Project Crashing Problem

Uploaded by

Altamash Munir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

5/5/2020

Project Crashing problem


The activities necessary for automation of a machine are listed.
What is the project completion time?
Activity Pred Time t (days)

A -- 3
B A 4
C B 2
D A 5
E -- 6
F E 5
G C, D, F 4

© 2014 Pearson Education, Inc. 3 - 24

24

© 2014 Pearson Education, Inc. 3 - 25

25

1
5/5/2020

Activity Pred Time ES EF LS LF S


A -- 3 0 3 2 5 2
B A 4 3 7 5 9 2
C B 2 7 9 9 11 2
D A 5 3 8 6 11 3
E -- 6 0 6 0 6 0
F E 5 6 11 6 11 0
G C, D, F 4 11 15 11 15 0

© 2014 Pearson Education, Inc. 3 - 26

26

Activity Pred Time ES EF LS LF S

A -- 3 0 3 2 5 2
B A 4 3 7 5 9 2
C B 2 7 9 9 11 2
D A 5 3 8 6 11 3
E -- 6 0 6 0 6 0
F E 5 6 11 6 11 0
G C, D, F 4 11 15 11 15 0

© 2014 Pearson Education, Inc. 3 - 27

27

2
5/5/2020

Normal Normal Crash Crash


Activity Pred Time Cost Time Cost
A -- 3 400 2 600
B A 4 160 3 240
C B 2 200 2 200
D A 5 150 3 350
E -- 6 230 4 490
F E 5 350 3 490

C, D, F 4 300 3 450
G

© 2014 Pearson Education, Inc. 3 - 28

28

Compute the crash cost per time period. If


crash costs are linear over time:

Crash cost (Crash cost – Normal cost)


per period =
(Normal time – Crash time)
Activit Normal Normal Crash Crash Crash Cost per
y Pred Time Cost Time Cost day ($)
A -- 3 400 2 600 200
B A 4 160 3 240 80
C B 2 200 2 200 --
D A 5 150 3 350 100
E -- 6 230 4 490 130
F E 5 350 3 490 70
C, D,
4 300 3 450 150
G F
© 2014 Pearson Education, Inc. 3 - 29

29

3
5/5/2020

© 2014 Pearson Education, Inc. 3 - 30

30

Project Crashing problem


Determine the minimum total cost of reducing the project completion date by 4 days.
Give a complete plan to the manager highlighting the cost of reduction for each day.

Activity Pred Normal Crash Crash


Time t Time Cost per
(days) (days) day ($)
A -- 3 2 200
B A 4 3 80
C B 2 2 --
D A 5 3 100
E -- 6 4 130
F E 5 3 70
G C, D, F 4 3 150
© 2014 Pearson Education, Inc. 3 - 31

31

4
5/5/2020

Crash Cost Crash


Activity Pred Time ES EF LS LF S per day ($) Time

A -- 3 0 3 2 5 2 200 2

B A 4 3 7 5 9 2 80 3

C B 2 7 9 9 11 2 -- 2

D A 5 3 8 6 11 3 100 3

E -- 6 0 6 0 6 0 130 4

F E 5 6 11 6 11 0 70 3

G C, D, F 4 11 15 11 15 0 150 3

© 2014 Pearson Education, Inc. 3 - 32

32

Crash Cost Crash


Activity Pred Time ES EF LS LF S per day ($) Time

A -- 3 0 3 2 5 2 200 2

B A 4 3 7 5 9 2 80 3

C B 2 7 9 9 11 2 -- 2

D A 5 3 8 6 11 3 100 3

E -- 6 0 6 0 6 0 130 4

F E 5 36 11 6 11 0 70 3

G C, D, F 4 11 15 11 15 0 150 3

© 2014 Pearson Education, Inc. 3 - 33

33

5
5/5/2020

Reduction by 2 days from 15 Days to 13 Days

Path E, F, G is critical
Minimum Non Zero Slack is 2

Reduce Activity F by 2 days from 5 to 3 days

Additional Cost: 2x 70 = 140

Project Completion Time is now 13 days

© 2014 Pearson Education, Inc. 3 - 34

34

Crash Cost Crash


Activity Pred Time ES EF LS LF S per day ($) Time

A -- 3 0 3 2 5 2 200 2

B A 4 3 7 5 9 2 80 3

C B 2 7 9 9 11 2 -- 2

D A 5 3 8 6 11 3 100 3

E -- 6 0 6 0 6 0 130 4

F E 5 36 11 6 11 0 70 3

G C, D, F 4 11 15 11 15 0 150 3

© 2014 Pearson Education, Inc. 3 - 35

35

6
5/5/2020

Crash Cost per


Activity Pred Time ES EF LS LF S Crash Time day ($)
A -- 3 0 3 0 3 0 2 200
B A 4 3 7 3 7 0 3 80
C B 2 7 9 7 9 0 2 --
D A 5 3 8 4 9 1 3 100
E -- 6 0 6 0 6 0 4 130
70
E 3 3
F 6 9 6 9 0 (compl used)
G C, D, F 4 9 13 9 13 0 3 150

Paths E, F, G and
© 2014 Pearson Education, Inc. A, B, C, G are critical
3 - 36

36

Reduction by 1 day from 13 Days to 12 Days

Project Completion Time is currently 13 days

Paths E, F, G and A, B, C, G are critical

We have to reduce the time on BOTH Paths

Reducing E by 1 day would cost $130


Reducing B by 1 day would cost $80
This leads to a total cost of 130 + 80 = $210

G is present on BOTH the paths


Reducing G will cost $ 150; HIGHER than individual costs for
E and B, but LESS than the combined cost of E and B
Hence, Reduce Activity G by 1 day from 4 to 3 days

Additional Cost: 1x 150 = 150


Project Completion Time is now 12 days
© 2014 Pearson Education, Inc. 3 - 37

37

7
5/5/2020

Which Activities are


Critical?
Calculate Again!

© 2014 Pearson Education, Inc. 3 - 38

38

Crash Crash Cost


Activity Pred Time ES EF LS LF S Time per day ($)
A -- 3 0 3 0 3 0 2 200
B A 4 3 7 3 7 0 3 80
C B 2 7 9 7 9 0 2 --
D A 5 3 8 4 9 1 3 100
E -- 6 0 6 0 6 0 4 130
70 (compl
E 3 3
F 6 9 6 9 0 used)
150 (compl
C, D, F 3 3
G 9 12 9 12 0 used)
Paths E, F, G and
A, B, C, G are critical

© 2014 Pearson Education, Inc. 3 - 39

39

8
5/5/2020

Reduction by 1 day from 12 Days to 11 Days


Project Completion Time is currently 12 days

Paths E, F, G and A, B, C, G are critical

We have to reduce the time on BOTH Paths

Reducing E by 1 day would cost $130


Reducing B by 1 day would cost $80
This leads to a total cost of 130 + 80 = $210
G is present on BOTH the paths, but no further reduction in
G is possible
Hence, Reduce Activity E by 1 day and B by 1 day

Additional Cost: 1x 130 + 1 x 80 = 210


Project Completion Time is now 11 days
© 2014 Pearson Education, Inc. 3 - 40

40

Total Additional cost =


140 +150 +210 = $500

© 2014 Pearson Education, Inc. 3 - 41

41