain design can reduce the cost to a utility
company and minimize the cost to the public. At other times, it may not be practical or
cost effective to accommodate a utility company proposal. Utility companies often take
the opportunity to upgrade their systems or add facilities during the Department’s
construction project. Do not assume they will relocate their systems in the process.
On projects with long storm drain systems in areas of many utilities, include one
additional manhole in the quantities for unforeseen utility conflicts.
Check sizes of structure bottoms to make sure that the pipes fit. When doing so, use the
outside diameter of concrete pipe 3. It has the thickest wall of any of the optional pipe
materials. Type P structure bottoms are either 4’-0” or smaller diameter round (Alternate
3
An easy way to remember the wall thickness of the concrete pipe is to take the inside diameter in feet
and add one (1). The result is the wall thickness in inches. Examples: 30” pipe, I.D. = 2.5 feet, Wall
Thickness = 2.5 + 1 = 3.5”.
A) or 3’-6” square (Alternate B). 30-inch pipe is the maximum size that will fit in Type P
bottoms.. The contractor has the option of using either Alternate A or Alternate B for
Type P bottoms unless restricted by the plans. Type J structure bottoms are larger than
Type P bottoms and come in various sizes, as described in Standard Plans, Index 425-
010. The plans usually specify the alternate and the size of the J bottoms. Standard
Plans, Index 425-010 gives the minimal structure dimensions for various pipe sizes.
Table 6.4-2 is an excerpt of Standard Plans, Index 425-010. Refer to the latest version
of the index for updates.
The skew at which a pipe enters a precast rectangular structure is limited by the precast
pipe opening. The maximum opening is six inches larger than the pipe outside diameter
(Standard Plans, Index 425-001). The maximum pipe skew varies with the structure wall
thickness and the pipe size. The maximum skew for various pipe sizes passing through
eight-inch structure walls is shown in Table 6.4-3. Standard Plans, Index 425-010
provides skew values for six-inch structure walls and other pipe sizes. Use round
structure bottoms (Alternate A) where the pipe enters the structure at a larger angle.
Skew
Figure 6.4-2
Standard Plans, Index 425-001 includes a detail of a pipe opening at a corner of a
structure. Although a detail exists for this condition, restrict its use to situations where
other alternatives do not exist. Make every attempt to ensure pipes do not enter the
corner of rectangular structures (“corner-cutouts”).
When placing pipes in existing rectangular structures, the maximum skew is limited by
the dimension of the skewed pipe cut fitting between the walls.
Table 6.4-3
Pipe Size
18" 24" 30" 36" 42" 48" 54" 60"
Max. Skew 19o 17o 16o 16o 15o 14o 14o 13o
These values are based on two inches of construction tolerance, precast structures with eight-inch walls,
and concrete pipe dimensions.
When using round structure bottoms, consider the need to maintain a precast section
between the openings of adjacent pipes. Try to maintain at least a two-inch section along
the inside wall between adjacent pipe openings, as shown to the right. Table 6.4-6
provides the minimum angle between adjacent pipe centerlines to maintain the two-inch
precast section along the inside wall. The values in Table 6.4-6 are based on equal pipe
centerline elevations and standard concrete pipe openings. Using these minimum
angles for pipes with offset centerline elevations and other pipe materials is conservative
and would yield more than two inches of precast section.
2"
Precast Opening
Figure 6.4-3
Where large pipes are stubbed into the main line or a large main line pipe makes a 90-
degree turn, rectangular structures can be smaller than round structures given the same
pipe sizes. Figure 6.4-4 shows 48-inch pipes making a 90-degree turn at a structure. An
eight-foot round structure is needed, while a six-foot rectangular structure would work.
Figure 6.4-4
Table 6.4-4: Recommended Min. Distance from Inlet Elevation to Pipe Flow Line
PIPE LOCATION RECOMMENDED MIN. DISTANCE (FT.) FROM GRATE (INLET) ELEVATION TO PIPE FLOW LINE
INLET SLOT
TYPE TYPE Wall Wall Dim. 15” Pipe 18” Pipe 24” Pipe 30” Pipe 36” Pipe 42” Pipe 48” Pipe 54” Pipe 60” Pipe
Short 2’-0” 2.2 (1) 2.5 (1) 4.8 (5) 5.4 (5) 5.9 (5) 6.5 (5) 7.0 (5) 7.5 (5) 8.1 (5)
Type A
Long 3’-1” 2.5 (2) 2.8 (2) 4.8 (5) 5.4 (5) 5.9 (5) 6.5 (5) 7.0 (5) 7.5 (5) 8.1 (5)
No Slot 2.6 (2) 2.9 (2) 3.4 (2) 4.0 (2) 6.9 (4) 7.5 (4) 8.0 (4) 8.5 (4) 9.1 (4)
Type B Short
Travers Under Slot 3.4 (3) 3.6 (3) 4.2 (3) 4.7 (3) 6.9 (4) 7.5 (4) 8.0 (4) 8.5 (4) 9.1 (4)
(Note 3)
Long 2.6 (2) 2.9 (2) 3.4 (2) 4.0 (2) 4.5 (2) 7.5 (4) 8.0 (4) 8.5 (4) 9.1 (4)
Short 2’-0” 2.2 (1) 2.5 (1) 4.7 (5) 5.2 (5) 5.8 (5) 6.3 (5) 6.8 (5) 7.4 (5) 7.9 (5)
None
Long 3’-1” 2.4 (2) 2.6 (2) 4.7 (5) 5.2 (5) 5.8 (5) 6.3 (5) 6.8 (5) 7.4 (5) 7.9 (5)
No Slot 2.2 (1) 2.5 (1) 5.3 (4) 5.8 (4) 6.3 (4) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
Short
Type C Travers Under Slot 2.8 (3) 3.0 (3) 5.3 (4) 5.8 (4) 6.3 (4) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
(Note 3) Long 2.4 (2) 2.6 (2) 5.3 (4) 5.8 (4) 6.3 (4) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
No Slot 2.2 (1) 2.5 (1) 5.7 (4) 6.2 (4) 6.8 (4) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
Non-Trav Short
Under Slot 3.2 (3) 3.5 (3) 5.7 (4) 6.2 (4) 6.8 (4) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
12” Std.
Long 2.4 (2) 2.6 (2) 5.7 (4) 6.2 (4) 6.8 (4) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
Short 3’-1” 2.4 (2) 2.6 (2) 3.2 (2) 5.2 (5) 5.8 (5) 6.3 (5) 6.8 (5) 7.4 (5) 7.9 (5)
None
Long 4’-1” 2.2 (1) 2.5 (1) 3.0 (1) 3.5 (1) 4.1 (1) 6.3 (5) 6.8 (5) 7.4 (5) 7.9 (5)
Short 2.4 (2) 2.6 (2) 3.2 (2) 5.8 (4) 6.3 (4) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
Type D Travers No Slot 2.2 (1) 2.5 (1) 3.0 (1) 3.5 (1) 4.1 (1) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
Long
(Note 3) Under Slot 2.8 (3) 3.0 (3) 3.6 (3) 4.1 (3) 4.7 (3) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
Short 2.4 (2) 2.6 (2) 3.2 (2) 6.2 (4) 6.8 (4) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
Non-Trav
No Slot 2.2 (1) 2.5 (1) 3.0 (1) 3.5 (1) 4.1 (1) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
12” Std. Long
Under Slot 3.2 (3) 3.5 (3) 4.0 (3) 4.5 (3) 5.1 (3) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
Short 3’-0” 2.2 (1) 2.5 (1) 3.0 (1) 5.2 (5) 5.8 (5) 6.3 (5) 6.8 (5) 7.4 (5) 7.9 (5)
None
Long 4’-6” 2.4 (2) 2.6 (2) 3.2 (2) 3.7 (2) 4.3 (2) 6.3 (5) 6.8 (5) 7.4 (5) 7.9 (5)
No Slot 2.2 (1) 2.5 (1) 3.0 (1) 5.8 (4) 6.3 (4) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
Short
Type E Travers Under Slot 2.8 (3) 3.0 (3) 3.6 (3) 5.8 (4) 6.3 (4) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
(Note 3) Long 2.4 (2) 2.6 (2) 3.2 (2) 3.7 (2) 4.3 (2) 6.9 (4) 7.4 (4) 8.0 (4) 8.5 (4)
No Slot 2.2 (1) 2.5 (1) 3.0 (1) 6.2 (4) 6.8 (4) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
Non-Trav Short
Under Slot 3.2 (3) 3.5 (3) 4.0 (3) 6.2 (4) 6.8 (4) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
12” Std.
Long 2.4 (2) 2.6 (2) 3.2 (2) 3.7 (2) 4.3 (2) 7.3 (4) 7.8 (4) 8.4 (4) 8.9 (4)
Notes: 1. The number in parentheses ( ) refers to one of the structure pipe combinations shown in Figure 6.4-5.
2. *** CAUTION *** Where multiple pipes enter a structure, needing a J-bottom because of one pipe could dictate greater distances than shown above for
other pipes entering the structure.
3. The values shown for Type B, C, D, and E inlets are based on Alternate B Bottoms. Alternate A Bottoms have thicker slabs, so add two inches for up
through six-foot diameter bottoms. Add four inches for eight-foot diameter bottoms.
4. The distances are based on precast structures and standard precast openings for concrete pipes.
5. The designer should check that the minimum cover requirements of Drainage Manual, Appendix C are met.
Figure 6.4-5
Table 6.4-5: Recommended Min. Distance from Inlet Elevation to Pipe Flow Line
PIPE LOCATION RECOMMENDED MIN. DISTANCE (FT.) FROM GRATE (INLET) ELEVATION TO PIPE FLOW LINE
INLET SLOT
TYPE TYPE Wall Wall Dim. 15” Pipe 18” Pipe 24” Pipe 30” Pipe 36” Pipe 42” Pipe 48” Pipe 54” Pipe 60” Pipe
Short 2’-6” 2.2 (1) 2.5 (1) 4.8 (5) 5.3 (5) 5.8 (5) 6.4 (5) 6.9 (5) 7.5 (5) 8.0 (5)
Type F n/a
Long 4’-0” 2.4 (2) 2.7 (2) 3.3 (2) 3.8 (2) 4.3 (2) 6.4 (5) 6.9 (5) 7.5 (5) 8.0 (5)
Short 3’-0” 2.2 (1) 2.5 (1) 3.0 (1) n/a n/a n/a n/a n/a n/a
None
Long 6’-7” 2.4 (2) 2.6 (2) 3.2 (2) 3.7 (2) 4.3 (2) 4.8 (2) 5.3 (2) 5.9 (2) 6.4 (2)
Type H
Non-Trav Short 3’-0” 3.2 (3) 3.5 (3) 4.0 (3) n/a n/a n/a n/a n/a n/a
12” std. Long 2.4 (2) 2.6 (2) 3.2 (2) 3.7 (2) 4.3 (2) 4.8 (2) 5.3 (2) 5.9 (2) 6.4 (2)
6’-7”
Short 3’-3” 2.6 (2) 2.9 (2) 3.4 (2) 5.5 (5) 6.0 (5) 6.5 (5) 7.1 (5) 7.6 (5) 8.2 (5)
Type J n/a
Long 3’-10” 2.4 (2) 2.7 (2) 3.3 (2) 3.8 (2) 6.0 (5) 6.5 (5) 7.1 (5) 7.6 (5) 8.2 (5)
Short 3’-3” 2.6 (2) 2.9 (2) 3.5 (2) 5.5 (5) 6.0 (5) 6.6 (5) 7.1 (5) 7.7 (5) 8.2 (5)
Type S n/a
Long 3’-10” 2.3 (2) 2.5 (2) 3.1 (2) 3.6 (2) 6.0 (5) 6.6 (5) 7.1 (5) 7.7 (5) 8.2 (5)
Short 3’-3” 2.6 (2) 2.9 (2) 3.4 (2) 5.5 (5) 6.0 (5) 6.5 (5) 7.1 (5) 7.6 (5) 8.2 (5)
Type V n/a
Long 3’-10” 2.4 (2) 2.7 (2) 3.3 (2) 3.8 (2) 6.0 (5) 6.5 (5) 7.1 (5) 7.6 (5) 8.2 (5)
Manhole RECOMMENDED MIN. DISTANCE3 (FT.) FROM TOP ELEVATION TO PIPE FLOW LINE
n/a n/a
Type 8 3.7 (10) 4.0 (10) 4.5 (10) 5.0 (10) 6.3 (11) 6.8 (11) 7.3 (11) 7.9 (11) 8.4 (11)
RECOMMENDED MIN. DISTANCE (FT.) FROM LOW POINT OF GRATE TO PIPE FLOW LINE
Barr-
n/a Short 3’-3” 4.2 (8) 4.5 (8) 5.0 (8) 6.2 (9) 6.8 (9) 7.3 (9) 7.8 (9) 8.4 (9) 8.9 (9)
Wall 218
Long 3’-8” 4.2 (8) 4.5 (8) 5.0 (8) 5.5 (8) 6.8 (9) 7.3 (9) 7.8 (9) 8.4 (9) 8.9 (9)
RECOMMENDED MIN. DISTANCE (FT.) FROM EDGE OF PAVEMENT TO PIPE FLOW LINE
Curb 1-9 n/a n/a
3.9 (6) 4.2 (6) 4.7 (6) 5.3 (6) 6.5 (7) 7.0 (7) 7.5 (7) 8.1 (7) 8.6 (7)
Notes: 1. The number in parentheses ( ) refers to one of the structure pipe combinations shown in Figure 6.4-6.
2. *** CAUTION *** Where multiple pipes enter a structure, needing a J-bottom because of one pipe could dictate greater distances than shown above for
other pipes entering the structure.
3. *** CAUTION *** For curb inlets and manholes, where 30” pipes with similar inverts enter a structure at 90 degrees,a J-bottom is required, thus the
minimum distance may be greater than shown above. This may apply to other inlets also.
4. The distances are based on precast structures and standard precast openings for concrete pipes.
5. The designer should check that the minimum cover requirements of Drainage Manual, Appendix C are met.
Figure 6.4-6
Table 6.4-6
If you calculate all minor energy losses, it is acceptable for the hydraulic grade line to
reach the theoretical gutter elevation. Minor losses include all the losses at inlets,
manholes, and junctions due to expansion, contraction, and changes in flow direction.
Minor losses also include exit losses at the outlet of the system. The Drainage Manual
states that minor losses must be calculated when the velocity is greater than 7.5 fps and
for systems longer than 2,000 feet.
where:
n = Roughness coefficient (refer to the Drainage Manual)
L = Pipe length, in feet (ft.)
V = Velocity, in feet per second (fps)
Q = Flow rate, in cubic feet per second (cfs)
R = Hydraulic radius, in feet (ft.) = Area/wetted perimeter
D = Pipe diameter, in feet (ft.)
g = Gravitational constant = 32.2 ft/s2
The most accurate approach to calculating this number is to do water surface profile
calculations throughout the pipe section. Although acceptable, these calculations are
tedious and not usually required. The Department accepts the following approach to
calculating the hydraulics of partial full and pressure pipes.
Three values must be determined for each pipe section: (1) the lower-end hydraulic
gradient (lower-end HG), (2) the upper-end hydraulic gradient (upper-end HG), and (3)
the flow velocity.
Where the downstream hydraulic gradient is low enough, one of two pipe flow conditions
will control the lower-end HG. See Detail C & D of Figure 6.5-1. The appropriate flow
condition is dependent on the relationship of the physical pipe slope and the full-flow
friction slope. If the pipe is sloped steeper than the full-flow friction slope, it is reasonable
to assume that normal depth flow exists at the lower end. Then the lower-end HG is the
normal depth plus the lower-end flow line elevation. (Actual depth could be above normal
depth because the pipe was not long enough to allow normal depth to be reached.)
Partial depth pipe flow graphs in Appendix E, or the Department’s hydraulic calculator,
can be used to get normal flow depth and associated velocity.
If the pipe slope is equal to or flatter than the full-flow friction slope, the pipe is flowing full
over most of its length. Although the flow may be dropping through critical depth 4 near
the outlet, assuming full flow at the outlet is reasonable and conservative. During very low
flow rates, even flat pipes will not flow full, but such low rates are not typical for design
conditions.
In short, use the higher of the following for the lower-end HG, as shown in Figure 6.5-1.
OR
Condition 2: The normal depth + lower-end flow line elevation (for pipes sloped steeper
than full-flow friction slope) or lower-end crown elevation (for pipes sloped equal to or
flatter than full-flow friction slope).
For the outlet pipe of the system, the lower-end HG elevation is the Design Tailwater
elevation.
4 - For a slightly more refined analysis in this situation, midway between critical depth and the crown of the
pipe of [(Dc+ D)/2} could be used as the Lower End HG.
You can determine the pond stage by “routing” the storm drain design event (frequency)
through the pond. “Routing” refers to the use of the storage indication method that is
commonly used to simulate runoff hydrographs flowing through stormwater management
facilities. HEC 22 contains a discussion and example of the storage indication method.
OR
Condition 2: The elevation of normal depth in the pipe at the upper end
A comparison may not be necessary. First, add the full-flow friction loss to the lower-end
HG. If this is above the upper-end crown, there is no need to calculate normal depth. The
lower-end HG plus full-flow friction loss will control.
where:
Q = Flow rate, in cubic feet per second (cfs)
D = Diameter, in feet (ft.)
For pipes flowing partially full, it is more complicated to determine the velocity. There can
be a water surface profile in the pipe, so the cross sectional flow area can change, thus
changing the velocity along the pipe section. The most accurate velocity should represent
the average velocity through the pipe section, assuming the velocity associated with
normal depth is a conservative assumption. See Figure 6.5-3.
You can use partial depth pipe flow graphs in Appendix E, or the Department’s hydraulic
calculator, to get normal flow depth and associated velocity.
The flow velocity is referred to as the Actual Velocity in the Storm Drain Tabulation Form,
Figure 6-1. The actual velocity is sometimes called the design velocity.
Use Figure 6.5-4 to determine the loss factor in conflict boxes where the pipes are flowing full.
2
Vo
Head loss [in feet] = K
2g
where:
K = Loss factor (or coefficient)
Vo = Flow velocity in the outlet pipe of the junction box, in feet per second (ft/s)
g = Gravitational constant = 32.2 ft/s2
FHWA has printed the latest information on computing minor losses in HEC 22, and they
continue to do research on minor losses. A report titled Junction Loss Experiments:
Laboratory Report summarizes work that has been done more recently than the
information published in HEC 22. The report and HEC 22 are available on the Internet at:
http://www.fhwa.dot.gov/engineering/hydraulics/library_listing.cfm?sort=Publication_title&archived=0
6.6 PROCEDURE
The following is a basic procedure for designing a storm drain system. You can vary
slightly from the procedure and still develop an adequate design. With experience, you
will develop shortcuts and personal preference. The goal is to minimize pipe sizes while
meeting the appropriate standards.
The numbers in parentheses (xx) refer to a space on the Storm Drain Tabulation Form.
LAYOUT PIPES
6. Connect pipes between the
You will use the schematic of the piping system for the
inlets to create a schematic of
rest of the design procedure.
the piping system layout.
8. Multiply the subtotal areas Record the result in space (11) on the tabulation
by their respective C-factors. form.
9. Add the sub-total (C*A) Record the total in space (15) on the tabulation
values. form.
10. Repeat Step 7 through
Step 9 for the entire system.
Step 20 and Step 21 are done on each pipe segment, beginning at the outlet and
working up the system toward the most remote inlet.
20. Determine the Lower- The Lower-End HG for the outlet is the Design
End Hydraulic Gradient Tailwater (DTW). See the discussion in Section 6.5.
Elevation. Record the value in space (22) on the tabulation form
for the outlet pipe and in space (41).
21. Determine the Upper- See the discussion in Section 6.5. Record the Upper-
End HG Elevation, HGL End HG Elevation (21). Record the HGL Clearance
Slope, and HGL Fall. (20).
22. Compare the HGL The current standard requires that the Hydraulic
Elevation to the standard Gradient be at least one foot below the inlet elevations.
and adjust pipe diameters.
For systems where the distance between the Hydraulic
Gradient and the gutter elevation is greater than the
standard, the diameter of one or more pipe segments
may be reduced to raise the Hydraulic Gradient. Here,
try to reduce the larger-diameter pipe segments first,
since this will provide a greater cost reduction than
reducing the size of the smaller-diameter segments.
For systems where the distance between the Hydraulic
Gradient and the gutter elevation is less than the
standard, you will need to increase the diameter of one
or more pipe segments to lower the Hydraulic Gradient.
Here, increase the smaller-diameter pipe segments
first, since this will provide less of a cost increase than
increasing the size of the larger-diameter pipe
segments. Look for “flow-pipe size” combinations that
have substantial friction losses. For example, there is
very little reduction in the losses by increasing the
diameter of a 24-inch pipe that is carrying only 3 cfs.
Alternatively, if another 24-inch pipe were carrying 15
cfs, increasing the pipe diameter could achieve a
significant reduction in friction losses.
23. Return to Step 14, When you have made enough iterations through the
working the changes system that any changes in diameters of pipe
through the system. segments would cause the distance between the
Hydraulic Gradient and the gutter elevation to be less
than the standard, your design is essentially complete.
Note:
Examples 6.6-1 and 6.6-2 were created before the Plan Preparation Manual (Volume 2,
Chapter 1.3) required that flow lines be shown to two decimal places and before the
Drainage Manual required that HGL Clearance be provided in the storm tab. The
examples have not been revised to reflect these changes. Although the examples have
not been revised, they still represent a valid design procedure.
Table 6.6-1
LOCATION OF UPPER DRAINAGE AREA NOTES AND REMARKS
STRUCTURE
END (ac) ZONE: 6
STRUCTURE
LENGTH (ft)
ALIGNMENT NAME C = 0.95 FREQUENCY (yrs): 3
TYPE OF
NO.
C= INLET ELEV MANNING’S “n”: 0.012
DISTANCE
STATION
Find:
• The pipe sizes to meet the standard hydraulic gradient clearance of 1.13 feet to the
inlet (edge of pavement) elevation
1. Add the areas that contribute flow to each pipe segment. For each of the pipe
segments, the total impervious area (C = 0.95) is obtained as follows.
The same approach is applied to drainage areas associated with the pervious runoff
coefficient. Table 6.6-2 is a partial tabulation form with the above information.
Table 6.6-2
DRAINAGE AREA
STRUCTURE
(ac.)
C= 0.95
NO.
C=
C= 0.20
2. For each pipe section, multiply the total area associated with each runoff coefficient
by the corresponding runoff coefficient to obtain the subtotal CA values.
P 1-2: 0.3 x 0.95 = 0.29
0.05 x 0.20 = 0.01
P 2-3: 0.5 x 0.95 = 0.48
0.08 x 0.20 = 0.02
Etc.
3. For each pipe section, add the subtotal CA values to obtain the Total CA.
P 1-2: 0.29 +0.01 = 0.3
P 2-3: 0.48 + 0.02 = 0.5
Etc.
Table 6.6-3
STRUCTURE
NO.
SUB-TOTAL
TOTAL
C •A
C •A
UPPE C= 0.95
R C=
C= 0.20
LOW
INCREMENT TOTAL
ER
0.3 0.3 0.29
1
0.30
2 0.05 0.05 0.01
0.2 0.5 0.48
2
0.50
3 0.03 0.08 0.02
--- 0.5 0.48
3
0.50
4 --- 0.08 0.02
0.4 0.9 0.86
4
0.9
7 0.1 0.18 0.04
0.4 0.4 0.38
5
0.48
7 0.5 0.5 0.1
--- 1.3 1.24
7
1.38
8 --- 0.68 0.14
0.15 0.15 0.14
6
0.24
8 0.5 0.5 0.1
0.25 1.7 1.62
8
1.96
outlet 0.5 1.68 0.34
11. Determine the pipe flow lines, physical slope, and fall. [P1-2]
For this example, we will use 4.5 feet clearance between the inlet (edge of
pavement) elevation and the flow line of an 18-inch pipe. (The minimum clearance
for an 18-inch pipe in a precast Type P-5 structure is 4.2 feet. See Table 6.4-5.)
Then:
Upper-End Flow Line = 10.9 – 4.5 = 6.4 feet
For this example, we will assume there are no constraints such as utilities that
would prevent the pipe from being set at the minimum physical pipe slope (0.15
percent). Then:
Minimum pipe fall = 110 ft x 0.15% = 0.17 feet
Pipe fall = 0.2 ft (minimum fall rounded up to nearest 0.1 foot)
Physical Slope = 0.2 ft/110 ft = 0.18 percent
Lower End Flow Line = 6.4 – 0.2 = 6.2 feet
If this were an actual project, you also should check that the minimum
cover heights in Appendix C of the Drainage Manual are satisfied. To
simplify this example, we will assume that adequate cover is provided.
Using the hydraulic calculator, the velocity of 1.95 cfs flowing full through an 18-
inch pipe is 1.1 fps.
Table 6.6-4
VELOCITY
ACTUAL
TYPE OF STRUCTURE CROWN SIZE
(FPS)
STRUCTURE
TIME OF CONCEN-
INTENSITY (iph)
(%)
TOTAL C • A
LENGTH (ft)
RISE
LOWER END
UPPER END
ELEV. (ft)
ELEV. (ft)
FALL (ft)
HYD.
PHYSICAL
VELOCITY
GRAD.
(FPS)
UPPER SPAN PHYSICAL
MIN.
LOWER
PHYS.
.03
1 18 1.1
P5 110 10 1.7 6.5 0.30 1.95 10.90 7.9 7.7 .18
0.2
2 6.4 6.2 18 .15 2.7
16. Calculate the total runoff for the pipe section. [P2-3]
Flow rate = Total CA x Intensity
= 0.5 x 6.1 = 3.1
18. Determine the pipe flow lines, physical slope, and fall. [P2-3]
Since this inlet is higher than S-1, the potential conflict with the inlet top will not
control the flow lines. For this example, we will attempt to match flow line
elevations across structures. Therefore:
Upper-end flow line = 6.2 (previous pipe section downstream flow line)
Minimum pipe fall = length x min. phys. slope
= 200 ft x 0.15% = 0.3 ft
Pipe fall = 0.3 ft
Physical slope = 0.3 ft/200 ft = 0.15%
Lower-end flow line = 6.2 – 0.3 = 5.9 feet
Table 6.6-5
HYD. GRADIENT
VELOCITY
PIPE
ACTUAL
CROWN
STRUCTURE
TYPE OF STRUCTURE
(FPS)
SIZE
FLOW LINE
TIME OF CONCEN-
(IN)
INTENSITY (iph)
SECTION (min)
NO.
TOTAL C • A
LENGTH (ft)
SLOPE (%)
LOWER END
UPPER END
ELEV. (ft)
ELEV. (ft)
RISE
FALL (ft)
PHYSICAL
VELOCITY
UPPER
(FPS)
HYD. GRAD.
SPAN
LOWER PHYSICAL
MIN. PHYS.
0.03
1 18 1.1
P5 110 10 1.7 6.5 0.30 1.95 10.90 7.9 7.7 0.18
0.2
2 6.4 6.2 18 0.15 2.7
0.07
2 18 1.8
P5 200 11.7 1.9 6.1 0.50 3.1 11.10 7.7 7.4 0.15
0.3
3 6.2 5.9 18 0.15 2.5
Step 14 through Step 20 are repeated for the remaining pipe sections. Situations that
are different from the above pipe sections are discussed below. Table 6.6-6 shows the
results of doing these steps for the entire system.
As stated in Step 18, we will attempt to match flow lines across structures for this
example. The upper-end flow line is set to match the lower-end flow line of pipe
section P4-7. The lower-end flow line is set to match the flow line of S-8.
VELOCITY
ACTUAL
SIZE
TYPE OF STRUCTURE
STRUCTURE
CROWN
(FPS)
TIME OF CONCEN-
TIME OF FLOW IN
INTENSITY (iph)
FLOW LINE
INLETELEV. (ft)
TRATION (min)
SECTION (min)
TOTAL C • A
NO.
LENGTH (ft)
SLOPE (%)
LOWER END
UPPER END
RISE
ELEV. (ft)
ELEV. (ft)
FALL (ft)
PHYSICAL
VELOCITY
(FPS)
UPPER HYD. GRAD.
SPAN PHYSICAL
LOWER
MIN. PHYS.
.03
1 18 1.1
P5 110 10 1.7 6.5 0.30 1.95 10.90 7.9 7.7 .18
0.2
2 6.4 6.2 18 .15 2.7
0.07
2 18 1.8
P5 200 11.7 1.9 6.1 0.50 3.1 11.10 7.7 7.4 0.15
0.3
3 6.2 5.9 18 0.15 2.5
0.07
3 18 1.8
MH 200 N/A 1.9 N/A 0.50 3.1 11.40 7.4 7.1 0.15
0.3
4 5.9 5.6 18 0.15 2.5
0.18
4 18 2.8
P5 100 15.5 0.6 5.4 0.9 4.9 11.10 7.1 6.9 0.2
0.2
7 5.6 5.4 18 0.15 2.9
0.07
5 18 1.8
P5 110 10 1.7 6.5 0.48 3.1 10.90 7.1 6.9 0.18
0.2
7 5.6 5.4 18 0.15 2.7
0.09
7 24 2.4
MH 25 16.1 0.2 5.3 1.38 7.3 10.50 7.4 6.5 3.6
0.9
8 5.4 4.5 24 0.1 14.8
0.02
6 18 1.3
P5 32 10 0.4 6.5 0.24 1.56 9.60 6.1 6.0 0.3
0.1
8 4.6 4.5 18 0.15 3.5
0.18
8 24 3.4
P5 250 16.3 1.9 5.3 1.96 10.4 9.60 6.5 6.2 0.12
0.3
outlet 4.5 4.2 24 0.1 2.7
So the Total CA from S3 is reduced by: 0.5 (1 - 0.65) = 0.18 This value is not the reduced
CA; it is the amount the Total
CA is reduced by.
Reducing the Total CA for pipe section P4-7 by this amount yields: 0.9 – 0.18 = 0.72
The flow in the pipe downstream of S4 = CAi = 0.72 x 6.5 = 4.7 cfs.
This is less than the 4.9 cfs calculated for the entire contributing area for P4-7, as
shown in Table 6.6-6. So, peak flow in pipe section P4-7 does not result from
reduced area. Although other pipe sections could be checked for peak flow from
reduced area, this effort shown above is acceptable for this system.
CALCULATE THE HYDRAULIC GRADE LINE ELEVATION (first pass up the system)
The full-flow friction slope was previously recorded as the hydraulic gradient slope
in Table 6.6-6 when we moved down the system calculating flow rates.
Table 6.6-7
HYD. GRADIENT
STRUCTURE
CROWN
NO.
LENGTH (ft)
UPPER LOWER
UPPER ELEV ELEV FALL HYD. GRAD.
(ft)
(ft) (ft) PHYSICAL
LOWER
MIN. PHYS.
Pipe sections P6-8 and P5-7 are stubs and their hydraulic gradient will not be
calculated during the first pass up the system.
The same steps are repeated for the remaining mainline pipe sections. Table 6.6-8 shows
the results of doing these steps for the entire system.
FLOW LINE
TOTAL FLOW
LENGTH (ft)
NO.
RISE
26. Compare the hydraulic gradient to the standard and adjust pipe sizes.
The standard clearance of 1.13 feet between the hydraulic gradient and the inlet
elevation (edge of pavement) is not met for S-8 and probably not met for S-6. The
remaining inlets have adequate clearance. Increasing the size of the outlet pipe
P8-out to 30 inches will reduce the hydraulic gradient at S-6 and S-8, so we will try
that. To reduce costs, we also will try reducing the pipe size of section P7-8 to 18
inches.
27. Calculate the hydraulic gradient using the changed pipe sizes.
Table 6.6-9 shows the new slopes and the recalculated hydraulic gradient for the
entire system.
CROWN (IN)
FLOW LINE
(cfs)
RISE
UPPER LOWER HYD. GRAD.
END END FALL
ELEV ELEV (ft) PHYSICAL
SPAN
UPPER (ft) (ft)
MIN. PHYS.
