0% found this document useful (1 vote)
2K views

Dynamic Pile Load Test PDF

This document provides technical specifications for pile load testing, including: 1) Pile load testing can be preliminary tests on expendable piles to failure or working tests on production piles up to 50% over design load. 2) Dynamic load testing involves monitoring pile response to hammer blows to predict static capacity based on stress wave theory. 3) Specifications require all load tests follow standard procedures, preliminary tests can go to 1.5 times working load, and working tests go to 1.05 times working load. Concrete strength and pile preparation are also specified.

Uploaded by

Sumit Ghose
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
2K views

Dynamic Pile Load Test PDF

This document provides technical specifications for pile load testing, including: 1) Pile load testing can be preliminary tests on expendable piles to failure or working tests on production piles up to 50% over design load. 2) Dynamic load testing involves monitoring pile response to hammer blows to predict static capacity based on stress wave theory. 3) Specifications require all load tests follow standard procedures, preliminary tests can go to 1.5 times working load, and working tests go to 1.05 times working load. Concrete strength and pile preparation are also specified.

Uploaded by

Sumit Ghose
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

TECHNICAL SPECIFICATIONS

PILE LOAD TESTING

1. Introduction

The piling work on this site will require one or more pile maintained load tests. These tests can be
of two types or as specified:

• Preliminary Test: This is a test carried out on an expendable pile in advance of the
main piling work. The pile is usually tested until it fails and the results are used to refine
the design of the subsequent working piles.

• Working (or Proof) Test: This is a test carried out on a working pile and the test load is
usually limited to 50% over the design load to avoid overstressing the pile or the ground.
This test is to check that the piles are capable of bearing the loads imposed on them.
The test piles (and reaction piles/anchorages, if any) will be installed by the piling
contractor. The loading test will be carried out by a specialist testing contractor. After
installation, any concrete cast-in-situ piles are left for a minimum period of 7 days or
until the concrete has gained sufficient strength.

2. Testing and Specification for Dynamic Load Test

Pile Load Test

In high strain dynamic and rapid load tests, although the force is comparable in
magnitude to a static test, it is applied over a much shorter period than in a static load
test. Careful consideration is therefore needed in the interpretation of the dynamic effects
in order to derive static load capacities.

The Dynamic Load test and its application are summarized below. More details of
dynamic testing methods are included in Point No 4 ‘Load Testing Methods’.

Instrumentation may be built into preliminary test piles to investigate the load transfer
mechanism during the test. Piles may be equipped with strain gauges, push rods, load
cells and other devices to enable the designer to isolate key pieces of information and
improve the analysis of the test result and confirm or refine the design approach. This
type of equipment is normally of a specialist kind and requires careful selection,
installation and additional monitoring. It is preferable to have specialist advice on the
installation, monitoring and testing of any instrumentation.

2.1 Dynamic Load Test

These methods are based on monitoring the response of a pile subjected to hammer
blows applied at the pile head. The measured response parameters are subsequently
analyzed to give predictions of the soil resistance that would be mobilized by the pile
under static load conditions, based on stress wave theory.

The analytical models of the pile /soil interaction is developed to provide prediction of the
load/settlement performance of the tested pile. Dynamic load testing of cast in place piles
is used to predict the static soil resistance and the load/settlement behavior. The test
method is similar to that used on driven piles with the monitoring of hammer blows and
subsequently analyzing the pile response to the stress wave propagation. A separate
hammer or drop weight is usually brought to site to allow the dynamic load to be applied
to a cast in place pile.

Due to the very high rate of applied loading, dynamic load testing cannot take into
account time-related effects such as consolidation, relaxation or creep; consequently care
should be exercised in reviewing the results of tests carried out in soils which may exhibit
these features. However, the use of dynamic testing after calibration within a particular

1
TECHNICAL SPECIFICATIONS

geological profile will allow more comprehensive testing at low cost in comparison to
static testing.

Typically a dynamic test will take about 15 minutes to perform on a precast concrete pile
using the piling rig hammer to 30 minutes on a bored cast in place pile requiring the use
of a separate drop weight.

2.6 Summary

Maximum Test
S.No. Test Type Reaction System Advantages
Load

Fast and
Relatively
3MN (generally, but
inexpensive.
can be greater)
Suitable for both
Piling hammer or Hammer weight
1 Dynamic driven and bored
separate drop weight should be in the
piles. Correlation
range 1 to 2% of
with static tests
load to be proved.
on bored piles
generally good.

3. Specification

3.1 Test Procedure

All load tests should be carried out in accordance with the ICE Specification for Piling
and Embedded Retaining Walls.

3.2 Maximum Test Load

Load tests on preliminary or non-working test piles, in advance of or during the early
stages of the piling works, are normally carried out to DVL plus 1.0 or 1.5 times the
specified working load (SWL). DVL is the working load plus allowances for soil induced
forces such as down drag or heave, and any other particular conditions of the test such
as a variation of pile head casting level.

Load tests on working piles are normally taken up to a maximum load of DVL plus 0.5
times the specified working load. This is sufficient to verify the load settlement
characteristics of the piles under service conditions.

