CC Block Pavement
CC Block Pavement
to
Sr. Item Rate Amount
MORD Description Unit Quantity
No. No. (Rs.) (Rs.)
Specificati
ons
42 6.6 1500 Rectangular Concrete Block Pavement
Manufacturing, laying of cement concrete blocks of size 0.450 m x 0.300 m x 0.15 m of Cement
Concrete (C.C.) M30 garde and spreading 25 mm thick sand under neath and filling joints with sand
on existing W.B.M. base as per Technical Specification Clause 1503.
Unit = sqm
Taking output = 112.5 sqm
Concrete M30 grade for block, 400 x (0.450 x 0.300 x 0.150) cum 8.10
Concrete M30 for edge block, 2 x 50 x (0.300 x 0.300 x 0.150)cum 1.35
TOTAL cum 9.45
a) Labour
Labour for Manufacturing the Cement Concrete Block :
(i) Mate day 1.70 245.00 416.50
(ii) Mazdoor (Unskilled) day 41.00 245.00 10,045.00
(iii) Mason (2nd class) day 6.00 282.33 1,693.98
(iv) Bhisti day 1.40 245.00 343.00
b) Machinery
Concrete mixer 0.28 / 0.4 cum hour 6.00 350.00 2,100.00
Plate vibrator hour 12.00 98.00 1,176.00
Water tanker 6 kl capacity hour 2.00 500.00 1,000.00
c) Material
(i) Coarse aggregates (9.450 x 0.84) cum 7.94 2,048.62 16,266.04
(ii)Sand (9.450 x 0.42) cum 3.97 1,771.04 7,031.03
(iii)
Cement t 3.80 7,899.94 30,019.77
(iv)Sand as per Table 1500.5 cum 1.725 1,771.04 3,055.04
Bed = 60*0.025 = 1.5 cum
Joints = 1.5*0.15 = 0.225 cum
(v) Cost of water kl 6.00 102.00 612.00
d) Formwork @ 3% of (a+b+c) 2,212.75
e) Contractor’s profit & Overheads @ 12.50% on (a+b+c+d) 9,496.39
f) Labour Cess @ 1% on (a+b+c+d+e) 854.68
Cost for 112.5 sqm = a+b+c+d+e+f 86,322.18
Rate per sqm = (a+b+c+d+e+f)/112.5 767.31
Executive Engineer,
Jogindernagar Division,
HP PWD Jogindernagar