LOWER
9.04 9.01 0.03 0.03
1 18
110 1.95 10.90 7.9 7.7 0.18
0.20
2 6.4 6.2 18 0.15
9.01 8.87 0.14 0.07
2 18
200 3.1 11.10 7.7 7.4 0.15
0.30
3 6.2 5.9 18 0.15
8.87 8.73 0.14 0.07
3 18
200 3.1 11.40 7.4 7.1 0.15
0.30
4 5.9 5.6 18 0.15
8.73 8.55 0.18 0.18
4 18
100 4.9 11.10 7.1 6.9 0.20
0.20
7 5.6 5.4 18 0.15
8.63 8.55 0.08 0.07
5 18
110 3.1 10.90 7.1 6.9 0.18
0.20
7 5.6 5.4 18 0.15
8.55 8.45 0.10 0.40
7 18
25 7.3 10.50 6.9 6.0 3.60
0.90
8 5.4 4.5 18 0.15
8.46 8.45 0.01 0.02
6 18
32 1.56 9.60 6.1 6.0 0.30
0.10
8 4.6 4.5 18 0.15
8.45 8.3 0.15 0.06
8 30
250 10.4 9.60 7.0 6.8 0.08
0.20
outlet 4.5 4.3 30 0.08
The increased velocity in pipe section P7-8 reduced the time of flow in the pipe by
only 0.1 minute because the pipe is so short. As a result, the time of concentration
of the outlet pipe was reduced by only 0.1 minute from 16.3 to 16.2 minutes. It is
hard to read a change in the intensity from the IDF curve for a change in tc of 0.1
minute. Although we changed the size of the two pipes, there was no noticeable
change to the flow rate in the system.
A completed tabulation form is shown in Table 6.6-10.
Example 6.6-1
Table 6.6-10
VELOCITY(FPS)
LOCATION DRAINAGE AREA HYD. GRADIENT PIPE NOTES AND REMARKS
ACTUAL
TYPE OF STRUCTURE
UPPER END (IN) SLOPE (%)
STRUCTURE
C • A SUBTOTAL
C = 0.95 FLOW LINE FREQUENCY (Yrs) : 3
ALIGNMENT NAME
C • A TOTAL
TOTAL FLOW
LENGTH (ft)
INTENSITY
NO.
C= RISE MANNING’S “n” : 0.012
INLET
(MIN)
(MIN)
(iph)
(cfs)
C = 0.20 ELEV. HYD. TAILWATER EL. (ft): 8.3
DISTANCE
PHYSICAL
VELOCITY
FALL
SIDE
END END
(ft)
(ft)
STATION
(FPS)
INCRE- ELEV ELEV PHYSICAL
TOTAL SPAN
MENT (ft) (ft)
UPPER
MIN.
LOWER PHYS.
0.3 0.3 0.29 9.04 9.01 0.03 0.03
Ricardo Way 1 18 1.1
P5 110 10 1.7 6.5 0.3 1.95 10.90 7.9 7.7 0.18
0.2
40 + 80 46.5 R 2 0.05 0.05 0.01 6.4 6.2 0.15 2.7
0.2 0.5 0.48 9.01 8.87 0.14 18 0.07
Ricardo Way 2 1.8
P5 200 11.7 1.9 6.1 0.5 3.1 11.10 7.7 7.4 0.15
0.3
41 + 25 46.5 L 3 0.03 0.08 0.02 6.2 5.9 0.15 2.5
--- 0.5 0.48 8.87 8.73 0.14 0.07
Ricardo Way 3 18 1.8
MH 200 N/A 1.9 N/A 0.5 3.1 11.40 7.4 7.1 0.15
0.3
43 + 25 44 L 4 --- 0.08 0.02 5.9 5.6 0.15 2.5
0.4 0.9 0.86 8.73 8.55 0.18 0.18
Ricardo Way 4 18 2.8
P5 100 15.5 0.6 5.4 0.9 4.9 11.10 7.1 6.9 0.2
0.2
45 + 25 46.5 L 7 0.1 0.18 0.04 5.6 5.4 0.15 2.9
0.4 0.4 0.38 8.63 8.55 0.08 0.07
Ricardo Way 5 18 1.8
P5 110 10 1.0 6.5 0.48 3.1 10.90 7.1 6.9 0.18
0.2
46 + 00 46.5 R 7 0.5 0.5 0.1 5.6 5.4 0.15 2.7
--- 1.3 1.24 8.55 8.45 0.1 0.40
Frank Blvd. 7 18 4.1
MH 25 16.1 0.1 5.3 1.38 7.3 10.50 6.9 6.0 3.6
0.9
30 + 50 10 R 8 --- 0.68 0.14 5.4 4.5 0.15 12.3
0.15 0.15 0.14 8.46 8.45 0.01 0.02
Frank Blvd. 6 18 1.3
P5 32 10 0.4 6.5 0.24 1.56 9.60 6.1 6.0 0.3
0.1
30 + 75 16 L 8 0.5 0.5 0.1 4.6 4.5 0.15 3.5
0.25 1.7 1.62 8.45 8.3 0.15 0.06
Frank Blvd 8 30 2.2
P5 250 16.2 1.9 5.3 1.96 10.4 9.60 7.0 6.8 0.08
0.2
30 + 75 16 R Outlet 0.5 1.68 0.34 4.5 4.3 0.08 2.5
Drainage Design
Guide
Figure 6.6-6
Drainage Design
Guide
Table 6.6-11
LOCATION
DRAINAGE AREA
OF NOTES AND REMARKS
TYPE OF STRUCTURE
(ac)
UPPER END
STRUCTURE
ALIGNMENT NAME C= INLET
ZONE: 7
NO.
ELEV.
LENGTH
C = 0.80
(ft)
(ft)
DISTANCE
C= FREQUENCY (Yrs): 3
SIDE
STATION
INCRE- TAILWATER EL. (ft): 47.1
TOTAL
UPPER MENT All overland tc < 10 min.
LOWER
Patrick Place 15
P1 300 0.2 59.70
14
Patrick Place 14
P1 300 1.0 59.80
13
Patrick Place 13
P1 300 0.6 59.00
12
Patrick Place 12
P1 300 0.5 54.50
11
Patrick Place 11
P1 300 1.1 50.50
outlet
1. Add the areas that contribute flow to each pipe segment. For each of the pipe
segments, the total area is obtained as in Example 6.6-1.
2. For each pipe section, multiply the total area associated with each runoff
coefficient by the corresponding runoff coefficient to obtain the subtotal CA
values.
3. For each pipe section, add the subtotal CA values to obtain the total CA value.
Table 6.6-12 is a partial tabulation form complete with the information from the first three
steps.
Drainage Design
Guide
Table 6.6-12
DRAINAGE AREA
(ac)
STRUCTURE
C=
TOTAL C • A
NO.
C = 0.80
SUB-
C= TOTAL
C•A
UPPER INCRE-
TOTAL
MENT
LOWER
15
0.2 0.2 0.16 0.16
14
14
1 1.2 0.96 0.96
13
13
0.6 1.8 1.44 1.44
12
12
0.5 2.3 1.84 1.84
11
11
1.1 3.4 2.72 2.72
outlet
5. Assume which inlet will be critical. For this example, we will assume that S-15 is
critical.
6. For this example, we will base the preliminary HGL slope on the following formula.
Drainage Design
Guide
11. Determine the pipe flow lines, physical slope, and fall. [P15-14]
For this example, we will use a 4.5-foot clearance between the inlet (edge of
pavement) elevation and the flow line of an 18-inch pipe. (The minimum clearance
for standard precast structures is 4.2 feet. See Table 6.4-5.) Then:
Upper-end flow line = 59.7 – 4.5 = 55.2 feet
For this example, we will assume there are no constraints such as utilities that
would prevent the pipe from being set at the minimum physical pipe slope (0.15
percent). Then:
Minimum pipe fall = 300 ft x 0.15% = 0.45 ft
Pipe fall = 0.5 ft (minimum fall rounded up to nearest 0.1 foot)
Physical Slope = 0.5 ft/300 ft = 0.167%
Lower-end flow line = 55.2 – 0.5 = 54.7 feet
Drainage Design
Guide
If this were an actual project, you also should check that the minimum
cover heights in Appendix C of the Drainage Manual are satisfied. To
simplify this example, we will assume that adequate cover is provided.
The full-flow cross sectional area used for the first pass through the system. Using
the hydraulic calculator, the velocity of 1.04 cfs flowing full through an 18-inch pipe
is 0.59 fps.
Using the hydraulic calculator, the full-flow velocity for an 18-inch pipe sloped at
0.17 percent = 2.6 fps
A partially completed tabulation form with the information from this pipe is shown below.
Drainage Design
Guide
Table 6.6-13
HYD. GRADIENT PIPE
VELOCTIY
STRUCTURE
CROWN SIZE
ACTUAL
(FPS)
TIME OF CONCEN-
TIME OF FLOW IN
FLOW LINE (IN)
SECTION (MIN)
TRATION (MIN)
NO.
TOTAL FLOW
TOTAL C • A
SLOPE (%)
INTENSITY
LENGTH
INLET RISE
(iph)
(cfs)
(ft)
FALL
(ft) END END
CELOCITY
PHYSICAL
(ft)
UPPER ELEV ELEV HYD. GRAD.
(FPS)
(ft) (ft)
SPAN PHYSICAL
LOWER
MIN. PHYS.
0
15 18 .59
300 10 8.5 6.5 0.16 1.04 59.70 56.7 56.2 .167
0.5
14 55.2 54.7 18 .15 2.6
Step 7 through Step 13 are repeated for the remaining pipe sections. We have assumed
that all the pipes are flowing full for this pass down the system. Situations that are
different from the above pipe section are discussed below.
Drainage Design
Guide
The full-flow friction slope was recorded as the hydraulic gradient slope for all the pipes.
Table 6.6-14 shows the results of doing Step 7 through Step 13 for the entire system.
VELOCITY
CROWN SIZE
ACTUAL
(FPS)
TIME OF CONCEN-
TIME OF FLOW IN
SECTION ( MIN )
TRATION ( MIN )
TOTAL FLOW
TOTAL C•A
SLOPE (%)
INTENSITY
NO.
LENGTH
INLET
( iph )
( cfs )
RISE
(ft)
FALL
(ft ) END END
( ft )
PHYSICAL
VELOCITY
ELEV ELEV
(FPS)
( ft ) ( ft ) HYD GRAD
UPPER SPAN PHYSICAL
LOWER MIN PHYS
≈0
15 18 .59
300 10 8.5 6.5 0.16 1.04 59.70 56.7 56.2 0.167
0.5
14 55.2 54.7 18 .15 2.6
0.18
14 18 2.8
300 18.5 1.8 5.1 0.96 4.9 59.80 56.2 55.7 0.167
0.5
13 54.7 54.2 18 0.15 2.6
0.38
13 18 4.0
300 20.3 1.3 4.9 1.44 7.05 59.00 55.7 51.5 1.4
4.2
12 54.2 50.0 18 0.15 7.6
0.58
12 18 4.9
300 21.6 1.0 4.7 1.84 8.65 54.50 51.5 47.5 1.33
4.0
11 50.0 46.0 18 0.15 7.5
1.2
18 7.0
11 300 22.6 - 4.6 2.72 12.5 50.50 47.5 46.0 0.50
1.5
46.0 44.5 18 0.15 4.5
Drainage Design
Guide
For the outlet pipe, the lower-end HG is the design tailwater (DTW). For this
example, the design tailwater is the higher of: (1) the crown of the pipe (elev. 46.0
feet), or (2) the normal high water stage (47.1) of the lake. Thus:
Lower-end HG = 47.1 feet
OR
2) The elevation of normal depth upstream. The above elevation is higher than
the upper-end crown, so normal depth cannot control.
The standard HG clearance is not met (S-11 inlet elev. = 50.5). We will increase
this pipe size to 24 inches before continuing upstream. To match the crowns at the
upper end, the flow line of the 24-inch pipe will be set 0.5 foot lower than for the
18-inch pipe. [P11-out]
Upper-end flow line = 45.5 ft
Pipe fall = 45.5 – 44.5 = 1 ft (holding lower-end flow line)
Physical slope = 1/300 = 0.33 percent
OR
2) The elevation of normal depth upstream. The above elevation (47.9 feet) is
higher than the crown (47.5 feet), so normal depth does not apply.
Drainage Design
Guide
Table 6.6-16 shows the results of completing these steps for the entire system.
For Pipe Section P12-11:
The lower-end HG is the higher of:
OR
2) Controlling pipe condition at the lower end. The above elevation (47.9 feet) is
Table 6.6-15
higher than the crown (47.5 feet), so normal depth does not apply.
OR
Upper-end normal depth elev. = 50.0 + 0.6 x 1.5 = 50.9 ft (dNORM = 0.6 x D)
OR
2) Controlling pipe condition at the lower end. The pipe slope (1.4 percent) is
Drainage Design
Guide
steeper than the full-flow friction slope (0.38 percent) so, if the downstream HG
is low enough, the flow depth at the lower end is normal depth. Thus, the
controlling pipe condition is normal depth (Figure 5-1C). Using the hydraulic
calculator (Q = 7.05 cfs, 18-inch pipe @ 1.4 percent slope) the normal depth =
0.52 x Diameter
OR
OR
2) Controlling pipe condition at the lower end. The pipe slope (0.167 percent) is
flatter than the full-flow friction slope (0.18 percent), so use the crown of the
pipe (Figure 6.5-1D) as the controlling pipe condition at the lower end. Lower-
end crown elev. = 55.7 ft
Drainage Design
Guide
OR
2) The elevation of normal depth upstream. The above elevation (56.24 feet) is
higher than the crown (56.2 feet), so normal depth does not apply.
OR
2) Controlling pipe condition at the lower end. The above elevation (56.24 feet)
is higher than the crown (56.2 feet), so normal depth does not apply.
OR
Table 6.6-16 shows the results of doing Step 16 and Step 17 for the entire system.
Drainage Design
Guide
CROWN SIZE
TOTAL FLOW SLOPE (%)
LENGTH (ft)
(IN)
NO.
FALL
(ft) END END HYD. GRAD.
(ft)
ELEV ELEV
UPPER (ft) (ft) PHYSICAL
SPAN
LOWER MIN. PHYS.
56.24 56.24 ≈0
15 18
300 1.04 59.70 56.7 56.2 0.167
0.5
14 55.2 54.7 18 0.15
The HG slopes shown for pipe sections P15-14, P13-12, P12-11 are the full-flow friction slopes.
The values are not the true HG slopes because these pipes are flowing part full. The
values will be revised in subsequent iterations through the system. The full-flow friction
slopes have been shown in Table 6.6-16 to help follow the discussion of Step 16 and Step
17 for the entire system.
Drainage Design
Guide
pipes flowing partly full will be based on normal depth velocity (see Figure 6.5-3).
Table 6.6-17 shows the results of recalculating the flow rates.
VELOCITY
ACTUAL
STRUCTURE
PIPE
(FPS)
ZONE: 7
TIME OF CONCEN-
IN SECTION (min)
TOTAL FLOW
FREQUENCY (Yrs): 3
NO.
LENGTH (ft)
TOTAL C•A
INTENSITY
(IN)
MANNINGS “n”: 0.012
(iph)
(cfs)
HYD. TAILWATER EL. (ft):
PHYSICAL
VELOCITY
GRAD. 47.1
RISE
(FPS)
All overland tc < 10
UPPER PHYSICAL
min.
LOWER SPAN MIN PHYS
≈0 Act Vel based on
15 18 2.1
300 10.0 2.4 6.5 0.16 1.04 0.167 normal
14 18 .15 2.6 Depth. d/D = 0.32
0.25
14 18 3.25
300 12.4 1.5 6.0 0.96 5.76 0.167
13 18 0.15 2.6
0.5 Act Vel based on
13 18 8.0
300 13.9 0.6 5.7 1.44 8.2 1.4 normal
12 18 0.15 7.6 Depth. d/D = 0.55
0.8 Act Vel based on
12 18 8.3
300 14.5 0.6 5.6 1.84 10.3 1.33 normal
11 18 0.15 7.5 Depth. d/D = 0.67
0.38
11 24 4.8
300 15.1 - 5.6 2.72 15.2 0.33
Outlet 24 0.10 4.5
Drainage Design
Guide
SIZE
TOTAL FLOW
SLOPE (%)
LENGTH ( ft )
FALL
END END
(ft)
ELEV. ELEV.
UPPER PHYSICAL
(ft) (ft) SPAN
LOWER MON PHYS All overland tc < 10 min.
56.45 56.45 ≈0
15 18 Act.Vel based on Norm
300 1.04 59.70 56.7 56.2 0.167
0.5 Depth. d/D = 0.32
14 55.2 54.7 18 0.15
56.45 55.7 0.75 0.25
14 18
300 5.76 59.80 56.2 55.7 0.167
0.5
13 54.7 54.2 18 0.15
55.03 51.0 0.5 Act Vel & Upper End HG
13 18
300 8.02 59.00 55.7 51.5 1.4 Based on Norm Depth
4.2
12 54.2 50.0 18 0.15 D/D = 0.55
51.0 48.24 0.8 Act Vel & Upper End HG
12 18
300 10.3 54.50 51.5 47.5 1.33 Based on Norm Depth
4.0
11 50.0 46.0 18 0.15 D/D = 0.67
48.24 47.1 1.14 0.38
11 24
300 15.2 50.50 47.5 46.5 0.33
1.0
OUT 45.5 44.5 24 0.10
The HG slopes shown for pipe sections P15-14, P13-12, P12-11 are the full-flow friction slopes.
The values are not the true HG slopes because these pipes are flowing part full. The full-
flow friction slopes have been shown in Table 6.6-18 to help you compare HG elevations
as you work through the system. The values are changed in Table 6.6-19, which reflects
the completed design.
Throughout the system, the hydraulic gradient elevation is more than 1.13 feet
below the inlet elevation (edge of pavement), so it meets the current standard. Pipe
section P11-out cannot be reduced in diameter without violating the standard HG
clearance at S-11 (see Step 15). The other pipes are the minimum standard
diameter, so their diameter cannot be reduced.
Pipe section P15-14 is flowing full for about half of its length. Consequently, the flow
velocity is less than the 2.1 fps we estimated in Table 6.6-17. We could make
another iteration through the system recalculating flows based on the reduced
velocity, but there is nothing to be gained from doing that here. None of the pipe
diameters can be reduced. A completed tabulation form is shown in Table 6.6-19.
Example 6.6-2
Table 6.6-19
LOCATION DRAINAGE HYD. GRADIENT
VELOCITY (FPS)
OF AREA NOTES AND REMARKS
UPPER END (ac) CROWN PIPE
ACTUAL
STRUCTURE SIZE
ALIGNMENT
TYPE OF STRUCTURE
C= FLOW LINE (IN) ZONE: 7
NAME
TIME OF CONCEN-
IN SECTION ( min )
SLOPE (%)
NO.
SUBTOTAL C•A
TRATION (min )
TIME OF FLOW
TOTAL FLOW
LENGTH (ft)
C = 0.80
TOTAL C•A
INTENSITY
INLET FREQUENCY (Yrs): 3
(iph)
(cfs)
C= ELEV
UPPE
DISTANCE
(ft) LOWER
R RISE
FALL
SIDE
END
(ft)
(ft)
STATION END
PHYSCIAL
VELOCITY
INCRE ELEV HYD GRAD MANNING’S “n”: 0.012
ELEV
(FPS)
TOTA (ft)
UPPER - (ft)
L TAILWATER EL. (ft):
MENT PHYSICAL
SPA 47.1
LOWER N MIN PHYS All overland tc < 10 min
56.45 56.45 ≈0 ≈0
Patrick Place 15 18 2.1 Act Vel based on Norm
P1 300 0.2 0.2 0.16 10 2.4 6.5 0.16 1.04 59.70 56.7 56.2 0.167 Depth.
0.5 d/D = 0.32
14 55.2 54.7 18 0.15 2.6
56.45 55.7 0.75 0.25
Patrick Place 14 18 3.25
P1 300 1.0 1.2 0.96 12.4 1.5 6.0 0.96 5.76 59.80 56.2 55.7 0.167
0.5
13 54.7 54.2 18 0.15 2.6
55.03 51.0 4.03 1.3
Patrick Place 13 18 8.0 Act Vel & Upper End HG
P1 300 0.6 1.8 1.44 13.9 0.6 5.7 1.44 8.2 59.00 55.7 51.5 1.4 based on Norm Depth.
4.2 d/D = 0.55
12 54.2 50.0 18 0.15 7.6
51.0 48.24 2.79 0.9
Patrick Place 12 18 8.3 Act Vel & Upper End HG
P1 300 0.5 2.3 1.84 14.5 0.6 5.6 1.84 10.3 54.50 51.5 47.5 1.33 based on Norm Depth.
4.0 d/D = 0.67
11 50.0 46.0 18 0.15 7.5
48.24 47.1 1.14 0.38
Patrick Place 11 24 4.8
P1 300 1.1 3.4 2.72 15.1 1.0 5.6 2.72 15.2 50.50 47.5 46.5 0.33
1.0
OUT 45.5 44.5 24 0.10 4.5
7. EXFILTRATION SYSTEMS
7.1 GENERAL
7.1.1 Hydrology
Chapter 2 in this design guide and the Drainage Manual encompass the Department’s
general guidance regarding hydrology. Coordinate in advance with the District Drainage
Engineer for approval of the design criteria and calculation methods.
7.1.2 Hydro-Geology
7.1.2.1 Darcy’s Law
Darcy’s Law characterizes the flow through porous media, assuming that the viscosity,
temperature, and density of the fluids are constants. The flow rate is a function of the flow
area, the hydraulic gradient, and the proportionality constant (refer to Figure 7.1-1):
Q=kiA
where:
Q = Flow rate, in ft3/sec
k= Permeability constant, in ft/sec
i= Hydraulic gradient (i = ∆H/L)
A = Cross-sectional area of soil conveying flow, in ft2
∆H = Change in the hydraulic grade line, in ft
L= Distance between points of interest, in ft
Darcy’s Law was established for saturated flow. As such, it may be adjusted for
unsaturated and multiphase flows.
K= Q
A ∆H
where:
Q = Flow rate, in ft3/sec
A = Flow area, in ft2
∆H = Hydraulic head, in ft
The hydraulic conductivity of a soil is the ratio between the discharge through the unit
area of soil perpendicular to the flow per unit of head (i.e., cfs/ft2 – ft of head). This is the
primary factor used to determine the exfiltration rate of a system.
The flow transmission through a soil increases as the water content increases. As such,
the maximum hydraulic conductivity occurs under saturated conditions. The hydraulic
conductivity for horizontal-saturated flow (Ks) usually is several times greater than the
hydraulic conductivity for vertical-unsaturated flow (Ku).
Evaluate the hydrologic and geologic characteristics of the site where the exfiltration
system will be installed to define the test procedures to be used. The following tests are
suggested:
The initial data to determine the seasonal high water table (SHWT) elevation is the
measurement of the stabilized ground water level in a boring or well. Adjust the initial
(encountered) water table elevation to estimate the SHWT based on antecedent rainfall,
examination of the soil profile (color variations, depth to hardpan, etc.), consistency with
water levels of the adjacent water bodies, vegetative indicators, etc.
• Topographic Data. You usually can find preliminary topographic data in the
United States Geological Survey (USGS) quadrangle maps, topographic LIDAR
data, and previous project construction plans. Supplement this information with a
detailed topographic survey of the project area.
• Geotechnical Data. The Soil Survey Reports by the United States Department of
Agriculture (USDA) Natural Resources Conservation Service (NRCS) provide
general geological and geotechnical properties information. Previous geotechnical
reports for the project area and adjacent developments can provide more specific
information regarding the geotechnical conditions at the project location. After
preliminary evaluation of the available data, request a detailed geotechnical study.
The site-specific geotechnical report should classify the types of soils within the
project location and soil engineering characteristics, including hydraulic
conductivity (refer to Section 7.1.2.3), ground water elevations, etc.
• Receiving Water Bodies. The Water Management Districts, FEMA, and some
local agencies can provide information regarding water elevations under different
storm frequencies for lakes, rivers, canals, and reservoirs. Some agencies also
can provide potentiometric surface maps to assist in determining the ground water
elevations. Tidal information is available on the National Oceanic and Atmospheric
Administration (NOAA) website. You can determine the design tailwater elevation
from the above sources.
• Permit Data. Previous permit information for the site and surrounding
developments can provide information related to design criteria, existing wetlands,
possible outfalls, discharge limitations, control elevations, off-site contributors,
geotechnical data, prior soil testing results, etc.
• Right-of-Way Data. You can obtain the right-of-way information from the
Department’s right-of-way maps and county and city right-of-way documents.
• Field Reviews. Visiting and inspecting the site provides first-hand updated
information to the designer regarding the existing drainage system, off-site
contributors, water management facilities, outfalls, and other site conditions.
Typically, you would not use exfiltration systems within any type of manmade, compacted
embankment since there is little to no percolation in compacted fill as compared to natural
soils.
Do not install exfiltration systems in close proximity to or behind MSE walls. Install solid
conveyance pipes behind the MSE wall in accordance with the Drainage Manual,
Appendix D, and install exfiltration systems away from the walls. Do not use exfiltration
trenches in locations where a 1H:1V mound could allow the filtrate to impact the MSE soil
reinforcements. In this situation, the potential exists for accelerated corrosion of metallic
reinforcements to occur without warning. Furthermore, seepage forces would need to be
included in the design of the wall, and daylighting filtrate could result in soil washouts,
unsightly mildew, vegetation, staining, and other maintenance problems.
In the case of drainage wells, provide the injection well chamber with physical access
devices for maintenance activities. Maintenance of the injection well includes cleaning,
removing debris, and, in some cases, redeveloping the well to re-establish discharge
capacity. The well location needs to be accessible from the surface to allow these
activities to take place.
The permeability of the soils at the exfiltration trench location and the anticipated water
table elevation determine the applicability and performance of the exfiltration trench
system. This system must exfiltrate the required stormwater treatment volume and draw
down the treatment volume to return to its normal condition within a specific time after the
design storm event. When the trench bottom is at or above the average wet season water
table, the exfiltration trench is considered a dry system.
7.2.1.1 Use
For projects where the areas available for water management facilities are limited and
high right-of-way acquisition costs are anticipated, exfiltration trench systems can provide
the required stormwater treatment if the hydro-geological conditions are suitable for runoff
infiltration (i.e., permeable soils with hydraulic conductivity exceeding 1 x 10-5 cfs/ft2 per
foot of head). Exfiltration trenches, like other types of retention systems, are able to
efficiently remove stormwater pollutants. Additionally, exfiltration trenches contribute to
recharge of the ground water aquifer, thus assisting in combatting saltwater intrusion in
coastal areas.
Because of the direct infiltration of the surface runoff with its associated pollutant load into
the ground water aquifer, do not install exfiltration trench systems in the proximity of
potable water supply wells. Usually, you are not allowed to install exfiltration trenches
within the 10-day well field protection contour, but you should verify specific requirements
for each well field with the permitting authorities. Do not propose exfiltration trenches
within or near contaminated ground water areas to avoid the potential migration of the
polluted plume due to the direct injection of surface runoff into or adjacent to the
contaminated groundwater plume. In areas with high ground water elevation, the
available hydraulic head for exfiltration trench operation is minimal but the required
hydraulic head can be obtained by pumping, if feasible.
The limited life span of exfiltration trenches is their main disadvantage. The accumulation
of sediments and clogging of the filter fabric and the void spaces of the aggregates usually
shorten the operational life of exfiltration trenches. Consider the need of future
replacement costs in the evaluation of their effectiveness. Prior to replacing existing
systems or using them as part of a new drainage system, test the remaining treatment
capacity of existing exfiltration trenches.
The Standard Specifications for Road and Bridge Construction (Section 443, French
Drains) includes directions, provisions, and requirements for exfiltration trenches.
Standard exfiltration trenches are detailed in Standard Plans, Index 443-001, French
Drains. In the cases where Standard Plans, Index 443-001 is not suitable for a specific
project need, develop a detailed design and include this information in the design
documentation. The following are the Department’s general design criteria. It is
recommended that additional specific criteria from the permitting agencies be evaluated
in the design process.
The off-line treatment method (Figure 7.2-2) diverts runoff into the exfiltration trench
designed to provide the required treatment volume; subsequent runoff in excess of the
treatment capacity bypasses the off-line exfiltration trench toward the outfall. For off-line
systems, a diversion drainage structure usually is required.
The on-line exfiltration trench (Figure 7.2-3) provides the required water treatment but the
treatment volume is mixed with the total runoff volume. As such, runoff volume in excess
of the treatment capacity carries a portion of the pollutant load to the receiving water body.
In some special locations (i.e., Miami-Dade County and Monroe County) with very limited
area available for water treatment, the exfiltration trench systems could be credited for
discharge attenuation if the ground water is considered variable, rising from the Seasonal
High Water Table along with the design storm event.
Closed Systems. The effective head for exfiltration trenches with no outfall (self-
contained system) should be the vertical distance from the SHWT to the average distance
between the SHWT and the design high water (DHW):
7.2.2.8 Dimensions
The minimum pipe diameter is 18 inches, but 24 inches is preferable; and the minimum
trench width is four feet. The maximum dimensions should depend on site-specific
conditions and construction methods. In general, exfiltration trenches with bottoms wider
than eight feet and/or deeper than 20 feet are not recommended. Perforated pipes with a
diameter of more than 36 inches should be approved by the District Drainage Engineer.
Pipe perforations can be slotted or perforated. Standard locations and dimensions of the
pipe perforations are included in the Standard Specifications, Section 443, French Drains.
b. The maximum length of the exfiltration trenches with access through only one end
should be half of the maximum length of exfiltration trenches with access through
both ends.
7.2.2.11 Aggregates
Use uniform-graded, natural or artificial coarse aggregate with no more than 3-percent
weight of material passing the Number 200 Sieve at the point of use.
The filter fabric will comply with the requirements established in the latest FDOT Standard
Specifications, Section 985. Additionally, the permeability of the filter fabric must be equal
to or greater than the permeability of the surrounding soil.
Drainage structures have to provide adequate access to the exfiltration trench for
maintenance operations; the minimum grate size should be two feet and two-piece cast
iron covers (Standard Plans, Index 425-001) are recommended. Provide manholes for
inspection and clean out at the end of each exfiltration trench with no inlet. Inlets Type 1
to 4 (Standard Plans, Index 425-020) are recommended for exfiltration trenches installed
along or from a gutter line.
Refer to Sections 3.10 and 3.12 of the Drainage Manual for standards related to drainage
structures of exfiltration systems.
The equations and formulas included in the following sections present the conceptual
development of the procedures and calculations, which are applicable with any unit
system. As such, the conversion factors are not included, but the designer has to convert
the units of each parameter as required to be consistent.
Note: The water quality criterion from St. Johns River Water Management District
(SJRWMD) is used for the sample problem.
If you propose on-line treatment, increase 0.5-inch runoff on the total drainage area to the
off-line treatment volume above:
If discharging into shellfish harvesting areas or other receiving water bodies with specific
regulations, provide the water quality volume as required: Vspec = 0 acre-ft
Total required water quality volume: VWQ = Von; VWQ =0.192 acre-ft
Trench bottom width: Wtr = 5.00 ft Perforated pipe invert: Pinv= 10.00 ft
Trench bottom elevation: Bel = 8.00 ft
The storage capacity of an exfiltration trench is the available void space above the SHWT,
including pipe and aggregate voids.
If the pipe invert is higher than the SHWT, the storage area in the pipe is:
Afull = π D2 Afull = 3.142 ft2
4
Note: If the required length does not fit within the available location, return to Step 2 and
modify the preliminary characteristics of the exfiltration trench as necessary.
Unsaturated exfiltration will occur only through the walls (2) and the bottom if the trench
bottom is above the SHWT:
Auwb = Lnet (2Du + Wtr) Auwb = 9,076 ft2
The empirical equations have incorporated the adjustment to consider that exfiltration
trenches are retention systems (50 percent of the treatment volume required for wet
detention systems) and have a safety factor of 2. As such, the treatment volume to be
used in these formulas is the greatest of one-inch runoff on the contributing area or 2.5
inches on the pavement area:
When the unsaturated depth of trench is greater than the saturated depth or the trench
width is lesser than two times depth:
L1 = FS %WQ.VWQ L1= 33 ft
K (H2W + 2Heff Du – Du2 + 2Heff Ds) + 0.000139 W Du
When the saturated depth of trench is greater than the unsaturated depth or the trench
width is greater than two times depth:
L2 = FS %WQ.VWQ L2=579 ft
K (2Heff Du – Du2 + 2Heff Ds) + 0.000139∙W∙Du
For the sample problem, the saturated depth of trench is greater than the unsaturated
depth, but the trench width is less than two times the trench depth. As such, the required
length of trench is 33 feet.
This method considers that there is no flow through the bottom of the exfiltration trench
(assuming that the bottom is the first portion of the trench to get clogged), but only through
the vertical areas (walls) of the exfiltration trench. The hydraulic conductivity of the
existing soils at the depth where the exfiltration trench will be located is considered in
calculating the dimensions and required length of the trench. A test procedure has been
developed to determine the hydraulic conductivity (K) of the soils at different depths. The
initial investigation includes soils from 0 to 10-foot depths; if the test hole exfiltration rate
is less than 6 gpm, then soils from 10-foot to 15-foot depths are investigated. If the
accumulated exfiltration rate is still less than 6 gpm, soils from 15-foot to 20-foot depths
are investigated. Deeper exfiltration trenches are not considered economically practical.
Construct the exfiltration trench with its bottom elevation coinciding with the depth of the
selected test results.
Note: The following procedure is applicable only in Miami-Dade County, and it is required
by the Miami-Dade Department of Environmental Resources Management (DERM).
Note: All the runoff generated from a storm event lasting TT or less is assumed to be
polluted or contaminated. As such, the maximum polluted volume (V) usually is greater
than the treatment volume required by the Water Management Districts.
The storage capacity of an exfiltration trench is the available void space above the design
ground water elevation (SHWT), including pipe and aggregate voids.
If the pipe invert is higher than the SHWT, the storage area in the pipe is:
Afull = π (D/12)2 Afull=3.14 ft2
4
If the pipe invert is lower than the SHWT, the available storage depth in the pipe is:
Dpipe = Pinv + D – SHWT Dpipe=1.00ft
12
Note: The exfiltration rate values are limited by the District VI Drainage Section to 0.15
cfs/linear foot of trench.
S + 60∙ET∙TT
The exfiltration trench design procedure for discharge attenuation should be similar to the
procedures described above. The difference is the required treatment volume. For closed
basins, the treatment volume should be the pre-development versus post-development
discharge increase instead of the required water quality volume. You could apply the
same criteria for basins with positive outfall if the Rational Method is used because this
method considers the rainfall intensity constant throughout the storm duration. If you use
hydrograph methods, the runoff hydrograph has to be combined with the exfiltration
hydrograph to determine the outflow from the drainage system. Spreadsheets and
modeling programs are available to perform hydrograph calculations.
Drainage wells in Florida are grouped into two broad types: surface-water injection wells
and inter-aquifer connector wells. Surface-water injection wells are further categorized as
either Floridan aquifer drainage wells or Biscayne aquifer drainage wells.
7.3.1.1 Use
The Floridan aquifer drainage wells generally are effective as a method of urban drainage
and lake level control. They emplace more recharge into the Floridan aquifer than the
recharge it would receive under natural conditions. The most common use of Floridan
aquifer drainage wells is to supplement surface drainage for urban areas in the karst
terrains of the topographically higher areas of central and north Florida. Be cautious,
however, with regard to the water quality aspects of these wells because they often inject
surface runoff into the same aquifer from which public water supplies are withdrawn.
In southeast Florida, drainage wells to the Biscayne aquifer dispose of stormwater runoff
and other surplus water. The majority of these wells dispose of water from swimming
pools or heated water from air-conditioning units. Some of the wells dispose of urban
runoff or wastewaters from business and industry in the area. The use of Biscayne aquifer
drainage wells should have minimal effect on aquifer water quality as long as the injection
of runoff and industrial wastes is restricted to zones where chloride concentrations exceed
1,500 milligrams per liter and 10,000 milligrams per liter total dissolved solids (TDS).
The data collection for drainage well design should include researching similar installed
wells within the project area. Local well contractors can provide an estimate of the
discharge capacity of wells based on previous drainage well installations and pumping
tests. In cases where there is no available data, perform test holes and pumping tests.
The exfiltration capacity of a well will be determined in gallons per minute per foot of head.
Stormwater pollutant load is very dependent on climatic and topographic features, such
as storm intensity and duration, distribution over the basin, land use, and topographic
features such as hills, swamps, and soil types. Design the type of stormwater treatment
to meet the needs of the particular location (i.e., more stringent water quality measures
should be required for wells discharging into the Floridan aquifer). Pretreatment methods
include physical, chemical, and biological control measures. Physical treatment includes
typical operations like settling and screening. An example of chemical treatment would
be the injection of alum into the stormwater on a storm-by-storm basis. Biological
treatment might be accomplished by using plants, fish, or other types of treatment in
retention ponds. In many instances, a combination of the above methods are used prior
to the discharge of stormwater into the freshwater injection well.
The discharge of the wells needs to occur below the 10,000 ppm Total Dissolved Solids
(TDS) level.
Ps g Hf = Pf g (Z +Hf)
where:
Ps = Density of the saline water, in lb/ft3
Pf = Density of the fresh water, in lb/ft3
g= Acceleration of gravity, in ft/sec2
Z= Head difference, in ft
Hf = Fresh water height above Mean Sea Level, in ft
Z = (Pf / Ps –Pf ) Hf
Figure 7.3-2: U-Tube Hydrostatic Balance between Fresh and Saline Water
Translating the U-tube to a coastal situation, as shown in Figure 7.3-3, Hf is the elevation
of the water table above the sea level and Z is the depth to the fresh water-saline water
interface below the sea level.
For typical seawater conditions (Ps = 63.9 lb/ft3 and Pf = 62.4 lb/ft3), the hydrostatic head
balance is approximately: Z = 40 Hf.
The cased portion of drainage wells in coastal areas is placed at least up to the fresh-
saline water interface. You can approximate the head loss due to the difference in the
density of salt water and fresh water as one foot of head loss per 40 feet of casing based
on the relationship Z = 40 Hf. As such, a typical design with 60-foot average casing up to
the interface would require 1.5 feet of head to displace the salt water, which is the usual
rule-of-thumb value used to design drainage wells discharging into the Biscayne aquifer.
This additional head is not required for wells discharging into a freshwater aquifer.
In areas where gravity head is not available, you can obtain the required hydraulic head
artificially by pumping. Pressurized drainage wells basically have the same design
requirements as the gravity wells but the hydraulic head is produced by a lift station.
Runoff pretreatment is necessary prior to the lift station, which usually is provided by a
retention basin with baffles and a bar screen for protection of the pumps. Typically, you
can combine these features with a finer screen to block smaller debris from discharging
into the well. The FDEP has waived the requirement of the Reasonable Assurance Report
(refer to Appendix K) when a passive by-pass at or below 8.00-foot NGVD ’29 is provided
from the pump’s common header. This requires a vertical stack pipe with a top elevation
at 8.00-foot NGVD ’29. If the head on the pumps is larger, there will be overflow in this
stack. Provide a cap/bird screen to avoid tampering.
7.3.3.4 Dimensions
Drainage (deep) wells usually are 24 inches in diameter and 100 feet to 150 feet deep.
When more than one well is necessary for the system, try to separate them by 75 feet to
100 feet.
7.3.3.6 Casing
The casing point is usually determined by finding the required minimum total dissolved
solid levels in the aquifer or by finding structurally stable rock formations. Typically, about
70 percent of the well depth is steel encased.
Well design data: (Based on information from other wells near the project site)
Depth to interface: Z = 60 ft
Step 2: Determine the peak discharge rate into the gravity well system.
tc = ti + tt tc = 13.3 min
Note: You can determine the rainfall intensity for other project locations using the
appropriate Intensity-Duration-Frequency (IDF) Curves. For IDF curves, go to the
Department’s Internet site at:
http://www.fdot.gov/roadway/Drainage/ManualsandHandbooks.shtm
Note: Consider attenuating the peak discharge when substantial runoff storage capacity
exists or is proposed within the contributing area. In these cases, use the NRCS
(formerly SCS) Method.
Note: The head loss (∆H = 1.5 ft.) used above is based on the rule of thumb described
in Section 7.3.3.1. Although usually disregarded, you can consider additional head
loss due to friction along the well casing (approximately 0.001 foot per foot of
casing). You may need a more accurate head loss calculation when dealing with
deep casings and very high flow rates coupled with low available hydraulic heads.
Step 5: Determine the 90-second retention volume for each gravity well.
Note: Provide the 90-second retention volume right before the drainage wells, below the
top of the well (usually at the SHWT).
Step 2: Determine the peak discharge rate into the gravity well system.
Step 3: Determine the net hydraulic head required for a pressurized well system.
Note: The head loss (∆H = 1.5 ft.) used above is based on the rule of thumb described in
Section 7.3.3.1. You can consider additional head loss due to friction along the
well casing (approximately 0.001 foot per foot of casing), but usually you would
disregard it. You may need a more accurate head loss calculation when dealing
with deep casings and very high flow rates coupled with low available hydraulic
heads.
Note: The sample problem would require approximately 12 wells to function by gravity
(see Section 7.3.4.1, Step 4, above). By pressurizing the system with 7.34 ft head
(at 8.94 ft NGVD), only one well would be needed. Notice that a Reasonable
Assurance Report will be required by FDEP (see Section 7.3.3.2 and refer to
Appendix K) because the head elevation at 8.94 ft NGVD is higher than 8.00 ft
NGVD.
Step 4: Determine the 90-second retention volume for each pressurized well.
Note: The 90-second retention volume has to be provided right before the pump station
or stations for the pressurized drainage wells.
The pump station would have to deliver a flow of 9.78 cfs with a maximum head of 8.94
ft NGVD. The system design then will consist of pump selection, design of the pump pit,
and the forced line, which is not in the contents of this document. The procedure for the
lift station design could be done by manual methods, spreadsheets, and other computer
software commercially available for lift station design.
The main elements in a hydraulic model setup are nodes and links. A node is a point with
a defined location in the drainage system used to simulate inlets, manholes, grade
breaks, bends, outlets, etc. Nodes usually are points that maintain the conservation of
mass during the calculation process. Links are the connections between nodes used to
simulate pipes, ditches, and channels. You can use links to transfer or convey water
through the drainage system.
Other important modeling elements are the boundary conditions, which usually simulate
the tailwater conditions as time-stage nodes, and the drainage areas, which are closed
boundaries contributing into their respective nodes. Rainfall and peak runoff
computations, usually related to the drainage areas, are calculated using the Rational
Equation or the NRCS methods.
It is necessary to include a special link to model the transference of runoff from the node
simulating the exfiltration trench to the node simulating the design ground water (See
Figure 7.4-1). This special link usually is a head-discharge ratio or rating curve, which
could be defined by giving different head values (∆H) to calculate their respective
discharges (Q) using the following equation (refer to Section 7.1.2.3):
Q = (Ku Au + Ks As) ∆H
where:
Q = Flow rate, in cfs
Ku = Unsaturated hydraulic conductivity (cfs/ft2 – ft of head)
Ks = Saturated hydraulic conductivity (cfs/ft2 – ft of head)
Au = Unsaturated flow area (ft2) = Lnet (2Du)
As = Saturated flow area (ft2) = Lnet (2Ds + W)
∆H = Hydraulic head (ft)
If the unsaturated depth of the exfiltration trench (Du) is less than one tenth of the total
trench depth, disregard the unsaturated exfiltration because the unsaturated hydraulic
conductivity usually is several times less than the saturated hydraulic conductivity of the
soils. If the trench width is greater than two times the depth, disregard the exfiltration
through the trench bottom (As = 2Lnet Ds).
The head-discharge ratio or rating curve may not be accurate if the design ground water
is considered variable and the modeling program uses elevations instead of hydraulic
head for calculations. You can consider the variable ground water to be rising from the
average October ground water elevation to the anticipated ground water elevation at the
end of the design storm event. In these cases, a family of tailwater-headwater-discharge
rating curves is necessary to simulate the transference of runoff from the exfiltration
trench to the ground water. You can calculate the rating curves by giving specific values
to couples of tailwater and headwater elevations to calculate their corresponding head
values (∆H). Having the hydraulic head (∆H), you can calculate the discharges (Q) using
the above equation and the tailwater-headwater-discharge relationship would be
complete.
Basin represents the drainage area contributing into the drainage well. Node N-WELL
simulates the retention box prior to discharge into the well. The rating curve link simulates
the well discharge into the water table. Node N-GW is the boundary node representing
the ground water elevation.
Connect the rating curve link to a time series node representing the water table at the
discharge point. If the system includes several drainage wells, you would develop a rating
curve for each well. There are a number of acceptable computer software hydrologic and
hydraulic models capable of analyzing the system.
8.6 Specifying Optional Pipe Materials in the Contract Plans .......................... 8-47
8.1 INTRODUCTION
It is important to consider the array of materials available for culverts. After you complete
the initial hydraulic design, evaluate the list of culvert materials shown in Table 6-1 of the
Drainage Manual to choose among potential options. Chapter 3 of the Drainage Manual
provides the roughness coefficients you can use to evaluate the various materials. Your
evaluation must consider functionally equivalent performance in durability and structural
capacity. If you are constructing a culvert extension, you should match the existing culvert
material to avoid misleading future maintenance assumptions about the type of buried
pipe material. However, if the existing culvert fails a corrosion evaluation when the length
of time of service is factored in or if it shows signs of deterioration, the existing culvert
should be replaced or rehabilitated (e.g., lined).
Although Table 6-1 of the Drainage Manual provides comprehensive policy on the
selection of Design Service Life, practical considerations sometimes will override the
guidance material. For instance, gutter drains are listed as a 25-year DSL application, but
if a gutter drain, or any other pipe, is to be located where replacement would require
closure or major traffic disruption during the design life of the facility, then a longer DSL
is appropriate. Any pipe that is beneath or within the soil zone that provides stability to a
structural wall must have a 100-year service life due to the potential for wall damage or
failure and because of the difficulty of replacing that pipe in the future.
Changing the diameter may change the Estimated Service Life (ESL) of concrete and
metal pipe. This occurs because of the change in wall thickness. As the diameter of
concrete and metal pipe increases, so logically does the wall thickness of the pipe. For
concrete pipes, the wall thickness increases as a result of the thickness change in the
cover over the reinforcing wire, and in metal pipes, the increase is due to the thicker gage
metal used for larger-diameter metal pipes.
Table 6-1 from the Drainage Manual is included on the next page for easy reference by
users of this design guide. Refer to the Drainage Manual for the latest version.
8.3 DURABILITY
The requirements for DSL may vary between projects as well as within a project,
depending on the highway functional classification and the application of the culvert.
The projected service life, hereafter referred to as the Estimated Service Life (ESL), of a
culvert is the duration of service time after which significant deterioration is predicted to
occur. After this point, you would need to consider major rehabilitation, lining, or
replacement. For a material to be included in the design of a project, its ESL must meet
or exceed the required DSL.
For metal pipe, the time of first perforation (complete penetration) is the service life end
point. For concrete culvert, the service life ends when the culvert has experienced a
corrosion-related crack in the concrete. The ESL of a specific culvert material is
determined from an evaluation of the corrosiveness, based on the environmental
conditions of both the soil and water, at the intended culvert site.
For plastic pipe (polyvinyl chloride [PVC] and high density polyethylene [HDPE]), the
service life is independent of the environmental conditions. The service life ends when
any crack appears in the pipe. Plastic pipes sometimes crack from initial field loadings,
but can also crack through a creep/rupture mechanism called slow crack growth. The ESL
of plastic pipe is determined by the State Drainage Office rather than by site-specific
corrosion analysis.
• pH
• Resistivity
• Chlorides concentration
• Sulfates concentration
Instances of high pH values are extremely rare. Observed pH values in virtually all soils
and waters in Florida are less than 10. pH values between 5.5 and 8.5 are of no concern.
pH values less than 5.5 are common in swampy areas; a pH below 5 is an aggressive
environment for reinforced concrete and a pH below 4 is highly aggressive. Generally, a
low pH is conducive to steel corrosion. Both a low pH and a high pH (> 8.5), coupled with
low resistivity, create a corrosive environment for aluminum.
Resistivity—A measure of the electrical resistance of soils and waters. Resistivity is the
inverse of conductivity. Highly conductive media tend to promote corrosion. Corrosion is
an electrochemical process. For corrosion to occur, charged ions must migrate through
the soil or water from a corroding area (anode) to a non-corroding area (cathode). Soils
with relatively high resistivity values (> 3,000 Ohm-cm) impede the migration of these
ions, which slows corrosion. Environments with low resistivity values (< 1,000 Ohm-cm)
provide an easy path for ions to migrate from anode to cathode, which in turn accelerates
corrosion. In general, clayey soils, organic soils, or chloride-bearing soils would tend to
generate low resistivity values.
Sulfate Concentration—A measure of the number of sulfate ions present. Sulfate can
cause concrete components to deteriorate. If the sulfate concentration is high (> 5,000
ppm), concrete is vulnerable to accelerated deterioration. Sulfate ion concentrations
rarely exceed 1,500 ppm in Florida; therefore, the threat sulfate ions pose is not as
considerable as that of chloride ions.
Elevated chloride values typically are seen only in or near coastal areas. High sulfates
can be seen anywhere, but are more prevalent in coastal areas.
There are other factors that may affect service life. These factors are not the primary
factors, and as such are not included in the FDOT Culvert Service Life Estimator (CSLE)
Program. They are mentioned here to alert you to their potential affects.
Roadway plans include a “Roadway Soils Survey” sheet, as shown in Figure 8.3-1, which
identifies a range of values of all tests performed. The complete geotechnical report
contains test results for the specific locations sampled, and you can use these data for
culvert analysis. Review the data and correlate them to actual field conditions where
possible. A prediction of the actual service life of a culvert material at a particular site can
be determined by the performance of a similar culvert material in the same or similar
environmental condition. If the test data do not correlate with the observed culvert
conditions, then request additional testing at the site in question. Ultimately, you should
weight conclusive field performance more heavily than predicted service life when field
performance and predicted service life disagree.
Analysis of the test data should take into consideration the most corrosive values of the
native soils. However, with site-specific project environmental test data available, you
won’t need to use the most corrosive individual site data for the entire project or extract
the most aggressive individual parameter results from the testing data to create a worst-
case, project-wide condition. This over-conservatism is unwarranted and unrealistic.
Instead, you can review the soil boring strata and apply test data to those locations that
are most representative of the soil strata and conditions where the corrosion test data
were obtained. There may be particular segments of the project where corrosive
conditions exist, and other segments where the corrosion potential is low.
Figure 8.3-1
DSL: This application is to be a storm drain system that is located on a major urban facility
and will function as an urban principle arterial road. The appropriate DSL for this
application is 100 years.
The following data were furnished and a field review gave no indication that these values
were suspect:
pH: 7.6
Resistivity: 2,610
Chlorides: 2,390
Sulfates: 1,120
Diameter (Pipe Size): 42 inches; because this is a storm drain system, an n-value of 0.012
was used.
Figure 8.3-2 illustrates materials you would use in performing the structural analysis.
Figure 8.3-2
Note that the ‘Hint’ field changes while this screen is open. The colored lines indicate
warnings: a yellow highlight indicates a warning concerning environmental data; a red
highlight indicates a warning based on the structural data [Appendix C of the Drainage
Manual].
If any one of the lines is double-clicked, another window pops up with more detailed
information about the particular material option. The program allows you to print and save
a file with a unique name; this allows you to maintain the corrosion parameters and site
data, but vary the pipe size or roughness coefficient, re-analyze and print to unique output
files. The printouts are very useful for documentation of the analyses. See Figure 8.3-3.
Figure 8.3-3
Give no additional consideration to one material over another having less service life if all
meet the minimum required. In looking at the printout, culverts made from steel-reinforced
concrete, aluminum, aluminized steel, polypropylene, and high density polyethylene class
II all meet the 100-year DSL. If the DSL was 50 years, then additional materials may be
allowable.
Pipe size affects materials by invoking different gages of metal pipes. Additionally, pipe
size affects the life of reinforced concrete pipe because, with larger diameters, the wall
thickness increases, as does the cover over the reinforcing steel. See Figure 8.3-4 for
allowable materials when the pipe size is reduced to 24 inches, given the same corrosion
parameters and DSL as the previous example. Reinforced concrete pipe is no longer
allowable, whereas non-reinforced concrete pipe is allowable. The gage of spiral-ribbed
aluminized pipe (SRAP) has changed because of the smaller diameter, and PVC is now
an allowable option because it is available in the smaller diameter.
Figure 8.3-4
8.3.4 Special Cases (Jack and Bore Casings, Ductile Iron Pipe, any
Ferrous Metals)
When you choose to install a culvert by jacking and boring instead of open cutting, use
the jacked and bored casing as the conveyance pipe except under railroads or in high-
pressure designs. See Standard Plans, Index 430-001 for railroad company
requirements.
Because jack-and-bore locations typically have a high AADT, this service life estimation
example will assume a 100-year DSL. Use the following steps to determine the casing
requirements.
1. Run the Service Life Estimator Program or use the figures or tables in Appendix M
with site-specific environmental parameters. If the casing or pipe will be exposed
to water (surface or ground) for extended periods of time, compare the
environmental parameters of the water with those of the soil. Use the test results
that produce the shortest service life for the galvanized steel option. Note that
when using the CSLE Program, reduce the DSL as needed for the galvanized steel
option (corrugated steel pipe [CSP] or spiral rib steel pipe [SRSP]) to show up as
an allowable option. Although the required DSL may be 100 years, you must first
obtain the service life for the particular corrosion parameters, or you can use Figure
M1 to determine estimated service life.
2. To be conservative, deduct 10 years from the ESL of the galvanized steel option
generated by the program (or determined by service life tables/figures).
3. Determine the pitting rate by dividing the wall thickness of the galvanized steel
option estimated by the program by the estimated service life determined in Step
2 (ESL – 10 years). From the Drainage Manual, Appendix C, identify the wall
thickness of the gage pipe called out on the output.
Knowing the pitting rate, you can determine the required wall thickness by multiplying the
DSL for the application by the pitting rate.
Figure 8.3-5
14 gage = 0.079 inches (thickness of 14 gage galvanized steel culvert per Drainage
Manual, Appendix C)
Required wall thickness = 100 years (DSL) x 0.00168 (pitting rate) = 0.1681 inches
Note that the pitting rate determined when other DSLs are input and resultant service
lives are obtained will be approximately the same. For example, if a DSL of 25 years is
input in the above example, the gage of SRSP allowed is 16 (0.064 inch), with a
corresponding service life of 46 years. This results in a pitting rate of 0.00177 inches/year.
In summary, you would need to use a steel casing with a wall thickness of at least 0.17
inches. In the plans, include a note such as: “For corrosion purposes, steel casing must
have a minimum wall thickness of 0.17 inches.”
The required wall thickness is for corrosion purposes only. Typically, you will need greater
wall thicknesses for the structural loadings associated with the jacking of the steel casing.
The CSLE program has an option for “Jack and Bore Steel Casing Pipe” under “Analysis”;
the window will show the approximate wall thickness of pipe suitable for jack and bore
and the associated service life. Check the pipe size in the pop-up window; it may not be
the size input for the initial analysis. The metal thickness shown is that of a typical steel
pipe that you would use for jack and bore. The program uses the thickest galvanized steel
pipe gage to determine the pitting rate (even if that particular gage is not available in the
given size). That pitting rate is applied to the typical jack and bore pipe wall thickness to
estimate service life. If the ESL of the jack-and-bore casing pipe is less than that required,
input the service life in the portion of the window that says “Calculate Metal Thickness…”
and then press return/enter on the keyboard for the required thickness to meet service
life. The print output from this pop-up window contains only the pitting rate analysis, not
the pipe size, nor the corrosion data; so a screen print is a better option for documentation.
The minimum thickness that meets service life is that determined by the pitting rate
equation. Show the thickness in the construction plans with a note stating it is the
minimum thickness to meet service life. The contractor is responsible for determining the
wall thickness required for the jack-and-bore pipe to meet Specification 556.
For the example shown in Figure 8.3-6, the minimum metal thickness based on service
life is thicker than the typical jack-and-bore pipe because of the aggressive
environmental parameters.
Figure 8.3-6
The printout for this jack-and-bore service life analysis is shown in Figure 8.3-7.
Figure 8.3-7
When using the casing alone is not allowed, you should place a note disallowing this
practice in the plans to communicate to the Contractor that a VECP (Value Engineering
Change Proposal) eliminating the interior pipe will not be approved.
For each of the acceptable pipe materials based on the corrosion analysis and pipe
location within the embankment, verify that the depth of backfill over the pipe is between
the minimum and maximum fill heights in the appropriate table in the Drainage Manual,
Appendix C. If the cover height is outside the limits, the following options are available:
1. Adjust the flow line of the pipe as long as this adjustment does not violate any other
design criteria.
2. Increase the gage of metal pipe or the class of concrete pipe. For metal pipe, verify
that the specified gage thickness is available for the corrugation specified.
The FDM requires that you call out all the acceptable types of pipe materials in the plan.
You can establish the required class of concrete, or gage and corrugation for metal pipe,
using the CSLE program or the service life tables/figures in Appendix M, and the Drainage
Manual, Appendix C. The tables in Appendix C have been incorporated into the CSLE;
however, you will need to back check the results of the CSLE structural check against the
tables in Appendix C for final verification. Generally, it is more efficient to look at the tables
when determining the structural suitability than to input discrete height values in the
Structural Check option of the CSLE. The tables allow you to readily see the lower and
upper limits of allowable cover, whereas the CSLE output provides only a “pass” or “fail”
for a particular value.
For example, given the allowable pipe materials shown in Figure 8.3-2, find the pipes that
are structurally sufficient for a minimum fill height of 23 inches and maximum fill height of
25 feet.
Using the CSLE program with corrosion data and DSL shown on Figure 8.3-2, click on
the box next to “Structural Check.” A window pops up for input of pavement type and
cover thickness. The cover thickness here is input to the flowline of the pipe whereas the
cover is shown to the outside crown of the pipe in the Appendix C tables. Input a pipe
depth of 68 inches (from finished grade to pipe flowline), and 3 inches for the thickness
of flexible asphalt pavement. The CSLE program results in the elimination of HDPE and
PP pipe (Figure 8.4-1). Referring to the Drainage Manual, Appendix C, the table for Plastic
Pipe, you can see that the minimum cover from top of base course to top of pipe is 24
inches for both HDPE and PP pipe. Based on our inputs to the CSLE program, the cover
is [(68-3)-(42)] = 23 inches, not including deduction for pipe wall thickness. The Appendix
C table for SRAP shows minimum cover of 21 inches for the 42-inch diameter, 14 gage
pipe. Referring to the respective tables for the remaining allowable materials, we find that
12 inches is the minimum cover for both round and elliptical concrete, as well as for the
SRSP (SRASP has the same structural properties as SRSP).
Figure 8.4-1
Minimum cover and maximum fill heights obtained from the tables in the Drainage
Manual, Appendix C, are summarized in Table 8.4-1 for the acceptable materials shown
in Figure 8.3-2.
Table 8.4-1 Example Project Minimum Cover and Maximum Fill Heights
Allowable material for 42-inch Appendix C Appendix C
diameter, minimum DSL = 100 Allowable minimum Allowable maximum fill height (ft.)
years cover (in.) to finished grade
14 gage SRAP 21; from top of base 25 ft; special installation
Reinforced Concrete Pipe
12; from finished grade 21 ft to 33 ft; CL IV pipe required
(RCP); Typical Dry Cast
RCP; Elliptical Only 12; from finished grade max 25 ft; CL HE-IV required
14-gage SRASP
12; from top of base 54 ft
(use SRSP table)
HDPE CL II 24; from top of base 13 ft
Preparing a table with the allowable materials and their minimum cover and maximum fill
height allows one to quickly ascertain where the materials can be used within the project
if locations of the minimum cover and maximum fill are known. Plastic pipe would not be
acceptable for installation where the minimum cover is less than 24 inches, and fill heights
are greater than 13 feet, but there may be many locations throughout the project where
plastic pipe installation would be within the allowable structural limits. That is why it is
more efficient to use the tables directly rather than use the CSLE for the structural check.
Note that the fill heights shown in the Drainage Manual, Appendix C, are calculated using
a very conservative approach. In those cases where you encounter very high or very
shallow fill heights, you can use methods set forth in AASHTO LRFD Bridge Design
Specifications, Section 12.Where you must locate pipes within close proximity to walled
embankment areas of any type, review the figures in the Drainage Manual, Appendix D,
to determine what limitations are imposed on pipe location and material. The figures in
Appendix D show Wall Zones A, B, and C. Wall Zone criteria allow both longitudinal and
transverse Wall Zone Pipe (as listed in the Drainage Manual, Table 6-1) in Wall Zone A.
You are allowed to use Transverse Wall Zone Pipe conveyances in Wall Zone B, and you
may not use pipe conveyances of any type in Wall Zone C. A few of the figures in
Appendix D are reproduced here, with examples of where you may place pipes. Wherever
possible, it is best to avoid pipe placement in any of the Wall Zones.
Figure 8.4-2 shows MSE wall at a bridge abutment on shallow foundation and on deep
foundation. Wall Zone B extends under the deep foundation whereas Wall Zone C (no
pipes) extends under the shallow foundation. The figure shows pipes only within the
allowable zones.
Figure 8.4-2
Another example of pipe within MSE Wall Zone is shown in Figure 8.4-3. Longitudinal
conveyances are shown in Wall Zone A. Even though the pipe to the left of the wall is
only partially within Wall Zone A, it must meet the Wall Zone pipe requirements. If right of
way allows, this pipe should be aligned fully outside of Wall Zone A. The pipe that is within
the wall fill embankment can run longitudinally only within the top five feet. Minimize
longitudinal runs of pipe in Wall Zone A to the greatest extent practicable. Where inlets
are required that would extend into Wall Zone B, the preference would be to outfall
transversely to a trunk line located outside of the wall zones. If this is not feasible, then
you could use a deeper structure to allow the pipe to outfall transversely through or under
the wall; these configurations are not ideal. Any structure or pipe within the reinforcement
strap zone must be coordinated with the wall designer.
Figure 8.4-3
Figure 8.4-4 shows a gravity wall and its associated wall zones. Ascertain the wall scheme
proposed (there are other schemes) to ensure that any proposed drainage structures
meet the wall zone criteria.
Figure 8.4-4
Figure 8.4-5 shows wall zones associated with a cantilever wall. Note that this
configuration, as well as all supporting walls on shallow foundation, has a no-pipe zone,
i.e. Wall Zone C, which is directly under the structure and extends out in a trapezoidal
shape below the structure. The depth of the trapezoid is dependent upon the particular
structure.
Figure 8.4-5
8.5 DOCUMENTATION
You are required to provide justification if you allow or eliminate a pipe material. You can
find documentation requirements in Chapter 6 of the Drainage Manual. Requirements
include the Design Service Life required for the application, environmental data, and the
results of the structural evaluation.
The CSLE program provides an excellent form of corrosion analysis documentation in the
printout. The printout documents the site specific environmental parameters, the ESL,
and the materials that fail to meet or exceed the DSL. Also, you can add further comments
for documentation purposes. An example of additional comments would be: “not allowed
per Drainage Manual, Appendix C,” “minimum cover not available,” or “maximum cover
exceeded.”
• Side drain
• Cross drain (replacement and extensions)
• Storm drain
• Wall Zone Pipe
• Gutter drain
• French drain
For this example, each application will be addressed and will include a determination of
the design service life, commonly asked questions, and proposed solutions to those
questions.
Check the hydraulics at typical locations to determine if materials with N-values of 0.020
or greater should be included. Generally, if the hydraulic evaluation indicates the structure
is outlet controlled, only those materials with N-values equal to 0.012 need be considered.
In this case, the roadside ditches have minimal longitudinal slope and hydraulic
evaluations of a typical location showed the culvert operated in outlet control, so only
materials with N = 0.012 are suitable hydraulically. (See Cross Drains for side drains
under side streets.) The design calculations result in pipe sizes that include 18-inch, 24-
inch, and 30-inch.
Soil corrosion data obtained at shallow depths along the project were fairly consistent and
are shown in Table 8.5-1.
Table 8.5-1
Station Boring # pH Resistivity Chlorides Sulfates
527+50 A-1 5.6 32000 20 108
592+00 A-2 6.6 9500 20 118
610+00 A-3 6.8 17000 20 20
You can enter the information for each site into the CSLE program, or you can use the
tables or figures in Appendix M to determine suitability for the 25-year DSL. Let’s use the
figures to more quickly evaluate these three sets of test data. Looking at the tables and
figures, we can see that the environmental parameters that affect steel and aluminum are
pH and Resistivity. Those that affect reinforced concrete are pH, Chlorides, and Sulfates.
This example shows some of the Figures and Tables in Appendix M as Figures 8.5-1
through 8.5-4.
