By John Gregerson, Managing Editor
By John Gregerson, Managing Editor
tight, awkward site and an unwieldy pro- of the land," he said. Integrating new and
gram could have added up to trouble for the But not without a structural
Francois-Xavier Bagnoud (FXB) Building detour. According to Jolanda existing research
in Boston, a new research facility for the Kenyeres-Pavlinic, principal
Harvard School of Public Health (HSPH). with Souza, True & Partners buildings on a small
But project architect Payette Associates of Boston (ST&P), the project's
used geometry to solve the problem, employing a series Watertown, Mass.-based struc- p a r c e l p r o m p t s p r o -
of bold triangular forms to overcome site constraints tural engineer, existing below-
and reconcile some of the program's more diverse grade labs beneath the planned
ject members to
points. steel-framed lobby precluded
evaluate design and
Chief among them were directives to furnish HSPH the use of interior columns to
with sorely needed labs for AIDs and cancer research; support its roof and mezzanine c o n s t r u c t i o n i s s u e s
integrate the new spaces with a pair of older, neighbor- floor. The solution was to sus-
ing lab facilities; create a formal entrance for the larger pend the mezzanine from the from all angles
HSPH campus, located behind the FXB site; and pro- structure's roof beams via 1
vide HSPH with a contemporary image that comple- 1/2-in.-diameter steel rods. In
mented elements of the surrounding area. turn, the 55-ft. beams span
Payette responded with a 104,000-sq.-ft. complex from new perimeter columns along CONSTRUCTION COSTS
comprised of three interlocking triangles, the first a Huntington to the 11- and four-story Sitework $1,050,000
seven-story research center abutting an existing four- buildings, where they were tied into Concrete 2,430,000
story lab, the second a four-story skylit atrium nestled the structures. Masonry 710,000
between the seven- and four-story structures - essential- "The new roof beams rest on exist-
Metals 2,390,000
ly a triangle within a triangle - and the third a two-story ing beams, which needed to be adapt-
Carpentry 1,170,000
lobby - or "front door." The lobby connects to portions ed to accept the additional vertical and
Thermal/moisture protection 780,000
of the seven- and four story structures, as well as an horizontal loading," Kenyeres-Pavlinic
existing 11-story research building, providing grade- said. "We had to strengthen the beams Doors/windows 974,000
level access to all three. and beam-column connections with Finishes 2,543,000
If the solution sounds convoluted, consider plate stiffeners and with brackets Conveying systems 290,000
the architect's reaction. "After visiting the site - which is located beneath the beams. The plan Environmental rooms 480,000
only about 10,000 square feet in size - I found it hard to basically allowed us to use existing Mechanical 4,235,000
believe we were drawing to the correct scale," recalled beams to transfer lobby loads to exist- Electrical 2,832,000
David Feth, project designer for Payette. "It didn't look ing columns." Telecommunications 166,000
as if it would all fit." Integrating the seven- and four- Plumbing 1,130,000
Fit it does, albeit snugly. Paul Riccardi, associate story buildings likewise posed chal- Fire protection 428,000
dean of operations for HSPH, indicated that the site lenges for ST&P, and for contractor Other 2,392,000
helped drive the placement and configuration of FXB's Richard White Sons of Auburndale, Total $24,000,000
major components. He explained that while the existing Mass. Plans called for joining common
research buildings defined two edges of the site, the levels of the two by punching openings into the facade of
third edge was defined by a major diagonal street, the four-story structure where corridors for the two facili-
Huntington Avenue. This resulted in a roughly triangu- ties met, then cantilevering portions of the new floor slab
lar parcel. "To maximize space, we followed the layout across a 1 1/2-ft. joint separating the two buildings. (The
Second-Floor Plan
A. Atrium
B. Open lab
C. Office and support
D. Special purpose lab
E. Equipment room
F. Environmental room
G. Glasswash room
H. Desk room
I. Lounge
J. Entrance lobby (open to below)
K. Level to connector
WAT E R P R O O F I N G
Waterproofing requirements turned plans inside out
When Paul Riccardi became associate dean for operations at the Harvard School for Public
Health (HSPH), “I inherited three buildings that leaked," he said. He and other administrators
were determined to make sure that HSPH’s new seven-story Francois-Xavier Bagnoud
Building (FXB) didn't add to his troubles.
As a result, project architect Payette Associates selected a concrete masonry unit wall as
back-up for the building’s precast exterior, then
specified a continuous mastic sheet membrane to
waterproof the inner wall. The design also called
for locating 2-in.-thick insulation and a flashed 2-in.
air cavity between the masonry and precast walls.
The plan presented complications, however. “With
precast, you typically build from the outside to the
inside so there's nothing in the way when you're
securing panels to the building frame,” said Paul
Gransaull,
project manager with FXB contractor Richard
White Sons. “If we had done that here, we wouldn't
have had any room to apply waterproofing to the
masonry. There was only a 4-in. space between
the face of the masonry and the back of the pre-
cast."
The solution was to construct the masonry first,
leaving “tieback” and “bearing” openings in the wall
so that the precast anchors could be secured to
framing behind it. “The precaster had to be well-
coordinated with masons placing the block in the
field,” said Payette project designer David Feth
“And that's a step you usually don't worry about
much - how the block gets laid between column
“With precast, you often have metal studs as lines. We couldn’t afford to have huge precast mem-
your back up,” said Paul Gransaull, project bers dangling from a crane as a result of our points
manager with contractor Richard White Sons. not lining up.”
“But Harvard wanted masonry - something Once precast members were anchored in place,
that would last.” Openings in the masonry “we wrapped the openings in waterproofing from
wall allowed workers to anchor precast inside the building, insulated them, then closed
panels to the building structure behind it. them,” Feth said.n
Air-intakes had
to be rerouted
to prevent
dust from
reaching labs