Earth Work Excavation and Depositing On Bank

This document provides an estimate for the construction of a stilt + 2 upper floor building located in Macha Bollarum, Alwal, Telangana. It includes 21 line items detailing the quantities, rates, and amounts for various construction works such as earthwork excavation, laying of PCC and stone masonry, RCC works for floors, brick masonry, plastering, flooring, waterproofing, overhead water tank, borewell, compound wall, electrical works, and more. The total estimated construction cost is Rs. 78,00,000.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
208 views

Earth Work Excavation and Depositing On Bank

This document provides an estimate for the construction of a stilt + 2 upper floor building located in Macha Bollarum, Alwal, Telangana. It includes 21 line items detailing the quantities, rates, and amounts for various construction works such as earthwork excavation, laying of PCC and stone masonry, RCC works for floors, brick masonry, plastering, flooring, waterproofing, overhead water tank, borewell, compound wall, electrical works, and more. The total estimated construction cost is Rs. 78,00,000.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ABSTRACT ESTIMATION FOR THE PRO. STILT + 2 UPPER FLOOR BUILDING ON HOUSE NO.

2-
2-123/31, ON PLOT NO.237, SY.NO.156, SITUATED AT MACHA BOLLARUM, ALWAL (M) GHMC
ALWAL CIRCLE,MEDCHAL MALKAJGIRI DIST. TS.
BELONGING TO SRI.CHILAKALA PAND.

SNO DESCRIPTION QTY Rate/ Unit Amount


1 Earth work excavation and depositing on bank 3890.00 10.00 Cft 38900.00
With an initial lead of 15 mts and lift of 1.5 mts
For hard gravely soils for foundation including
Cost of lab our, materials equipment etc.,

2 Laying PCC 1:4:8 prop. Using 40 mm hard 895.00 75.00 Cft 67125.00
Granite metal including cost and convenience
Of all material lab our charges equipments etc,.
And including placing, vibrating, curing etc.,
Complete for base course of columns footings
And below masonry walls as per the specification.

3 CRS stone masonry second sort in cm 1:6 1200.00 85.00 Cft 102000.00
Prop using hard broken granite stone and bond
Stone at relevant intervals including cost and
Conveyance f all material lab our charges etc

4 Base ment over damp proof course. Its with 480.00 50.00 sft 24000.00
Cement mortor with watrer proof chemical.

5 Laying of all RCC works in(1:2:4) prop.


using 20mm H.G metal including cost &
conveyance of all materials & labour
charges etc., complete.
Stilt floor 2041.25 450.00 Cft 918562.50
First Floor 932.54 450.00 Cft 419644.13
Second Floor 852.86 450.00 Cft 383788.13
6 Construction of brick mas. In CM (1:6)
prop. Using second CLASS bricks
including cost & conveyance of all materials &
labour charges etc., complete.
First Floor 1845.66 65.00 sft 119967.90
Second Floor 1854.66 65.00 sft 120552.90
7 Fixing of Teak wood frames & prov.
Teak wood shutters Fittings ect.
Stilt floor
First Floor 279.50 1000.00 sft 279500.00
Second Floor 270.50 1000.00 sft 270500.00
8 Providing Plastering in CM(1:3) & (1:5)
prop. In two coats including cost &
conveyance of all materials and labour
charges etc., complete.
Stilt floor 1590.00 60.00 sft 95400.00
First Floor 5480.50 60.00 sft 328830.00
Second Floor 5489.50 60.00 sft 329370.00
9 Providing marble slab of 20 mm.Flooring and Scarting
in all Rooms. including cost & conveyance
of all materials and labour charges etc.,
Stilt floor
First Floor 980.16 125.00 sft 122520.00
Second Floor 980.16 125.00 sft 122520.00
10 a) Two coats of Birla Putty finishing with water
proof emulsion Paint in all rooms and doors & windows.
Material & labour etc.
First Floor 3520.00 35.00 sft 123200.00
Second Floor 3520.00 35.00 sft 123200.00
b) External walls for water prof emulsion and 1590.00 10.00 sft 15900.00
pearl white Mat finshing at requied places . 1590.00 10.00 sft 15900.00
1590.00 10.00 sft 15900.00
11 Water proofing to terrace in brickbat Coba and
with Approved Water Proofing Compound in
Recommonded proportions.
Stilt floor 960.00 100.00 sft 96000.00
First Floor 960.00 100.00 sft 96000.00
Second Floor 960.00 100.00 sft 96000.00
12 Under Ground sump in RCC with RCC cover slab,
partition for drinking water and CI man hole with ….. L.Sum ….. 35000.00
covers .

13 Over head water tank in RCC with RCC ….. L.Sum ….. 40000.00
Cover slab. With MS lader.

14 Bore well with Branded elecrtical motor . ….. L.Sum ….. 80000.00

15 Compound Wall In CRS Masonry of 300mm thick,


Bk work .75 cm thick 5-0' height, both side two
Coat plastering and ms gate. ….. L.Sum ….. 75000.00

16 Granite slab Top of 20 mm and 10 mm thick over


Kitchen platform with skirting of 4” th and wall dado ….. L.Sum 30000.00
Of 7’ height over kitchen platform, f approved size
And colour and full mounding the edges
In ground floor and first floor.
17 Flooring Dadoing to walls of toilets with Glazed
Ceramic tiles of approved make, size and colour.
First Floor 744.00 100.00 sft 74400.00
Second Floor 744.00 100.00 sft 74400.00

18 Add front elevation Inclu. Material & labour etc. ….. L.Sum ….. 120000.00

19 Add stair cases for stilt +ground+first ….. L.Sum ….. 60000.00

20 Cement tiles for out side flooring. ….. L.Sum ….. 65000.00

21 Add Lift for all floors with branded ….. L.Sum ….. 400000.00

Total…. 5379080.55
21 Add 10 % for superior quality electrical fixures. ….. ….. ….. 537908.06

22 Add 12 % for quality sanitary & water supply fixures. ….. ….. ….. 645489.67

construction cost Rs 6562478.27


23 Interios for first floor and second floor
First Floor
a Cubords and ward robes , kitchen cabine ect ….. L.Sum ….. 500000.00
b Add falce ceiling ….. L.Sum ….. 120000.00
Second Floor
c Cubords and ward robes , kitchen cabine ect ….. L.Sum ….. 500000.00
d Add falce ceiling ….. L.Sum ….. 120000.00
Total Rs 7802478.27
(Ruppes Seventy Eight lakhs only) Or Say Rs 78,00,000/-

Date : Sig Of Reg. Architect