From Figure 8.5-1, we see that—as long as the pH is above 5.5 and the resistivity is
above 9,000—the DSL of 25 years is met for 16-gage galvanized steel. For 16-gage
aluminized steel, Type II, we see on Figure 8.5-2 that the 25-year service life is met for
pH between 4.5 and 9, with resistivity greater than 1,500. Figure 8.5-3 reflects the service
life of 16-gage aluminum pipe; we can see that low resistivity values (<5,000) with pH
values lower than 6 or higher than 8 adversely affect the service life of aluminum. In our
case, the pH values range from 5.5 to 6.8 and the resistivity values are all greater than
9,000; therefore, the required DSL is met.
We will use the table in Figure 8.5-4 to evaluate the suitability of reinforced concrete pipe.
The table shows that service life decreases with increasing chloride concentrations and
as pH drops below 6. If sulfate concentrations go above 1,500 ppm, the service life should
be discounted as noted. Since all chloride values from the samples are 20 ppm or below,
there is no adverse effect on reinforced concrete. However, the table values are for 60-
inch pipe, which has a thick pipe wall. To estimate service life for 18-inch pipe, the service
life of 360 years must be multiplied by 0.36. The minimum service life anticipated for
reinforced concrete pipe on this project is, therefore, approximately 130 years.
Figure 8.5-1
Figure 8.5-2
Figure 8.5-3
Figure 8.5-4
All roadside ditches are 3.5 feet below the roadway edge of shoulder, and ground at the
right-of-way line is at or above the edge of shoulder, so available depth is 3.5 feet.
Referring to the cover height tables in the Drainage Manual, Appendix C, we see that
plastic pipe up to 48 inches in diameter requires 24 inches of cover below the top of base
course under flexible pavement. SRAP requires 12 inches of cover for pipe diameters up
through 24 inches and 15 inches of cover (below the top of base course) for 30-inch pipe.
SRSP requires 12 inches of cover below the top of base course for pipe diameters up
through 48 inches. Concrete pipe requires 12 inches of cover from finished grade of
flexible pavement.
For 18-inch pipe, 24 inches is available from inside crown of pipe to finished grade, so
the plastic pipe minimum cover is not met. Where side drains are 24-inch diameter, there
is 18 inches from finished grade to inside crown of pipe and 15 inches from the top of
base course. So for 18-inch and 24-inch side drains, you are allowed to use all pipe
materials with an N value of ≤ 0.012 except plastic. For 30-inch diameter side drains,
there is 12 inches of cover from inside crown of pipe to finished grade; therefore, the
SRAP and SRSP pipe cover requirements are not met. Concrete pipe wall is much thicker
than other types of pipe materials and must be taken into account. In this case, there will
be only 8.5 inches of cover on 30-inch round concrete pipe. The wall thickness for elliptical
concrete pipe is slightly greater for a size equivalent to round concrete pipe. A 24-inch by
38-inch elliptical concrete pipe wall is 3.75 inches thick, so there is 14.25 inches of
clearance (42 – 27.75). The elliptical concrete pipe is the only pipe that will meet the
structural requirement where a 30-inch side drain is needed.
Note that if the structural check is used in the CSLE program, it does not use the 30-inch
round equivalent dimension (24-inch by 38-inch) for the elliptical pipe; it uses the 30-inch
diameter input and will, therefore, show that all pipes will fail the structural check where
there is 42 inches from pipe invert to finished grade under flexible pavement. (See the
CSLE output for 24-inch and 30-inch pipe in Figure 8.5-5 and Figure 8.5-6.) So, for pipe
arch or elliptical pipe, it is best to use the cover height tables and to calculate the cover
available based on pipe dimensions.
Figure 8.5-5
Figure 8.5-6
To present the results in the plans, use notes under the side-drain table stating the
allowable materials. In this case, an appropriate note might read:
Allowable pipe materials for 18-inch and 24-inch side drains, unless otherwise
noted, are: RCP, NRCP, SRSP, SRASP, SRAP and ERCP. Allowable pipe
material for 30-inch side drain is ERCP (30-inch-other) only.
In cases where there is minimal cover and the structural requirements could not be met
by using elliptical pipe or pipe arch in lieu of the hydraulically required round pipe, then
you will need to analyze alternate pipe configurations. This could include multiple smaller-
diameter pipes or, possibly, a larger diameter pipe buried deeper so that the flow area is
from normal ditch line to crown. The latter also may require adjustment of the roughness
coefficient in the analysis.
For example: if the cover condition at the side drain resulted in less than 12 inches, even
with the elliptical concrete pipe, two 24-inch pipes could be used as long as they fit within
the ditch. The Mitered End Section (MES) width for a double 24-inch pipe installation is
8.92 feet out to out (Standard Plans, Index 430-022). A 42-inch pipe half buried has the
equivalent capacity to a 30-inch (fully open) pipe if the fill has a roughness coefficient only
slightly greater than the pipe wall. This installation would be 20 inches narrower than the
double 24-inch, with an MES width of 7.25 feet. If you were to use this option, place a
note in the plans stating that the pipe size is hydraulically necessary and used to meet
cover and dimensional limitations. Additionally, you would need to specify the fill.
For the project example, these are local streets with AADT less than 1,000, so the
side/cross drains must meet a 50-year DSL. The pipes for the four locations where the
side streets cross roadside ditches were hydraulically checked to ensure that the
appropriate design frequency flow could be passed without damage to the roadway or
offsite properties. The side drains at these locations are 24 inches in diameter. You can
classify these “side” drains as cross drains because they are under public roads.
Therefore, these structures are not included in the side drain summary table, but are
instead included with structure numbers in the Summary of Drainage Structures table.
The materials for these structures were checked using the CSLE to determine which met
the 50-year DSL. All materials previously determined are acceptable, but the SRSP has
changed from 16-gage to 10-gage so that the service life can be met.
Figure 8.5-7
There are two cross drains that convey offsite runoff under the design roadway. One of
the cross drains is located within a sag vertical curve in the rural section of the design
roadway; the other is located within the urban section.
The location of the first cross drain has a history of roadway over-topping due to basin
diversions and increased runoff from upstream development. It is a 36-inch corrugated
galvanized steel culvert with straight endwalls that are located 18 feet from the edge of
travel lanes. During the Project Development and Environmental (PD&E) study, it was
determined to raise the roadway profile, along with cross drain replacement, to minimize
risk to motorists. The location of this cross drain warrants a DSL of 50 years. The new
cross drain analysis determined that the cross drain is inlet controlled; therefore, both
rough and smooth wall pipe materials were considered. The hydraulic analysis showed
that a 54-inch culvert opening is needed to pass the design discharge of 160 cfs.
The location of the second cross drain, a 36-inch RCP, has exhibited no hydraulic
insufficiencies. Since it is within an urban section, it should have a DSL of 100 years. The
cross drain was analyzed hydraulically and this analysis determined that you could extend
the cross drain with no adverse upstream effects.
Specific environmental data were obtained at the site of the two cross drains as follows:
Table 8.5-2
Station Boring # pH Resistivity Chlorides Sulfates
505+00 Rural A-4 5.2 17,000 51 6
589+00 Urban A-5 6.9 18,000 42 6
The CSLE program was used to find culvert materials that meet the DSL and structural
requirements for the 54-inch culvert. The depth from finished grade to flow line of pipe is
96 inches. The CSLE output file is shown in Figure 8.5-8. Figure 8.5-8 does not contain
all data for each metal option; see the screen shot of the output in Figure 8.5-9.
Figure 8.5-8
Figure 8.5-9
So, there are 10 options for CD-1 at station 505+00. There are metal pipe arch options
that you also could include. However, it is unlikely that the elliptical or arch options would
be economical to construct. Generally, round pipe is easier to construct, so only the round
options need to be shown. If there were utility conflicts, then they could be avoided with
a maximum pipe height of 48 inches; then the 3” x 1” Corrugated Aluminum Pipe Arch,
16 gage pipe; the Corrugated Steel Pipe Arch, 10 gage in both the 2-2/3” x ½” and 3” x
1” corrugations; and the Aluminized Corrugated Steel Pipe Arch, 12 gage, would be
acceptable alternates.
You can extend the second cross drain and still meet the hydraulic requirements. Check
to verify that this cross drain still will have the required DSL. The corrosion data obtained
for this location were input to the CSLE program, along with the depth of cover. The
results, shown in Figure 8.5-10, show that the RCP has a service life of 360 years.
However, Table M-4 of Appendix M indicates that you should adjust the service life of 360
years by multiplying by 0.54 for 36-inch diameter pipe. This results in 194 years. This pipe
has been in service only 40 years, so the DSL of 100 years is met.
When extending cross drains, try to use the same existing pipe materials. If, upon
inspection, the existing pipe shows corrosion or has structural cracking, then you should
replace or line the existing pipe. When the extension of an existing pipe results in a minor
Figure 8.5-10
When choosing the appropriate DSL, use the same steps as those previously stated.
Remember, all storm drains do not require the 100-year DSL criteria. Refer to the notes
on Table 6-1 for guidance on the selection of DSL.
The 100-year DSL is required for our example project because the storm drain system is
located within a curb-and-gutter section (see Note 2, Table 6-1). The corrosion data
produced by the geotechnical survey were correlated to the field review observations and
these values are not suspect. The corrosion data values are from the most aggressive
test site (not the most aggressive parameter value from all test sites) along the applicable
subsection of the project.
Table 8.5-3
Station To Station Boring # pH Resistivity Chlorides Sulfates
550+00 630+00 B-1 thru B-5 5.2 17,000 51 6
Because this is a storm drain system, only the smooth wall pipe options may be
considered. The corrosion test data were input to the CSLE program for pipe sizes of 18,
24, 30, and 36 inches. Minimum cover is 25 inches and maximum cover is 11 feet. The
CSLE program provided the materials described below for both 18-inch and 24-inch pipe
sizes (Figure 8.5-11). For 30-inch and 36-inch, 12-gage SRAP is an additional option. A
thicker gage of SRAP is needed because of the low pH and 12 gage is not available in
diameters of less than 30 inches. See Figure 8.5-12 for a screen shot of the CSLE
program for 36-inch pipe.
Figure 8.5-11
Figure 8.5-12
Figure 8.5-13
Zone C is below the median barrier cantilever wall, which is back and ahead of the median
barrier inlet. The pipe options, as shown in the Drainage Manual, Table 6-1, are:
polypropylene, PVC, and J&B Steel. The steel pipe will cost substantially more than the
PVC or polypropylene, so it would be included as an option only if structurally necessary.
In this case, the 24-inch pipe from the barrier wall inlet to the SGI has 13.5 feet of cover,
so polypropylene may be acceptable. However, because this pipe is under the wall with
roadway on both sides of the wall, you are encouraged to use the methodology in the
AASHTO LRFD (Load Reduction Factor Design) Bridge Design Specifications, Chapter
12, to ensure that the pipe installation will withstand the load conditions. Consider the
need for resilient connections at structures, particularly where there may be some
differential settlement.
Figure 8.5-14
Figure 8.5-15
For these applications, consider whether a roughness coefficient ≥ 0.020 will result in a
hydraulically acceptable design. Where the French drain also is the primary storm
conveyance system, only materials with N-value = 0.012 need to be considered. Where
the French drain is “offline” or is a secondary conveyance, analyses should consider N
value ≥ 0.020. After ascertaining the hydraulic needs, use the CSLE program or the
figures and tables in Appendix M to select materials that meet the required DSL based
upon the corrosion data and pipe size. Then determine minimum and maximum cover
and use the CSLE program or Appendix C of the Drainage Manual to select pipe materials
that meet the structural requirements.
Side drains are listed in a Summary of Side Drains table. The two formats within Basis of
Estimates, Chapter 8, have columns for five round and five “other” pipe sizes with
corresponding MES widths; one has additional columns for offset and flowline. You
shouldn’t modify the tables except to “hide” columns not used or to change pipe sizes as
needed. As noted in the side drain example in Section 8.5, you should place notes stating
allowable side drain options below the table. Include any particular exceptions in the
Design Notes column. Do not use the Construction Remarks column, since that is
reserved for the construction phase of the project. The two Summary of Side Drain tables
are shown in Figure 8.6-1. See the current version of Basis of Estimates for the most
current form of these tables.
Figure 8.6-1
French drains also may be listed in a Summary Table; however, that table form has only
the actual limits of pipe/French drain and does not have a column for the structures or the
non-perforated pipe without the gravel envelope that extends a minimum of four feet on
each side of the drainage structure. If you decide to use this Summary Table, then the
Summary of Drainage Structures (SDS) tabulation should include the drainage structure
and non-perforated pipe and a separate column for the French drain segment. You can
note the pipe options allowable for French drains below the French Drain Summary Table
or within the Design Notes Column. You cannot use dissimilar types of pipe within a
continuous run of pipe, and the non-perforated pipe should be of the same material as
the perforated pipe.
All other pipes that are listed in the SDS tabulation should have options listed in the
Optional Materials table. When elliptical pipe or arch pipe are the only allowed options,
these are listed in the Summary of Drainage Structures under the column heading “Other”
with the round equivalent size. The Optional Materials tabulation for these pipes should
include elliptical or arch pipe configurations that meet the DSL and structural
requirements. There are two Optional Materials tabulation formats; one includes flowlines
and one does not. Generally, flowlines for all options will be the same. However, in some
cases, minimum cover will control storm drain flowlines and it will be necessary to list the
required alternate flow lines. If round pipes meet the required clearances, there is no need
to even list elliptical and arch pipes as options since they usually are more expensive than
their round equivalents. For instance, where a round concrete pipe and arch metal pipe
meet all requirements, it is not necessary to list elliptical concrete as an option.
You can group pipe options by size and, if necessary, by location (station to station) or
by structure numbers. The structure numbers are listed as “Exceptions” in the “STR No.”
column next to the corresponding pipe size column. If the exceptions all have the same
limited options, the options can be listed with that group; otherwise, show the exceptions
individually with allowable material. Ideally, you can group the options by pipe size and
you can use the suitable materials for a spectrum of sizes. The intent of allowing options
is for the contractor to choose acceptable materials from a fair, competitive pipe supply
market, not to have numerous materials installed within a particular storm drain system.
In general, if you group material options by pipe size, one Optional Pipe Tabulation Sheet
is sufficient to describe allowable options for most projects.
Figure 8.6-2 is a spreadsheet format of the Optional Pipe Tabulation sheet containing the
optional materials determined for the examples in Section 8.5.
Figure 8.6-2
Note that both of the Optional Materials Tabulation forms have a “PLOTTED” column. It
is important to check the material used for determining clearances at drainage structures.
If spiral rib pipe was assumed/used to determine clearances at structures and concrete
is listed as a pipe option, then the thicker wall of concrete pipe may not fit into the
structure. Structure fit may be another rationale for choice of pipe material. For example,
pipes with thinner walls would allow for smaller precast openings, which in turn allows for
smaller angle between pipes entering a round structure.
For design/build projects, you still need to create materials analyses to demonstrate
suitability of the pipe to be installed, and then you can include the analyses in project
documentation. You can include either an optional materials tabulation sheet in the
construction plans or make sure that the pipe material to be installed is noted somewhere
in the plans, such as on the plan sheets or on the Summary of Drainage Structures.
There are numerous design features (depth, size, shape, treatment method, landscaping,
etc.) that you can modify to accommodate a pond site. However, hydraulic constraints
may preclude the use of some sites. Alternate sites and their different design features
usually will result in different costs and impacts. As a result, an evaluation of alternates
must be made to select the most appropriate pond site. The purpose of the evaluation is
twofold: (1) it will show that alternate sites were considered and that the selected site was
the most appropriate, and (2) when you combine the evaluation with the final design
details, they become the documentation that justifies the need to acquire property rights.
In the case where one person owns all the property in the area and that person is
agreeable to any pond location proposed by the Department, evaluating alternates may
not seem necessary. In these situations, the evaluation will not be as extensive as in other
situations; nevertheless, you should perform some amount of evaluation to show that the
site selected results in the lowest total cost.
The evaluation should weigh and balance numerous factors, such as cost; maintainability;
constructability; public opinion; aesthetics; and environmental, social, and cultural
impacts. The costs associated with right of way, environmental impacts, construction, and
long-term maintenance usually are the easiest factors to estimate and compare. Other
factors are more subjective and qualitative.
Because the evaluation involves a broad range of subjects, you should put together a
multi-functional team to select the most appropriate pond site. Teams should have
representatives from right of way, design, drainage, landscape architecture,
environmental management, maintenance, construction, and eminent domain. At times,
other units may provide critical information to the evaluation process. Although all of the
team members may not participate in the entire process, they will likely provide critical
information at some stage. The project manager, with support from the Drainage and
Right-of-Way offices, will be responsible for coordinating the team effort and ensuring that
the appropriate personnel participate.
Consider the value of existing vegetation during site selection and pond siting. In some
cases, the need to preserve existing vegetation for aesthetic purposes may justify
additional project expenses (retaining walls, acquisition of additional right of way, etc.).
Perform pond site evaluations during the Project Development Phase. Often, you will re-
evaluate pond sites during the Design Phase. Before doing a design reevaluation, check
what commitments have been made and what work has been done during the Project
Development Phase.
Sometimes the acquisition schedule dictates that results of the pond site evaluation form
the basis for the final pond site right-of-way requirements. For these projects, you should
determine the pond size as accurately as if doing the final detailed design.
There are other projects where the determination of the final right-of-way requirements
occurs shortly after the pond site evaluation. After establishing the final right-of-way
requirements, the acquisition process starts. For these projects, you would perform a
pond site evaluation only to compare alternate sites or drainage schemes. Make your size
estimates accurate enough to minimize changes to the right-of-way requirements during
the final design.
In a third category of projects the right-of-way acquisition is scheduled for several years
after the pond site evaluation, or the acquisition is not even funded in the Department’s
work program. For these projects, changes in pond size and location from that established
in the original evaluation will not affect production schedules or the right-of-way
acquisition process substantially. Therefore, your pond size estimates need not be very
accurate. For these projects, you typically would perform a pond site re-evaluation shortly
before right-of-way acquisition.
Other factors that affect the level of accuracy for pond size estimates are property costs
and the existing and anticipated development of the project area. In a rural area with
relatively large tracts of land, changes to pond size and location will have less impact to
property owners and the Department than in an expensive urban area that is rapidly
developing and has relatively small parcels. As a result, the pond size estimates you use
for these evaluations do not need to be as accurate as in urban, rapidly developing areas.
The ground line at the pond (or the berm elevation) minus the freeboard dictates
the top of the treatment and attenuation volume.
For urban projects, the low point in the gutter minus the hydraulic gradient
clearance dictates the hydraulic gradient of the storm drain. This constraint often
is critical in flat terrain but not steep terrain.
Retention ponds must recover a certain volume in a certain time. The size of the
pond bottom area sometimes controls the recovery or drawdown time. This may
be particularly critical for ponds discharging to closed basins.
For wet detention facilities, most regulatory agencies limit the treatment volume
depth to 18 inches and you must provide the required permanent pool volume.
To contain a substantial portion of the pond volume in rolling or steep terrain, you
would berm the low side of the pond site. The horizontal distance of the
embankment from the berm top to natural ground dictates how much right of way
you will need in this direction. The embankment slope must be flat enough to be
stable. For example, a 1 (vertical) to 2 (horizontal) slope in sandy soil with seepage
may not be stable. In this case, it would be appropriate for you to conduct a slope
stability analysis. Discuss these situations with the geotechnical engineer to
establish an acceptable slope and thus a reasonable estimate of the surface area
requirements.
You might adjust the shape of the pond—and, therefore, the surface area—due to
existing on-site natural features (mature vegetation, a significant stand of
vegetation on a slope, a visual landscape barrier, etc).
Given:
1. Since the SHWT is so close to the surface, you choose a wet detention pond.
For these conditions, one of two requirements typically control the surface area. Both
involve spreading the treatment and attenuation volumes over a large enough area
to keep the height of the volume within limits. The height (H) of the treatment and
peak attenuation volume is constrained on the top, by the ground elevation minus the
freeboard, and on the bottom, by the controlling groundwater elevation. Although
some Water Management Districts (WMDs) allow treatment below the SHWT, this
example will assume that treatment is above the SHWT. First, determine the surface
area necessary to meet these constraints. The other requirement that may control
the surface area is discussed after Step 5.
2. Conservatively, assume the SHWT is 2.5 feet below ground. The standard
freeboard is given in Section 5.4.4.2 of the Drainage Manual. The treatment and
peak attenuation volume are constrained to the following height (H).
Shape: Assume the shape of the pond will be rectangular. Irregular shapes usually
can be approximated by a rectangular shape so this is a reasonable assumption and
it greatly simplifies estimating the surface area.
Length to Width Ratio (L/W): The property lines may suggest a preferred ratio to
make best use of a parcel. Without other guidance, assume L/W = 2.
Side Slopes: Assume flat slopes, such as 1 (vertical) to 5 or 6 (horizontal) for sites
required to be aesthetically pleasing. Assume 1 (vertical) to 4 (horizontal) for most
other conditions.
4. Use the formula for a rectangular box to determine the water surface area of a
pond with vertical sides.
where:
H= Height (m) = 1.5 ft for the above condition
LRECT = Length (ft) of vertical-sided pond
WRECT = width (ft) of vertical-sided pond
Assume for this example that L/W = 2, then
For this example, assume side slope = 5, thus adding 7.5 ft to each dimension.
Then,
Water Surface at Peak Design Stage = 210.5 x 109 = 22,944.5 ft2 = 0.53 ac
The other requirement that may control the surface area in flat terrain is the
requirement to maintain the clearance between the low point in the gutter and the
hydraulic gradient in the storm drain system. On the top, the low point in the gutter
minus both the hydraulic gradient clearance and the energy losses in the storm drain
system constrain the treatment volume and three-year attenuation volume. On the
bottom, the groundwater elevations (SHWT for this example) constrains these
volumes. The standard hydraulic gradient clearance is given in the Drainage Manual.
You can estimate the energy losses in the storm drain system in two ways. Assume
a hydraulic gradient slope. Slopes of 0.05 percent to 0.1 percent are common in flat
terrain. Multiply the length between the pond and the low point by the assumed slope
to obtain the losses. Another approach is to assume a fixed energy loss, ignoring the
length between pond and low point. In flat terrain, a reasonable value for this
purpose is two feet.
6. The SHWT elevation is 56.5 feet (59 – 2.5). For this example, you can assume
the energy loss in the storm drain to be 0.7 ft. Then, the treatment and three-year
attenuation volume are constrained to the following height (H):
This is greater than the height (1.5 feet) available to “stack” the peak attenuation
volume (Step 2). Since the three-year attenuation volume is less than the peak
attenuation volume, this constraint will not control the water surface area. If the
height was less than determined in Step 2, you would estimate the water surface
area as done in Step 4 except using different values for H and the total volume.
Realize that this is only the pond size estimate. You also must make estimates for
access and conveyance, as discussed in the next section.
Sites placed far from the project will require more right of way to get stormwater to the
pond than sites adjacent to the project. Similarly, different pond sites can have different
right-of-way requirements for the outfall (discharge) from the pond. Guidelines for
establishing the width or “footprint” of the right-of-way requirements for conveyance are
provided in Section 9.2 of this document.
The Department often provides access through the same property obtained for conveying
the project’s runoff. For pond sites placed far from the project, providing access from a
local road closer to the pond is sometimes more reasonable.
Usually, the Department will obtain the right of way required for access and conveyance
as a perpetual easement. Fee simple right of way may be appropriate sometimes. The
opinion of the District Maintenance Office, balanced with property owner preference and
right-of-way costs, is the primary factor for determining which type of right of way is
appropriate.
Refer to Appendix B of the Drainage Manual and the FDM113. Both contain additional
information about acquisition of property rights.
Advantages of a joint-use or regional facility are that: (1) the Department often can relieve
itself of the maintenance requirements, (2) water quality improves downstream, and (3)
stormwater re-use is incentivized when a larger volume of water is available. A joint-use
facility can have disadvantages, such as affecting production schedules, a more complex
permitting process, and resolving any non-complying discharges, if they occur.
When developing a joint-use agreement, avoid commitments that hold the Department to
completing construction of the site by a certain date because there often are unforeseen
delays in permitting and funding. Developing an acceptable joint-use agreement often
requires an extensive coordination effort involving the project manager and
representatives from numerous other offices. Discuss this option with the project manager
or District Drainage Engineer.
Consider contacting the owner during the evaluation of alternate sites. A situation where
contacting the owner during the evaluation may be appropriate is where one person owns
all the property in the area. If a contact is not made during the evaluation process, it is
recommended that a contact be made shortly afterward and before starting final design.
For example, perhaps the property owner may prefer a shallower pond although it would
require more right of way, or the owner may be interested in re-acquiring and maintaining
the pond. A certain pond shape could give the owner better use of the remainder of the
parcel. This is important information to know before starting final design. In some
instances, contacting homeowner’s associations or abutting property owners may be
beneficial to find out if a negative perception of the proposed pond exists.
Sometimes, contacting the owner may not be appropriate. Where the Department needs
an entire parcel, there is no need to obtain the owner’s preference about pond location.
The project manager, with participation from the right-of-way office, should decide
whether to contact the property owner based on individual circumstances.
The Department’s project manager or a right-of-way specialist or both could make the
contact. As a drainage designer, you are the best source to answer technical questions
and will likely be asked to be present when the contact is made. You cannot provide
specifics early in the design process, but you can speak about general principles of
stormwater management facilities.
When obtained in writing, you should accommodate the property owner’s preference to
the greatest degree possible. The Department may not be able to accommodate all of the
owner’s preferences in the design of the pond due to hydraulic constraints or other
limitations. However, after weighing and balancing the owner’s requests with other
factors, it is likely that some aspects of the owner’s preference can be satisfied, thus
improving relations during the right-of-way acquisition process.
If a commitment is made to a property owner, follow through or notify the owner that the
Department cannot meet the commitment. Usually, you will not have enough information
to commit to anything during the first contact with the owner. Remember that the purpose
of the initial contact is to learn the owner’s preference regarding the shape and location
of the pond and location of the access road. The most that you can commit to is to try to
accommodate the owner’s requests. If, during any discussion, the property owner is told
about the operation, shape, or location of the pond, this is a commitment. If you
subsequently design the pond differently, you should notify the property owner. If the
owner is not notified, the right-of-way specialist is placed in the difficult situation of
approaching the owner with a proposed pond configuration that is different than what was
discussed previously.
This holds true for changes that occur through the detailed design phase. The owner must
be notified if the shape, size, and location of the pond are going to be different than what
was discussed previously.
The steps listed below are directed toward you, the drainage designer, but there also is
information about activities that team members from other offices should perform.
Normally, you should proceed through the steps in order, but, often, doing certain steps
earlier in the process or doing several steps concurrently will be reasonable and prudent.
The most important issue is to maintain the coordination necessary to ensure that pond
sites are selected using a multi-functional team.
The degree of detail will vary with individual projects and between FDOT districts. It is
essential that you discuss this with the project manager or the District Drainage Engineer
before starting the evaluation.
The purpose of this coordination is to provide a preliminary pond size and a general
location to the right-of-way office and to ask the right-of-way office to identify potential
sites.
Shortly after the roadway typical section is set, provide the right-of-way office with a
preliminary estimate of the size and a general location of the pond. Use aerial contour
maps, old construction plans, available surveys, and other data to identify the primary
basins and the general outfall locations (discharge points). Identifying the high points
along the project usually separates the primary basins. At this stage, assume that the
pond site will be near the lows in the terrain and will be close to the existing outfalls. As a
preliminary size estimate, use 20 percent of the roadway right of way draining to the
outfall. The area identified for the general location should be large enough to allow for
several alternates to be developed. Refer to Figure 9.1-1. The project manager should
relay this information to the right-of-way office so it can include the preliminary costs for
pond sites in the cost estimates.
Figure 9.1-1: Size and Location for Initial Coordination with the Right-of-Way
Office
When the corridor and alignment (left, right, or center) are set, the project manager should
request the right-of-way office to identify parcels along the roadway that could be
economical for a pond, due to the impacts of the roadway footprint. The right-of-way office
also should identify existing excess property in the area.
At this stage, impacts of the roadway footprint at intersections and interchanges may be
uncertain still simply because the geometry has not been set. These areas may warrant
discussions with the right-of-way office at a later time.
When the right-of-way office completes this task, the project manager should arrange a
meeting with the team to discuss all potential pond sites, aesthetic concerns, and possible
contacts with property owners. Representatives from right of way, drainage, landscape,
and environmental management should attend.
Refer to tax maps while discussing potential pond sites. The project manager should have
these; if not, the local government should.
Before developing the alternates, familiarize yourself with soils and groundwater
conditions in the area and with the various stormwater quality treatment methods. Use
the Natural Resources Conservation Service (NRCS) (formerly Soil Conservation
Service) soil surveys to obtain the soil information. The treatment methods are discussed
in Section 9.3, below.
It may be reasonable to start this step by qualitatively eliminating areas that are not
hydraulically feasible. For example, some areas may be too high in elevation, or may be
at the beginning of the drainage system rather than at the end.
For projects in developing areas, consider contacting the Planning (or Development)
Department of the local government to find out the zoning for the area, the planned land
use, and if proposed developments exist. Although this information should not
automatically eliminate a site from being evaluated, it may help you to identify viable
alternatives, such as a joint pond use with future land developers.
Identify two or three alternate drainage schemes for each primary basin. If two or three
vacant sites are not available, then consider developed sites. Familiarize yourself with the
list of considerations in Section 9.1 when identifying your drainage schemes. Also
consider the sites identified by the right-of-way office in Step One. This is not to say that
these sites need to be evaluated as alternates, but all of the alternates evaluated must
be viable. You should consider these sites during the evaluation.
The alternates may be as simple as two different locations for a wet detention pond, or a
wet detention pond compared with a dry pond with underdrain at the same location. A
system using two ponds, one for off-line quality treatment and one for attenuation, could
be compared with a single pond designed for both quality treatment and attenuation. In
areas with expensive right of way, identifying an alternate that uses a non-standard
approach—such as sand box filters or pumping stations—may be prudent. Check with
the District Drainage Engineer before doing so. See Figure 9.1-2.
Step Three Estimate the right of way required for each alternate
A. Consider the need for additional soils and groundwater information. Most of the
Department’s districts accept the NRCS soil surveys for pond site evaluations. For
alternates using retention or exfiltration in areas where there are poor soils and for
projects discharging to a closed basin, site-specific data may be appropriate. If you
feel that additional information is warranted, discuss this with the District Drainage
Engineer.
Steps B through G apply to ponds discharging to open basins. Ponds
discharging to closed basins have the additional complication of assuring that
the drawdown requirements are met (see Section 9.4).
B. Determine the required treatment (quality) volume. See the discussion of treatment
volumes in Section 9.3. Refer to the appropriate regulatory agency’s rules or meet
with the agency at this time.
C. Estimate the required attenuation volume. See the discussion of Estimating
Attenuation Volume in Section 9.4.2.
D. Coordinate with the Landscape Architect to perform a preliminary identification of
existing landscape, natural and aesthetic features, and opportunities and
constraints that could impact the placement and design of the pond.
E. Estimate the low point in the proposed roadway. Discuss the grade with the
roadway designer as necessary.
F. Obtain ground elevations around each alternate site. Using a contour map with
one-foot intervals usually is sufficient. In flat terrain where one-foot contour maps
are not available, obtaining a survey of the ground elevations around each
alternate site may be appropriate.
G. Determine the pond surface area necessary to satisfy all applicable criteria. Refer
to the typical controlling factors in Section 9.1.1.1. If you know of aesthetic
preferences that will affect the surface area, such as shape, side slopes,
landscaping, or preserving existing vegetation, account for them in the surface
area determination. Example 9.1-1 goes through this and the following two steps.
H. Add the maintenance berms to the above area.
I. Increase this area by 10 percent to 20 percent to account for the preceding
information being preliminary.
J. Place these surface area requirements within parcel boundaries in a way that
minimizes the number of parcels required. For example, avoid using part of two
parcels when the pond will fit within one.
K. Determine the right-of-way requirements for access to the pond and for
conveyance to and from the pond.
L. Sketch each alternate site and its requirements for conveyance and access on the
tax maps (preferably on aerial background). Refer to Figure 9.1-3.
Check with the project manager or District Drainage Engineer to see if they want to review
the above work before proceeding to the next step.
The project manager should arrange a meeting with the team to discuss the alternates.
