Time Study
Time Study
to establish the work content of a specified task, and the time required for a qualified worker to
carry out that work at a defined level of performance.
Work Measurement: Work measurement is the application of techniques designed to establish the
time for a qualified worker to carry out a specific job at a defined level of performance.
1
PURPOSE OF WORK MEASUREMENT
1. To find ineffective time in a process
2. To set standard for output level
3. To evaluate worker's performance
4. To plan work force needs.
5. To determine available capacity
6. To compare work methods
7. To facilitate operations scheduling
8. To establish wage incentive schemes
STANDARD RATING
Rating is the assessment of the worker's rate of working relative to the observers' concept of the
rate corresponding to standard pace.
STANDARD PERFORMANCE
It is the rate of output which qualified workers will naturally achieve without over-exertion as an
average over the working day or shift, provided that they know and adhere to the specified
method and provided that they are motivated to apply themselves to their work.
It provides the standard time that is the time needed by worker to complete a job by the
specified method. Therefore for any job, the method of doing it is first improved by method
study, the new method is implemented as a standard practice and for that job to be done by the
new method, and standard time is established by the use of time study. Standard times are
essential for any organization, as they are needed for proper estimation of
manpower, machinery and equipment requirements
daily, weekly or monthly requirement of materials
production cost per unit as an input to selling price determination
labor budgets
Worker’s efficiency and make incentive wage payments.
By the application of method study and time study in any organization, we can thus achieve
greater output at less cost and of better quality, and hence achieve higher productivity.
2
FACTORS AFFECTING RATE OF WORKING
(outside the control of worker)
1. Variation in the quality of materials used
2. Changes in the operating efficiency of the equipment
3. Changes in climatic and surrounding conditions of operation.
FACTORS WITHING THE CONTROL OF WORKER
a. Acceptable variations in the quality of the product
b. Variations due to his ability
c. Variations due to his attitude
Example 1: Time study analyst has recorded average observed time (OT) for machining is
4.0 minutes, The Worker rating is 85% while the allowance factor is 13%. Calculate the
standard time (ST).
Solution:
3
Example 2: The following observation is recorded by time study engineer. Calculate the
standard time considering allowance factor of 15%.
(c) Add the normal times to find the total normal time
Total normal time = 11.40 + 2.31 + 1.65 = 15.36 minutes
Example 3: The time study engineer noted observed time for machining operation as 0.41
minute. The worker is working at 90% rating. The PFD allowance is 13%.Calculate the
standard time for the operation?
4
Assuming normally distributed use the following formula to determine the sample size, n,
for a time study:
Example 4: KFC delivers fresh sandwiches each morning to vending machines throughout the
city. Workers work through the night to prepare the sandwiches for morning delivery. A worker
normally makes several kinds of sandwiches. A time study for a worker making ham and cheese
sandwiches is shown in Time Study Sheet. (a) Calculate the standard Time (b) Calculate the
standard time for sandwich assembly. How many ham and cheese sandwiches can be produced
in a 2-hour? (c) If the average cycle time is 0.361 minutes, and the standard deviation is 0.03
minutes. Calculate the number of cycles for a time study such that it can be 95 percent confident
that the average time computed from the time study is within 5 percent of the true average cycle
time.
Solution:
5
Summary: t Total of individual element, t =Average, RF=Rating Factor, Nt=Normal Time
(b) Calculate the standard time for sandwich assembly. How many ham and cheese
sandwiches can be produced in a 2-hour?
(c) If the average cycle time is 0.361 minutes, and the standard deviation is 0.03 minutes.
Calculate the number of cycles for a time study such that it can be 95 percent confident that the
average time computed from the time study is within 5 percent of the true average cycle time.
The average cycle time = 0.361
Total cycle time for 10 cycles =0.361/10=3.61 minutes
6
CI= 95% , Using z = 1.96 for a probability of 0.95
The time study should include 11 cycles to be 95 percent confident that the time-study average
job cycle time is within 5 percent of the true average job cycle time.
Example 5: A time study engineer measures three elements A,B,C as 18.16,26.97 and 8.85
for 257 cycles. Calculate the standard time if the RF for elements A,B and C is 115,100 and
90.Consider PFD as 8.4
Solution:
7
Example 6: A job having 9 elements is timed for 8 cycles. The average time for each element
and the respective standard deviation is given in table. If 90% CI and 10% accuracy is
recommended. Determine the number of cycles required..
=[(1.645)(0.62)/(0.10)(2.9)]2
=12.37 or 13 cycles for element one
Solution Table: