ACTUAL /
SCHEDULED RYG
EXPECTED STATUS
DELIVERY STATUS
PROCUREMENT LONG LEAD/CRITICAL ITEMS DELIVERY
Paint for Façade (Dulux Acratex) 30th Sep’16 27 Oct’16
th Green
Steel Structures for Banquet Hall/Meeting Room Areas 22nd Oct’16 15th Nov’16 Yellow
Lift Equipment 15th Jan’17 Yellow
Transformers (6 Month lead-time) Feb’17 Red
Generators Feb’17 Red
Bus-duct 15th Nov’16 30th Dec’16 Green
Feeders Feb’17 Depend on Green
YESC
Diesel Storage Tank Feb’17 31st Jan’17 Green
HT panels/cubical Feb’17 31st Jan’17 Green
LV main MSB (MSB Total) tbc 30th Dec’16 Green
Floor by floor DBs tbc 30th Dec’16 Green
PABX tbc 30th Dec’16 Green
BOH Lighting fittings & fixtures 30th Dec’16 Green
FOH Lighting fittings & fixtures 30th Nov’16 Green
IT Servers Tbc on 28th Sep’16 Green
CCTV system Tbc on 28th Sep’16 Green
Chilled Water pumps 31st Dec’16 Green
Chillers 31st Dec’16 Green
Cooling Towers 31st Dec’16 Green
AHUs 31st Dec’16 Green
Kitchen Exhaust System 31st Dec’16 Green
Heat pumps tbc 31st Jan’17 Green
Circulation pumps tbc 31st Jan’17 Green
GRP Tank (Roof tank) 31st Jan’17 Green
20 m3 FRP Receiving tank 15th Nov’16 7th Nov’16 Green
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
Column bases not leveled Bases to be leveled off before column installation CIMAC 15th Nov’16
Gaps between existing structure & new Raft Slab Fill the gap using Grout mortar CIMAC 26th Oct’16
Shotcrete surface finish not acceptable CIMAC to request inspection with RFP CIMAC ASAP
- Revise equipment & spraying method
Flooding on Level 4 as a result of Shotcrete Overflow bay & housekeeping to be done. CIMAC ASAP
Existing stormwater gutter system Remove at Level – 5 building PR ASAP
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
Basement Access Staircase Remove shoring structure to inspect existing soil condition and propose CIMAC 20th Oct’16
method by CIMAC