Introduction To The Change Request Log Template: (Insert Department/Project Logo) (Insert Department Name)
Introduction To The Change Request Log Template: (Insert Department/Project Logo) (Insert Department Name)
This Change Request Log Template with Instructions contains directions for properly initiating and maintaining the Change Request
Log As you complete the template, please remember to delete all instructional text (including this "Introduction" tab and the
"Instructions" tab) and update the header and footer. Update the document to a minor version (e.g., 1.1, 1.2) when minimal
changes are made and a major version (e.g., 2.0, 3.0) when significant changes are made.
Style Convention
Normal text Indicates placeholder text that can be used for any project
Example text in italics Indicates example text that might be replaced/edited/deleted by user
• Date of Request – The request date associated with the specific Change Request
• Change Request Number – The unique number assigned to identify the specific Change Request
• Change Request Title – The unique name for the change request
• Assigned to – The name of the lead Change Request Analysis / Implementation resource
• Description of Change – Narrative describing the requested change
• Current Status – The current workflow step or disposition for the change request. Typically, one of the following:
- Submitted - The change request has been developed and submitted for consideration
- Accepted - The Change Control Board has accepted the change request and has approved use of project resources for analysis
- Assigned - The Change Request Analysis / Implementation team has been assigned to the Change Request
- Rework - The Change Request has been sent back to a previous step for additional information
- Withdrawn - The Change Request Originator has withdrawn the request
- Deferred - The Change Request has been put on hold until later in the project
- Approved - The Change Control Board has approved the Change Request and the Change Request Analysis / Implementation team's
recommendation
- Completed - the Change Request has been implemented
3 Example
An example Change Log entry is provided on the Change Request Log tab in this workbook. The requested change is to add an additional
technical resource to accommodate project workload.
Date of Request CR# Change Request Title Assigned To Description of Change Current Status Implementation Date
12/22/2015 1 Addition of 1 full time DBA J. Smith Staffing increase to accommodate level of effort in data conversion tasks Approved 1/31/2016