Implementation Plan
Implementation Plan
IMPLEMENTATION PLAN
Version <1.0>
<mm/dd/yyyy>
VERSION HISTORY
[Provide information on how the development and distribution of the Project
Implementation Plan was controlled and tracked. Use the table below to provide the
version number, the author implementing the version, the date of the version, the name
of the person approving the version, the date that particular version was approved, and
a brief description of the reason for creating the revised version.]
Table of Contents
1 INTRODUCTION............................................................................................................6
1.1 PURPOSE.....................................................................................................................6
1.2 SYSTEM OVERVIEW......................................................................................................6
1.2.1 System Description...........................................................................................6
1.2.2 Assumptions and Constraints...........................................................................6
1.2.3 System Organization.........................................................................................6
1.3 GLOSSARY...................................................................................................................6
2 Management Overview.................................................................................................6
2.1 DESCRIPTION OF IMPLEMENTATION...............................................................................6
2.2 POINTS-OF-CONTACT...................................................................................................7
2.3 MAJOR TASKS..............................................................................................................7
2.4 IMPLEMENTATION SCHEDULE........................................................................................8
2.5 SECURITY AND PRIVACY...............................................................................................8
2.5.1 System Security Features.................................................................................8
2.5.2 Security Set Up During Implementation............................................................9
3 Implementation Support..............................................................................................9
3.1 HARDWARE, SOFTWARE, FACILITIES, AND MATERIALS....................................................9
3.1.1 Hardware...........................................................................................................9
3.1.2 Software............................................................................................................9
3.1.3 Facilities...........................................................................................................10
3.1.4 Materials..........................................................................................................10
3.2 DOCUMENTATION....................................................................................................... 10
3.3 PERSONNEL...............................................................................................................10
3.3.1 Staffing Requirements.....................................................................................10
3.3.2 Training of Implementation Staff.....................................................................11
3.4 OUTSTANDING ISSUES................................................................................................11
3.5 IMPLEMENTATION IMPACT........................................................................................... 11
3.6 PERFORMANCE MONITORING......................................................................................12
3.7 CONFIGURATION MANAGEMENT INTERFACE.................................................................12
4 Implementation Requirements By Site.....................................................................12
4.1 SITE NAME OR IDENTIFICATION FOR SITE X.................................................................12
4.1.1 Site Requirements...........................................................................................12
4.1.2 Site Implementation Details............................................................................13
4.1.3 Risks and Contingencies.................................................................................14
4.1.4 Implementation Verification and Validation.....................................................14
4.2 ACCEPTANCE CRITERIA..............................................................................................14
APPENDIX A: Project Implementation Plan Approval...............................................15
APPENDIX B: REFERENCES........................................................................................16
1 Introduction
1.1 Purpose
[This subsection of the Project Implementation Plan describes the purpose of the plan
and identifies the system to be implemented.]
1.2 System Overview
[This subsection of the Project Implementation Plan provides a description of the
system to be implemented and its organization.]
1.3 Glossary
[This subsection of the Project Implementation Plan lists all terms and abbreviations
used in this plan. If it is several pages in length, it may be placed in an appendix.]
2 Management Overview
[This section of the Project Implementation Plan provides a description of how the
implementation will be managed and identifies the major tasks involved.]
2.1 Description of Implementation
[This subsection of the Project Implementation Plan provides a description of the
planned deployment, installation, and implementation approach. Include whether the
system will be implemented using a phased approach or an “instant-on” approach. ]
2.2 Points-of-Contact
[This subsection of the Project Implementation Plan identifies the System Proponent,
the name of the responsible organization(s), titles, and telephone numbers of the staff
who serve as points of contact for the system implementation. These points-of-contact
should include the Business Sponsor, Program Manager, Project Manager, Quality
Assurance Manager, Configuration Management Manager, Security Officer, Database
Administrator, or other managers and representatives with responsibilities relating to
the system implementation. The site implementation representative for each field
installation or implementation site should also be included, if appropriate.]
Add additional lines as needed to the table. If the applicable team members are listed
in the Project Management Plan, reference the appropriate section within that
document.]
2.3 Major Tasks
[This subsection of the Project Implementation Plan provides descriptions of the major
system implementation tasks. Add as many subsections as necessary to this
subsection to describe all the major tasks. The tasks described in this subsection are
not site-specific, but generic or overall project tasks that are required to install
hardware, software, and databases, prepare data, and validate the system
If several implementation approaches are being reviewed, then identify the advantages,
disadvantages, risks, issues, estimated time frames, and estimated resource
requirements for each option considered. These options could include:
Parallel execution
One-time conversion and switchover
Any combinations of the above.
Include the following information for the description of each major task, if appropriate:
Consider addressing the changes that may be necessary once the system has been
implemented. These changes may include, but are not limited to, personnel and
technology equipment alignment, and contractor support.]
2.4 Implementation Schedule
[This subsection of the Project Implementation Plan provides a schedule of activities to
be accomplished. Show the required tasks (described in Subsection 2.3, Major Tasks)
in chronological order, with the beginning and end dates of each task. If MS Project is
used to plan the implementation, include the project Gantt chart. Include any milestones
from the projects that are dependent on this project and vice-versa.]
ensure that the system meets all the criteria appropriate to its Certification level.
