Tutorial 6 Civil Engineering Project & Cost Management
Tutorial 6 Civil Engineering Project & Cost Management
Q1). The activities shown are for the construction of a rotating restaurant on a tower. The
project together with their durations (weeks) and their inter-relationships are as shown in the
table below:
Draw a network for the project.
Calculate the expected duration, standard deviation, and variances for each activity
Using the expected durations determine the ES, LS, EF, LF, TF, FF and the critical path and
calculate the probability of finishing the project in 120 weeks.
Determine the project duration that has a 95% probability of completion
Q2). The activities to be used for the contract program for a small project together with their
durations (in days) and their inter-relationships are as shown in the table below.
Draw a network for the project.
Calculate the expected duration, standard deviation, and variances for each activity
Using the expected durations determine the ES, LS, EF, LF, TF, FF and the critical path and
calculate the probability of finishing the project in 300 days.
Determine the project duration that has a 95% probability of completion
1
Q3). The following table presents a breakdown of the activities in a construction contract
prepared by the project manager based on the prevailing company resources.
a). Calculate the duration of the project using the optimistic, most likely and pessimistic
activity times.
b). what are the chances that the project will be completed in 35 weeks
c). Determine the project duration that has a 95% probability of completion
Duration in weeks
Activity Predecessor Optimistic Most likely Pessimistic
A 4 5 9
B A 4 8 9
C A 6 7 11
D A 5 9 10
E D 3 4 6
F B,E 2 8 9
G C 5 9 10
H G 3 6 8
K F,H 5 6 9
2
Q4). The table gives the activity duration estimates in weeks for a project with nine activities
a). Calculate the duration of the project using the optimistic, most likely and pessimistic
activity times.
b). what are the chances that the project will be completed in 20 weeks
c). Determine the project duration that has a 95% probability of completion
Duration in weeks
Activity Predecessor Optimistic Most Likely Pessimistic
A NONE 1 2 4
B A 5 6 7
C A 2 4 5
D A 1 3 4
E B 4 5 7
F B 3 4 5
G D 1 2 3
H G,C,F 2 3 5
I H,E 2 4 5
Q5). These are two alternative schedules for building six identical houses. In Schedule 1 it
takes 15 weeks to build one house whilst in Schedule 2 it takes 20 weeks to build one house.
Which alternative would result in the quickest project completion time if all activities must be
continuous?
Schedule 1 Schedule 2
Foundations (team A): 3 4
Brickwork (team B): 2 4
Roof construction (team C): 4 4
Internal finishes (team D): 2 4
Services & Connections (team E): 4 4