Proposed New Explosive Complex On Lot 4650, Batu 7, Jalan Tras, 28700 Bentong, Pahang Darul Makmur

The document summarizes a client consultant meeting regarding a proposed new explosive complex in Bentong, Pahang. It lists the attendees from the client and various consulting firms. The minutes discuss contractual matters like signing a letter of attorney and non-disclosure agreement. It also outlines the project schedule and timelines for surveys, planning approval, and architectural drawings. Consultants provide updates and request information from each other. The next meeting is scheduled and the current one is adjourned.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views

Proposed New Explosive Complex On Lot 4650, Batu 7, Jalan Tras, 28700 Bentong, Pahang Darul Makmur

The document summarizes a client consultant meeting regarding a proposed new explosive complex in Bentong, Pahang. It lists the attendees from the client and various consulting firms. The minutes discuss contractual matters like signing a letter of attorney and non-disclosure agreement. It also outlines the project schedule and timelines for surveys, planning approval, and architectural drawings. Consultants provide updates and request information from each other. The next meeting is scheduled and the current one is adjourned.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

CLIENT CONSULTANT MEETING

PROPOSED NEW EXPLOSIVE COMPLEX ON LOT 4650, BATU 7, JALAN TRAS, 28700 BENTONG,
PAHANG DARUL MAKMUR.

Date : 3rd Oct 2019 Prepared by:

Time : 3.00 p.m BESTARI CONSULTING ENGINEERS SDN BHD

Venue : TENAGA KIMIA SDN BHD


No. 8, Jalan SS 22/21, Damansara Utama,
47400 Petaling Jaya, Selangor Office.

CLIENT CONSULTANT MEETING NO. 6

Attendance:
No Name Company Contact no Email Address
1 Leong Soon Kit TKSB 012-675 6789 [email protected]
2 Hakeem Hamzah TKSB 012-321 1503 [email protected]
3 Lim Xin Ning TKSB 012-370 3675 [email protected]
4 Adam Leong Weng Kai TKSB 012-511 0982 [email protected]
5 Ir. Muhamad Abdul Rahman BCE 012-500 2091 [email protected]
6 Nusaibah Yusof BCE 017-424 5800 [email protected]
7 Abd Rahman Rosli SAHA 012-660 2695 [email protected]
8 Ahmad Rasydan b Rossidin SAHA 018-243 6169 [email protected]
9 Nurulfarehah Mohamed JUB HRM 014-814 8153 [email protected]
10 Muamar Adib Hakimi HSK Consult 013-370 1554 [email protected]
11 Muhd Shamirul HSK Consult 016-661 2400 [email protected]
12 Zahir Solihin b Zawawi Uniti Consultant 013-985 7216 [email protected]

CCM 06-2019 1
MINUTES OF MEETING

No Descriptions Action by Target Date

1.0 INTRODUCTION

1.1 Chairperson welcomed all representatives from Client and


Consultants.

2.0 CONTRACTUAL MATTERS

2.1 TK is currently finalizing LOA and to be issued to BCE by next week. TK 10th Oct 2019
2.2 Non-Disclosure Agreement (NDA) for main consultants and sub TK
consultant has been signed off and returned to TK.

2.3 TK informed that Power of Attorney Letter (PA) is currently in TK


process and target to be ready by next week.
2.4 TK advised BCE to submit 1st claim due to completion of survey work. TK

3.0 PROJECT SCHEDULE & TIMELINE

3.1 LAND SURVEYOR

3.11 UD completed land surveys for lot 3749, 4931 5031 and 4929, info
3921,4559, 5482, 5483, 5736,26280 & 26279 and has emailed
to all.

3.12 UD to carry out topographic survey for the remaining lot UD 19th Oct 2019

3.13 SAHA requested key plan and location of development area UD


from UD and to email to all parties.

3.2 TOWN PLANNER

3.21 ESP updated that LCP for planning approval is almost done BCE
but still waiting for confirmation of final layout. BCE to confirm
final layout by next week.

3.22 ESP to email temporary title to be used in tender document ESP


and pre-consultation with all correspondent.

3.3 ENVIRONMENTAL CONSULTANT

3.31 UCSB informed not yet received any response about PAT form Info
from DOE

3.32 BCE requested UCSB to arrange a meeting with DOE to appeal UCSB
on consent letter from Jabatan Perancang, KDN and PBT/YDP
for this project.

CCM 06-2019 2
3.4 ARCHITECT, C&S & M&E CONSULTANT

3.41 SAHA informed drawing of buildings will be sent to all Info


progressively.

3.42 TK informed TKAD will be in Phase 2. Info

3.43 BCE to visit existing plant and to proceed on structural analysis. BCE

3.44 SAHA requested final proposed layout plan from BCE to BCE
proceed site plan.

3.45 BCE informed structure drawing will proceed upon final drawing TK
from SAHA. SAHA informed drawing still pending on final
review from TK.
3.46 SAHA requested M&E room & TNB substation location from HSK
HSK.

4.0 OTHER MATTERS

4.1 HRM reminded all drawings to be finalised before 15th Nov 2019 to Info
meet time frame.

4.2 HRM advised this project will be in one contract with separate Info
element and bill (building & retaining structure)

4.3 BCE to set up appointment with En Affandi, Pegawai Perancang MP BCE


Bentong by next week.

5.0 ADJOURNMENT AND NEXT MEETING

5.1 The next meeting is tentatively on Thursday 10th Oct 2019 at 3.00
p.m. Meeting adjourned at 4.30 p.m.