Reference the applicable security guidance documents.]
3 Implementation Support
[This section of the Project Implementation Plan describes the support hardware,
software, facilities, and materials required for the implementation, as well as the
documentation, necessary personnel and training requirements, outstanding issues and
implementation impacts to the current environment. The information provided in this
section is not site-specific. If there are additional support requirements not covered by
the subsequent sections, others may be added as needed.]
3.1.1 Hardware
[This subsection of the Project Implementation Plan provides a list of support equipment
and includes all hardware used for installing and testing. This hardware may include
computers, servers, peripheral equipment, simulators, emulators, diagnostic equipment,
other non-computer equipment as well as any network and data communication
requirements. The description should include the specific models, versions,
configuration settings, and the equipment owner. Also include information about
manufacturer support, licensing, and usage and ownership rights, and maintenance
agreement details.
3.1.2 Software
[This subsection of the Project Implementation Plan provides a list of non-hardware
components (software, databases, and compilers, operating systems, utilities, etc.)
required to support the implementation. Identify the component by specific name, code,
or acronym, identification numbers, version numbers, release numbers, and applicable
Implementation Plan Template (v1.0) Page 10 of 20
configuration settings. Also, include information about vendor support, licensing, usage,
and ownership rights, as well as any required service and/or maintenance contract
costs and associated payment responsibility. Identify whether the component is
commercial off-the-shelf, custom developed or legacy. Identify any component used to
facilitate the implementation process.
3.1.3 Facilities
[This subsection of the Project Implementation Plan identifies the physical facilities,
accommodations and their location(s) required during implementation. Examples
include physical workspace for assembling and testing hardware components, desk
space for software installers, floor space for equipment, and classroom space for
training the implementation staff. Specify the hours per day needed, number of days,
and anticipated dates.
3.1.4 Materials
[This subsection of the Project Implementation Plan identifies any other consumables
(i.e. technology, supplies, and materials) required to support the system. Provide the
names, identification numbers, version numbers, release numbers, owners, and any
associated maintenance or operational costs.
3.2 Documentation
[This subsection of the Project Implementation Plan lists any additional documentation
needed to support the deliverable system. Include any security or privacy protection
considerations associated with the systems use. If created, make reference to the
Software User Documentation Guide for user documentation.]
3.3 Personnel
[This subsection of the Project Implementation Plan describes committed and proposed
staffing requirements. Describe the training, if any, to be provided for the
implementation staff.]
clearances for the staff required during the implementation period. If particular staff
members have been selected or proposed for the implementation, identify their roles
and responsibilities.]
Describe the type and amount of training required for each of the following areas, if
appropriate, for the system:
List the courses that will be provided, a course sequence, and a proposed schedule. If
appropriate, identify which courses particular types of staff should attend by job position
description.
If one or more commercial vendors will provide training, identify them, the course
name(s), and a description of the course content.
If Center staff will provide the training, provide the course name(s) and an outline of the
content of each course. Identify the resources, support materials, and proposed
instructors required to teach the course(s).]
3.5 Implementation Impact
[This subsection of the Project Implementation Plan describes how the system’s
implementation is expected to impact the network infrastructure, support staff, user
community, etc. Include any references to Service Level Agreements which describe
the performance requirements, availability, security requirements, expected response
times, system backups, expected transaction rates, initial storage requirements with
expected growth rate, as well as help desk support requirements.
3.6 Performance Monitoring
[This subsection of the Project Implementation Plan describes the performance
monitoring tool, techniques and how it will be used to help determine if the
implementation is successful.]
The "X" in the subsection number should be replaced with a sequenced number
beginning with 1. Each subsection with the same value of "X" is associated with the
same implementation site. If a complete set of subsections will be associated with each
implementation site, then "X" is assigned a new value for each site.]
Any site requirements that do not fall into the following three categories and were not
described in Section 3, Implementation Support, may be described in this subsection, or
other subsections may be added following Facilities Requirements below:
Database -- Describe the environment where the system and the database(s) will
be installed. Include a description of the different types of databases and library
environments (such as, production, test, and training databases).
o Control inputs
o Operating instructions
o Database data sources and inputs
o Output reports
o Restart and recovery procedures]
Signature: Date:
Print Name:
Title:
Role: Project Manager
APPENDIX B: REFERENCES
[Insert the name, version number, description, and physical location of any documents
referenced in this document. Add rows to the table as necessary.]
The following table summarizes the documents referenced in this document.
Document Name Description Location
<Document Name and <Document description> <URL or location where document is
Version Number> located>
Name/ ID Type Model/ Physical Equipment Maintenance Maintenance Maintenance Maintenance Required
Version Location Owner Contract? Contact Type/ Level Period Licenses
(Person or Y/N Point of Coverage Expiration
Dept) Date
Name/ ID Type Model/ Physical Equipment Maintenance Maintenance Maintenance Maintenance Required
Version Location Owner Contract? Contact Type/ Level Period Licenses
(Person or Y/N Point of Coverage Expiration
Dept) Date
https://ohiocea.files.wordpress.com/2011/04/medical-equipment-life-expectancy-list.pdf
reference for medical equipment life expectancy