A LifeCycle Cost Analysis of Railway Turnouts Exposed To Climate
A LifeCycle Cost Analysis of Railway Turnouts Exposed To Climate
Abstract. Turnouts are the critical components of modern railway tracks where the vehicle
movement is transferred between two continuing tracks, inevitably resulting in high dynamic
forces on the turnout system which eventually cause the turnout failures. Consequently, the
turnouts have imposed operational restrictions such as operational limits for speed, axle load and
headway, and high maintenance works on the system. Numerous studies have been carried out
to find a mitigation method for turnout failures. Nonetheless, most of the studies consider the
physical phenomena. Hence, it is believed that it would be beneficial to investigate the problem
from the economic aspect. For this purpose, a life-cycle cost analysis is done for turnouts,
particularly crossing nose in this study. Life-cycle cost analysis is a total cost estimate of a system
or a component from acquisition to disposal, to find a cost-effective solution. It could be a simple
analysis based on an expert’s judgement to evaluate the feasibility or complex analysis using
statistical theories covering the uncertainties to decide the budget. In this study, the life-cycle
cost analysis relies on the breakdown work structure based on the reports published by the
biggest Infrastructure Manager in the United Kingdom. Additionally, the effects of extreme
weathers are also concerned while calculating the life-cycle cost. The results indicate that
crossing renewal and tamping activities have high costs similar to miscellaneous maintenance
costs. Another interesting result is that maintenance costs could be as high as acquisition costs.
Finally, crossing nose renewal and maintenance costs seem to occupy high shares in the
maintenance budget.
1. Introduction
Infrastructure Managers (IMs) in the Euro Zone have replied to the question “What infrastructure
characteristics may increase the complexity of your network and impact performance”. IMs indicated
that Switches & Crossings (namely, turnouts) is the top concern[1]. Turnouts are special track systems
designed to change the railway traffic from one route to another route since the railways are naturally
guided systems where the track is continuous. At this section of the track, the dynamic behaviour of the
vehicle transforms from relatively simple to complex and becomes more sensitive to environmental
factors. Therefore, IMs take serious precautions to keep the safety standards high, which increase their
costs. Furthermore, the turnouts restrict the operational speed and increase the possibility of derailment
[2, 3]. As a result, numerous studies have been conducted to deal with the issue. In general, the studies
focus on the physical phenomena such as material properties, dynamic characteristics of the vehicle, the
Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution
of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Published under licence by IOP Publishing Ltd 1
WMCAUS 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 471 (2019) 062026 doi:10.1088/1757-899X/471/6/062026
wheel-rail interaction and environmental effects [4-8] or management strategies such as maintenance
scheduling [9]. Although most of the studies have mentioned the importance of capital expenditure for
switches and crossings, only a few studies consider the economic aspect [10-12]; however, none of them
considers the extreme weather events affecting the system resilience.
Different methods are in use to evaluate the performance of a system from the economic aspect. Life-
Cycle Cost (LCC) analysis is the common one to estimate the total cost originating from different stages
of a long-term investment and to compare alternative systems. Switches & Crossings are expected to
serve at least 30 years and manufactured with many variations, thereby being suitable for an LCC
analysis. In this paper, it is aimed to carry out a life-cycle cost analysis to evaluate turnouts exposed to
climate change from the economic aspect, which may help the Infrastructure Managers to focus on the
specific areas affecting their maintenance and climate change adaptation policies.
2. Methodology
Life cycle cost is an estimate that considers the costs of acquisition, operation, maintenance and disposal
of a system or component. LCC analysis could be used to evaluate the expected economic performance
of a whole system or to compare different systems to achieve the best solution for a problem. Moreover,
LCC analysis could be preliminary to assess the feasibility or elaborate to be used in a bid tender. The
accuracy of LCC analysis relies on the collected historical data and expertise owned by analysts. Higher
accuracy is aimed for tender level works and lower accuracy is acceptable for preliminary works. Due
to the lack of collecting actual and accurate data, a preliminary LCC analysis is preferred in the scope
of this study.
Acquisition, replacement, and maintenance costs are considered in this study. The disposal cost is
included in the maintenance costs since it has relatively low value[12]. All direct costs are assumed as
fixed costs. On the other hand, non-direct costs (i.e. operational delay…) are ignored. Regarding the
nature of the track operation where every case is exclusive, learning ratio is low and so, learning costs
are ignored[13]. Average inflation and labour rates are applied depending on the data published by
Office of National Statistics (Table 1). The advised discount rate of 3.5% is used in order to calculate
Net Presented Value (NVP)[14]. Life-cycle is expected as 30 years[15]. Costs are divided into two
groups such as labour and materials. Estimated costs are presented in (Table 1). All the values estimated
from public reports or the literature [10, 16-22] including labour hours, labour cost per hour and material
costs. The uncertainties are included in the discount rate [14].