The meeting has several purposes: (1) discuss how the right-of-way requirements fit
within parcel boundaries, (2) confirm that alternates being considered are viable, (3)
consider the need to contact property owners to obtain their preference of pond shape
and location, (4) confirm that the access and conveyance requirements are reasonable,
and (5) discuss social, cultural, and environmental impacts, including the existing
landscape, natural and aesthetic features, and opportunities and constraints of each
alternate.
If the property owners are contacted, their preferences should be discussed among the
appropriate team members, and the sites appropriately adjusted before proceeding to the
next step.
When the team agrees on the alternate drainage schemes, the project manager should
request environmental assessments, right-of-way cost estimates, and utility impact
assessments for each alternate site. The purpose of the environmental assessments is
to determine potential hazardous material contamination and potential impacts to
environmental resources such as threatened, endangered or significant species and
cultural resources. Environmental specialists from the Environmental Management Office
usually do the assessments, which should include cost estimates associated with any
mitigation and environmental cleanup.
The purpose of the utility assessment is to determine the existence of utility corridors
through each alternate site.
You, as the drainage designer, should estimate the construction cost of each alternate,
including the conveyance requirements to and from the pond. Usually, the largest costs
are associated with earthwork, pond liner (when required), and pipe. Statewide average
unit prices for the standard pay items are provided in the publication Item Average Report,
which is available for download at:
https://fdotwp1.dot.state.fl.us/wTWebgateReports/login.aspx (note: the user must have a
login and password for a specific project). For alternates that are similar, estimating
construction cost differences rather than total construction costs may be reasonable. If
different alternates are expected to have substantially different maintenance costs,
estimate these as well. Since maintenance costs will be spread over time, it will be
necessary to equate these to initial costs using a life cycle analysis. Contact the District
Maintenance Office to obtain the latest unit prices for routine maintenance activities.
Each alternate should have, at a minimum, cost estimates for right of way. When the
estimates and assessments are complete, the various offices should furnish their findings
to you via the project manager.
For each basin, combine the findings of the other offices with your construction cost
estimates. Use a summary table similar to Figure 9.1-4 to compare the alternates. The
Drainage Manual lists the minimum documentation requirements.
Check with the project manager to see if the district staff wants to review the summary
before proceeding to the next step.
The team should meet to discuss all alternates and select the most appropriate site. Cost,
maintainability, constructability, public opinion, aesthetics, and environmental (social,
cultural, natural, and physical) impacts will affect the selection of a pond site. The team
should weigh and balance all factors in their decision. Include documentation of the
decision with the summarized findings of the previous step.
Figure 9.1-4
Figure 9.1-5
Use a slope of 1 (vertical) to 4 (horizontal) or flatter. Steep slopes are harder to mow and
are more susceptible to erosion than flat slopes. Slopes steeper than 1:3 must be mowed
with special equipment. This is generally more expensive than using regular mowers.
Where possible, conserve established slope vegetation to increase stability and add an
aesthetic feature to the pond.
Maintenance berms:
The Drainage Manual gives the minimum widths and slopes. These are acceptable for most
situations, but discuss site-specific concerns with the local maintenance staff.
For ponds that will maintain a permanent or normal pool, keep the lowest point of the
maintenance berm at least one foot above the top of the treatment volume. This will
minimize saturation of the maintenance berm.
Corners:
Use a radius of 30 feet or larger for the inside edge of the maintenance berm. This is based
on the largest piece of normal maintenance equipment. Several maintenance vehicles
were modeled using the AUTOTURN program (Transoft Solution, Inc.). The GRADALL
880 requires the largest turning radius and gate opening.
Benchmark:
Have a benchmark constructed in or near all ponds. It will be used to check critical
elevations of the pond and outlet control structure. Avoid installing benchmarks in areas
subject to settlement such as high fill sections and areas subject to vehicle loads. An
outside corner of the maintenance berm in a minimal fill section would be an appropriate
location.
Sediment buildup:
Design the pond with a three-foot deep sediment sump near the inlet. In retention ponds
(described in Section 9.3.4.2) where the groundwater is close to the pond bottom, the
depth of the sump may need to be reduced to avoid exposing the groundwater. The area
of the sump should be approximately 20 percent of the pond bottom area.
In retention ponds, the sediment is visible, but often it accumulates so slowly that it is
difficult to see how much exists. A staff gage placed near the inlet allows the buildup to
be measured.
The main body (not the littoral shelf) of the permanent or normal pool should be deep
enough to minimize aquatic growth, but shallow enough to maintain an aerobic
environment throughout the water column. The regulatory agencies usually will specify
the maximum depth for water quality credit, but this depth may be exceeded for harvesting
fill needed for the project or to preclude future maintenance cleaning; in such cases, the
extra pond depth will not be credited toward the regulatory permanent pool requirement.
If the minimum depth is not specified, use five feet to minimize aquatic growth.
Do not construct these around the entire pond. Design the pond to have at least 20 feet
of the side slope without underdrains so that maintenance vehicles can get to the pond
bottom without running over the underdrain.
Where the pond discharges to something other than an existing storm drain system,
obtain right of way from the pond to a receiving surface water body (lake, wetland, ditch,
canal, etc.) even if there are no physical changes proposed to the conveyance path. This
assures that the Department will have the right to maintain the flow path.
Sometimes, you can use the right of way available for conveyance to provide
maintenance access to the pond. For pond sites located far from the project, it may be
more reasonable to reach the pond from a local road. In flat terrain, an ideal width of right
of way for access only (not including conveyance) is 15 feet. Larger widths may be
necessary for turns. In irregular terrain, consider the distance to tie into natural ground.
Concentrated flows crossing the access road may require a culvert crossing. If the vertical
clearance is restricted, discuss it with maintenance personnel.
The roadway designer should design and incorporate curb cuts and driveways in the
plans where the access road joins the public road.
Gates:
If you plan to fence the pond, use a 24-foot or two 12-foot sliding cantilever gates
(Standard Plans, Index 550-003). This will allow the largest piece of normal maintenance
equipment to enter and exit without having to back out along the access road. If you must
use a swinging gate, pave the area under the arc of the gate swing. Show the gate type,
location, and size in the plans.
9.2.2 Construction
Consider the right of way needed to construct the facility. The right of way needed to
maintain the facility, i.e., the permanent right of way, may be, but is not always, sufficient
to construct the facility. If the construction area is outside the permanent right of way, you
should use temporary construction easement documents to obtain sufficient area for the
contractor to construct the facility.
Some water management districts require a professional land surveyor to lay out final
placement of drainage structures. Some of the Department’s districts are directing the
contractor to do this. Discuss this with the project manager or district construction
personnel. If they want to have the contractor survey the final placement, include the
requirement in the contract documents, as directed by the district.
Often, the regulatory agencies place special requirements on the Department’s projects
as “conditions of the permit.” Requirements that will affect the contractor’s work must be
incorporated into the plans or specifications for bidding and payment purposes. It is not
sufficient that the permits will become part of the contract documents.
During design, if you realize that the designed discharge is sensitive to small changes in
weir dimensions, you should conservatively account for the tolerance in the calculations.
For example, to maintain the discharge rate at or below the allowable rate, specify a weir
width that is 0.05 feet smaller than the width required to discharge at the allowable rate.
And include the tolerance mentioned above. If the contractor constructs the weir 0.05 feet
wider than specified, it will match the designed width. If the weir is constructed 0.05 feet
narrower than specified, the discharge rate still will be less than the 0.05 feet maximum
allowed. In the last condition, you should check that stage has not increased to a point
where the pond is now discharging through the overflow point.
Although not often used, another option is to use “bolt on weir plates” with slotted bolt
holes. The plate elevation then can be adjusted to exact elevations after the structure is
set.
Do not specify a tolerance that may conflict with the Standard Specifications. If the
standard tolerance will substantially reduce the retention or treatment volume—as in a
shallow retention pond—design the pond to allow for the bottom being 0.3 feet higher or
lower than shown in the plans. In other words, specify a pond bottom that is 0.3 feet lower
than necessary to retain the minimum volume. For example, the pond bottom may need
to be 0.7 feet below the weir to provide the treatment volume. Specify the bottom to be
1.0 foot below the weir to allow for the earthwork tolerance. Determine the recovery time
assuming that the pond bottom is 1.25 feet below the weir, i.e., 0.3 feet below the
specified bottom elevation.
You should reserve this extra effort for facilities where the earthwork tolerance could
substantially reduce the retention or treatment volume.
9.2.3 Aesthetics
The Florida Department of Transportation has adopted a Highway Beautification Policy
to include aesthetic considerations in the design aspects of highways. Chapter 5 of the
Project Development & Environmental Manual summarizes the requirements and
provides direction in applying them to Department projects. Aesthetic considerations are
cited in Section 5.4.4.2 of the Drainage Manual as an integral part of sound pond design.
Often, programmatic or aesthetic commitments are made during the project development
phase. If so, the environmental document will contain a discussion of visual impacts and
aesthetic requirements for stormwater ponds. Discuss this with the Landscape Architect
and Environmental Management Office project manager.
The location, size, shape, side slopes, fencing, and landscaping all affect the aesthetic
quality of a pond. In general, irregular shapes, gradual slopes, and no fence are more
aesthetically pleasing and have less visual impact than rectangular shapes and steep
slopes with a chain link fence. For this reason, the Drainage Manual mandates that the
default pond design should not include fencing, and that fencing must be justified within
the design documentation. You can use irregular side slopes for permanently wet ponds
to create an undulating water edge even when the perimeter of the site is rectangular.
Preservation of existing vegetation and inclusion of native and wetland vegetation can
greatly improve the visual appearance of a pond. Typically, this will require that you
design and construct physical barriers to protect the existing vegetation from construction
equipment.
In urban areas, ponds designed with a park-like appearance will encourage the local
government to undertake the maintenance. If you design a pond site to be landscaped, a
memorandum of agreement (MOA) for maintenance may be executed with the local
government. In the absence of an MOA, the Department may undertake the landscape
maintenance of a pond. The District Landscape Architect is familiar with the MOA
procedure. Any landscape projects should be coordinated by the project manager with
support from the District Landscape Architect.
The shape, depth, and side slopes will affect how much right of way is required for a pond.
Therefore, you must evaluate and weigh aesthetics among the other factors during the
site selection process (see Section 9.1). The Department has determined that pond
aesthetics is an acceptable design objective that would justify acquisition of additional
right of way, including eminent domain acquisition, when appropriate. Seek out the District
Landscape Architect to coordinate and develop appropriate aesthetic features. Your
responsibility is to ensure that the design constraints (volumes, depths, littoral shelves)
are met while accommodating the aesthetic features. Coordinate with the District
Landscape Architect to establish the quantity of right of way needed to meet aesthetic
and design constraints.
9.2.3.1 Fence
The Drainage Manual mandates that the default pond design does not include fencing
and that use of fencing must be justified within the design documentation. Design
stormwater ponds to avoid the need for fence, if feasible. Typically, the flow velocities
within a stormwater pond are low and, therefore, the velocities do not create a hazard.
Unexpected deep standing water—such as an immediate 1:2 drop off at the water’s
edge—should be avoided or fenced. Under the Statewide Environmental Resource
Permit (ERP Ch. 62-330) Rule, the Drainage Manual, Florida Department of
Environmental Protection (FDEP), and all the water management districts allow for
unfenced facilities if the slopes are 1 (vertical) to 4 (horizontal) or flatter. Refer to Section
2.6.1 of the Drainage Manual for further discussion of protective treatment.
When it is necessary to provide a fence, one that fits the surrounding community is ideal.
The style (wood, block, chain link, wrought iron, etc.) will vary from community to
community. Pay item 0550-10 series covers special fencing; however, special details and
specifications will need to be included in the contract documents. Because of the extra
work, special fencing has not been commonly used. Another complication with special
fencing is that the Department’s maintenance units do not normally have the materials to
repair them; therefore, confer with the local maintenance engineer anytime you are
considering special fencing.
If it is not feasible to provide a special fence, the next option is to use standard FDOT
fence. In rural areas, the Type A fence, Standard Plans, Index 550-001 usually is
appropriate. In urban areas, Type B fence (chain link), Standard Plans, Index 550-002
usually is appropriate.
Fence Color:
One of the simplest things you can do to reduce the visual impact of chain link fence is to
specify that it be color coated. Standard Plans, Index 550-002 offers an option for PVC
(vinyl) coated fence fabric that is a soft gray color; however, you can specify the color to
be medium green, dark green, or black as allowed by AASHTO M 181. The posts, rails,
and fittings also can be color coated. To specify color-coated fence, use a pay item
footnote (0550-102x2 thru 0550-102x2, as applicable to the fence height required) similar
to the following:
Color coat the fence fabric, posts, rails, and fittings around the stormwater facilities
with xxx (state the desired color) PVC. Apply the PVC coating of the posts and
rails in addition to the standard metallic coating and ensure that it meets the
requirements of ASTM F 1043. The PVC coating of the fittings must meet the
requirements of ASTM F 626. Include the cost of the coating in the cost of these
items.
The best choice, in responding to FAA requirements, is to move the proposed pond
outside the glide paths of the air traffic. If this is imprudent, dry ponds are less attractive
to birds than wet ponds. Additionally, several design approaches are routinely used in wet
ponds to minimize attracting birds:
Use steep, rocked slopes, typically 1:2, without littoral zones, to discourage the
presence of food sources for birds.
Suspend nets over the surface of the pond to make the area less hospitable for
ducks, geese, and other water fowl.
Figure 9.2-3
Although the criteria are similar around the state, there is some variation. It is essential
that you become familiar with the applicable agency’s criteria. Read their manuals and
coordinate as necessary. Arrange a pre-application meeting to review the status of
applicable rules and to identify potential problems and concerns to be addressed during
design. Agencies usually have checklists and standard forms to be completed for a
stormwater permit. Review these forms and address the items relating to stormwater
management.
In general, the treatment volume will vary depending on the classification of the receiving
water body and whether the volume is captured on-line or off-line. Sensitive water bodies
such as shellfish harvesting waters (Class II) and Outstanding Florida Waters require a
larger treatment volume. The classification of the receiving water body should be
identified in the Project Development phase as a part of the water quality impact
evaluation. FDEP includes a list of sensitive water bodies in Rule 62-302, F.A.C.
Compensatory treatment may be an option when trying to meet water quality regulations.
Sometimes, limited or very expensive right of way creates hardship conditions in which it
is unrealistic to provide the standard treatment. Sometimes, the Department can arrange
to provide compensatory treatment for an area that currently does not receive any
treatment. Providing this treatment compensates for not providing the standard treatment
in the area where the hardship condition exists. Treating a larger volume of runoff at
another location (drainage area) on the project usually is not considered replacement
treatment.
Nutrient-Impaired Basins
When designing stormwater systems that discharge to basins verified for nutrient
impairment, state law requires the applicant to demonstrate that there will be no net
increase of the pollutant of concern. To satisfy this requirement, all WMDs require a pre-
vs. post-development comparison of annual nutrient loading, using the Harper (2007)
Methodology, to demonstrate that the post-development annual loading is not greater
than the pre-development loading for the pollutant of concern. Guidance on this analysis
is contained in Section 9.3.4.6 of this document.
Another concern is that there will be some additional attenuation storage in the off-line
basin associated with the hydraulic gradient of the peak flow passing over the weir. When
there is significant attenuation storage above the treatment volume, there is a concern
that the system will function more as an on-line system than as an off-line system due to
mixing. You could use metal or rubberized flap gates to address this concern, but they
can be a maintenance problem and a noncompliance issue if not carefully designed.
The outlet control structures of off-line systems are difficult to maintain simply because
they normally are placed in junction boxes. They are neither seen nor reached as easily
as the outlet control structures of on-line systems.
Use the NRCS soil surveys, project-specific soil investigations, and field observations
(vegetative indicators, observation wells, etc.) to estimate the SHWT. Recognize,
however, that soil staining may denote a relic or historic water table that has since been
lowered by other drainage features in the region.
Surface Surface
FILTRATION
SHWT
OR
RETENTION
WET DETENTION
As shown, wet detention is the only option in areas where the SHWT is near the surface.
However, wet detention also may be appropriate in areas where the SHWT is far from the
surface and clay soils exist. The use of retention requires that the SHWT be far from the
surface and that sandy soils exist. Filtration requires that the SHWT be far from the
surface unless impermeable liners are used. The Department does not encourage the
use of liners, although their use is justifiable sometimes. Consult the District Drainage
Engineer before proposing liners.
You cannot apply specific values to this figure because site-specific factors—such as
pond shape, groundwater boundary conditions, and drainage basin characteristics—need
to be considered. Situations exist where both filtration and wet detention are suitable. In
these cases, the Department should weigh and balance other factors—such as right-of-
way costs, property owner preference, and long-term maintenance costs—to select the
most appropriate treatment method.
Advantages Disadvantages
1. Very effective at removing dissolved and 1. Treatment requirements are typically
suspended pollutants. double the requirements for retention and
filtration.
2. High probability to function as designed. 2. Depth of the treatment volume is
sometimes limited to 1.5 feet.
3. Recovery of treatment volume is easily 3. Because of the above items, right-of-way
predicted. requirements are greater than other
methods.
4. Easy and low-cost long-term 4. Sometimes requires planting of the littoral
maintenance. zone.
5. Produces on-site fill material for project 5. Creates a potential mosquito habitat.
needs
Despite the disadvantages, the Department encourages the use of wet detention.
The average length-to-width ratio of the pond should be at least 2:1. Maximize the flow
path of water from the inlet to the outlet to promote good mixing and avoid “dead” storage
areas. If you cannot avoid short flow paths, use the littoral shelf to increase the effective
flow path, provided this is acceptable to the regulatory agency. Figure 9.3-1 shows
examples of pond configurations.
Per the regulatory agency requirements, you may need to plant the littoral shelf. If so,
consult with the District Landscape Architect.
Most regulatory agencies require that the treatment volume be available within 72 hours
after a storm. See Section 9.4.6.1 on the subject of groundwater flow from retention
systems and a recommended approach to modeling recovery of the treatment volume.
Compared with the previous two treatment methods discussed, underdrains are the least
reliable. They are subject to clogging during and after construction and are difficult to
maintain. Vehicle loads can crush the underdrain pipes. Filtration systems also do not
remove dissolved constituents, such as nitrogen and phosphorus, and therefore do not
count toward load reduction credit in impaired basins. The Department realizes that using
underdrains is sometimes necessary due to clayey soils, but encourages a thorough
evaluation of other treatment methods first.
Configuration:
When you use side bank underdrain (Standard Plans, Index 440-001, Type Va), slope
the pond bottom up from the underdrain. This will reduce the saturated soil condition and
localized ponding associated with a flat pond bottom. It also increases the chances of
sustaining a stand of grass on the bottom. See Figure 9.3-2.
If feasible, construct underdrains out of the primary flow path to avoid directing debris and
sediments there.
To account for construction tolerances, the underdrain pipe should be placed on a slope.
Specify flow lines for the pipe at the beginning, at bends, and at the end of the underdrain.
In all but very short runs of underdrain, the flow line should drop six inches or more to
account for construction tolerances.
Design Technique
For design purposes, use K = 0.5 ft/hr as the hydraulic conductivity of the fine aggregate
media. This does not include the factor of safety of two required by the regulatory
agencies. You do not have to apply that factor of safety to the hydraulic conductivity. It is
sometimes applied to the length of the underdrain or to the time to draw down the
treatment volume. You could refine the above value by experience from permeability
testing of locally available fine aggregate media meeting the requirements of the standard
specifications for underdrain filter material.
2. Determine the effective head (HE), the average flow length (LAVG), and the average
width (WAVG) for flow paths through the underdrain. Determine these for each water
surface elevation considered in Step 1. See the discussion following Step 10 for a
suggested approach to determining these values. Record these in Column 4
through Column 6.
3. Calculate the hydraulic gradient (i) for each water surface elevation considered in
Step 1 using the values determined in Step 3, and record the results in Column 7.
Hydraulic gradient (i) = HE/LAVG.
4. Assume an underdrain pipe length (L) and calculate the area of filter (A) for each
water surface elevation considered in Step 1. Record results in Column 8.
5. Calculate the Darcy flow (Q) using the hydraulic conductivity (K), the hydraulic
gradient, and the filter area for each water surface elevation considered in Step 1.
Record results in Column 9.
6. Calculate the average flow rate for each depth interval and record results in
Column 10.
7. Divide the incremental storage volume (ΔV) from Column 3 by the average flow
rate from Column 10 to obtain the incremental time (ΔT) to draw down that storage
volume. Record results in Column 11.
8. Sum the incremental drawdown times recorded in Column 11 to obtain the
drawdown time (ΣT). Record results in Column 12.
9. If the total computed drawdown is longer than required, increase the underdrain
length and return to Step 5.
10. Size the underdrain pipe to handle the design flow rate.
Determining the Effective Head, Average Flow Length, and Average Width:
To determine the effective head (HE) at a given water surface, use the vertical distance
from the water surface to the bottom of the fine aggregate material. For the average flow
length (LAVG) through the filter, use the depth of fine aggregate, 2.0 feet. For the average
width (WAVG) of filter normal to flow, use the standard width of 1.5 feet unless you use
non-standard geometry.
The standard plans index shows the upper and lower limit to side bank underdrain. Try to
avoid using the upper limit configuration because of its limited flow capacity in low head
conditions. There is very little head and the length of the filter material through which the
water must pass is long, resulting in a very small hydraulic gradient.
1. Make a scaled drawing of the average cross section geometry. One is shown in
Figure 9.3-3. The average should represent the midpoint between the high end
and low end of the underdrain.
2. For the effective head (HE) at a given water surface elevation, use the vertical
distance from the water surface to the pipe centerline. At high heads, this is non-
conservative because the free draining effect of the course aggregate reduces the
head. At low heads, this is a reasonable assumption.
The combined effect of using HE & LAVG as described here should result in
conservative flow rates in low head conditions and reasonable rates in high
head conditions. At high heads, the non-conservatism of using the effective
head (HE) to the center line of the pipe is offset by using an average length
(LAVG) that is longer than the actual distance through the fine aggregate. At
low heads, the conservatism of using a longer-than-actual average length
(LAVG) is justified because this zone of the filter is most likely to receive
sediment and clog.
3. For the average flow length (LAVG) through the filter at a given water surface, use
the average of several straight-line distances from the outside of the pipe to the
top of the fine aggregate. This is conservative because it ignores the course
aggregate, which is relatively free draining. Refer to Figure 9.3-3 and Table 9.3-1
for an example.
4. For the average width (WAVG) of filter normal to flow, use the average of the
saturated fine aggregate area. Due to the complex transition between vertical and
horizontal flow, this is best determined by “visually” estimating the average width
based on your scaled drawing. Refer to Figure 9.3-3 and Table 9.3-1 for an
example.
Table 9.3-1: Average Flow Length and Average Width through Side
Bank Underdrain
3. Property adjacent to the state highway, previously targeted for usage as a pond,
is available for development.
Regional treatment facilities can be difficult to permit because of the Class III treatment
requirements of conveyance facilities between the FDOT site and the location of the
regional pond. These intermediate waterway requirements sometimes can be eliminated
by classifying the manmade, intermediate conveyance waterways as part of the
stormwater system, thereby severing jurisdiction. The cooperation of the WMD will be
essential in such efforts.
The above draft publication is referenced ONLY for its helpful outline of the background
rationale and computational steps involved in the Harper Methodology, NOT for
regulatory requirements.
Since 2010, event mean concentrations (EMCs) for different land uses have changed as
additional data have become available. Current general EMCs are tabulated below:
The BMPTRAINS computer program was developed to employ the latest policy and
methodology for assessing nutrient loadings and BMP performance related to nutrient
removal. The program is available on-line at the UCF Stormwater Management Academy
website: http://stormwater.ucf.edu/
Additional helpful tools sponsored by the Academy are available under the title
Stormwater Management and Design Aids (www.SMADAonline.com). A partial list of
programs in the SMADA online package is below:
FDOT has extracted relevant design criteria and combined them into one reference
publication and computer program, named BMPTRAINS. The design engineer should
verify the design criteria at a pre-meeting with the WMD or FDEP, since newer regulations
may exist. The BMPTRAINS model provides the option to over-ride existing criteria and
assumptions. An example of an assumption is the event mean concentration (EMC) data.
A wet detention pond serves a section of a two-lane highway that is about 1,100 feet long
and the right-of-way width is about 200 feet. The catchment area is five acres and is part
of a larger watershed that may impact the design. The existing portion of highway was
not served by any treatment system. The existing and proposed portion of the highway
will be treated in the post-development condition. The site is located in West Palm Beach,
Florida, on Hydrologic Soil Group D. The existing land use condition is assumed to be a
highway with a non-DCIA Curve Number of 80 and 40 percent DCIA. The post-
development land use condition is assumed to be a highway with a non-DCIA Curve
Number of 80 and 85 percent DCIA. The area needs net improvement using a wet
detention pond with a littoral zone (assumed 10 percent removal efficiency credit for the
littoral zone) in the design. The area and depth for the pond allowed an average annual
pond residence time of 50 days.
First, identify the meteorological zone, which is Zone 5, and the mean annual rainfall,
which is 61 inches, as shown in Table 9.3-3.
Using the BMPTRAINS program, the net improvement expected with the wet detention
design is 71.5 percent removal of total phosphorus and 46.2 percent removal of total
nitrogen, as shown in the BMPTRAINS program screenshot below. Note that, for the wet
detention option, a residence time greater than 50 days will only marginally improve
removal. Thus, a design criterion of 50 days annual residence time is above the minimum
required by the water management district (21 days x 1.5 = 31.5 days) and can fit within
the existing right of way.
Example Problem 9.3-2: A highway receiving runoff from an industrial park that will
have retention systems in a series—a pre- vs. post-development loading analysis
is required
The water table conditions in this area are suitable for retention systems. An exfiltration
trench in series with a retention basin can serve a five-acre light-intensity commercial site.
The catchment also can contain 10 tree wells along the road. The tree wells are designed
to be three feet deep with a six-inch depth above soil column. The length and width of the
tree wells are designed to be four feet each. Use a 0.2 sustainable water storage capacity
of the soil. Treat the tree wells as retention systems. The site is located in Orlando,
Florida, on Hydrologic Soil Group C. The existing land use condition is assumed to be
undeveloped-dry prairie with a non-DCIA Curve Number of 79 and 0.0 percent DCIA. The
post-development land use condition is a low-intensity commercial area with a non-DCIA
Curve Number of 85 and 65 percent DCIA. The combination of treatment systems is to
provide treatment sufficient to match the post-development annual nutrient loads with the
pre-development annual nutrient loads.
First identify the meteorological zone and annual rainfall for the project.
A summary of the catchment characteristic data is shown below. Note that the catchment
is highly developed, leaving no feasible space for a retention basin or other land-intensive
BMP. You need to consider BMPs that are more useful for ultra-urban environments.
The tree wells receive runoff water first and, thus, the effectiveness associated with a
design is examined first. The capture effectiveness is low (1.3 percent) because of the
number and size of the catchment. The results are shown below.
Next, you can use an exfiltration system to collect some of the runoff water. Using the
geometric design for the exfiltration, the retention storage volume is calculated as 0.55
inches. The effectiveness of using the exfiltration design is shown below.
EXFILTRATION TRENCH:
EXFILTRATION TRENCH SERVING ENTIRE CONTRIBUTING WATERSHED:
EXFILTRATION TRENCH FOR MULTIPLE TREATMENT SYSTEMS (use only if other BMP
method is oversized or undersized) :
Finally, you can use a retention basin at the discharge from the watershed. The land for
the retention basin within the watershed is part of the industrial park but did not provide
sufficient removal by itself to meet post-equal-pre average annual mass loading. The
retention basin can hold 0.50 inches of runoff and, thus, was limited to the removal
effectiveness associated with that volume of storage. Using a combination of retention
basin, tree wells, and an exfiltration trench provided by the roadway was sufficient to meet
the post-equal-pre requirements.
The retention options are in a series. The first flush of water is captured by the tree wells
and what is not captured is routed to the inlets for the exfiltration trench. The exfiltration
trench can handle a fraction of that runoff, so the bypassed water is routed to the retention
basin. All of these retention BMPs are designed to be off-line BMPs. Summary results of
the tree well, exfiltration, and retention basin designs with the overall effectiveness
removal are shown below.
Summary Performance
Catchment
A - Single Catchment
Configuration 3/25/2014
Nitrogen Pre Load (kg/yr) 5.35 BMPTRAINS MODEL
Phosphorus Pre Load (kg/yr) 0.29
Nitrogen Post Load (kg/yr) 18.00
Phosphorus Post Load (kg/yr) 2.73
Target Load Reduction (N) % 70
Target Load Reduction (P) % 89
Target Discharge Load, N (kg/yr) 5.35
Target Discharge Load, P (kg/yr) 0.29 1
Provided Overall Efficiency, N (%): 57
Provided Overall Efficiency, P (%): 57
Discharged Load, N (kg/yr & lb/yr): 7.72 17.00
Discharged Load, P (kg/yr & lb/yr): 1.17 2.58
Load Removed, N (kg/yr & Ib/yr): 10.28 22.65
Load Removed, P (kg/yr & Ib/yr): 1.56 3.44
For additional example problems, see the User’s Manual to be used with the BMPTRAINS
model (www.stormwater.ucf.edu) located at:
Most of the current widely used rainfall distributions address this by nesting short-
duration, high-intensity storms in the middle of a long duration storm, although very
intense peaks do not usually occur in long storms. You usually would place the largest
intensity value in the middle of the storm pattern, then place the remaining values
alternately before and after this point, in order of decreasing intensity. The various NRCS
distributions, the South Florida Water Management District (SFWMD) three-day
distributions, and the St. Johns River Water Management District (SJRWMD) four-day
distributions are examples of design storm distributions created using this approach.
These “nested” distributions are not indicative of actual rainfall patterns and subsequently
may produce inaccurate representations of actual runoff characteristics.
You may have used these distributions in the past for the design of conveyance systems
because they give conservatively high runoff estimates. But, when you use these
distributions to determine the pre-developed discharge, they can overestimate it. In the
developed condition, the outlet control structure would be designed to pass the
“overestimated pre-developed discharge,” thereby discharging more in the post-
developed condition.
Another problem with these distributions is that different drainage areas will react
differently to the same rainfall pattern. Small basins with short times of concentration and
little storage will have higher runoff rates from short, intense storms than from long-
duration, low-intensity storms. Long-duration, low-intensity storms usually do not
generate peak discharges from small basins. The opposite is true for large basins. Very
large basins with large amounts of storage will have less runoff from short, intense storms
than from long-duration, low-intensity storms. Large river systems and static water bodies
such as lakes reach peak stages when extreme antecedent conditions exist and
variations in intensity usually do not affect their stages.
To overcome the concerns of a single design storm distribution, the Suwannee River
Water Management District (SRWMD) developed a series of design distributions to better
reflect actual rainfall patterns. They developed distributions for 1-, 2-, 4-, and 8-hour
storms and for 1-, 3-, 7-, and 10-day storms using National Oceanic and Atmospheric
Administration (NOAA) hourly and sub-hourly data. SRWMD requires the use of these
distributions for projects within the district.
In 1986, the Department established Chapter 14-86 of the F.A.C., requiring adjacent
developments to maintain discharges at or below pre-developed discharges using a
multiple storm approach. In the Department’s Drainage Connection Handbook (February
1987), the SRWMD design distributions mentioned above were accepted as appropriate
for the entire state. These distributions can be found at the Department’s website, listed
below: http://www.fdot.gov/roadway/Drainage/files/IDFCurves.pdf
In a July 1988 memorandum, the State Roadway Design Engineer directed the districts
to design the Department’s stormwater management systems to Chapter 14-86. In
October 1992, the Drainage Manual was revised to require the design of the Department’s
stormwater management systems to comply with Chapter 14-86. In 2013, the Drainage
Manual was amended to require the application of Chapter 14-86 on FDOT stormwater
designs only for closed basins and areas where downstream historical flooding is
documented.
“Critical Duration” means the duration of a specific storm event (i.e., 100-year storm) that
creates the largest volume or highest rate of net stormwater runoff (post-development runoff
less pre-development runoff) for typical durations up through and including the 10-day
duration event. The critical duration is determined by comparing various durations of the
specified storm and calculating the peak rate and volume of runoff from each. The duration
resulting in the highest peak rate or largest total volume is the “critical duration” storm.
