NOTIFICATION
In exercise of the powers conferred on me under Section 192 read with S.54(1)(e) and
Clause 39 of 6th Schedule of the PUNJAB LOCAL GOVERNMENT Ordinance 2001, I,
Ch. Muhammad Amir Khan Bhatti, Tehsil Nazim Chakwal, hereby enforce, with the
approval of Tehsil Council Chakwal the under mentioned Building Bye-laws in super
cession of the previous Building Bye-laws published in the Punjab Government Gazette
Notification No.746/TPO/GB/MCC dated 13 November, 1995 for general information.
PART - 1
PRELIMINARY
ii) These Bye-laws shall extend to the whole Tehsil Chakwal except the areas
exempted by the Tehsil Council, Chakwal.
iii) These Bye-laws shall come into force with effect from 1st July, 2003.
iii) The Tehsil Municipal Administration Chakwal may sanction any erection
or re-erection of a building either absolutely or subject to modifications as
it deems necessary.
PART -II
GENERAL ADMINISTRATIVE MATTERS
3. Interpretation of Terms.
Unless otherwise expressly stated, the following terms shall for the purpose of
these Bye-laws have the meanings indicated in this part. Where the terms are not
defined they shall have their ordinarily accepted meaning of such as the context
may apply.
xi. Cardinal Points - means the directions of North, South, East and West.
xii. Commercial Building - means a building having shops or show rooms,
offices, hotel, private school, filling/servicing station etc. and may also
have housing units/apartments.
xiii. Competent Authority - means the Nazim, or authorized officer by the
Nazim to approve plans and to control the building activity.
xiv. Council - means Tehsil Municipal Council, Chakwal.
xv. Damp Proof Course (DPC) - means a layer of material impervious to
moisture.
xvi. Draftsman - means draftsman of P & C office.
xvii. Floor Area Ratio - means the aggregate covered area of the building on a
plot divided by the total area of the plot.
xviii. Foundation - means a structure entirely below the level of the ground
which carries and distributes the load from pillars, beams or walls on the
ground.
xix. Gallery - means an open or a covered walk-way or a long passage or an
underground passage.
xx. Government - means the Government of Punjab.
xxi. Industrial Building - means a building designed for use as a factory or
workshop and includes an office or other accommodation on the same site,
which is intended for use in connection with the mining or minerals
including brick or the earth or warehouse, depository or stores etc.
xxii. Kacha Building - means a building having walls made of bricks/stones laid
with mud, roof material grass, hay, straw, reed temporarily made for
residence or animal shelter.
xxiii. Kanal - means a size of land equal to 20 marlas @ 272 sft. as in revenue
papers and @ 248 sft. as otherwise described and generally applied in
Chakwal city.
4
xxxv. Residential Building - means a building exclusively designed for the use as
a human habitation together with such other uses as are ordinarily ancillary
to the main building and used in connection therewith.
xxxvi. Semi Detached Building - means two buildings but on adjacent plots
having a common partition walls.
xxxvii. Septic Tank - means a tank in which sewage is collected and decomposed
before its discharge into a public sewer or soakage pit.
xxxviii. Soakage Pit - means a pit filled with aggregate, boulders or broken bricks
and intended for the reception of waste water or effluent discharged from a
septic tank.
xxxix. Sq. Ft. - means Square Feet.
xl Structural Calculations - means detailed calculations showing sufficiency
of the strength of every load bearing part of the proposed structures.
xli. Sun Shade - means an outside projection from a building over minimum
height of 7 feet from the plinth level meant to provide protection from sun
and rain.
xlii. Structural Engineer - means Civil Engineer having Msc Degree in
Structural Engineering and registered with Pakistan Engineer Council as
Structural Engineer
xliii. Tehsil Municipal Administration (TMA) - means Tehsil Municipal
Administration Chakwal.
xliv. Tehsil Officer Planning & Coordination TO (P&C) - means Tehsil Officer
Planning & Coordination, Tehsil Municipal Administration Chakwal.
xlv. Verandah - means a roofed gallery, terrace or other portion of a building
with at least one side open to courtyard or a permanent open space.
xlvi. Zone - means an area/areas earmarked for particular use of character
including an area in which sizes of plots have been prescribed.
PART -III
4. Application of Building Bye-Laws. Every prospective builder who intends to
carry out building works within the boundary of the area controlled by the Tehsil
Municipal Administration shall comply with the requirements of these Bye-laws.
5. Submission of Plans
i.. All applications shall be made on building application Forms A & B as
prescribed by the Tehsil Municipal Administration at Appendix A & B.
