Rapid Load Testing of Foundation Piles in Barcelona:: Issue
Rapid Load Testing of Foundation Piles in Barcelona:: Issue
IFICATIO
ISSUE: Foundation Piles in Barcelona
UA
Q N
COVER STORY
Verifying the capacity of deep foundations is an important part of An essential part of this test is determining the correct location of
the construction phase of a project. Various pile load test methods the jack assembly such that the resistance above the assembly equals
can be used to verify capacity; two different test methods were used the resistance below it. Otherwise, this test may underestimate the
for such purposes at a project in Barcelona, Spain. axial resistance of the foundation element, as the capacity of the
The construction of an important project in Barcelona began in most resistant section may not be mobilized. Unfortunately, this is
2017. Given the size of the large diameter (1.5 m [5 ft]) cast in-situ exactly what happened with the first bi-directional test performed
piles, specified service loads (between 6 and 8 MN [1,350 and on the project. It was then decided to perform the other load tests
1,800 kip]) and results of the geotechnical site characterization, it using a different method with the understanding that the tests had to
was decided to perform full-scale load tests to ensure that the piles be performed in such a way to not delay the project.
provided the necessary axial resistance. Axial compression load
testing using the bi-directional method was selected for this project. Pile Load Test Methods
With this type of load test, an embedded jack assembly is attached Of the foundation load test methods available, top-down static load
to the steel reinforcement and positioned and cast within the shaft. tests are considered the most reliable. These tests apply a static load
Once the concrete has obtained sufficient strength, hydraulic to the pile, either through weights (i.e., dead load) placed on a
pressure is applied to the jack assembly, which then pushes the two reaction structure on the pile head or, more generally, by anchoring
parts of the shaft (above and below the jack assembly) in opposite the test beam to anchor piles adjacent to the pile being tested. A
directions. The pressure increases gradually until one of the hydraulic cylinder then applies the loading gradually to the pile
sections reaches geotechnical failure or until the assembly’s thrust head, while both the applied load and resulting movement of the
limit (i.e., stroke) is reached. At that time, the test ends and the axial pile head are monitored and recorded. Performing a top-down
capacity of the pile is determined to be at least twice the load that static load test is a long and cumbersome process, both for the
caused the failure. construction of the reaction system and for the test itself. This
Nicolás Moscoso, Allnamics España; Carlos Fernández Tadeo, CFT Asociados; Marcel Bielefeld, Allnamics; and
AUTHORS Gerald Verbeek, Allnamics USA
Test Device
The StatRapid test device used on the Barcelona project consisted of
a main frame, a modular hammer and a system of specially-
designed springs, and was capable of generating a test load up to 12
MN (2,700 kip). The entire system was transported to the site on
three trucks. Once the trucks arrived on site, the test device was
assembled in about three hours due to its modular design.
Measurements used to determine needed to determine static Offloading components of the testing device
resistance using the Unloading Point Method (UPM)