Acceptable Post-
Pre-Dev Runoff
Duration Dev Runoff XX
XX Year Event
Year Event
1-hour 65
2-hour 70 60
4-hour 66 70
8-hour 60 65
24-hour 30 35
3-day 25
7-day 24
10-day 21
This approach is consistent with the last sentence of the definition of critical duration. “The
duration resulting in the highest peak rate . . . is the critical duration.” With this approach,
the pre-developed critical duration can be different from the post-developed critical
duration, as shown in the values above. Also, the pre-developed runoff rate could be
calculated with the rational method (Q = CIA) for small basins; therefore, it would not be
directly associated with any of the eight durations. The examples in the Drainage
Connection Handbook follow this interpretation.
The above discussion pertains to discharges to open basins only with historical flooding
documented. For discharges to closed basins, a similar approach is used with an
additional constraint on the runoff volume. For a given frequency, the allowable post-
developed runoff volume is the largest pre-developed runoff volume of any duration.
When using the NRCS technique for computing runoff, the 10-day duration event will
always produce the largest runoff volume and, therefore, be the critical duration. But, for
other more-refined approaches to modeling infiltration, the critical duration could be
something other than the 10-day duration.
Acceptable Post-
Pre-Dev Runoff
Duration Dev Runoff XX
XX Year Event
Year Event
1-hour 65 60
2-hour 70 68
4-hour 66 66
8-hour 60 57
24-hour 30 26
3-day 25 23
7-day 24 22
10-day 21 20
This approach is consistent with the first sentence of the definition of critical duration.
“Critical Duration means the duration . . . that creates the . . . highest rate of net
stormwater runoff (post-development runoff less pre-development runoff). . . .” In the
example above, when you subtract the pre-development runoff rate from the
corresponding post-development runoff rate, all the “net stormwater runoff” values are
negative except the 4-hour duration, which has zero “net stormwater runoff.” So, the 4-
hour duration has the highest rate of net stormwater runoff; therefore, it is the critical
duration. This approach is better than the peak discharge approach, where the release
timing of the facility is critical. FHWA’s Hydraulic Engineering Circular No. 22 (HEC 22)
contains a discussion of the concern for release timing.
The above discussion pertains to discharges to open basins only with historical flooding
documented. For discharges to closed basins, a similar approach is used with an
additional constraint on the runoff volume. For a given frequency, the post-developed
runoff volumes for each duration cannot exceed the pre-developed runoff volumes of
corresponding duration.
Although both the Peak Discharge Approach and the Storm for Storm Approach have
been applied to FDOT projects in the past, the Department prefers that you use the Storm
for Storm Approach on its projects. The examples in Section 9.4 are based on the Storm
for Storm Approach.
The more frequent FDOT design storms (2-year to 50-year) do not usually control the
size of the pond because the runoff from these storms is less than the runoff for the 100-
year storm. The purpose of evaluating the less frequent storms is to ensure that the pre-
developed discharges are not exceeded. And so it becomes a check of the operation of
the outlet control structure under various rainfall event frequencies.
Where the discharge is controlled by a simple rectangular weir (one with a constant
width), it may be reasonable to run only the 2-year, 25-year, and 100-year events. Where
the discharge is controlled by a complex weir (width varies with elevation), an orifice, a
pipe, tailwater conditions, or any combination of these, evaluate all frequencies (2-year,
5-year, 10-year, 25-year, 50-year, and 100-year). Some software programs can run all
the frequencies at once. If these programs are available to you, run all the frequencies,
regardless of the outlet control structure configuration.
When diverting runoff, be careful how you calculate the allowable discharge. Base your
allowable (pre-developed) discharge calculations on the pre-developed drainage area
that discharges to the proposed outfall. If an area does not drain to the proposed outfall
in the pre-developed condition, do not include that area in the allowable (pre-developed)
discharge calculations. Therefore, in a basin you divert runoff to, the pre-developed
drainage area is smaller than the post-developed drainage area. Conversely, in a basin
you divert runoff from, the pre-developed drainage area is larger than the post-developed
drainage area.
The actual attenuation volume cannot be determined until you “route” the design storms
and design the pond. There are several methods for estimating the attenuation volume.
The methods more commonly used on the Department’s projects are discussed below.
P - 0.2S )
2
QR =
P + 0.8S
As written, this assumes the initial abstraction (Ia ) = 0.2S & S =(1000/CN) – 10
where:
P= Rainfall depth (in inches); Use the 100-year, 24-hour depth for evaluating
alternate drainage schemes or pond sites
An advantage of this technique is that it does not involve any design storm distributions.
So there is no concern for which storm duration is critical. On the other hand, this
technique ignores the timing differences between the pre-developed and post-developed
hydrographs. As a result, it may underestimate the attenuation volume.
Given:
Pre-developed roadway pavement = 2 10-foot lanes
Drainage area: includes roadway right of way &
off-site drainage to the roadway = 10.4 ac
For preliminary pond sizing, use the information from the old drainage map unless
you have reason not to.
Example 9.4-1
Assume the pond area is 20 percent of the roadway right of way (0.2 x 1,706 ft x
98 ft = 0.77 ac). For this example, the proposed pond is located outside the area
draining to the roadway; thus, the pond must be added to the other areas.
For this example, the roadway right of way to be acquired is within the area
draining to the roadway. For your project, the acquired right of way may be
outside the area draining to the road, thereby requiring that the additional right of
way be added to the other areas.
2. Post-developed area and curve number:
Roadway, curb, and sidewalk: = 3.24 ac @ CN = 98 (82.7 ft x 1,706 ft)
Pervious area = 7.17 ac @ CN = 85 (10.4 ac – 3.24 ac)
Pond area = 0.77 ac @ CN = 98
Total = 11.2 ac @ CN = 89.7
3. Calculate the difference in runoff volume between the pre-developed conditions
and post-developed conditions for the 100-year, 24-hour storm using the NRCS
equation for runoff.
Refer to the NOAA website link in Section 1.4 of the Drainage Manual to obtain
location-specific precipitation data for the 100-year, 24-hour volume. For this
example, the 100-year, 24-hour volume for Somewhere City, Florida, is 10.7
inches.
Pre Post
Potential abstraction (S) = 1.64 1.15
Runoff depth (Q) in inches 8.95 9.44
Runoff volume (ac-ft) = 8.36 8.81
As with any routing, this is an iterative process. During each iteration, the estimated
storage volume is changed to bring the routed peak stage close to the top of the pond.
The storage volume that causes the peak pond stage to match the top of the pond is the
estimated attenuation storage.
This approach is useful when the discharge rate is limited to something other than the
pre-developed rate. It is complicated when working with the Department’s multiple design
storms. Which design storm do you route? The following suggestions will help to simplify
working with the multiple design storms:
Determine the pre-developed discharges for the 100-year, 1-hour design storm
through the 100-year, 8-hour design storm. Use the smallest of these calculations as
the allowable discharge rate. For the Storm for Storm Approach to critical duration,
the post-developed discharge rate will be limited to all of the corresponding pre-
developed rates, so using the rate for estimating purposes is reasonable. The basis
for running only the 1-hour through the 8-hour design storm is that one of these design
storms usually is critical to sizing ponds discharging to open basins.
Route the post-developed conditions using a “nested” design storm such as the NRCS
Type 2 Florida modified or the applicable WMD design storm. These distributions often
are as severe as or more severe than the Department’s distributions.
Given:
The same conditions as in Example 9.4-1
Pre-developed time of concentration = 29 min.
Post-developed time of concentration = 21 min.
1. Pre-developed runoff:
Determine the pre-developed discharge rates for the 100-year FDOT 1-hour and
8-hour design storms. Using a typical program based on the NRCS unit
hydrograph approach, you should obtain values similar to these when using a
peak shape factor of 256. The rainfall volumes for Somewhere City, Florida, are
tabulated in Step 1 of Example 9.4-3.
The discharge associated with the 4-hour, 100-year design storm is the smallest
and will be used as the allowable discharge.
3. Route a nested design storm through the pond using post-developed conditions.
For this example, we will route the 25-year, SFWMD 72-hour storm. Adjust the
storage as necessary to have the routed peak stage match the top of pond. After
numerous iterations, a storage value of 1.3 ac-ft was found acceptable, so:
Tailwater conditions can become more challenging when discharging at or close to the
confluence of two streams, as shown in the figure below. Depending on the relative size
of each basin, it may be overly conservative to use the combined (or coincident) 100-year
probability for each stream. National Cooperative Highway Research Program (NCHRP)
conducted Project 15-36: Estimating Joint Probabilities of Design Coincident Flows at
Stream Confluences (http://www.trb.org/Publications/Blurbs/169456.aspx) to develop
practical procedures for estimating joint probabilities of coincident flows at stream
confluences. This paper focuses on two practical design methods and provides a step-
by-step application guide for designers in Appendix H of the document.
Pond Site
Large River
Placing a pond in a 100-year riverine floodplain can complicate the design due to high
tailwater conditions that may be coincident with the design storm. Other complications
such as flood plain compensation and changes to floodway conveyances may exist as
well. Chapter 5 (Bridge Hydraulics) addresses impacts to floodway conveyances.
Although the computer reduces the effort, it does not eliminate the iterative process of
modifying the pond and outlet control structure after each run. To design an acceptable
pond and outlet control structure, you usually will run numerous iterations. You can adjust
six items to meet the discharge requirements: (1) weir width (or orifice size), (2) weir crest
(or orifice invert) elevation, (3) pond surface area, (4) pond depth, (5) pond length to width
ratio, and (6) outlet pipe size. Although some of these items may be constrained by
regulatory requirements, the following provides general guidance for making adjustments
during the iterative process.
Given:
The following information has been verified since the time of the pond site evaluation.
Find:
The required pond configuration to meet the FDOT criterion. For this example, the pond
also will be designed to meet SWFWMD and SFWMD criteria.
1. Determine the location-specific rainfall volumes using the NOAA website link in
Section 1.4 of the Drainage Manual.
Rainfall Volumes: Somewhere City, Florida
2-yr 5-yr 10-yr 25-yr 50-yr 100-yr
1-hr 2.4 2.95 3.25 3.75 4.1 4.5
2-hr 2.8 3.5 3.9 4.5 5.0 5.5
4-hr 3.3 4.0 4.6 5.4 6.0 6.6
8-hr 3.8 4.9 5.6 6.5 7.3 8.0
1-day 4.8 6.3 7.7 8.7 9.7 10.7
3-day 6.1 7.9 9.1 10.8 12.2 14.1
7-day 7.5 9.4 11.5 13 14.8 16.8
10-day 8.5 11 13 15 17 19
To simplify this problem, we have used the time of concentration, roadway pavement
area, and offsite land use from prior examples. Actually, you should use the latest
information from the design surveys and field reviews of the proposed project to establish
the pre-developed conditions. Using a typical program, which uses the NRCS unit
hydrograph approach, you should obtain values similar to these when using a peak shape
factor of 256. This peak shape factor is used throughout this example.
For the first round of iterations for a pond discharging to an open basin (with documented
flooding history), it is usually sufficient to run the 100-year FDOT 1-hour to 8-hour duration
design storms and the regulatory agency design storm.
3. Post-developed runoff:
In urban sections, the time of concentration is best determined from the storm
sewer design tabulations. For this example, assume the storm sewer tabs have a
Tc = 21 min.
Pond: = 0.94 ac @ CN = 98
Total: = 11.3 ac @ CN = 89.7
4. Develop a stage-storage relation (pond configuration) for the first round of
iterations.
For the first iteration, use the configuration estimated in the pond siting evaluation unless you have
reasons not to.
Although some WMDs allow treatment below SHWT, this example assumes that
treatment is above SHWT. Then, the pond length and width at SHWT elevation (for
routing purposes, the SHWT elevation is considered pond bottom) are:
Using these dimensions and side slopes, develop a stage-storage relationship. The
values below were obtained using the equation for the volume of a frustum of a pyramid.
5. Develop an outfall structure for the first round of iterations. Do so using the
maximum allowable stage and discharge. For this example, the maximum
allowable stage is the ground elevation minus the freeboard [59.1 ft – 1.0 ft =
58.1 feet]. The maximum allowable discharge is the largest pre-developed
discharge, which, for this example, is the SFWMD 72-hour, 25-year design storm
(see Step 2).
Weir crest elevation = 56.7 ft The treatment volume (10,950 ft3, given in Ex.
9.1-1) stacks 0.59 ft high.
For this example, we have assumed no tailwater effects. For your projects, you will
need to consider the effects of the tailwater conditions on the outfall control
structure.
During this round of iterations, ignore the effects of the water quality bleed down
orifice and start the routings at the top of the treatment volume.
6. Route the selected design storms. Using a typical routing program, you should
obtain values similar to the following.
Table 9.4-1
Discharge Peak Pond
Design Storm
(cfs) Stage (ft)
FDOT 1-hr, 100-yr
Pre 33.6
Post 38.2 58.1
Pond configuration: FDOT 2-hr, 100-yr
Pond dimensions at SHWT = 191 ft x Pre 30.4
90 ft Post 35.0 58.1
SHWT elev. = 56.1 ft FDOT 4-hr, 100-yr
Avg side slope = 1:5 Pre 25.8
Weir crest elev. = 56.7 ft Post 28.8 57.9
Weir width = 7.3 ft
FDOT 8-hr, 100-yr
Starting WS = 56.7 ft
Pre 28.1
Post 30.6 57.9
Allowable Stage = 58.1ft
SCS-T2FLM, 25-yr
Pre 30.6
Post 33.0 58.0
SFWMD 72-hr, 25-yr
Pre 36.3
Post 38.0 58.1
From this table, it appears that the 100-year, 1-hour or 2-hour may be critical because
they exceed the pre-developed discharge more than the others. Overall, the configuration
used in the first iteration is close to meeting the requirements. Shorten the weir length to
decrease the peak discharge. Doing so will cause the stage of the 1-hour, the 2-hour, and
the SFWMD design storm to exceed the allowable stage, so the pond size needs to be
increased also.
After making several runs, the stage-storage relationship shown below and a weir width
of 6.0 ft is close to meeting the requirements of the design storms modeled. The second
row in the table is the weir crest elevation sufficient to store the treatment volume.
From this table, it appears that the FDOT 4-hour is critical since it is the only duration for
which the post-developed discharge is not less than the pre-developed discharge. The
SFWMD design storm creates the highest stage of the storms modeled.
Post-developed CN:
Roadway, curb, and sidewalk: = 3.24 ac @ CN = 98 (same as Step 3)
Pervious area: = 7.64 ac @ CN = 85 [7.17 ac (Step 3) + 0.47
ac]
Pond: = 1.06 ac @ CN = 100
Total = 11.9 ac @ CN = 89.9
8. Calculate the pre-developed runoff and then route the design storms. For this
example, we will add the FDOT 24-hour, 100-year design storm at this time. The
results are shown in the following table.
Table 9.4-3
Peak Pond
Discharge
Design Storm Stage
(cfs)
(ft)
FDOT 1-hr, 100-yr
Pond configuration: (Same as Pre 35.2
previous table) Post 28.7 57.8
Pond Dimensions at SHWT = FDOT 2-hr, 100-yr
288.7 ft x Pre 31.9
131.2 ft Post 28.9 57.8
SHWT El. =56.1ft FDOT 4-hr, 100-yr
Avg Side Slope = 1: 5 Pre 27.0
Weir Crest El. = 56.40 ft Post 27.9 57.7
Weir Width = 6.0 ft FDOT 8-hr, 100-yr
Starting WS = 56.4 ft Pre 29.5
Post 28.9 57.8
Allowable Stage = 58.1ft FDOT 24-hr, 100-yr
Pre 11.2
Post 11.1 57.2
SCS-T2FLM, 250-yr
Pre 32.1
Post 29.0 57.8
SFWMD, 72-hr, 25-yr
Pre 38.1
Post 32.5 57.9
From this table, we can see the discharge for the 4-hour needs to be reduced and
the stage of the SFWMD storm can still be increased, so the weir width can be
reduced. After several iterations, a weir 4.5 ft wide works. The results are as
follows.
Table 9.4-4
Peak Pond
Design Storm Discharge Stage
(cfs) (ft)
FDOT 1-hr, 100-yr
Pond configuration: Pre 35.2
Pond dimensions at SHWT = Post 25.8 57.9
288.7 ft x 131.2 ft FDOT 2-hr, 100-yr
SHWT elev. = 56.1 ft Pre 31.9
Avg. side slope = 1:5 Post 26.7 57.9
Weir crest elev. = 56.4 ft FDOT 4-hr, 100-yr
Weir width = 4.5 ft Pre 27.0
Starting WS = 56.4 ft Post 26.8 57.9
FDOT 8-hr, 100-yr
Allowable stage = 58.1 Pre 29.5
Post 27.6 58.0
FDOT 24-hr, 100-yr
Pre 11.2
Post 10.9 57.3
SCS-T2FLM, 25-yr
Pre 32.1
Post 27.5 58.0
SFWMD, 72-hr, 25-yr
Pre 38.1
Post 30.3 58.0
Since this configuration meets the requirements for these design storms, the pond
size is probably adequate. We need to make sure that the discharges are not
exceeded for the less frequent (2-year through 50-year) DOT design storms. We
also will check the longer-duration storms, though it appears that the long duration
storms (24-hour to 240-hour) will not control the size of the pond, since the stages
and discharges of the 24-hour are much less than the 1-hour through 8-hour
duration storms.
9. Check the size of the bleed down orifice. For this example, you will need a 1.5-
inch diameter orifice or less to meet the typical wet detention criteria [discharge no
more than half of the treatment volume in 60 hours and discharge the total
treatment volume in no less than 120 hours]. At maximum pond stage, the
discharge through this orifice is less than 0.1 cfs. This is insignificant for this
problem. The orifice flow will be ignored and the routing calculations will be started
at the weir crest, as done in previous iterations.
If the discharge through the bleed down orifice at peak stage is small, ignore it. If not, model
the orifice in the routing. If the orifice is modeled, the starting water surface should reflect
some amount of drawdown. The average inter-event period between storms is 72 hours.
Most wet detention systems hold at least half of the treatment volume for 60 hours.
Therefore, for most wet ponds, starting the water surface at an elevation associated with
half of the treatment volume would be reasonable. If the regulatory requirements allow for a
quicker drawdown, it may be reasonable to start the water surface at the bleed down orifice.
10. Run the other design storms. The other design storms were routed through the
above pond configuration and all the post-developed rates were less than the pre-
developed rates, except one. A summary of these is shown below.
Table 9.4-5 (Example 9.4-3)
Pond Config. 100-yr 50-yr 25-yr 10-yr 5-yr 2-yr
as in Table Discharge Discharge Discharge Discharge Discharge Discharge
5.3-4 (cfs) (cfs) (cfs) (cfs) (cfs) (cfs)
1-hr
Pre 35.2 31.0 27.4 22.3 19.3 14.0
Post 25.8 22.3 19.4 15.3 13.0 9.1
2-hr
Pre 31.9 28.0 24.2 19.8 16.9 11.9
Post 26.7 23.3 20.0 16.1 13.7 9.6
4-hr
Pre 27.0 24.0 21.1 17.1 14.2 10.8
Post 26.8 23.7 20.7 16.8 13.8 10.5
8-hr
Pre 29.5 26.5 23.0 19.0 16.0 11.3
Post 27.6 24.5 21.1 17.3 14.3 9.9
24-hr
Pre 11.2 10.0 8.9 7.7 6.0 4.3
Post 10.9 9.7 8.6 7.4 5.8 4.1
3-day
Pre 8.2 7.1 6.2 5.2 4.5 3.4
Post 8.2 7.1 6.2 5.2 4.4 3.3
7-day
Pre 5.9 5.2 4.5 4.0 3.2 2.5
Post 5.9 5.2 4.5 4.0 3.2 2.6
10-day
Pre 7.8 6.9 6.1 5.3 4.4 3.4
Post 7.8 6.9 6.1 5.3 4.4 3.4
The 7-day, 2-year post-developed discharge rate is greater than the pre-developed
rate. If carried to three significant digits, the increase is 0.02 cfs (2.56-2.54). This
is within the accuracy of these calculations and would be acceptable for most
projects. If you or your project reviewers are concerned about an increase like this,
you could modify the weir configuration slightly, as is done in Step 8 of Example
9.4-4.
The stage-storage values used in this example are based on length and width
dimensions applied to a frustum of a pyramid. When you apply the radii to the
corners, you would reduce the storage using the same pond dimensions, so use
an equivalent stage-area relationship when working with the contours within the
CADD file. Doing so also will allow you to configure the pond for aesthetic
purposes while maintaining the necessary stage-storage relationship.
Ensure the retention volume is large enough that the post-developed discharge volumes
do not exceed the pre-developed discharge volumes. The retention volume is the volume
between the pond bottom and lowest discharge elevation of outlet control structure.
When using the NRCS runoff methodology, you can conservatively calculate the retention
volume as the difference between the pre-developed and post-developed discharge
volume for the 100-year, 10-day event. Some of this volume is infiltrated into the soil
during the storm, so the actual retention volume is sometimes less than this. During long-
duration design storms, such as the 3-day through 10-day durations, the volume infiltrated
during the storm can be substantial. You can account for this by using a program that
models the infiltration while routing the storm hydrograph. When you do this, you will not
know the required retention volume until you have routed the storms and know how much
volume infiltrates during the storm event.
The retention volume must recover at a rate such that half of the volume is available in
seven days and the total volume is available in 30 days. When measuring the recovered
volume, the pond is instantly (or over a very short time) filled with a runoff volume equal
to the retention volume. Then, the water can infiltrate with no inflow to the pond.
The next several pages summarize the critical information contained in the following
documents. We suggest that you read these documents before designing a retention
system.
http://www.sjrwmd.com/technicalreports/pdfs/SP/SJ93-SP10.pdf
During a storm event, runoff from the drainage basin enters the pond and infiltrates the
pond bottom. At the beginning of a storm, the groundwater beneath the pond moves
primarily vertically downward through unsaturated soil. If runoff to the pond exceeds the
infiltration, the water depth in the pond increases as the wetting front continues to move
down. Although the soil between the wetting front and the pond bottom is wet, it is not
totally saturated due to entrapped air. After the wetting front reaches the water table, the
vertical infiltration adds water to the water table aquifer. At this time, the groundwater
moves primarily horizontally within the saturated aquifer while the water table begins to
mound and saturate the soil beneath the pond. If infiltration continues, the mound rises
to and above the pond bottom. When the mound reaches the pond bottom, the area
beneath the bottom is fully saturated and flow moves primarily horizontally. See Figure
9.4-1.
Determining the drawdown characteristics and the recovery time may involve modeling
the downward vertical flow through unsaturated soil, or the horizontal saturated flow of
the groundwater mound, or both.
The source for the above equations is the modified Green and Ampt infiltration equation.
Their derivation is presented in Stormwater Retention Pond Infiltration Analyses in
Unconfined Aquifers (Jammal and Associates, 1991).
The total volume of water required to saturate the voids in the soil below the pond
bottom is: VOLVOIDS = APB HB f
where:
HB = Height of pond bottom above groundwater (see Figure 9.4-1)
ID = Design infiltration rate
KVU = Unsaturated vertical hydraulic conductivity
You can obtain this typically from a Double Ring Infiltration (DRI) test.
Although infiltration is occurring during the test, the soil is not fully
saturated due to entrapped air. The unsaturated K is less than the
saturated K. Unsaturated K ranges from one-half to two-thirds saturated K
(Bouwer 1978, ASTM D 5126, & Jammal and Assoc., 1991).
f= Fillable porosity. See description in following pages.
APB = Area of pond bottom
FS = Factor of safety, usually 2.0.
You can use this factor of safety to account for the variability of the measurements and
for the sediment that inevitably will enter the pond and clog the bottom surface.
Model the aquifer as having a single homogeneous layer of uniform thickness and a
horizontal initial water table.
Several computer models are available to analyze saturated flow. Most use a form of the
USGS program MODFLOW. A simplified approach was developed by Jammal and is
discussed in the SJRWMD’s, “Applicant’s Handbook for Regulation of Stormwater
Management Systems.” Regardless of which program or technique is used, four
parameters are needed to model saturated flow: (1) the thickness of the aquifer, (2) the
groundwater table elevation, (3) the fillable porosity, and (4) the horizontal saturated
hydraulic conductivity of the aquifer.
This is the thickness of soil through which the horizontal flow will occur. You usually
will measure this depth to the top of a confining or very dense layer, such as
hardpan, that will restrict the downward vertical movement of groundwater. Use
the lesser of the depth of the soil boring or the width of the pond as the maximum
value in the analysis. (The maximum depth of the mobilized aquifer is about equal
to the width of the pond. [Bouwer, 1978]).
Groundwater Elevation:
For modeling the recovery of the treatment volume, you usually will use the SHWT
elevation. For modeling the infiltration of a pond discharging to a closed basin, this
groundwater elevation should represent the groundwater elevation during an
extreme event like the 100-year, 10-day design storm. Currently, there is no
standard procedure for determining this elevation; nevertheless, it could be
substantially higher than the SHWT. For example, where the pond is located near
the low in the watershed (lake or flood plain at the low), it may be reasonable to
use the 100-year lake or floodplain elevation as the extreme event groundwater
elevation. Where the pond is located higher in the watershed, the extreme event
groundwater elevation may be closer to the SHWT. Use your judgment and handle
these situations on a case-by-case basis.
Fillable Porosity:
voids to be substantially filled with water. In fine sands, the distance saturated due
to capillary rise is roughly six inches. Therefore, the fillable porosity varies with the
depth to the water table.
Specific field or laboratory testing usually is not required for determining the fillable
porosity. For most calculations associated with fine sands, the fillable porosity will
vary from 0.1 to 0.3 (10 percent to 30 percent). The SFWMD has produced soil
storage curves that you can use to estimate the fillable porosity. For fine sand
aquifers, the SJRWMD recommends using a fillable porosity in the range of 20
percent to 30 percent in infiltration calculations. The higher values of fillable
porosity will apply to the well-to-excessively-drained, hydrologic group “A” fine
sands, which generally are deep and contain less than 5 percent by weight passing
the No. 200 sieve.
With all other dimensional and aquifer factors being the same, the predicted
recovery time decreases as the assumed value of fillable porosity increases.
Increasing the fillable porosity from 0.2 (20 percent) to 0.3 (30 percent) decreases
the recovery time by 15 percent to 30 percent.
Since you assume horizontal flow for the saturated analysis, the hydraulic
conductivity should represent that direction. This should represent the weighted
value of the soil above the confining layer. There are numerous techniques for
measuring this value, and they are briefly described below. The Department
recommends applying a safety factor of 1.5 to 2.0 to the measured values. You
can apply this factor of safety to account for the variability in the elevation of the
impermeable layer, measurement of the conductivity, and the estimate of fillable
porosity.
Pumping tests:
These tests generally are expensive and should be reserved for highly sensitive
projects. They can overestimate hydraulic conductivity if the bore holes extend into
a highly permeable layer which is below a confining layer and the proposed pond
bottom is above the confining layer.
Pond location
The ideal functional characteristics of the pond, such as: “This pond will be
designed to retain a volume of stormwater for flood control purposes. It should
infiltrate half the retention volume in no more than seven days and all of the volume
in no more than 30 days.”
The Geotechnical Engineer needs to know the information listed above because the soils
investigation can vary depending on the groundwater flow condition anticipated during
your design conditions. Refer to Table 9.4-6
Anticipated Groundwater
Soil Investigation1
Flow Conditions/Analysis
1) Thickness of mobilized aquifer.
2) Determine SHWT elevation.
Saturated
3) Determine weighted saturated horizontal
hydraulic conductivity of mobilized aquifer.
1) Obtain unsaturated vertical hydraulic
conductivity at or near pond bottom.
Unsaturated
2) Determine SHWT or confirm that SHWT is at
(Probably limited to high,
least as low as drainage engineer estimated.
sandy ridges)
3) Confirm that no confining layer exists between
pond bottom and SHWT.
Karst Areas See discussion in this section.
1 Preliminary results of the soil investigation may dictate that a different soil
investigation is necessary. For example, you may have estimated sandy
conditions down to a deep water table, planned on doing an unsaturated
analysis, and requested appropriate soil information. Then the initial soil borings
could indicate a confining layer close enough to the pond bottom to warrant a
saturated analysis.
If the groundwater elevation is within two feet of the pond bottom, you can assume that
horizontal saturated flow will occur. If the groundwater is farther from the pond bottom,
you should compare the volume of the voids under the pond to the volume of runoff that
must be infiltrated.
For estimating the groundwater flow conditions, the volume to be infiltrated should be the
treatment volume for retention systems discharging to open basins with known historical
flooding. It should be the difference between the 100-year, 10-day runoff volume for
ponds discharging to closed basins. If the volume to be infiltrated is larger than the volume
of the voids under the pond, the groundwater mound will rise to the pond bottom, thus
forcing saturated horizontal flow.
Karst Areas:
The WMDs and FDEP have identified known Karst areas and usually have special
requirements for stormwater facilities in these areas to assure that water quality of the
aquifer is maintained. Sink holes can present problems during or after construction, so it
is important that you are aware of potential sink hole locations.
Some sink holes can be only a meter or two in diameter, thus making it difficult to identify
their potential as a hazard. Sometimes potential sink holes can be identified in the field
by localized depressions in the ground surface. You may find it useful to try ground
penetrating radar in some situations, but this tool has a disadvantage in that it does not
penetrate clay layers. Work closely with the Geotechnical Engineer to identify potential
sink holes.
As a preventive measure, you could place a permeable geotextile strong enough to span
a small opening several feet below the pond bottom. This would allow small sink holes to
develop without requiring any maintenance work. Doing this will add substantial costs and
may not be warranted for all facilities in Karst areas. You and the Geotechnical Engineer
should make a joint decision to follow this approach.
Given:
Pre-developed roadway pavement = 2 10-foot lanes
Drainage area: includes roadway right of way and
offsite draining to the roadway: =13.0 ac
Offsite land use = Residential lots averaging 1/2 ac
Proposed typical section = 4-lane urban section
Combined roadway, curb, and
sidewalk width = 73 ft
Length of roadway within drainage
area = 2,313 ft
Treatment volume = 17,600 ft3
Maximum allowable pond stage = 104 ft
Offsite runoff draining to the project will be taken through the pond, not bypassed
around.
Project located near Somewhere City, Florida; rolling terrain, approx. 2 percent
grades, Hydrologic Soil Group B
A confining or impermeable layer exists at approximately elevation 92 ft
The saturated horizontal hydraulic conductivity was estimated to be 8 ft/day
The SHWT was estimated at approximately elevation 93 ft
Find: Pond size and outlet control structure configuration.
1. Pre-developed runoff:
Time of concentration = 21 min (given)
Area & curve number:
Roadway pavement: = 1.06 ac @ CN = 98 (20 ft x 2,313 ft)
Pervious area: = 11.94 ac @ CN = 70 (13 ac – 1.06 ac)
Proposed pond area: = 1.50 ac @ CN = 70 (preliminary size)
Total: = 14.5 ac @ CN = 72.1
As in Example 9.4-1, the proposed pond is outside the area draining to the
roadway; thus, the pond area must be added to the other areas.
Also, as in Example 9.4-1, the roadway right of way to be acquired is within the
area draining to the roadway. For your project, the acquired right of way may be
outside the area draining to the road, thereby requiring that the additional right of
way be added to the other areas.
2. Post-developed runoff:
Time of concentration = 16 min. (given)
Area and curve number:
Roadway, curb, and
sidewalk: = 3.88 ac @ CN = 98 (72.8 ft x 2,313 ft)
Pervious area: = 9.12 ac @ CN = 70 (13 ac – 3.88 ac)
Pond: = 1.50 ac @ CN = 98
Total: = 14.5 ac @ CN = 80.4
3. Determine the location-specific rainfall volumes using the NOAA website link in
Section 1.4 of the Drainage Manual.
Rainfall Volumes (inches): Somewhere City, FL
2-yr 5-yr 10-yr 25-yr 50-yr 100-yr
1-hr 2.2 2.7 3.0 3.5 3.8 4.1
2-hr 2.7 3.3 3.7 4.2 4.6 5.1
4-hr 3.1 3.9 4.4 5.0 5.6 6.1
8-hr 3.6 4.6 5.1 5.9 6.6 7.3
1-day 4.4 5.8 6.8 7.8 8.7 9.6
3-day 5.6 7.2 8.3 9.9 11 12.4
7-day 7.0 8.9 10 12 13.4 15
10-day 7.6 9.5 11.2 13.7 15.2 16
For this example, we will use peak shape factor = 323 for all NRCS hydrograph runs.