6
ii. The land shown as set-back on the building plan for street or road
widening or parking shall vest in the Tehsil Municipal Administration
Chakwal
iii. No building application shall be entertained unless the plan is drawn by an
Architect/Town Planner/Draftsman holding the license for the said
purpose issued by the Tehsil Municipal Administration.
iv. Only those Architects / Town Planners shall be registered who keep a
Degree or Diploma in Architecture / Town Planning from a recognized
University. Draftsman holding diploma as Civil Draftsman from a
Government recognized Institute can be registered as Architect provided
they keep work experience not less than three years and Tehsil Officer
Planning & Coordination is satisfied with their practical performance.
vi. Every person intending to erect or re-erect a building shall give notice of
such intention in writing to the Tehsil Municipal Administration by
submitting Form - An appended to these Bye-laws, in order to
obtain permission to execute work, shall at the same time submit:
i. Every builder who carries out building works shall use sound building
material which shall be of good quality and properly put together so as to
ensure safety and stability of the building.
ii. A certificate of durability and in accordance with building plan be
obtained from Architect and Engineers concerned after completion of each
floor.
iii. Structure strength according to design be certified by the structural
Engineer after on the spot inspection of the quality of the material
especially of steel and concrete the completion of the building.
iv. In case of failure of the Structure Engineer should be held personal
responsible.
v. If on making inspection, the authorized officer/official of the Tehsil
Municipal Administration finds that the building works:-
a) Contravene any of the provisions of the Bye-laws, Tehsil
Municipal Administration may by written notice require the person
carrying out building work within a period to be specified in such notice,
either to make such alteration as shall be specified in such notice, with the
object of bringing the work in conformity with the said plans or provision
of the bye-laws or get amended plans approved by Tehsil Municipal
Administration after complying with the requirements of the bye-laws.
b) In the event of non-compliance with the requisition as made under
sub clause (i) above, Tehsil Municipal Administration may order cessation
of work or order of demolition of such construction which may contravene
any of the provisions of the building bye-laws and the expenses thereof
shall be paid by the owner.
9. a) Completion Certificate
i. Every prospective builder who carries out and completes building works
as approved under these Bye-laws shall within 30 days of the completion
of work apply in writing to Tehsil Municipal Administration together with
the certificate signed by the licensed Architect/Town Planner/Draftsman,
unless in the opinion of the competent authority such a certificate in not
required.
iii. In case the prospective builder intends to construct the building in phases,
the sequence of construction in phases duly numbered shall be indicated
on the drawings.
b) Lapse of Sanction
iii. The result of every inspection under clause (i) above shall be recorded in
the building form ‘C’ appended to these Bye-laws and brought to the
notice of Tehsil Officer Planning & Coordination who may ensure that
adequate action has been taken with regard to each case of contravention
of the Ordinance or Rule or Bye-laws framed there-under.
iv. The authorized officer of Tehsil Municipal Administration may enter into
or upon any premises with or without assistant in order to make any
inspection, survey, or inquiry, provided :-
PART - IV
i. The height of any building for the purpose of these Bye-laws shall be
measured from the top of the plinth to the top of the parapet wall.
ii. No person shall construct any building abutting on any street:-
COMMERICAL
13. Height of the building
a) Minimum effective height of any shop shall not be less than 9 feet
6 inches without any gallery (storage space) or 15 feet 6 inches
with gallery (storage space).
15. GENERAL
ii. No person shall start building works on a site abutting on a street / road
without having first provided hoarding or barrier to the satisfaction of the
competent authority along the same length of such site so as to prevent
danger of injury to the public or the persons employed to the work
however, this rule does not apply in the case of building work in
connection with structures situated 15 feet away from edge of the public
street and being not more than 25 feet high.
16
iii. No part of any street shall be used in connection with construction repair
or demolition of any building except with the written permission of the
competent authority. Any person holding such permission shall put up and
maintain to the satisfaction of the concerned authority the fences or
barriers in order to separate the building work from such street without
interruption in the flow of traffic.
vii. All materials, hoarding, fences or other obstructions in any street shall be
kept clear of hydrants and other utility services, installations or alternative
arrangements to the satisfaction of the competent authority and precautions
shall be taken to divert or keep clear of obstructing any road side or drain
during the period of temporary construction.
viii. If any material, hoarding, excavation or any other thing in or near any
street be in the opinion of the Tehsil Officer Planning & Coordination
dangerous to the passengers along such street the competent authority shall
cause the same to be removed, protected or enclosed so as to prevent
danger there from and shall be entitled to recover the expenses thereof
from the owner of such material or from the person who made such
hoarding, excavation or the other thing to become dangerous.
ix. The competent authority may give notice canceling any permission issued
for the breach of any of the imposed conditions or for any other reason it
may think fir and person holding the permission shall within 7 days of the
17
receipt of such notice have hoarding, fence or material removed and any
excavation refilled or otherwise made good.
x. All obstruction and erections in any street shall be removed with in 7 days
of the completion of the work and the street and all drains and public
utility installations shall be left in clean tidy and serviceable condition.
xii. A site once excavated shall not be kept open beyond the period stipulated
for completion of the work below ground level.
xiii. Material shall not be placed or stacked near the edge of any excavation to
endanger any person.
xv. No roof, floor or the parts of the building shall be so over loaded during
the process of demolition / construction with debris of materials so as to
render it unsafe.
xvi. Every part of load shall be securely fixed or supported while being raised,
lowered or suspended and shall be adequately secured to prevent danger
from slipping or displacement. Every receptacle used for raising, lowering
and suspending blocks, bricks, tiles or other objects shall be so designed
and constructed as to prevent accidental fall of such objects.
xvii. In all buildings where the load of electricity would require installation of
independent transformer / sub-station appropriate space for location and
18
i. Inter floor shall only be permitted in rooms other than those meant for
habitation purposes, such as bath rooms, stores, kitchen pantries, passages,
garges if combined with the main building, verandahs rooms meant for
similar ancillary uses.
ii. A minimum clear height of all the rooms referred to in clause a. above
shall be as per schedule - II, except that the inter floor may have a clear
height of 5 feet 6 inches when used as storage space.