2
WMCAUS 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 471 (2019) 062026 doi:10.1088/1757-899X/471/6/062026
The result shown in Figure 1 reveals that a significant difference between acquisition and
maintenance costs could be observed throughout the life-cycle. Even though the material costs are
estimated in a similar range (100-150k pounds), the difference is due to the higher labour share in the
maintenance activities which are based on mainly manpower. As a consequence, the cost mitigation
methods should focus on the labour-oriented costs.
Labour Material
250000
200000
150000
100000
50000
0
Acquisition Maintenance
For control case, it is assumed that the maintenance interval has been determined by the division of
total S&Cs by yearly maintenance capacity. In other words, there is no corrective maintenance and no
delayed maintenance. Maintenance Unit Cost (MUC) and maintenance period are presented in Table 3.
As can be seen from the table, the period for crossing renewal is higher than the S&C life-cycle, which
means that an S&C is likely to complete its life without any crossing replacements in contrast to
switches. A significant difference between switches and crossings failures as regards the frequencies of
occurrence has been observed[25]. Nonetheless, for the control case, the S&C is assumed to be subjected
to at least one replacement since they occupy a significant amount of money in the maintenance budget.
Under these assumptions, a life-cycle cost analysis based on the breakdown work structure is presented
below.
3
WMCAUS 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 471 (2019) 062026 doi:10.1088/1757-899X/471/6/062026
25000
20000
15000
10000
5000
In Figure 3 below, an LCC analysis for different scenarios is presented. Even though small changes
have been applied to the scenarios, significant deviations are visible. It seems that crossing and switch
replacements have a large contribution to the total cost but the LCC is more sensitive to tamping
activities.
4
WMCAUS 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 471 (2019) 062026 doi:10.1088/1757-899X/471/6/062026
200000
180000
160000
140000
120000
100000
80000
60000
40000
20000
0
Sc1 Sc2 Sc3 Sc4 Sc5
5
WMCAUS 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 471 (2019) 062026 doi:10.1088/1757-899X/471/6/062026
100000
90000
80000
70000
60000
50000
40000
30000
20000
10000
0
Normal High Temperature Flood
300000
250000
200000
150000
100000
50000
0
Minimum Maximum Average Average Min Max
Acquisition Replacement Maintenance Total
4. Conclusions
This study has covered the cost issues of switches & crossings as a preliminary cost analysis. For better
or detailed cost analysis, the historical and actual data and the field experience should be harmonised
with advanced cost analysis methods. This kind of work requires a high amount of time and resources.
The study shows that an LCC analysis could show significant variations as a consequence of different
economical parameters, environmental conditions and maintenance policies. Another outcome is that
the maintenance costs are expected to be higher than acquisition costs in the S&C. Besides, the
difference is not because of the material costs as they are in same range but results from labour costs.
6
WMCAUS 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 471 (2019) 062026 doi:10.1088/1757-899X/471/6/062026
Depending on these results, it is recommended that IMs should focus on decreasing labour-oriented
costs, increasing tamping periods and measures for the flood. A final observation is that when
considering only crossing nose effect on the LCC cost, the replacement and maintenance costs have a
serious impact similar to acquisition cost. In conclusion, an investigation providing a better
understanding of the crossing nose degradation will considerably contribute to reducing the total cost.
Acknowledgment(s)
The first author would like to express his gratitude to the Ministry of National Education (MEB) and
ITU for the scholarship. The first author also thanks to Basaksoy Turnout Systems Inc. for sharing their
expertise. The authors sincerely appreciate the European Commission for the project H2020- “RISEN:
Rail Infrastructure Systems Engineering Network”, which provides a global research environment,
www.risen2rail.eu.
References
[1] EIM-EFRTC-CER, Market Strategy Report - Track Maintenance
& Renewal. 2012, The Community of European Railway and Infrastructure Companies
(CER): Brussels.
[2] Dindar, S., et al., Natural Hazard Risks on Railway Turnout Systems. Procedia Engineering, 2016.
161: p. 1254-1259.
[3] Dindar, S., et al., Derailment-based Fault Tree Analysis on Risk Management of Railway Turnout
Systems. IOP Conference Series: Materials Science and Engineering, 2017. 245.
