This document is a precommissioning completion checklist for a JTB Utilization Project system. It consists of 13 check items to verify various aspects of instrument serial link function, including: 1) Verifying the control cabinet and panel have been completed 2) Ensuring the correct data communication mapping list is available 3) Checking for updates to the data communication list from iFAT testing 4) Establishing communication channels and checking for abnormalities 5) Performing 100% point-to-point verification according to the mapping list

Uploaded by

Guston Supriyadi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
147 views

Modbus Check Sheet Example

This document is a precommissioning completion checklist for a JTB Utilization Project system. It consists of 13 check items to verify various aspects of instrument serial link function, including: 1) Verifying the control cabinet and panel have been completed 2) Ensuring the correct data communication mapping list is available 3) Checking for updates to the data communication list from iFAT testing 4) Establishing communication channels and checking for abnormalities 5) Performing 100% point-to-point verification according to the mapping list

Uploaded by

Guston Supriyadi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PRECOMMISSIONING COMPLETION

CHECK SHEET
JTB UTILIZATION PROJECT
COMPLETION MANAGEMENT SYSTEM
System No. Sub System No. Discipline
Printed Date Area Unique No
Tag No.
Sub System Description
Equipment Description
Drawing No.

Check Record No. I09PC Instrument Serial Link Function

Specify Type of Serial Cable:

S/N Description Yes N/A P/L No.


I01-PC (Control Cabinet & Panel) has been completed for the respective
1
system
Ensure the data communication mapping list is available with the correct
2
revision and attached to this report.
Ensure iFAT report is available, and identify if there is any update on the
3
data communication list or not.
Establish the communication channel and ensure there is no abnormality
found.
4
With reference to data communication mapping list, perform 100% point to
point check (refer to point-5 ~ point-8)

DIGITAL SIGNAL
5 Verify that digital signals function correctly.
6 Verify that normally open / normally closed connections are correct.

ANALOG SIGNAL
7 Verify that analog signals function correctly.
8 Verify that analog signals are scaled properly.

CABLE REDUNDANCY
9 Perform communication redundancy check (if applicable)
10 Perform communication failure alarm

AFTER TEST
Confirm the device is left in the proper state once completion of loop test
11 activity has been carried out (No bypass, no force item, terminal cover is
closed, no overrides etc.)
Red line latest issue of design drawings for “As-Built” information (showing
12
FCN number)
Ensure all temporary bypass, connection, and settings are to be normalized
13 after pre-commissioned. Should they are to be normalized later, they shall
be recorded in punch list category ‘C’.

Test Equipment
Maker: Model: S/N: Exp. Cal. Date:
Maker: Model: S/N: Exp. Cal. Date:
Maker: Model: S/N: Exp. Cal. Date:
Maker: Model: S/N: Exp. Cal. Date:
Maker: Model: S/N: Exp. Cal. Date:

I09PC Rev. 0 P1/2


PRECOMMISSIONING COMPLETION
CHECK SHEET
JTB UTILIZATION PROJECT
COMPLETION MANAGEMENT SYSTEM
System No. Sub System No. Discipline
Printed Date Area Unique No
Tag No.
Sub System Description
Equipment Description
Drawing No.

Check Record No. I09PC Instrument Serial Link Function

Remarks:

Outstanding Punch List attached? ( Yes / No )


Description Completed By Verified By Accepted By Witnessed By Input By
COMPANY
CONTRACTOR CONTRACTOR Third Party /
Company / Dept Commissioning/ CMS Admin
Pre-commissioning System Completion Regulatory
Start-Up
Name

Signature

Date

I09PC Rev. 0 P2/2