3.3 Concrete and Reinforcement

The strength of the concrete in the pile must be considered in all cases where a load test
is to be carried out, in order to ensure that the concrete is not over-stressed during
testing. This is particularly important with preliminary test piles where the stresses in the
concrete may be very high. Preliminary test piles are often loaded to between two and
three times their normal specified working load and this may call for higher grades of
concrete than those to be used in the works. Enhanced reinforcement may also be
required in preliminary piles to prevent structural failure under such loading conditions.

For working pile tests, the test should not proceed until compressive tests on works
cubes have confirmed that the concrete strength is at least twice the concrete stress in
the pile at the maximum specified test load. It is also necessary to ensure that the

2
TECHNICAL SPECIFICATIONS

trimmed head of the pile is in intimate contact with the pile cap with a horizontal, clean
and well formed joint.

Pile head preparation of bored/CFA piles undergoing dynamic load testing is critical.
Unless the pile has a permanent liner, the pile shaft must be built up 2 to 3 pile
diameters above ground level at the pile position within a thin-walled liner, suitably
reinforced and finished with a smooth flat surface normal to the pile axis. A pair of
diametrically opposed windows, 200mm square, must be cut into the liner to reveal
smooth concrete surface to which the gauges can be attached. CFA piles subject to
dynamic load tests will require the main reinforcement to extend to the pile toe. The
heads of piles undergoing rapid load tests will require similar pile head preparation to
that necessary for static load tests.

4. Load Testing Method

4.1 Dynamic Load Testing

In order to carry out this method of testing an


impact hammer is required. The hammer
should ideally be sufficiently large to fully
mobilize and therefore characterize the
dynamic pile capacity without damaging the
pile, and in the case of driven piling will
usually be the same hammer as used to install
the pile (see side Picture).

Dynamic load testing of bored cast-in-place or


CFA piles will generally require the use of a
separate hammer or drop weight (see Picture
below).

As Dependent upon the method employed, electronic


gauges are attached to the pile as illustrated in side
picture. The gauges measure the acceleration of the
pile (and therefore (indirectly) velocity with a
knowledge of the pile properties) and strain within
the pile just below the head as the hammer strikes
the pile. The information is then recorded in the
associated site computer. A variation of the method
involves deflection measurement directly by laser
theodolite.

3
TECHNICAL SPECIFICATIONS

In addition to access for the piling hammer/drop weight only minimal access is required
to attach the gauges, provided that the pile shaft protrudes at least 2 to 3 pile
widths/diameters above ground level; this safeguards the gauges and allows the
propagation of a uniform stress wave.

A large number of piles can be tested in the course of one day using dynamic load testing
methods.

Analysis of data

Once the data has been recorded, it can then be analyzed by suitably experienced
personnel using associated programs to provide the information on mobilized soil
resistance, pile integrity and hammer performance.

5. Pile Protection between Installation and Testing

Between installation and testing, the test pile and reaction piles/anchorages must be
protected from damage and interference, specifically:

• Reaction piles are normally reinforced with pre-stressing bars which protrude
from the piles to allow connection to the test beams. The bars are formed from
high grade steel which can be damaged by heat or bending. The test area must
therefore be barriered off from plant movement and no hot work allowed in the
vicinity. In the unfortunate event of a bar being bent, it must never be
straightened, but the piling contractor should be informed so that they can re-
end the bar. This may require the breaking down of the pile.

• No excavations must take place around reaction piles/anchorages as these have


been designed assuming ground level remains undisturbed. Excavations or
loosening of the ground can cause these to pull out, stopping the test.

6. Pile Load Testing – Test Cap

Dimensions for the test cap should be agreed with the testing contractor prior to its
construction. The test cap must be designed and constructed so that it:

• Is concentric with the centre of pile (with a stated allowable tolerance)

• Is able to safely transfer all the vertical and any other induced forces from the
cap into the pile

• Comprises a continuous uniform section without any inclusions.

The design and/or the method statement should made be available to the Principal
Contractor or Engineer upon request.

If not constructed integral with the pile then the ICE Specification for Piling and
Embedded Retaining Walls requires concrete test cubes to be taken from the concrete
used to cast the cap.

7. Testing

The testing contractor will need road access from the public highway to the test location
for the lorries which contain test beams and the data-logging cabin. The lorries will need
to be able to park adjacent to the test pile to enable the data cables to run from the data

4
TECHNICAL SPECIFICATIONS

cabin to the test assembly without interference. The lorries will also need to be able to
park a safe distance from the test area.

The area around the test must be made suitable for the technician to safely work, i.e.
leveled, hard-cored and without trip hazards or excavations.

An exclusion zone will need to be established around the area of the test, clearly marked
and signed. This zone then becomes a restricted area.

8. Guidance for the Principal Contractor

During the test, no work that could cause vibration should be carried out adjacent to the
test as the measurements being made may be affected.

The Principal Contractor can usually mitigate the disruptive effects of complying with the
above requirements by careful selection of the location of the pile(s) to be tested.

You might also like