Project Status Report - 42
Project Status Report - 42
RYG
SCHEDULED ACTUAL / EXPECTED STATUS
STATUS
PROCUREMENT LONG LEAD/CRITICAL ITEMS DELIVERY DELIVERY
Paint for Façade (Dulux Acratex) 30th Sep’16 27th Oct’16 Delivered
Steel Structures for Banquet Hall 22nd Oct’16 20th Jan’17 Delivery to site on 10th Feb’17
For Skylight Steel Structure: ETA 22nd
March’17. Expected delivery 31st Mar’17
Last delivery at 02nd May’17. Delivered
Steel Structures for Meeting Rooms 27th Jan’17 17th Feb’17 Arrived on site at 21st Feb’17.
Last Container to Site at 06th May’17. Delivered
Lift Equipment – First Shipment (Service Lifts) 1st Mar’07 22nd Feb’17 Shipped on 4th Feb. ETA 20th Feb’17
Revised: Delivered to site. Delivered
Lift Equipment – Second Shipment 1st Mar’07 31st Mar’17 PL (Confirmed to ship out on 31st
Mar’17)
Arrived at port on 5th Apr’17.
Custom clearance.
Arriving at site on 26th Apr’17. Delivered
Transformers & Switch Gear (5.5 Month lead-time) 25th Apr’17 15th August’17 Pending confirmation letter by YESC for
33kV – 0.4kV.
YESC approval acquired.
FAT completed.
Generators 09th Mar’17 03rd Apr’17 Custom Clearance in process. Delivered
Delivered at 1st Apr’17
Bus-duct 15th Nov’16 30th Apr’17 Shipped out on 18th May’17. Delivered
Arrived to port. Custom Clearance in
Process.
Feeders Feb’17 Depend on YESC.
Approval acquired. Road damage fees
will be paid shortly.
APQ to start work soonest possible.
Diesel Storage Tank Feb’17 22nd Mar’17 Delivered to site. Diesel
Storage
Permit to be
applied asap.
HT panels/cubical 25th Apr’17 Same as Transformers
LV main MSB (MSB Total) 13th Jan’17 14th March’17 *Waiting MIC Permit. Delivered
Delivered to site.
PROJECTED /
SCHEDULED PERCENT
ACTUAL START ACTUAL STATUS
COMPLETION COMPLETE
ACTIVITIES ONGOING FROM PREVIOUS WEEK COMPLETION
Gypsum Closing at Guestrooms L1 – including DK & DT (80% for SW) 1st Feb’17 10th Feb’17 30th Jun’17 98%
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
Paint finish not smooth at West Wing Repair after the scaffold is relocated to adjacent area GHS -
MEP penetrations through dry-walls Construct walls first and trim/cut openings to dry-wall panels after PR/JEC/Primflux KIV
Compaction after backfill of drainage Primeflux to compact using compactor/backhoe at the backfilled trench Primeflux KIV
Damage on Zinc Oxide Paint on Steel Structures Touch-up with zinc phosphate primer before fireproof coating CIMAC Being
Rectified
Cross beam not painted. To paint base coat and fire-proof coating CIMAC Rectified.
Damaged Fireproof Paint on L5 Yoga Roof Repair the paint after roof structure installation CIMAC 13th Apr’17
CONDUITING IN KITCHEN AREAS NO EXPOSED CONDUITS IN ALL KITCHEN AREAS. PR / PF / JEC / KIV
AMT
Gap between Floor slab and floor beam at Lift Shafts Fill grout between the gap HTH KIV
Sealant underneath dry-walls Inject sealant underneath dry-walls for every area. KANOK Rectified.
Waterproofing membrane between Drywall and Slab Apply stick-on waterproofing membrane and complete before topping work PR
commence.
Peeled off fireproof paint on steel structure Re-apply fireproof paint at peeled off areas. CIMAC 05th May’17
Waterproofing for L2 Slab at CY2 Apply waterproofing membrane as soon as possible. CIMAC -
PU Foam installation around window frames. Make sure the foam is fully inserted into the frame and voids. KAMA 06th May’17
QA/QC meeting proposed at 1:30 every Thursday *Senior management personnel & in-charge to attend QA/QC meeting.
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
Lifting Method Statement PF to get approval from PR Safety Officer PF 23rd Jun’17
Testing Method for Rooftank PF to propose PF 27th Jun’17
MISCELLANEOUS ISSUES