4. Assumptions:
a) Unsaturated vertical hydraulic conductivity: A DRI could not be performed
because of the depth of the pond bottom. The unsaturated vertical hydraulic
conductivity was estimated from the saturated horizontal conductivity (KHS = 8
ft/day)
8 ft/day (1.5 – 1.5) = 3.6 ft/day (see discussion of DRI)
A factor of safety of 2 was applied to both values; thus, the modeled values
are KHS = 4 ft/day, and KVU = 1.8 ft/day
b) Groundwater elevation: The extreme event groundwater elevation is assumed
to be 3 feet above the SHWT. Then, extreme event groundwater elevation =
96.0 feet.
c) Fillable porosity is assumed = 0.1 (10 percent), worst case for fine sands
Assume the retention volume will be the difference in runoff volume for the
100-year, 10-day design storm. Using the approach of Example 9.4-1, the
volume difference is 66,588 ft3 for this example.
Assume a height of the peak stage over the weir crest. For this example,
we will use 1 foot. With a peak pond stage of 104 feet, this puts the weir
crest at approximately 103 feet.
Determine a pond size and shape that will fit the retention volume
between the pond bottom and the weir crest. For this example, a pond
with a 200 foot x 100 foot bottom and 1:4 side slopes meets these
constraints and will be used as a starting size.
6. Calculate the pre-developed discharge rates and volumes, and route the post-
developed runoff through the pond. The weir width was arbitrarily selected for this
iteration. Using a typical routing program that models infiltration during the storm,
you should obtain values similar to the following.
For the first round of iterations for a pond discharging to a closed basin, it is usually
sufficient to run the 100-year, FDOT 8-hour through 10-day duration storms.
Table 9.4-6
Disch.
Disch. Peak Pond
Volume
Design Storm Rate Stage
(ft3 x
(cfs) (ft)
Pond Configuration: 103)
Pond bottom dimensions = 200 ft x Pre
100 ft 216 29.1
FDOT 8-hr, 100-year Pos 104.2
Pond bottom elevation = 100 ft 182 27.3
t
Avg side slope = 1: 4 Pre
Weir crest elevation = 102.9 ft FDOT 24-hr, 100- 323 10.4
Pos 103.7
Weir width = 5 ft year 289 10.9
t
Volume below weir crest = 68,585 ft 3 Pre
Allowable stage = 104 ft FDOT 3-day, 100- 459 8.2
Pos 103.6
year 422 8.4
t
Modeled Soil Conditions: Pre
Aquifer base elevation = 92 ft FDOT 7-day, 100- 589 6.1
Pos 103.5
Saturated horizontal condition (K HS) year 543 6.2
t
= 4 ft/day Pre
Water table elevation = 96 ft FDOT 10-day, 100- 639 7.5
Pos 103.5
Fillable porosity = 0.1(10%) year 589 7.7
t
Unsat Vert Cond. (K VU) = 1.8 ft/day
Quantity Control Retention Volume
7-Day 30-Day
Total recovered in 28 days (ft3) (ft3)
Vol. Reqd. to be Recovered = 33,300 66,590
Vol. Recovered (infiltrated) = 30,600 53,400
All the post-developed discharge volumes are substantially less than the pre-
developed discharge volumes of corresponding duration, so the pond retains more
volume than needed. That is, the post-developed discharge volumes could be
increased. This is done by lowering the weir. Although most of the post-developed
discharge rates exceed the pre-developed rates, they are close to the pre-
developed rates. To maintain similar post-developed rates, we will need to reduce
the weir width as it is lowered. After making several iterations of weir adjustments,
the following configuration produces the results in the following table.
For this example, we will add the 1-hour, 2-hour, and 4-hour duration storms.
Table 9.4-7
Peak
Disch. Disch.
Pond
Design Storm Volume Rate
Stage
(ft3 x 103) (cfs)
Pond Configuration: (ft)
Pond bottom dimension = 200 ft x Pre 83.3 33.8
100 ft FDOT 1-hr, 100-year 103.5
Post 64.3 16.8
Pond bottom elevation = 100 ft Pre 122 31.1
Avg side slope = 1:4 FDOT 2-hr, 100-year 103.7
Post 109 19.9
Weir crest elevation = 101.5 ft Pre 164 25.4
Weir width = 1.5 ft FDOT 4-hr, 100-year 103.9
Post 155 22.6
Volume below weir crest = Pre 217 29.1
32,768 ft 3 FDOT 8-hr, 100-year 104.0
Post 212 24.0
Allowable stage = 104 ft FDOT 24-hr, 100- Pre 323 10.5
103.0
year Post 322 10.2
Modeled Soil Conditions:
FDOT 3-day, 100- Pre 459 8.2
Aquifer base elevation = 92 ft 102.8
year Post 458 8.3
Saturated horizontal cond.(KHS) =
FDOT 7-day, 100- Pre 588 6.1
4 ft/day 102.6
year Post 581 6.2
Water table elevation = 96 ft
Fillable porosity = 0.1(10%) FDOT 10-day, 100- Pre 638 7.6
102.8
Unsat vertical cond. (KVU) = 1.8 year Post 631 7.7
ft/day Retention Volume
7-Day 30-Day
Total recovered in 17 days
(ft3) (ft3)
Vol. Reqd. to be Recovered = 16,390 32,770
Vol. Recovered (infiltrated) = 24,200 32,770
This pond configuration meets the drawdown and discharge volume requirements. The
rate requirements are close to being met as the 3-day through 10-day storms at only 0.1
cfs above the pre-developed discharge rates.
7. Adjust the drainage basin characteristics due to the pond size being smaller than
estimated in Step 1. Remember that, for this example, the pond is located
outside the area draining to the road, so changing the pond size also changes
the total area. In Step 2, we assumed the entire pond area had a CN = 98. A
more-refined estimate of the pond area curve number can be made at this time.
Pond Area:
This essentially meets all the requirements. The 24-hour and 3-day are critical durations
for discharge volume. The 8-hour duration creates the highest stage. The 3-day through
7-day are critical durations for discharge rate and they exceed the pre-developed
discharge rates by less than 2 percent. This may be acceptable. For this example, several
more iterations could be made to bring these rates down without increasing the pond size.
Notice that the retention volume recovered in 7 days was more than necessary and the
total volume was recovered in only 17 days. This indicates that we can lower the pond
bottom. We can lower the weir crest the same amount that the pond bottom is lowered
and maintain similar discharge volumes, which we need to do. As we lower the weir crest,
we can reduce the weir width to reduce the discharge rate, which is the primary intent. So
after several iterations, the following configuration using two weirs seems to do the trick.
Notice it involves a compound weir.
Table 9.4-9
Peak
Disch. Disch.
Pond
Design Storm Volume Rate
Pond Configuration: Stage
(ft3 x 103) (cfs)
Pond bottom dimension: = 192 ft x (ft)
92 ft Pre 81.2 32.9
FDOT 1-hr, 100-year 103.0
Post 38.9 8.2
Pond bottom elevation = 99 ft Pre 119 30.3
Avg side slope = 1:4 103.5
FDOT 2-hr, 100-year Post 78.5 13.8
#1 weir crest elevation = 100.5 ft Pre 160 24.7
#1 weir width = 0.5 ft FDOT 4-hr, 100-year 103.7
Post 124 21.1
Volume below #1 weir crest = Pre 211 28.4
29,120 ft3 FDOT 8-hr, 100-year 103.7
Post 185 21.7
#2 weir crest elevation = 103.3 ft FDOT 24-hr, 100- Pre 315 10.1
#2 weir width = 12 ftAllowable stage year 103.0
Post 299 8.1
= 104 ft
FDOT 3-day, 100- Pre 447 7.9
102.9
year Post 436 7.4
Modeled Soil Conditions:
FDOT 7-day, 100- Pre 572 5.9
Aquifer base elevation = 92 ft 102.6
year Post 556 5.9
Saturated horizontal cond. (KHS) = 4
ft/day FDOT 10-day, 100- Pre 621 7.3
102.9
Water table elevation = 96 ft year Post 610 7.3
Fillable porosity = 0.1(10%) Quantity Control Retention Volume
Unsat vertical cond. (KVU) = 1.8 7-Day 30-Day
Total recovered in 28 days
ft/day (ft3) (ft3)
Vol. Reqd. to be Recovered = 14,560 29,120
Vol. Recovered (infiltrated) = 17,590 29,120
This configuration meets all the requirements for the storms modeled. The 7-day and 10-
day durations are critical for discharge rate. The 3-day and 10-day durations are critical
for discharge volume, and the 4-hour and 8-hour durations create the highest stage. The
total retention volume is recovered in 28 days, just under the 30-day requirement.
Although it appears that the pond size could be reduced slightly, remember that the
earthwork tolerance will slightly affect characteristics of this pond. A slightly lower pond
bottom will reduce the aquifer thickness, thus reducing the recovery time. A slightly higher
pond bottom will reduce the retention volume and increase the discharge. So, when
considering the construction tolerance, this configuration looks good.
The other storm frequencies should be calculated to check that the pre-
developed discharges are not exceeded. The results are in Table 9.4-10.
10. The stage-storage values used in this example have been based on length and
width dimensions applied to a frustum of a pyramid. When you apply the radii to
the corners, you would reduce the storage using the same pond dimensions, so
use an equivalent stage-area relationship when working with the contours within a
CADD file. Doing so will allow you to configure the pond for aesthetic purposes
while maintaining the necessary stage-storage relationship.
FDOT generally has four options when dealing with offsite flows that would be
intercepted by a linear transportation project:
2) Accept offsite flows and direct them to a treatment system that is designed
to treat the transportation project and the offsite flow
3) Accept offsite flows and direct them to a treatment system that is designed
to treat only the project
4) Accept offsite flows and direct them to a treatment system that is designed
to treat the project and partially treat the off-site property
Empirical nutrient loading model results (Harper Methodology) show that—in all cases
involving wet detention treatment, even when the treatment facility is designed for only
the project area—there is an overall environmental benefit achieved by commingling
(i.e., the net pollutant reduction is greater).
The same modeling shows that—for retention-type treatment systems, when the offsite
lands provide equal or greater nutrient loading when compared to the FDOT project—
there is also an overall environmental benefit achieved by commingling, even when the
treatment facility is designed for only the project area. Thus, in these cases, the water
quality at downstream points of discharge from the commingled system will be equal to
or better than those systems that bypass offsite flows. Based on these results, FDEP
and the WMDs support allowing commingling in these cases without requiring further
analysis as long as the proposed treatment pond meets the ERP design requirements
for the runoff from the project area and results in an overall environmental benefit.
The same empirical nutrient loading model results (Harper Methodology) show that—
where undeveloped or unimproved offsite lands flow into onsite FDOT dry retention
In summary:
For wet detention:
Commingle offsite inflows unless cost or hydraulic issues lead to
bypassing
For dry retention:
Commingle developed offsite inflows unless cost or hydraulic issues lead
to bypassing
For inflows from lower EMC areas, consult the District Drainage Engineer
- Calculate change in nutrient removal
- If reduction in treatment, evaluate B/C
Sometimes outlet control structures contain multiple (or staged) weirs, such as a small
weir at a low elevation with a larger weir at a higher elevation. These compound weirs
can be handled in one of two ways. SWFWMD recommends treating the lower slot as an
orifice, with head (H) measured to the centroid when the opening is submerged. Then
you can model the upper portion with standard weir formulas and the two flows are added.
Alternatively, you can extend the lower slot computations to the water surface. Then you
model the flows from the sides of the upper slot as a separate weir and add the flows. In
either case, a totally smooth transition in the performance curve at the stage of the upper
weir crest cannot be expected. Some amount of manipulation of the curve should be
made to smooth it at the transition.
The first two tables apply to control devices formed into the wall of the outlet control
structure. As a result, the thickness of the structure wall will affect the discharge
coefficient. The discharge coefficient first rises with increasing head and then remains
constant. This behavior is observed for both orifices and weirs and is caused by
attachment of the flow at the sides of the opening. The wall thickness of the typical FDOT
structure can vary depending on whether the structure is precast or “cast in place.” Unless
you specify “cast in place,” assume that the structure will be precast. The Roadway and
Traffic Design Standards specify the wall thickness.
Thin plate weirs fabricated from metal and bolted over a larger opening in the wall provide
a more-uniform, predictable performance. Install the metal weir plate over an opening of
sufficient size to ensure that the flow passing over the weir encounters no interference
from the headwall. The plate’s thickness should be 0.25 inch or less to approximate a
sharp edge. If you construct it as discussed here, the weir coefficient is as follows and is
independent of height.
Metric US Customary
Weir Coefficient CW for Thin Plates 1.73 3.13
QS
= (1 - S n )0.385
QF
where
QS = Flow under submerged conditions
QF = Flow under free discharge
S = H2/H1 = Submergence ratio
H1 = Upstream headwater
H2 = Downstream headwater
n = 1.5 for rectangular weirs, & 2.5 for triangular weirs
QS
= (1 - S )0.5
QF
9.5.3 Skimmers
Regulatory agencies commonly require skimmers to prevent oil and grease from leaving
the pond. The head loss due to skimmers is minimized if the flow area under the skimmer
is three times larger than the flow area of the weir. If this area is provided, you need not
calculate the head loss associated with the skimmer.
If it is impossible to provide the flow area mentioned above, the head loss across the
skimmer can be calculated using this formula:
HL = k V2/2g
where:
k= Loss coefficient
V = Velocity under the skimmer
9.5.4 Miscellaneous
To minimize plant growth, construct a concrete apron around the outlet control structure.
You should extend it five feet from the structure.
In wet detention facilities, the outlet control structure generally includes a drawdown
device, such as an orifice or a v-notch weir, to establish the normal water level and to
slowly release the treatment volume. If the drawdown device is smaller than three inches
wide or less than 20 degrees for v-notches, include a device to eliminate clogging.
Examples of such devices include baffles, grates, screens, and pipe elbows.
It is not necessary to use the ditch bottom inlet type grates on outlet control structures
unless needed for safety. If the structure is accessible to the public or maintenance
vehicles will traverse it, grates are recommended.
Always consider the effects of storms that are more severe than what was designed for.
Sometimes an overflow spillway can be built into the berm. Or additional flow can
sometimes pass through the top of the outlet control structure while using the freeboard
to store more volume and create additional head.
10.1 Purpose.........................................................................................................10-1
10.1 PURPOSE
The primary purposes for designing temporary drainage are to:
10.2 CRITERIA
Consult the Drainage Manual for hydraulic and hydrologic criteria that apply to the
design of temporary drainage systems. Specifically, refer to Section 2.2 in the
Drainage Manual for design frequencies at temporary roadside and median
ditches, swales, and side drains. Refer to Section 3.3 in the Drainage Manual
under “General Design” for design frequencies of temporary storm drain systems.
Refer to Section 4.3.2 in the Drainage Manual for design frequencies at temporary
culverts, bridge culverts, and bridges.
Some drainage situations are much more common in temporary conditions than in
permanent conditions. For example, in temporary MOT scenarios, a temporary
traffic lane ultimately will become a paved shoulder; thus, the shoulder area,
proposed to carry spread in the permanent condition, now has traffic flowing with
little room before being confined by a barrier wall. Thus, stormwater may pool
along the temporary barrier wall or curbing near an inside high-speed lane.
Be aware that criteria can be different for permanent and temporary conditions on
the same section of roadway, primarily because the two conditions can have
differing design speeds. Consult Section 3.9 of the Drainage Manual to determine
spread criteria.
10.3 METHOD
Carefully consider the temporary conditions that could arise during the construction
or rehabilitation of a permanent transportation facility. Safety of travelers and
workers, cost of construction, and the time required to complete construction tasks
all are affected adversely when temporary drainage is not adequately addressed
during design. You can reduce construction delays resulting from inclement
weather conditions by creating a well-designed temporary drainage system.
Further, unsafe traveling conditions and construction delays increase the cost of
projects. Provide temporary drainage features where and when they are needed.
Design temporary drainage for construction sites with emphasis on the following:
10.4 DETOURS
The term “detour” is defined in FDM 240. Detours may be either located on existing
streets or constructed with temporary paved or graded lanes. Design the drainage
for detours on existing streets by using the existing street drainage system while
preventing overtaxing of the system on those streets. When temporary lanes or
roads must be constructed, provide design for temporary drainage systems.
Include directional flow arrows in the plans when a swale is used between fill for a
temporary road and fill for a permanent road. See Figure 10.5-1.
Consider every temporary low area created when a detour road interrupts a
proposed ditch gradient as a possible location for temporary drainage structures.
Where you cannot avoid this curbing effect with construction phasing, provide
temporary measures to prevent flooding of adjacent travel lanes. Sandbags or
temporary asphalt curb can be effective in directing runoff away from travel lanes.
Prevent overtopping flow at drop-offs by calling for sandbags or temporary asphalt
curb to be placed along the drop-off to force water away from travel lanes. Refer
to Figures 10.5-3, 10.5-4 and 10.5-5.
If the speed limit in a work zone is 45 mph or less, you can use intermittent
transverse saw-cuts in travel lanes to allow water to flow through the travel area
without overtopping.
10.5.2 Driveways
Constructing driveways can cause water to pond in the turnout area and
subsequently flood adjacent lanes on the roadway. Include details in the plans for
placing sandbags or temporary asphalt curb along outside edges of pavement
adjacent to turnout construction to prevent water in the turnout site from flowing
across the travel lanes. Provide details for temporary flumes and inlets, where
needed, to direct water at turnout sites into the storm drain system, thus preventing
water from collecting in low areas and/or causing erosion.
1. Provide sizes for diversion pipes that are to be inserted into existing box
culverts.
2. Show the configuration requirements for sandbagging.
3. Include measures for stabilization and erosion control.
4. List any items that must be removed prior to final grading.
5. List descriptions and quantities for items not included in the cost of the
structure.
When needed, perform spread calculations for temporary precast concrete barrier
wall, based on rainfall of four inches per hour.
0.56 5 3 1 2 8 3
Q Sx SL T
n
where:
Q = Gutter flow rate, in ft3/sec
n= Manning’s roughness coefficient (see Table B-2, Appendix B)
Sx = Pavement cross slope, in ft/ft
SL = Longitudinal slope, in ft/ft
T= Spread, in ft
3. Using the depth of flow (y) at the edge of the barrier wall, determine the
flow through the slot using the capture equations in HEC 22, and
assuming that the two 27-inch slots operate independently. The
Department suggests that the slot flow be reduced to 75 percent of the
equation value to account for 25 percent blockage.
4. Subtract the flow through the slot from the flow approaching the slot to
determine the flow bypassing the slot.
5. Add the bypass flow to the surface runoff for the next slot.
6. Repeat steps 1 through 5 for the length of the barrier wall or until
equilibrium is achieved.
Table 10.5-1 provides the spread values for several pavement widths and slopes
using the approach described above.
For sag vertical curves, you will likely need a more complicated approach. Several
items change with changing (y) values. As the depth of ponding increases, the
length of roadway draining directly (not including the bypass from approach
grades) to the ponded area increases, as does the number of slots that operate in
sump condition.
1. Prevent water from being trapped in the area where the limits of temporary fill overlap the limits of permanent fill
by providing a design for temporary ditches that drain positively to the stream, as shown on the left side of this
detail, or provide a design for temporary drains under the detour, as shown on the right.
2. When the grade of a detour road is lower than ditch elevations, take care to avoid any sag in the ditch grade
that could collect water until it pops over and spills onto the detour. Find and solve this problem during design.
Do not force the contractor to handle it. The temporary pipe shown is a possible scenario.
1. Conditions shown here may differ as to location, amount, configuration, direction of flow, etc., with regard to
temporary barrier wall, temporary drainage structures, and work area.
2. Calculate spread using the method defined in Section 10.5.5. Prepare a design for temporary conditions that
meets the requirements of this chapter and the Drainage Manual.
3. Require installation of temporary drainage structures where needed to maintain normal flow through the work
area.
4. Where two or more runs of temporary barrier wall are parallel to each other, on or adjacent to a common width
of pavement, a temporary slotted drain may be required to hold spread within acceptable limits.
1. Place one row of sandbags, two bags deep, adjacent to drop-offs where
overtopping spread may occur and where the down-slope lanes must be
used to maintain traffic.
2. When possible, avoid this situation by phasing milling and pavement lifts
so that the exposed sides of drop-offs face down-slope.
3. Consider using this detail wherever new pavement lifts must be placed
or existing pavement must be milled, and where the exposed edge of a
drop-off faces upslope.
APPENDIX
TABLE OF CONTENTS
Table A-1, below, lists examples of data, along with typical sources and uses, for three
data categories, including:
Drainage projects typically require numerous potential sources of data. Identifying these
sources can be difficult, and making the subsequent necessary contacts can be time-
consuming. To assist in this process, Table A-1, below, includes typical data sources. In
many cases, the local community or Water Management District in which the drainage
project is being conducted is either the best source of data or the most logical starting
point.
Before initiating calculations, collect drainage data using the following general
guidelines:
1. Identify data needs, sources, and uses, using Table A-1 as a checklist. Much of this
information will have to be provided in the environmental document and supporting
files.
3. Compile and document the results of Step 2, and compare data needs and uses
with the availability of published data. Identify any additional field data needs.
4. Collect field data based on needs identified in Steps 1 and 3, using information
presented in Section A.3.
Flood Insurance Study U.S. Federal Emergency Establish flood flows, stages, and area of
Management Agency/Department of inundation of principle streams
Housing and Urban Development
City or County
Historic Inundation Areas and High U.S. Geological Survey Document location and severity of
Waters City or County historic inundation and other
Water Management District problems
Regional Planning Agency
2. Natural Resource Base News Media – Newspapers, Radio,
T.V.
Museums, Historical Societies
Residents
Field Survey
Historic Stage and Discharge National Weather Service Assess severity of historic floods
Water Management District
Stream Stage and Discharge U.S. Geological Survey Develop discharge-probability
Water Management District relationships
Asses severity of historic floods
Existing Land Use Areas and High Waters Regional Planning Agency Determine runoff coefficients, curve
Field Survey numbers, and other factors
Land Use Plan Regional Planning Agency Determine runoff coefficients, curve
3. Manmade Features City or County numbers, and other factors
Zoning Map and Ordinance City or County Project future land use
Transportation, Sewage and Other Public Regional Planning Agency Establish future watershed and sub-
Facility-Systems and Plans City or County basin divides
Department of Transportation Project future land use
Published data include soils, land use, precipitation, topography and contour,
streamflow and flood history, and groundwater. A good basic reference for water
resources data in Florida is the Water Resources Atlas of Florida (Florida State
University, 1984). Of particular relevance to drainage projects are data on weather and
climate, surface water, groundwater, water quality, drainage, flood control, navigation,
and ecosystems.
A.2.1 Soils
Collect published soils data by following this procedure:
1. Identify soils data needed to evaluate runoff, soil erosion, slope and foundation
stabilities, and hydraulic conductivity.
2. Obtain soils data from the U.S. Natural Resources Conservation Service (formerly
the U.S. Soil Conservation Service [SCS]) in the form of detailed soils reports for
the county area being considered. Old plans, construction logs, and soil boring
results can provide additional site-specific data. Specific project information usually
is available during the final design stage.
When a project involves a channel in which storm tide surge conditions may be
expected to result in erosion of the channel, the geology in the area of the channel is
important in analyzing the nature of the potential erosion enlargement. More detailed
and extensive borings may be important, which would not be the case where channel
stability is reasonably assured. You may need to make a preliminary assessment of the
potential for enlargement to specify the extent of the geotechnical study required.
1. Determine historical land use from older land use maps or aerials.
2. Determine current land use from sources such as land use maps, aerial
photographs, and field reconnaissance. Contact appropriate county and municipal
governments. Regional Planning Councils and Water Management Districts also
may have existing land use data. Compare historical (from Step 1) and current
land use to identify areas undergoing rapid growth and an approximate rate of
change. Establishing land use at the time of design can be crucial to project
success.
3. Determine future land use based on projections of existing land use, land use
plans, and site-specific layouts of proposed development, zoning maps, and
discussions with public officials. County and municipal governments as well as
Regional Planning Councils and Water Management Districts also may be good
sources of future land use data.
A.2.3 Precipitation
Collect published precipitation data by following this procedure:
3. Collect published precipitation data. The primary source is the National Weather
Service. Additional data may be available from Water Management Districts.
Sources of published precipitation data are briefly discussed below.
A series of publications by the National Weather Service (formerly the U.S. Weather
Bureau) presents precipitation depth-duration-frequency data developed from observed
precipitation data across the United States. HYDRO-35, by Frederick et al. (1977), is
particularly useful for small drainage areas, since rainfall depths for durations of 5, 10,
15, 30, and 60 minutes are presented for return periods of 2, 5, 10, 25, 50, and 100
years. Technical Paper No. 40, by Hershfield (1961), commonly known as TP-40, is a
standard reference for obtaining hydrologic design rainfall depths for durations of 30
minutes and one, 2, 3, 6, 12, or 24 hours, and for return periods of one, 2, 5, 10, 25, 50,
and 100 years. Technical Paper No. 49, by Miller (1964), extends the depth-duration-
frequency data presented by Hershfield (1961) to include rainfall depths for durations of
2, 4, 7, and 10 days at return periods of 2, 5, 10, 25, 50, and 100 years. The
Department has developed rainfall curves based on these references.
Statistical rainfall depth data for Florida is found in the National Oceanic and
Atmospheric Administration (NOAA) Atlas 14 Rainfall Data. These data are available at
http://hdsc.nws.noaa.gov/hdsc/pfds/pfds_map_cont.html?bkmrk=fl. FDOT rainfall
distributions and intensity-duration-frequency curves may be found at
http://www.fdot.gov/roadway/Drainage/files/IDFCurves.pdf.
2. If published data are either unavailable or inadequate for project needs, the
Department can develop contours from aerial photographs for large-scale projects
or by survey for small areas.
Collect streamflow and flood history data by using the following procedure:
1. Obtain published data. The principal source of published streamflow data is the
USGS. Additional sources include Water Management Districts and municipal or
county government agencies.
2. Because published streamflow data may not be available for a specific project site,
an evaluation of flood history may require researching news media sources,
making field survey observations, and interviewing local residents and other
knowledgeable persons.
Groundwater
Follow all drainage area boundaries from the project centerline, around the area being
covered, and close again at the centerline. There is no need to show ridges that do not
drain to the project unless this information is pertinent to determine runoff concentration
points or flow path segments. Clearly indicate by notation on the map all exceptions to
the rule for closing all drainage area boundaries. These notes should show location and
elevation of break-over or diversion to or from the drainage area.
Typically, a drainage area should close to each existing culvert along the project and for
each probable cross drain location. As an exception, note flow distribution information
where two or more structures operate together to drain a single area.
Show all areas contributing to existing storm drains, which drain to or across the project.
In very flat terrain, as is found in South Florida, it often is necessary to develop profiles
for cross streets and parallel streets to make a definite determination of drainage areas.
In flat terrain, consider collecting additional field data about agricultural ditches to
confirm flow patterns.
Specially flown aerial photography is available for most new construction projects.
Ridge lines usually can be indicated on the photographs. When using photographs, the
field survey party should verify questionable points and supplement the information with
structure sizes, elevations, and high water marks as required. Determine drainage
areas by stereo interpretation with spot field survey work as appropriate.
The soils crew usually supplies water table information within the right of way; however,
the survey crew should note information pertaining to standing water, areas of heavy
seepage, or springs within the basin area.
APPENDIX
TABLE OF CONTENTS
Tables
Figures
Figure B-1: Kinematic Wave Formula for Determining Overland Flow Travel Time ...B-23
Figure B-2: Overland Flow Velocities for Various Land Use Types ............................B-24
Figure B-3: Velocity versus slope for Shallow Concentrated Flow .............................B-25
Figure B-4: Regions for USGS Regression Equations – Natural Flow Conditions .....B-26
Figure B-5: Regions for USGS Regression Equations for Natural Flow Conditions in
West Central Florida ........................................................................................B-27
Recommended
Value Range of Values
Concrete 0.011 0.010 - 0.013
Asphalt 0.012 0.010 - 0.015
Bare sand a 0.010 0.010 - 0.016
Graveled surface a 0.012 0.012 - 0.030
Bare clay-loam (eroded) a 0.012 0.012 - 0.033
Fallow (no residue) b 0.05 0.006 - 0.16
Chisel plow (<1/4 tons/acre residue) 0.07 0.006 - 0.17
Chisel plow (1/4 - 1 tons/acre residue) 0.18 0.070 - 0.34
Chisel plow (1 - 3 tons/acre residue) 0.30 0.190 - 0.47
Chisel plow (>3 tons/acre residue) 0.40 0.340 - 0.46
Disk/Harrow (<1/4 tons/acre residue) 0.08 0.008 - 0.41
Disk/Harrow (1/4 - 1 tons/acre residue) 0.16 0.100 - 0.25
Disk/Harrow (1 - 3 tons/acre residue) 0.25 0.140 - 0.53
Disk/Harrow (>3 tons/acre residue) 0.30 -- --
No till (</4 tons/acre residue) 0.04 0.030 - 0.07
No till (1/4 - 1 tons/acre residue) 0.07 0.010 - 0.13
No till (1 - 3 tons/acre residue) 0.30 0.160 - 0.47
Plow (Fall) 0.06 0.020 - 0.10
Coulter 0.10 0.050 - 0.13
Range (natural) 0.13 0.010 - 0.32
Range (clipped) 0.08 0.020 - 0.24
Grass (bluegrass sod) 0.45 0.390 - 0.63
Short grass prairie a 0.15 0.100 - 0.20
Dense grass c 0.24 0.170 - 0.30
Bermuda grass c 0.41 0.300 - 0.48
Woods 0.45 -- --
__________
All values are from Engman (1983), unless noted otherwise.
a
Woolhiser (1975).
b
Fallow has been idle for one year and is fairly smooth.
c
Palmer (1946). Weeping love grass, bluegrass, buffalo grass, blue gamma grass, native grass
mix (OK), alfalfa, lespedeza.
Note: These values were determined specifically for overland flow conditions and are not
appropriate for conventional open channel flow calculations. See Chapter 3, for open
channel flow procedures.
Range of
Type of Gutter or Pavement Manning’s n
Asphalt pavement:
Smooth texture 0.013
Rough texture [2] 0.016
Concrete pavement:
Float finish 0.014
Broom finish [3] 0.016
_____________
Reference: FHWA HEC-22
Notes:
1) Estimates are by the Federal Highway Administration.
Rigid Linings
_____________
* Decrease 30% for flows > 0.7' (maximum flow depth 1.5').
aWeighted coefficient based on percentage of impervious surfaces and green areas must be selected for
each site.
Table B-5: Design Storm Frequency Factors for Pervious Area Runoff
Coefficients*
Design Storm
Return Period (years) Frequency Factor, XT
2 to 10 1.0
25 1.1
50 1.2
100 1.25
_____________
Reference: Wright-McLaughlin Engineers (1969).
* DUE TO THE INCREASE IN THE DURATION TIME THAT THE PEAK OR NEAR PEAK
DISCHARGE RATE IS RELEASED FROM STORMWATER MANAGEMENT SYSTEMS, THE
USE OF THESE SHORT DURATION PEAK RATE DISCHARGE ADJUSTMENT FACTORS IS
NOT APPROPRIATE FOR FLOOD ROUTING COMPUTATIONS.
Hydrologic
Soil Group Definition
Table B-7: SCS Runoff Curve Numbers – Agricultural, Suburban, and Urban Land
the street with a minimum of roof water directed to lawns where additional infiltration could occur,
which depends on the depth and degree of the permeability of the underlying strata.
d The remaining pervious areas (lawn) are considered to be in good pasture condition for these
curve numbers.
e In some warmer climates of the country, a curve number of 96 may be used.
f Use for temporary conditions during grading and construction.
Note: These values are for Antecedent Moisture Condition II, and Ia = 0.2S.
Reference: USDA, SCS, TR-55 (1984).
Meadow Good 30 58 71 78
Woods Poor 45 66 77 83
Fair 36 60 73 79
Good 25 55 70 77
Farmsteads ----- 59 74 82 86
Road (dirt)b ----- 72 82 87 89
(hard surface)b ----- 74 84 90 92
aClosed-drilled or broadcast.
bIncluding right-of-way.
Note: These values are for Antecedent Moisture Condition II, and Ia = 0.2S.