[4] Andersson, C. and T. Dahlberg, Wheel/rail impacts at a railway turnout crossing. Proceedings of
the Institution of Mechanical Engineers, Part F: Journal of Rail and Rapid Transit, 1998.
212(2): p. 123-134.
[5] Kassa, E., C. Andersson, and J.C.O. Nielsen, Simulation of dynamic interaction between train
and railway turnout. Vehicle System Dynamics, 2006. 44(3): p. 247-258.
[6] Pålsson, B.A., Optimisation of railway crossing geometry considering a representative set of
wheel profiles. Vehicle System Dynamics, 2015. 53(2): p. 274-301.
[7] Dindar, S., S. Kaewunruen, and J.M. Sussman, Climate Change Adaptation for GeoRisks
Mitigation of Railway Turnout Systems. Procedia Engineering, 2017. 189: p. 199-206.
[8] Ma, Y., A.A. Mashal, and V.L. Markine, Modelling and experimental validation of dynamic
impact in 1:9 railway crossing panel. Tribology International, 2018. 118: p. 208-226.
[9] Bin Osman, M.H., S. Kaewunruen, and A. Jack, Optimisation of schedules for the inspection of
railway tracks. Proceedings of the Institution of Mechanical Engineers, Part F: Journal of Rail
and Rapid Transit, 2017.
[10] Nissen, A., LCC analysis for switches and crossings: a case study from the Swedish Railway
Network. International Journal of COMADEM, 2009. 12(2): p. 10-19.
[11] Tavares de Freitas, R. and S. Kaewunruen, Life Cycle Cost Evaluation of Noise and Vibration
Control Methods at Urban Railway Turnouts. Environments, 2016. 3(4).
[12] Vitásek, S. and D. Měšťanová, Life Cycle Cost of a Railroad Switch. Procedia Engineering, 2017.
196: p. 646-652.
[13] Nachtmann, E.P.H., Life Cycle Costing, in Decision Making in Systems Engineering and
Management, G.S.P.P.J.D.D.L. Henderson, Editor. 2010, John Wiley & Sons, Inc. .
[14] Lowe, J., Intergenerational Wealth Transfers and Social Discounting: Supplementary Green
Book guidance, H. TREASURY, Editor. 2008, Office of Public Sector Information: London.
[15] Cornish, A., Life-time monitoring of in service switches and crossings through field
experimentation, in Mechanical Engineering. 2014, Imperial College London: London.
[16] Commission, E., Maintenance, Renewal and Improvement of Rail Transport Infrastructure. 2014,
Mainline Project Office: Paris.
[17] Ling, D., Railway renewal and maintenance cost estimating. 2005.
[18] Rail, N., Employment Costs Efficiency Review. 2008: London.
7
WMCAUS 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 471 (2019) 062026 doi:10.1088/1757-899X/471/6/062026
[19] Rail, N., Mandate AO/008: Network Rail Materials Costs Benchmarking Study. 2011: London.
[20] Rail, N., Part A Reporter Mandate AO/030:PR13 Maintenance & Renewals Review. 2013:
London.
[21] Rail, N., Periodic Review 2013: Final determination of Network Rail’s outputs and funding for
2014-19. 2013: London.
[22] Setsobhonkul, S., S. Kaewunruen, and J.M. Sussman, Lifecycle Assessments of Railway Bridge
Transitions Exposed to Extreme Climate Events. Frontiers in Built Environment, 2017. 3.
[23] Statistics, O.o.N. 2018 [cited 2018 01/03/2018]; Available from: https://www.ons.gov.uk/.
[24] Daniels, L.E., Track maintenance costs on rail transit properties. 2008.
[25] Hassankiadeh, S., Failure analysis of railway switches and crossings for the purpose of preventive
maintenance. Royal Institute of Technology, 2011.
[26] Antoni, M. Modelling of the ballast maintenance expenses. in World Congress on Railway
Research 2011. 2011. Lille.
[27] Thomas, S. Turnout grinding: why and how. in AusRAIL PLUS 2016, Rail-Moving the Economy
Forward, 21-23 November 2016, Adelaide, South Australia, Australia. 2016.
[28] Rail, N., Climate Change Adaptation Report. 2015: London.
[29] Esveld, C., Modern railway track. 2001, The Netherlands: MRT Productions.
[30] Rail, N., Climate Change Adaptation Report. 2011: London.
[31] Vu, M., S. Kaewunruen, and M. Attard, Nonlinear 3D finite-element modeling for structural
failure analysis of concrete sleepers/bearers at an urban turnout diamond, in Handbook of
Materials Failure Analysis with Case Studies from the Chemicals, Concrete and Power
Industries. 2016. p. 123-160.