Inspection and Test Plan: ACTIVITY: ITP For Inspection of Piling Work
Inspection and Test Plan: ACTIVITY: ITP For Inspection of Piling Work
HCC T 39 17 33
Project : LMNHP-EW II (WB) -III Rev.No. 0
Client : National Highways Autthority of India
Date of Rev. 4/24/2006
Engineer : Lea Associates South Asia Pvt. Ltd.
Contractor : Hindustan Construction Co. Limited Page
Material on site
02 Inspection of Incoming material NA On receipt of material W R
report
Concrete Design mix for each Grade MORT&H Clause- Concrete Design Once per each source of
03 W R
and Approval 1704 Mix Report(s) material
Relevant
Check for availability of approved List of approved
04 Construction Before start of activity W R
construction drawings drawings
Drawing
Survey & Setting out for relevant MORT&H Clause- As per Survey
05 Before start of activity W R
structure to be concreted 109 Records
MORT&H Cls:
1626, Every pour before & after
07 Concrete check list HCC F 39 17 48 W R
1606, 1500, 1713 to concreting
1715
MORT&H Clause-
09 Calibration of batching plant HCC F 39 14 80 Once in month W R
1704
INSPECTION AND TEST PLAN Doc No. HCC T 39 17 33
Project : LMNHP-EW II (WB) -III Rev.No. 0
Client : National Highways Autthority of India
Date of Rev. 4/24/2006
Engineer : Lea Associates South Asia Pvt. Ltd.
Contractor : Hindustan Construction Co. Limited Page
Check for mixing, transporting, MORT&H Clause- HCC F 39 14 72 Every pour before
10 W R
placing, compaction of concrete etc. 1709 HCC F 39 14 75 concrete
HCC F 39 17 56
11 Inspection and Record of Piling NA For every pile boring W R
HCC F 39 17 51
LEGEND: W: Witness; H: Hold Point; S: Surviellance Inspection; R: Review of Reports; MORT&H: Ministry of Surface Transport Specifications;
INSPECTION AND TEST PLAN Doc No. HCC T 37 17 34
Project : LMNHP-EW II (WB) -III Rev. No. 0
Client : National Highways Autthority of India
Date of Rev. 1/9/2005
Engineer : Lea Associates South Asia Pvt. Ltd.
Contractor : Hindustan Construction Co. Limited Page of 2
1. CEMENT
MTC/
M.O.R.T & H, Table:900-6
a Compressive Strength Once per each source/batch W/H R Receiving Inspection
IS:4031 (Part-6)
HCC F 39 14 65
MTC/
Consistency , Initial and Final Setting Time M.O.R.T & H, Table:900-6
b Once per each source/batch W/H R Receiving Inspection
test IS:4031 (Part-5)
HCC F 39 14 64
MTC/
M.O.R.T & H, Table:900-6
c Fineness test by dry sieving Once per each source/batch W/H R Receiving Inspection
IS:4031 (Part-1)
HCC F 39 14 62
MTC/
M.O.R.T & H, Table:900-6
d Soundness test Once per each source/batch W/H R Receiving Inspection
IS:4031 (Part-3)
HCC F 39 14 63
3. WATER
4. CONCRETE
HCC F 39 14 72
M.O.R.T & H, Table:900-6
a Workability of Fresh Concrete(Slump) One test per each batch W R In-Process
IS:1199
HCC F 39 14 75
M.O.R.T & H, Table:900-6
b Core strength on Hardened concrete External Lab Report As and when required H R Acceptance test
IS:516
5. CONCRETE ADMIXTURES
6. BENTONITE
Clause 115.2.3 of
a Gradation for Silt content HCC F 39 14 03 Once per Lot W R Screening test
M.O.R.T & H
Clause 115.2.3 of
b Liquid Limit HCC F 39 14 09 Once per Lot W R Screening test
M.O.R.T & H
LEGEND: W: Witness; H: Hold Point; S: Surviellance Inspection; R: Review of Reports; M.O.R.T & H: Ministry of Surface Transport Specifications;