This document is a study guide for an exam on water resource engineering. It lists 7 questions covering topics like hydropower development in Nepal, dam foundation treatment, penstock pipe thickness calculation, surge tank calculation, dam terminology, reservoir sedimentation control, run-of-river hydropower station calculation, spillway requirements, micro hydro application, Kaplan turbine calculation, turbine classification, and reservoir regulation. Students are instructed to answer all questions in their own words within a 3 hour time limit.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
82 views2 pages
Water Resource Engineering II
This document is a study guide for an exam on water resource engineering. It lists 7 questions covering topics like hydropower development in Nepal, dam foundation treatment, penstock pipe thickness calculation, surge tank calculation, dam terminology, reservoir sedimentation control, run-of-river hydropower station calculation, spillway requirements, micro hydro application, Kaplan turbine calculation, turbine classification, and reservoir regulation. Students are instructed to answer all questions in their own words within a 3 hour time limit.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2
POKHARA UNIVERSITY
Level: Bachelor Semester – Fall Year : 2007
Programme: BE Full Marks : 100 Course: Water Resource Engineering II Time : 3hrs. Candidates are required to give their answers in their own words as far as practicable. The figures in the margin indicate full marks. Attempt all the questions. 1. a) How do you justify the relevance of hydropower development in 5 Nepal? b) Determine the probable life of reservoir before its capacity is 10 reduce by 20%. The proposed reservoir has a capacity of 700ha-m. The catchment area is 200km 2 having an annual runoff and annual deposition of sediment are 20cm and 0.055 ha-m/km 2 Capacity inflow ratio and trap efficiency are given below: Capacity-inflow 0.05 0.07 0.1 0.15 0.25 0.4 0.6 0.8 ratio Trap 50 60 75 80 86 90 93 95 efficiency, % 2. a) Explain the method employed for the treatment of a faulty dam 7 foundation. b) What is phreatic line? How would you locate the corrected phreatic 8 line for homogenous dam without drainage? 3. a) A penstock pipe having a diameter of 2.5m supplies water from a 7 head of 150m. There is possibility of 25% increase in the pressure head due to the transient condition of flow. If the efficiency of joint and design stress of the pipe material is 85% and 1250kgf/cm 2 respectively. Find the thickness of the penstock pipe. b) A power station is fed through a 10,000m long concrete lined 8 tunnel of 5m diameter operating under a gross head of 200m. The discharge through the tunnel is 30m 3/s. A surge tank of 300 sq. m area has been provided at the end of the tunnel. Calculate : Maximum up surge in the tank Maximum down surge in the tank. Assume friction factor for concrete lining as 0.016. 4. a) Define the following terms with neat sketch: 5 Axis of dam Length of dam Structural height of dam Hydraulic height of dam b) What is reservoir sedimentation? What steps do you suggest to 5 control the reservoir sedimentation? c) A run-of-river hydropower station built across a river working at a 5 load factor of 50% and has an installed capacity of 40 MW, which serves as a peak load station. Find the minimum discharge required for base load if the available net head on the turbine is 50m with overall efficiency of 80%. Find the maximum load factor if the river discharge is 62m 3/s. 5. a) What is spillway? What are the requirements of spillway? Explain 8 the working principle of siphon spillway? b) Explain the application of micro hydro in the context of Nepal 7 6. a) The electric power produced by a hydropower station 98500kW 8 with net head of 65m. If the speed of a turbine is to be 165rpm with overall efficiency of 93%, find the number of units and flow discharge for each unit in that case. When the specific speed of Kaplan turbine is not exceeded by 295. b) Classify turbines in accordance with head, discharge and flow 7 direction? Explain the working principle of centrifugal pump. 7. Write short notes on (Any Two) 5×2 a) Reservoir regulation b) Technical causes of power crisis in Nepal. c) Operating principles of a governor of a hydro turbine.