The document is a checklist for reviewing civil drawings. It contains 30 items to check, including verifying equipment loads and dimensions, soil properties, reinforcement details, material specifications, orientation and clearances between structures, and ensuring drawings are consistent with general arrangement drawings and specifications. The checklist aims to confirm key design information and ensure drawings are complete before approval.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
156 views2 pages

Checklist - Civil - Drgs.

The document is a checklist for reviewing civil drawings. It contains 30 items to check, including verifying equipment loads and dimensions, soil properties, reinforcement details, material specifications, orientation and clearances between structures, and ensuring drawings are consistent with general arrangement drawings and specifications. The checklist aims to confirm key design information and ensure drawings are complete before approval.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

Format No.

Checklist For Civil Drawings APIL-NCR-STR-CHKL-001

June 2008

Contract / Project Name


Contract / Project No.
Boiler Type
Drawing Nos.

Sl. Checkpoints Status (Tick Remarks


No. if Confirmed)
Location / Reference
1. Check GA of Plan drawing of Boiler where all ground
level equipments have been shown
2. Check the plot plan with grid mark.

3. Check the customer plot plan and Customer Civil


Foundation detailed drawing if any.
4. Check the customer specification about soil, type of
concrete etc.
5.. Check with specified code and standard and whether
they are mentioned or not.
6. Check the designer’s detail for the foundation.(sketch)
7. Check whether elevation corresponding to 0.0m of the
plant is mentioned in the notes or not.
8. Check the drawing number and document number with
MDL.
9. Check whether the North Direction is specified in the
Drawing.
10. Check the equipment drawing for the loads, Area ,load
locations etc. which will be placed in concrete.
11. Check the civil area underground of each equipment
and Boiler columns etc.
12. Check the clear gap between static equipment civilwork
and dynamic equipment civilwork
13 Check the availability, type, size of fixing
attachment(anchor bolt, channel etc.) of
structural/equipments.(to be embedded in concrete)
14. Check the drawing titleblock, drawings Nos. with prefix/
suffix, signature, revision etc.
15 Check the notes & legends whether every information is
given or not.
16. Check whether detail related dwg. Nos. & ref. Dwg.
nos. are mentioned or not.
17. Check the quantity, grade of material, bar marks,
number of the detailed drawing as well as BBS
18. Check the details whether all dimensions and partmark

Checked by Approved by Date: Sh. 1 of 2


Signature : Signature :

Name : Name :
Format No. :

Checklist For Civil Drawings APIL-NCR-STR-CHKL-001

June 2008

no. is mentioned or not with respect to relevant GA


dwgs
19. All item nos. and quantity should match with relevant
GA drawings.
20. Check whether the material list is in accordance to
detail drawings as well as specifications
21. Is Pack plate included in the material list and in drawing
for proper alignment/straightness of structure
22. Check the level at different places with the GA
Drawings.
23. Check the structure/equipment orientation, size/section,
plan area etc as per GA drawing
24. Check whether BBS is as per reinforcement drawing or
not regarding number of bars and their weights.
25 Check for the availability of material at site.
26. Check whether the reinforcement details in the plan
marked is the same in the section.
27 Check the length of anchor bolt when concreting (if
needed to be embedded initially, write special note for
it)
28 Check location of anchor bolts whether they clash with
the reinforcement or not.
29 Check the TOC of pedestal with BOS of baseplate
30 Check whether grade of concrete, grade of
reinforcement bar, SBC of soil, clear cover of footing
and pedestal etc. is mentioned or not

Checked by Approved by Date: Sh. 2 of 2