Reference: USDA, SCS, NEH-4 (1972)
Standard
Error of
Prediction
Peak Runoff Equation (%)
Q2 = 127 A0.656 (ST+1)-0.098 43
_____________
Reference: Verdi (2006)
Standard
Error of
Prediction
Peak Runoff Equation (%)
_____________
Reference: Verdi (2006)
Standard
Error of
Prediction
Peak Runoff Equation (%)
Standard
Error of
Prediction
Peak Runoff Equation (%)
Standard
Error
Peak Runoff Equation R2 (%)
UQ2 = 2.35A0.41 SL0.17 (i2 + 3)2.04 (ST + 8)-0.65 (13 - BDF)-0.32 IA0.15 RQ20.47 0.93 38
UQ5 = 2.70A0.35 SL0.16 (i2 + 3)1.86 (ST + 8)-0.59 (13 - BDF)-0.31 IA0.11 RQ50.54 0.93 37
UQ10 = 2.99A0.32 SL0.15 (i2 + 3)1.75 (ST + 8)-0.57 (13 - BDF)-0.30 IA0.09 RQ100.58 0.93 38
UQ25 = 2.78A0.31 SL0.15 (i2 + 3)1.76 (ST + 8)-0.55 (13 - BDF)-0.29 IA0.07 RQ250.60 0.93 40
UQ50 = 2.67A0.29 SL0.15 (i2 + 3)1.74 (ST + 8)-0.53 (13 - BDF)-0.28 IA0.06 RQ500.62 0.92 42
UQ100 = 2.50A0.29 SL0.15 (i2 + 3)1.76 (ST + 8)-0.52 (13 - BDF)-0.28 IA0.06 RQ1000.63 0.92 44
UQ500 = 2.27A0.29 SL0.16 (i2 + 3)1.86 (ST + 8)-0.54 (13 - BDF)-0.27 IA0.05 RQ5000.63 0.90 49
UQT = Peak discharge, in cfs, for the urban watershed for recurrence interval T.
SL = Main channel slope, in ft/mile, measured between points which are 10 and 85 percent of
the main channel length upstream from the study site. For sites where SL is greater than
70 ft/mile, 70 ft/mile is used in the equations.
A = Contributing drainage area, in miles2.
i2 = Rainfall intensity, in inches, for the 2-hour 2-year occurrence.
ST = Basin storage, the percentage of the drainage basin occupied by lakes, reservoirs,
swamps, and wetland. In-channel storage of a temporary nature, resulting from detention
ponds or roadway embankments, is not included in the computation of ST.
BDF = Basin development factor, an index of the prevalence of the drainage aspects of (a)
storm sewers, (b) channel improvements, (c) impervious channel linings, and (d) curb
and gutter streets. The range of BDF is 0-12. A value of zero for BDF indicates the
above drainage aspects are not prevalent, but does not necessarily mean the basin is
non-urban. A value of 12 indicates full development of the drainage aspects throughout
aspects throughout the basin. See Chapter 2, Section 2.2.3 & Example 2.2-2 of this
document for details of computing BDF.
IA = Percentage of the drainage basin occupied by impervious surfaces, such as houses,
buildings, streets, and parking lots.
RQT = Peak discharge, in cfs, for an equivalent rural drainage basin in the same hydrologic area
as the urban basin, and for recurrence interval T.
_____________
Reference: Sauer et al. (1983).
Table B-15: Urban Watershed Regression Equations for Tampa Bay Area
Standar
d
Error
Peak Runoff Equation R2 in %
Table B-16: Urban Watershed Regression Equations for Leon County, Florida
Standard
Error
Peak Runoff Equation R2 in %
Q10 = 39.1 A0.776 IA0.867 Q10 (LL) = 7.98 A0.776 IA0.867 0.98 20
Q25 = 63.2 A0.787 IA0.791 Q25 (LL) = 14.6 A0.787 IA0.791 0.98 22
Q50 = 88.0 A0.797 IA0.736 Q50 (LL) = 22.1 A0.797 IA0.736 0.97 24
Q100 = 118 A0.808 IA0.687 Q100 (LL) = 32.4 A0.808 IA0.687 0.97 25
Q500 = 218 A0.834 IA0.589 Q500 (LL) = 71.7 A0.834 IA0.589 0.97 30
QT = Peak runoff rate outside Lake Lafayette Basin for return period T, in cfs.
A= Drainage area, in miles2
IA = Impervious area, in percentage of drainage area.
QT (LL) = Peak runoff rate inside Lake Lafayette Basin for return period T, in cfs.
_____________
Reference: Franklin and Losey (1984).
Table B-17: USGS Watershed Regression Equations for West Central Florida
_______________
Reference: Hammett and DelCharco (2001).
_____________
Reference: Hammett and DelCharco (2001).
Polynomial Coefficients
for a Third Degree Polynomial
Rainfall Storm Frequency
Zone in Years A B C D
1 2 11.0983 -2.47240 0.00711 0.01886
1 3 11.97845 -2.67930 0.02444 0.01812
1 5 11.82413 -2.28931 -0.07735 0.02535
1 10 12.01819 -1.91394 -0.20146 0.03519
1 25 13.48736 -1.84775 -0.32753 0.04818
1 50 13.12334 -1.04283 -0.52846 0.06176
(Page 2 of 3)
Polynomial Coefficients
for a Third Degree Polynomial
Rainfall Storm Frequency
Zone in Years A B C D
6 2 14.09519 -4.17207 0.31773 0.00029
6 3 14.98331 -4.44963 0.35683 -0.00224
6 5 14.54762 -3.89935 0.22564 0.00674
6 10 14.35386 -3.10140 -0.01003 0.02525
6 25 16.15961 -3.48135 -0.00160 0.02677
6 50 15.67671 -2.52635 -0.26055 0.04609
(Page 3 of 3)
Polynomial Coefficients
for a Third Degree Polynomial
Rainfall Storm Frequency
Zone in Years A B C D
11 2 10.09256 -2.25031 0.01661 0.01544
11 3 9.30810 -1.21537 -0.25504 0.03590
11 5 9.02699 -0.47796 -0.46784 0.05263
11 10 10.23814 -1.23242 -0.27724 0.03685
11 25 11.68811 -1.61200 -0.25239 0.03706
11 50 9.94772 0.31312 -0.73271 0.07222
_____________
I = A + BX + CX2 + DX3 X = loge (time in minutes)
These equations were derived from the rainfall curves and are not exact representations
thereof. Appropriate values for X are 8 to 180 minutes.
EXAMPLE
Zone 6 - 50 years
_____________
I = A + BX + CX2 + DX3 X = loge (time in minutes)
I = 15.67671 - 2.52635X - 0.26055X2 + 0.04609X3
_____________
* These values are provided for comparison purposes only, since the regression
equations are not valid beyond a 3-hour period.
Figure B-1: Kinematic Wave Formula for Determining Overland Flow Travel Time
Figure B-2: Overland Flow Velocities for Various Land Use Types
Ref: Chapter 15, Part 630, National Engineering Handbook, May 2010
Figure B-4: Regions for USGS Regression Equations – Natural Flow Conditions
_____________
Reference: Hammett and DelCharco (2001).
Figure B-5: Regions for USGS Regression Equations for Natural Flow Conditions in
West Central Florida
APPENDIX
TABLE OF CONTENTS
Figure C-1 Area, Hydraulic Radius, and Top Width of Trapezoidal Channels
Figure C-2 Normal Depth Velocity for a General Cross Section
Normal Depth Velocity in a Circular Pipe
Figure C-3 Normal Depth in a Trapezoidal Channel
Figure C-1 can be used to solve Example C.1 below and the Geometry of Examples
3.1-1 through 3.1-4 in Chapter 3 of this document.
1 1 ft 1
4 4
2.9 ft
Calculate: Area, Wetted Perimeter, Hydraulic Radius, Top Width, and Hydraulic
Depth
Water Area
A a bd zd 2
a (2.9 1) 4(1) 2 6.9 ft 2
Wetted Perimeter
P b 2d z 2 1
P 2.9 (2 1) 4 2 1 11.146 11.1 ft
Hydraulic Radius
bd zd 2
Rr
b 2d z 2 1
(2.9 1) 4(1) 2
r 0.619 0.62 ft
2.9 (2 1) 4 2 1
Top Width
T b 2 zd
T 2.9 (2 4 1) 10.9 ft
Hydraulic Depth
A 6.9
D 0.63 ft
T 10.9
This example is solved in the lower right hand corner of Figure C-1
Determine Normal Depth for Standard Ditch and Narrow Ditch given in Chapter 3,
Example 3.1-4 using Figure C-3.
Standard Ditch:
Qn (25)(0.04)
Solve for 8 1
8 1
0.193
b 3S 2
5 3 (0.005) 2
d
From Figure C-3, 0.22
b
Using a trial and error procedure to solve Manning’s Equation, normal depth = 1.12’
Narrow Ditch:
Qn (25)(0.04)
Solve for 8 1
8 1
0.501
b 3S 2
3.5 3 (0.005) 2
d
From Figure C-3, 0.34
b
Using a trial and error procedure to solve Manning’s Equation, normal depth = 1.25’
Figure C-4: Open Channel Geometric Relationships for Various Cross Sections
APPENDIX
TABLE OF CONTENTS
D.1 INTRODUCTION
Gutter flow is a form of open channel flow. Most gutter flow is associated with pavement
drainage and storm drain design, and is, therefore, discussed in Storm Drain Design,
Chapter 6 of this document. Some situations may warrant a more detailed approach to
gutter flow than presented in the Storm Drain Chapter. The gutter flow equation is:
0.56 5 3 8 3 12
Q SX T S
n
where:
Q = Discharge, in ft3/sec
T = Spread, in ft
The gutter flow equation is a normal depth equation that can be used in a manner
similar to Manning’s Equation. The slope of the energy gradient is the same as the
longitudinal slope of the gutter for normal depth of flow in the gutter. The equation
cannot be solved if the slope is zero or negative. While zero and negative slope
conditions should be avoided when designing a project, you will sometimes encounter
these conditions when analyzing existing or retrofit situations.
You can use the HEC-RAS model to analyze open channels with flat or reverse slopes,
so HEC-RAS is applicable to analyzing gutter flow with zero or negative slopes. In HEC-
RAS, the friction losses between cross sections are estimated using Manning’s
Equation. The Manning’s roughness coefficient can be adjusted, in effect, to make
HEC-RAS use the gutter flow equation to determine the friction losses.
If the gutter has a typical triangular cross section, such as a gutter against a curb or
barrier wall, the area and the hydraulic radius can be solved using the cross slope, S X,
and the spread, T:
SXT 2
A
2
P T
where:
P = Wetted perimeter, in ft
A SXT 2 SXT
R
P 2T 2
2
1.486 S X T 2 S X T 3 12 1.486 5 8 1 0.47 5 3 8 3 12
Q S S X 3T 3 S 2 SX T S
n 2 2
2
(2)2 n3 n
Therefore, Manning’s Equation can be manipulated to solve the gutter flow equation if
the Manning’s roughness coefficient is reduced by a ratio of 0.47/0.56 = 0.84. The
roughness value normally used in gutter analysis is 0.016 (see Appendix B, Table B-2).
The reduced value that should be used in HEC-RAS is 0.0134 or 0.013.
The shoulder will not be warped to provide a grade along the barrier wall. Instead, the
water collecting against the barrier will be allowed to seek out the nearest inlet despite
the flat grade. Pipe will be installed parallel to the barrier wall to connect the inlets.
Occasionally, a pipe will be jacked and bored under the existing lanes to outfall the flow
from the median storm drain systems. The maximum distance between inlets will be
500 feet. Analyze the maximum spread next to the barrier wall.
D.2.1 Solution
The flow is assumed to divide halfway between the two inlets and flow in both
directions. So the flow from one side of the inlet comes from 250 feet away. Table D-1
shows the flow rate at each cross section that will be used in the HEC-RAS analysis.
Calculate the flow rates using the rational equation. Calculate the drainage area by
multiplying the width of 36 feet by the distance from the midway point between the
inlets. The rainfall intensity used is four inches per hour. The runoff coefficient is 0.95.
The total flow into the inlet is 2 x 0.785 = 1.67 cfs. The capacity chart for a Type D DBI
from Appendix I (Inlet Efficiencies) shows that the depth above the inlet is less than 0.1
feet (which is a conservative estimate of the capacity of a barrier wall inlet). This depth
will be lower than critical depth, so the profile in HEC-RAS will start at critical depth.
Critical depth is not affected by the adjustment to Manning’s “n” because critical depth is
independent of the channel roughness.
The geometry of the shoulder next to the barrier wall is entered into HEC-RAS at
Station 0, which will be next to the inlet. See Figure D-1, below:
The flow data is entered. A flow of 0.01 cfs is entered at Station 250 because HEC-RAS
cannot use a value of zero when analyzing Steady State conditions. The downstream
boundary condition is set at critical depth. Figure D-2, below, shows the computed
profile:
The top width, which is equivalent to the spread, does not exceed six feet. Therefore,
the inlets prevent spread onto the travel lanes with a considerable safety factor.
Although spread will not be a problem, nuisance ponding will probably develop since the
elevation along the barrier will not be perfectly level. Although this will not be a hazard,
silt will collect next to the barrier and may require more maintenance.
APPENDIX
TABLE OF CONTENTS
Figure E-1: Circular Pipe Partial Flow Capacity Chart .................................................. E-1
Figure E-2: Circular Pipe Relative Flow, Area, Hydraulic Radius, and Velocity ............ E-2
Figure E-3: Horizontal Elliptical Pipe Relative Flow, Area, and Velocity ....................... E-2
Figure E-4: Vertical Elliptical Pipe Relative Flow, Area and Velocity ............................ E-3
Figure E-5: Pipe-Arch Relative Flow, Area, and Velocity ............................................. E-3
Qn
Q = Flow Rate (cfs)
D8 3 S 1 2
D = Pipe Diameter (ft)
S = Pipe Slope (ft/ft)
d = Normal Depth (ft)
Ref 1987 FDOT Drainage Manual
Figure E-1: Circular Pipe Partial Flow Capacity Chart
Figure E-2: Circular Pipe Relative Flow, Area, Hydraulic Radius, and Velocity
Figure E-3: Horizontal Elliptical Pipe Relative Flow, Area, and Velocity
Figure E-4: Vertical Elliptical Pipe Relative Flow, Area and Velocity
APPENDIX
TABLE OF CONTENTS
Table F-1: Application Guidelines for Pipe End Treatments - Part A ............................F-1
Table F-2: Application Guidelines for Pipe End Treatments - Part B ............................F-2
U Type Concrete
430-010 Single 15" thru 30" Limited Limited Yes Yes Fair 0.7
With Grate
430-011 U Type Concrete Single 15" thru 30" Limited No Yes Limited Good 0.5 to 0.7
Concrete Energy
430-012 Single 30" thru 72" Limited No No No NA NA
Dissipater
Cross Drain
Single & Multiple
430-021 Mitered End Yes No Yes Yes Fair 0.7
15” thru 72"
Section
0.7 w/o,
Side Drain Mitered Single & Multiple
430-022 No Yes No Yes Fair 1.0 w/
End Section 15” thru 60"
grate
430-031 Straight Concrete Single & Double 60" Yes No Limited Yes Excellent 0.2
430-032 Straight Concrete Single & Double 66" Yes No Limited Yes Excellent 0.2
430-033 Straight Concrete Single & Double 72" Yes No Limited Yes Excellent 0.2
430-034 Straight Concrete Single 84" Yes No Limited Yes Excellent 0.2
430-040 Winged Concrete Single 12" thru 48" Yes No Yes Yes Very Good 0.3
LEGEND:
(a) For back of sidewalk location, see Standard Plans, Index 425-060.
(b) For temporary construction or use on a minor facility.
(c) Construction of optional toewall and concrete jacket may be necessary. Flared end
section sizes 12 inch and 15 inch may be located as close as 8 feet beyond the
outside edge of the shoulder.
(d) Mitered end section sizes 15 inch, 18 inch, and 24 inch may be located as close
as 8 feet beyond the outside edge of the shoulder.
(e) Mitered end section size 30 inch and larger does not require a grate if pipe is
located outside CZ and is offset from approach ditch alignment.
NOTES:
1. All end treatments must be selected to satisfy hydraulic suitability with proper
consideration given to safety and economics.
2. CZ denotes clear zone; it was formerly CRA, denoting clear recovery area.
3. Grates should not be placed on outlet ends unless positive debris protection is
provided at inlet end.
4. Additional notes concerning application restrictions may be shown on individual
indexes.
5. Economic ratings are based on statewide average costs.
6. End treatments with a Ke of 0.5 or greater should be used only in areas of low
design velocities and negligible debris.
7. Pipe sizes are circular, Class III B wall, concrete pipe. Elliptical pipe and corrugated
pipe are to be checked for fit. Metal pipe sizes should be reviewed using 2 ⅔-inch
x ½-inch corrugation up to 30 inches and 3-inch x 1-inch corrugation for larger
sizes.
APPENDIX
G. RISK EVALUATIONS
TABLE OF CONTENTS
G. RISK EVALUATIONS
G.1 Risk Evaluation
All designs with floodplain encroachments should include an evaluation of the inherent
flood-related risks to the highway facility and to the surrounding property. In the traditional
design process, the level of risk is seldom quantified, but is instead implied through the
application of predetermined design standards. For example, the design frequency,
backwater limitations, and limiting velocity are parameters for which design standards can
be set.
Two other approaches, however, are available that quantify risk on projects involving
highway facilities designed to encroach within the limits of a floodplain. These are risk
assessment and economic analysis.
Consideration of capital costs and risks should include, as appropriate, a risk analysis or
risk assessment that includes:
The greatest flood that must pass through the highway drainage structure(s),
where overtopping is not practicable
Backwater
a. Is the overtopping flood greater than the design flood (100-year)?
b. Is the overtopping flood greater than the check flood (500-year)?
c. Is there potential for major flood damage from the overtopping flood?
d. Could flood damage occur even if the roadway crossing wasn't there?
e. Could flood damage be significantly increased by the backwater caused
Traffic-Related Losses
a. If the design flood is exceeded and the roadway is overtopped, is there
a detour available?
Roadway and/or Structure Repair Costs
a. Is the overtopping flood greater or less than the design flood (100-year)?
b. Is the embankment constructed from erosion-resistant material, such as
a clay type soil?
c. Does the embankment have good erosion-resistant vegetation cover?
d. How long will the duration of overtopping be?
e. Will the cost of protecting the roadway and/or structure from damage
exceed the cost of providing a relief structure?
f. Is there damage potential to the structure caused by scour, debris, or
other means during the lesser of the overtopping flood or the design
flood (100-year)?
If the risk assessment indicates the risks warrant additional study, a detailed analysis of
alternative designs and associated costs is necessary to determine the design with the
least total expected cost (LTEC) to the public.
The level of expense and effort required for an economic analysis is considerably higher
than for a risk assessment, and selection of the process to be used should be based on
the size of the project and the potential risk involved.
Further details of the economic analysis process and procedures for using it have been
documented in HEC-17 (USDOT, FHWA, 1981). The full-scale detailed risk analysis
described in HEC-17 would not be necessary for normal stream crossings, but would
apply to unusual, complex, or high-cost encroachments involving substantial flood losses.
An existing double 10-foot x 4-foot concrete box culvert (CBC) crossing is the subject for
this analysis.
Total Costs $
The following discussion estimates the additional losses associated with extending the
existing culvert and allowing the road to overtop. The losses usually consist of
embankment (and pavement), backwater, and traffic.
No embankment losses are expected. The existing road and culvert overtop, but there
is no history of embankment or pavement loss.
There will not be any additional backwater losses compared to Alternative 2. Both
Alternative 1 and Alternative 2 have essentially the same backwater characteristics.
There may be additional traffic losses associated with Alternative 1 when compared
with Alternative 2, which would raise the road to reduce overtopping potential. Traffic-
related costs consist of running time costs, lost time costs, and accident costs.
Running time costs were estimated, lost time costs were ignored (detour length added
only 1 mile to the travel distance), and accident costs were estimated but were found
to be insignificant.
1 day for 25-year storm event (roadway tops at about a 17-year event)
2 days for 50-year storm event
3 days for 100-year storm event
4 days for 200-year storm event
The additional detour distance is 0.5 mile on a two-lane undivided roadway and 0.5
mile on a four-lane divided roadway.
Additional running costs = Cost per mile x ADT x additional detour length (miles)
Assume cost per mile = $0.35/mile
Additional accident costs: These are additional costs due to increased travel distance
due to the need to detour.
Get the crash rate and the cost per crash from the FDOT Safety Office.
Crash rate = 1.9 crashes/million vehicle miles for urban, two-lane, undivided
roadways
0.8 crashes/million vehicle miles for urban, four-lane, divided
roadways
Cost per crash = $28,000 for urban, two-lane, undivided roadways
$26,000 for urban, four-lane, divided roadways
Using the same method, with 50-year detour = 2 days, 100-year detour = 3 days,
and 200-year detour = 4 days:
$50 = $2,016.50
$100 = $3,024.75
$200 = $4,033.00
Traffic losses in the following table are the sum of increased running costs and
increased accident losses.
10 0.1 0
15 0.07 0
25 0.04 10,546.25
50 0.02 21,091.50
0 42,183.00
This alternative would overtop at frequencies greater than the 50-year storm event and
would, therefore, have some annual risk costs. These risks were not calculated because
the annual cost alone is greater than the total cost for Alternative 1. If the capital costs for
Alternative 2 were less than the total cost for Alternative 1, it would be necessary to
calculate the other costs associated with this alternative.
Roadway fill and new base and asphalt. At a minimum, 900 feet of roadway would
have to be rebuilt to raise the grade to meet the bridge. (Bridge would be raised to
meet FDOT drift clearance requirements.)
Standard 1H:2V front slopes encroach into roadside ditches. Since the upstream
roadside ditch conveys substantial flow, it may not be possible or wise to reduce
its capacity. Vertical walls and/or additional right of way may be necessary.
Alternative 1 is the most economical alternative and the most desirable when considering
other impacts.
APPENDIX
If the profile grade line (PGL) of the road is flat, there will be a slope away from the
bridge created by the shoulder/gutter transition. The degree of slope will depend on the
width of the shoulder and the cross slopes of the bridge deck and the roadway shoulder.
Figure H.1 shows a transition with a 10-foot shoulder and standard cross slopes for the
bridge deck and roadway shoulder.
The drop from the edge of the travel lane to the bottom of the gutter at the end of the
bridge barrier wall is:
10’
4”
8’
The drop from the edge of the travel lane to the bottom of the gutter at the end of the
transition is:
The drop of the gutter bottom in the transition is 0.730 – 0.206 = 0.524 feet. The length
of the transition is 25 feet. The slope of the bottom of the gutter is 0.524/25 = 0.0210, or
2.10%.
APPENDIX
I. INLET EFFICIENCIES
TABLE OF CONTENTS
D I T C H B O T T O M I N L E T C A P A CI T Y
Fo r C o n d it io n s W h e re th e H G in th e Bo x is B e lo w th e G ra te
30
T yp e H re t .
20
T yp e G .
FLOW (cfs)
T yp e D & E re t.
T yp e H c .i .
T yp e E c . i.
T yp e F
T yp e C re t .
10
T yp e C c . i.
0
0 0.5 1 1.5 2
HEAD (ft) above Grate Top
1. The above graph should be used where the hydraulic gradient in the inlet box is below
the top of the grate. For other conditions, see the discussion below.
2. The above is based on 50% debris blockage and inlets without slots.
3. The symbols on the curves do not represent-measured data points. They are
calculated points from the equation and coefficients in the research report by the
University of South Florida titled “Investigation of Discharge through Grated Inlets”,
February 1993, WPI No. 0510611. Contact the FDOT Research Center at 850-414-
4615 to obtain a copy. The grate flow areas used in the equations are from U.S.
Foundry & Mfg. Corp.
Where the hydraulic gradient is above the top of the grate, the system capacity may
control the flow through the grate. The total system loss is a sum of friction losses
and various minor losses, including the loss across the grate. In this situation, the
loss across the grate is typically small but can be calculated from:
2
Vg
Head Loss [feet] = K
2g
Vg2
K
2g
Where K = 0.46 for reticuline grates; 3.2 for cast iron grates
Vg = velocity [fps] across the grate based on the grate full face area
(grate width x grate length)
g = acceleration of gravity
Example:
A DBI is needed to capture 5 cfs in a depressed area behind the sidewalk. The
hydraulic gradient due to friction loss in the system is estimated to be 0.8 ft above the
grate.
This is an insignificant amount of head loss and is typical of most design situations.
Where a DBI accepts high flow rates (usually under high head conditions) as perhaps
in a stormwater pond, the additional loss could be substantial and may dictate a larger
inlet (large grate area.)
APPENDIX
Table J-1: Coefficient of Permeability (k) for Saturated and Compacted Laboratory
Soil Specimens
SOIL TYPICAL SOIL CLASSIFICATION PERMEABILITY
NAME UNIFIED AASHTO (ft/day)
Well-graded gravels or gravel- GW A-3 300 to 0.3
sand mixtures with little or no Pervious
fines
Poorly graded gravels or gravel- GP A-3 3 x 104 to 30
sand mixtures with little or no Very pervious
fines
Silty gravels, gravel-sand-silt GM A-2-4 3 to 3 x 10-3
mixtures Semi-pervious to
pervious
Clayey gravels, gravel-sand-clay GC A-2-6 3 x 10-3 to 3 x 10-5
mixtures Impervious
Well-graded sands or gravelly SW A-3 30 to 0.3
sands with little or no fines Pervious
Poorly graded sands or gravelly SP A-3 300 to 3
sands with little or no fines Pervious
Silty sands, sand-silt mixtures SM A-2-4 3 to 3 x 10-3
Semi-pervious to
pervious
Clayey sands, sand-clay mixtures SC A-6 3 x 10-3 to 3 x 10-5
Impervious
Inorganic silts and very fine ML A-6 3 to 3 x 10-3
sands, rock flour, silty or clayey Semi-pervious to
fine sands or clayey silts with pervious
slightly plasticity
Inorganic clays of low to medium CL A-7 3 x 10-3 to 3 x 10-5
plasticity, gravely clays, sandy Impervious
clays, silty clays, lean clays
Organic silts and organic silty OL A-6 0.3 to 3 x 10-3
clays of low plasticity Semi-pervious to
pervious
Inorganic silts, micaceous or MH A-6 0.03 to 3 x 10-4
diatomaceous fine sandy or silty Semi-pervious to
soils, elastic silts pervious
Organic clays of high plasticity, CH A-8 3 x 10-3 to 3 x 10-6
fat clays Impervious
NOTE: Table adapted from Drainage Manual Volume 2, FDOT 1987.
APPENDIX
1) The report should provide a reasonable assurance that the buoyant stormwater
discharge into a Class G-III aquifer (total dissolved solids greater than 10,000 mg/L) via
the drainage well(s) has a minimum potential to:
Document the existence of sufficient confining strata above the base of the well
casing, to minimize the potential of injected buoyant stormwater to rise into a G-II
aquifer system.
Show the injected stormwater has minimum potential to impact any surface water
bodies in the vicinity of the project that may be affected via groundwater
discharge.
Show the pressurization of the well due to its location at elevation + XXX feet or
receiving stormwater flow from a building roof elevation + XXX feet will not cause
mounding that may rise into USDW and/or manifest as a spring on a land
surface.
2) The report may be submitted at this time or its submission may be deferred until the
stormwater drainage well(s) construction permit has been issued. However, it must be
submitted for Department review and approval prior to the Department’s authorization to
use the stormwater drainage well(s).
3) Indicate whether you wish to submit this report before or subsequent to Department
issuance of a stormwater drainage well construction permit. The Department strongly
advises the former option to most efficiently achieve the operational authorization of the
well(s).
4) Note that no fluid should be discharged into the stormwater drainage well(s) without
written authorization from the Department to use the well(s).
5) Issuance of a well construction permit does not obligate the Department to authorize
the use of well(s), unless the well(s), information required by the permit, and this report
qualifies for an authorization.
APPENDIX
APPENDIX
TABLE OF CONTENTS
Figure M-1: Estimated Service Life – 16 ga. Galvanized Steel Pipe ........................... M-1
Table M-1: Estimated Service Life – 16 ga. Galvanized Steel Pipe ............................ M-2
Figure M-2: Estimated Service Life – 16 ga. Aluminized Steel Pipe ............................ M-3
Table M-2: Estimated Service Life – 16 ga. Aluminized Steel Pipe ............................. M-4
Figure M-3: Estimated Service Life – 16 ga. Aluminum Pipe ...................................... M-5
Table M-3: Estimated Service Life – 16 ga. Aluminum Pipe........................................ M-6
Figure M-4: Estimated Service Life – 60” Dia. Reinforced Concrete Pipe, S = 1500... M-7
Table M-4: Estimated Service Life – 60" Dia. Reinforced Concrete Pipe, S = 1500 .... M-8
Figure M-4: Estimated Service Life – 60” Dia. Reinforced Concrete Pipe, S = 1500
Table M-4: Estimated Service Life – 60" Dia. Reinforced Concrete Pipe, S = 1500
Chlorides
pH 15000 13000 11000 9000 7000 5000 3000 2000 1000 750 500 250
5.0 88 93 99 107 118 135 164 192 250 278 324 360
5.1 89 94 101 109 119 136 165 193 251 279 325 360
5.2 90 95 102 110 121 137 167 194 252 281 327 360
5.3 91 96 102 111 122 138 167 195 253 282 327 360
5.4 92 97 103 111 122 139 168 196 253 282 328 360
5.5 92 97 103 112 123 139 168 196 254 282 328 360
5.6 93 98 104 112 123 140 169 196 254 283 329 360
5.7 93 98 104 112 123 140 169 197 254 283 329 360
5.8 93 98 104 113 124 140 169 197 255 283 329 360
5.9 93 98 105 113 124 140 170 197 255 284 330 360
≥6.0 94 99 105 113 124 141 170 197 255 284 330 360
Conversion Factors for Different Size Culverts SL Reduction Factors for Sulfates
Pipe Dia. Mult. By Pipe Dia. Mult. By Sulfate Content Subtract from SL
12” 0.36 48” 0.76 1500 0
18” 0.36 60” 1.00 3200 5
24” 0.41 72” 1.25 4900 10
30” 0.48 84” 1.51 6600 15
36” 0.54 96” 1.77 8300 20
42” 0.65 108” 2.04 10000 25
Note: Sulfate derating not applicable
when Type V cement is used.
APPENDIX
The overriding standards of the Stormwater Rule are the state’s water quality standards
and appropriate regulations established in other FDEP rules. Therefore, an application
for a stormwater discharge permit must provide reasonable assurance that stormwater
discharges will not violate state water quality standards. Because of the potential
number of discharge facilities and the difficulties of determining the impact of any facility
on a waterbody or the latter’s assimilative capacity, the Department decided that the
Stormwater Rule should be based on design and performance standards.
3. Runoff Pollutant Loads - The first flush of pollutants refers to the higher
concentrations of storm water pollutants that characteristically occur during the
early part of the storm with concentrations decaying as the runoff continues.
Concentration peaks and decay functions vary from site to site depending on
land use, the pollutants of interest, and the characteristics of the drainage basin.
Florida studies (6, 7) indicated that for a variety of land uses the first .5 inch of
runoff contained 80-95 percent of the total annual loading of most stormwater
pollutants. However, first flush effects generally diminish as the size of the
drainage basin increases and the percent impervious area decreases because of
the unequal distribution of rainfall over the watershed and the additive phasing of
inflows from numerous small drainages in the larger watershed. In fact, as the
drainage area increases in size above 100 ac the annual pollutant load carried in
the first flush drops below 80% because of the diminishing first flush effect.
4. BMP Efficiency and Cost Data - Numerous studies conducted in Florida during
the Section 208 program generated information about the pollutant removal
effectiveness of various BMPs and the costs of BMP construction and operation.
Analysis of this information revealed that the cost of treatment increased
exponentially after “secondary treatment” (removal of 80% of the annual load)
(8).
Selection of Minimum Treatment Levels - After review and analysis of the above
information, and after extensive public participation, the Department set a
stormwater treatment objective of removing at least 80% of the average annual
pollutant load for stormwater discharges to Class III (fishable/swimmable) waters.
A 95% removable level was set for storm water discharges to sensitive waters
such as potable supply waters (Class I), shellfish harvesting waters (Class II) and
Outstanding Florida Waters. The Department believed that these treatment levels
would protect beneficial users and thereby establish a relationship between the
rule’s BMP performance standards and water quality standards.
References:
5. Wanielista, M.P., et. al. Precipitation, Inter-event Dry Periods, and Reuse Design
Curves for Selected Area of Florida. Final report submitted to Florida
Department of Environmental Regulation, 1991.
8. Wanielista, M.P., et. al. Stormwater Management Manual. Prepared for Florida
Department of Environmental Regulation, 1982.