Method Statement For Plumbing System HDPE Drainage System
Method Statement For Plumbing System HDPE Drainage System
Page 1 of 4
1.0 Scope
1.1 This method statement details the method for installation and testing of
underground HDPE drainage piping.
2.0 Material
2.2 Equipment
4.0 Method
4.1 Storage
4.1.1 When off loading pipes shall be lowered to the ground either manually
or with mechanical aid like crane depending on the quantity of the pipe
and should not be dropped to the ground. Refer – Manufacturer’s
instruction for transport, handling and storage.
4.1.2 Pipes shall be stacked on a flat surface free from any sharp objects.
4.1.3 Pipes shall not be stored under direct sunlight to avoid ultra violet
degradation.
4.2 Installation
A. Pipe fabrication:
Fabricate pipe as much as you can in the workshop according to sizes as per
drawings to be ready for installation.
Page 2 of 4
After the completion of marking points ,fix the line with the
required levels.
4.4 Back-Filling
4.4.1 Filling around the pipes shall be done with the same bedding material
and be throughly compacted.
Page 3 of 4
5. Testing
5.1 Water test is conducted to ensure and prove the tightness of the joints and
ensure there are no leaks in the piping system.
5.2 The water pressure test can be applied to the system in its entirety or in sections.
All openings in the piping will be tightly closed, the system filled with water to
the point of overflow from the highest point. The plugs can be temporally
opened to make sure that all air has been vented and that water has reached all
parts of the system.
5.3 No section of the pipe shall be tested to less than 1.5-meter head of water.
5.4 The water shall be kept in the system or in the portion under test for at least 30
minutes before inspection starts. While the system is under pressure, a careful
inspection shall be made on all pipes and joints. If any leaks in joints or
evidence of defective pipe or fittings is revealed, the defective pipe / fitting
should be immediately replaced with new joints and materials.
5.5 After the correction is made, the test pressure will be maintained for minimum
30 minutes.
Page 4 of 4