Engineer1, Engineer2, Engineer3 Engineer4, Engineer5, Engineer6 Engineer1

The document outlines a technology project with 12 tasks over 16 weeks. It involves developing features for a student-teacher interphase including chat options, interrupt options, recording, community platform, and payment integration. The tasks require multiple engineers with dependencies between tasks. The project is scheduled to finish on August 3rd after 16 weeks of work.

Uploaded by

cs55cs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views1 page

Engineer1, Engineer2, Engineer3 Engineer4, Engineer5, Engineer6 Engineer1

The document outlines a technology project with 12 tasks over 16 weeks. It involves developing features for a student-teacher interphase including chat options, interrupt options, recording, community platform, and payment integration. The tasks require multiple engineers with dependencies between tasks. The project is scheduled to finish on August 3rd after 16 weeks of work.

Uploaded by

cs55cs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Start Finish Predecessors Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week

2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
Mode
1 Technology 50 days Tue 26-05-20Mon 03-08-20

2 Student Interphase20 days Tue 26-05-20 Mon 22-06-20 Engineer1,Engineer2,Engineer3

3 Teacher Interphase20 days Tue 26-05-20 Mon 22-06-20 Engineer4,Engineer5,Engineer6

4 Chat Option 10 days Tue Mon 2,3 Engineer1


(Platform) 23-06-20 06-07-20

5 Interrupt Option 10 days Tue Mon 4 Engineer1


(Raise a Doubt) 07-07-20 20-07-20

6 Recording Feature 10 days Tue 07-07-20 Mon 20-07-204 Engineer5

7 Community Platform
20 days Tue 23-06-20 Mon 20-07-202,3 Engineer2,Engineer3,Engineer4

8 Roaster Management
10 days Tue 07-07-20 Mon 20-07-204 Engineer6

9 Payment Integration
10 days Tue 21-07-20 Mon 03-08-208,7,6,5 Engineer2,Engineer3,Engineer4

10 Upload Content Feature


10 days Tue 23-06-20 Mon 06-07-202,3 Engineer5

11 Chatboat(Website) 10 days Tue 23-06-20 Mon 06-07-202,3 Engineer6

12 Finish 0 days Mon 03-08-20Mon 03-08-2011,10,9 03-08

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: Project1
Milestone Inactive Summary Start-only Progress
Date: Tue 26-05-20
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 1