17. Basement.
b. That the level of the public sewer permits gravity flow at a gradient
of not less than 1:40 or if this may not be possible pumping
arrangements shall be installed.
c. That minimum height of any basement room shall be 8 feet.
e. The minimum area of the basement shall not be less than 100 sq.
ft.
19
i. Every room other than rooms used predominantly for the storage of goods
shall, except where mechanical arrangements are provided, have a
combined glazed area of not less than 12% of the floor area of such room
and 50% of such opening shall be capable of allowing free uninterrupted
passage of air.
ii. Every latrine, water closet, urinal stall and bath room shall be provided
with natural lighting and ventilation by means of one or more openings in
external walls having a combined area of not less than 2 sq. ft. per water
closet, urinal stall or a bath room and such openings shall be capable of
allowing free uninterrupted passage of air.
iii. Kitchens, lavatories, WCs and bath rooms may have sources of daylight
and natural ventilation from internal air wells of adequate size.
ii. All means of escape from a building including extra corridors stairs etc.
shall permit unobstructed access to the street.
iii. An emergency stair case shall be sited at such a position that it should be
accessible to all the unit without any hindrance or obstruction and it
should be open to a permanently ventilated space.
iv. All buildings shall have windows on the street elevation within the
convenient reach and of adequate size to enable persons to escape in case
of emergency.
i. Sites
ii. Foundations
b. The owner shall cause tests to be made to prove the nature of the
soil, wherever considered necessary by the competent authority.
Such test must be made for all sites intended to be constructed
upon with buildings having more than 3 storeys.
APPENDICES
SCHEDULE - I -
SCHEDULE - II -
ANNEXURE - A -
APPENDIX - A -
Form - A
APPENDIX - B
- Form - B
APPENDIX – C
- Form - C
APPENDIX - D
- Reports
SCHEDULE – I
24
Above 20 marlas 65 %
Apartment Buildings 65 %
SCHEDULE - II
Habitable Room
i.e. Bed Room,
Drawing Room, 100 sq.ft. 9’ - 0” 8’ - 6”
Lounge,
Servant Room etc.
Kitchen 45 sq.ft. 8’ - 6” 5’ - 0”
Basements : If used for habitable purposes the rules for respective space use will
be applied.
ANNEXTURE - A
BUILDING APPLICATION FEE
Every prospective builder has to submit fee along with application as prescribed below:
COMPOSITION CHARGES
S.No. Nature of Deviation Composition Charges
Notes : i. In case where the owner does not apply for compounding the
offense committed by him or fails to pay penalty at the prescribed rates plus
composition fee, it shall be open to the Administration or any person authorized
by it on his behalf to demolish the offending structure.
APPENDIX - A
FORM - B
4. No. of storeys_________________________________________________________________
7. If any building or portion of the building already exists on the site. Whether its plan
Address ________________________________________
______________________________________________
27
address _______________________________________________________________
Building Inspector
Admit the plan in the relevant building register after collecting the above charges.
Building Clerck
Appendix -C
FORM - C
______________________________
Building Clerk
Draftsman
Planning and Coordination Branch,
Tehsil Municipal Administration,
Chakwal
Appendix D
REPORTS
point of view ?
____________________________________
30
____________________________________
____________________________________
____________________________________
____________________________________
____________________________________
FORM - Z
File No.__________
From ___________________________________________
31
___________________________________________
Page No.
N I Card _________________________________________ 1
Affidavit __________________________________________ 8
Appendix - A
FORM - A
From ____________________________________
____________________________________
Through this application under Section 24 of the Punjab Local Government Ordinance
2001, I hereby inform that I intend to erect/re-erect the building on this site bearing
Khasra No.______________ situated in Mohallah ______________________________
Mouzia ___________________ as per details mentioned in the Form B attached
herewith. I undertake not to start the erection/re-erection of the building before grant of
32
sanction by the Tehsil Municipal Administration Chakwal. Following documents are also
annexed:
a) Complete building plan on tracing cloth/paper in which all the requisite details of
the building have been given in accordance with the building bye-laws. The plan
has been drawn by the licensed architect of Tehsil Municipal Administration,
Chakwal.
b) Original/Certified copy of the title deed and Fard Jamabandi under which I claim
title to the site sought to be erected/re-erected (give the description of the title
deed).
c) I undertake that keeping in view the level of the street/drain existing nearby I shall
construct the drain and pave the street in accordance with the plan at my own cost.
I shall use the water from well and shall not claim the water supply from the
Tehsil Municipal Administration, Chakwal till such time that water supply is
arranged by the Tehsil Municipal Administration for this locality as a whole.
d) I shall not claim any other municipal / civic service, until and unless it has been