Project Status Report - 44
Project Status Report - 44
RYG
SCHEDULED ACTUAL / EXPECTED STATUS
STATUS
PROCUREMENT LONG LEAD/CRITICAL ITEMS DELIVERY DELIVERY
Paint for Façade (Dulux Acratex) 30th Sep’16 27th Oct’16 Delivered
Steel Structures for Banquet Hall 22nd Oct’16 20th Jan’17 Delivery to site on 10th Feb’17
For Skylight Steel Structure: ETA 22nd
March’17. Expected delivery 31st Mar’17
Last delivery at 02nd May’17. Delivered
Steel Structures for Meeting Rooms 27th Jan’17 17th Feb’17 Arrived on site at 21st Feb’17.
Last Container to Site at 06th May’17. Delivered
Lift Equipment – First Shipment (Service Lifts) 1st Mar’07 22nd Feb’17 Shipped on 4th Feb. ETA 20th Feb’17
Revised: Delivered to site. Delivered
Lift Equipment – Second Shipment 1st Mar’07 31st Mar’17 PL (Confirmed to ship out on 31st
Mar’17)
Arrived at port on 5th Apr’17.
Custom clearance.
Arriving at site on 26th Apr’17. Delivered
Transformers & Switch Gear (5.5 Month lead-time) 25th Apr’17 15th August’17 Pending confirmation letter by YESC for
33kV – 0.4kV.
YESC approval acquired.
FAT completed.
Generators 09th Mar’17 03rd Apr’17 Custom Clearance in process. Delivered
Delivered at 1st Apr’17
Bus-duct 15th Nov’16 30th Apr’17 Shipped out on 18th May’17. Delivered
Arrived to port. Custom Clearance in
Process.
Feeders Feb’17 Depend on YESC.
Approval acquired. Road damage fees
will be paid shortly.
APQ to start work soonest possible.
Diesel Storage Tank Feb’17 22nd Mar’17 Delivered to site. Diesel
Storage
Permit to be
applied asap.
HT panels/cubical 25th Apr’17 Same as Transformers
LV main MSB (MSB Total) 13th Jan’17 14th March’17 *Waiting MIC Permit. Delivered
Delivered to site.
PROJECTED /
SCHEDULED PERCENT
ACTUAL START ACTUAL STATUS
COMPLETION COMPLETE
ACTIVITIES ONGOING FROM PREVIOUS WEEK COMPLETION
Gypsum Closing at Guestrooms L1 – including DK & DT (85% for SW) 1st Feb’17 10th Feb’17 30th Jun’17 98%
SL 1, 2 Structure Work 10th Mar’17 10th Apr’17 24th Jun’17> 4th
July’17 > 10th July >
17th July’17 90%
PL4 Structure – including brickwork 05th Apr’17 24th Jun’17>4th
July’17 >10th July>
17th July’17 85%
Brickwork at Internal Façade – including plastering work 1st Apr’17 30th May’17 25th July’17 95%
Sanitary Ware Installation – L3 (Shower Mixer & Mixing Valve) 02nd May’17 09th May’17 65%
Cable Laying in UG Cable Trench 30th July’17 15th July’17 15th Aug’17 *Generator
Room Cable
ladder
installation
Gutter Installation at Roofs 19th May’17 3rd Jun’17 30th Jun’17 > 7th *To do flow
July’17> 13th July’17 test in every
95% gutter
Piping connection for Level 5 Guestrooms 01st July’17 06st July’17 > 14th Jul’17 21st Jul’17
Waterproofing Works at Courtyards and Roof 13th July’17
Vent Pipe Installation at Level 5 Workshop Roof 15th Jul’17
Epoxy Flooring at Kitchen Area
Roller Shutter Installation at Loading Dock
Sand filling and compaction at Strand Road Driveway 17th July’17
PU Injection at new structure cracks
QUALITY ISSUES
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
QA/QC meeting proposed at 2:00pm every Thursday *Senior management personnel & in-charge to attend QA/QC meeting.
- JECM, Primeflux, Kama, 29, Kanok CIMAC, Brickwork Contractors
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
MISCELLANEOUS ISSUES
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
Housekeeping Day Every Saturday @ 9 AM: All contractors to provide TWO labors to PR office to clean one particular All contractors KIV
area every week led by PR Safety Officer
Mock-Up Inspection Completed on 02nd of March 2017 PR/ Kanok 10th Apr’17
Second inspection to be confirmed. All defects needs to be resolved.
Underground Utilities All underground utilities to be completed in February for road and paving works. Primeflux 28th Feb’17
The activities are two weeks late according to current status.
Storm water drainage connections To be completed in early April in preparation for rain Primeflux April’17
Hot Works unsupervised All contractors to inform PR Safety and acquire Hot Work Permit for any hot work executed on-site. All Contractors KIV