Mels Constuction Limitada: Commercial Management Mechanical Completion Certificate

The document is a Mechanical Completion Certificate for the Matola Condensate Export Pumps project. It certifies that the condensate line and associated mechanical equipment and piping are mechanically complete according to engineering drawings and specifications. All punch list items have been signed off and as-built drawings and QA/QC documents have been provided. Representatives from MELS Construction and Petromoc have signed to accept mechanical completion and transfer of responsibility for the system to the client.

Uploaded by

Deon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
571 views

Mels Constuction Limitada: Commercial Management Mechanical Completion Certificate

The document is a Mechanical Completion Certificate for the Matola Condensate Export Pumps project. It certifies that the condensate line and associated mechanical equipment and piping are mechanically complete according to engineering drawings and specifications. All punch list items have been signed off and as-built drawings and QA/QC documents have been provided. Representatives from MELS Construction and Petromoc have signed to accept mechanical completion and transfer of responsibility for the system to the client.

Uploaded by

Deon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Document Number

MELS CONSTUCTION LIMITADA MEL-MCC-001


Revision Number/Date
COMMERCIAL MANAGEMENT 01 OCT 2017
Page Number
MECHANICAL COMPLETION CERTIFICATE Page 1 of 1

PROJECT No: TITLE: EXPORT PUMPS


UNIT No: PUMP 1 / 2 UNIT DESCRIPTION: MATOLA CONDENSATE EXPORT PUMPS
NOTICE OF MECHANICAL COMPLETION (MC) FOR CONDENSATE LINE - MATOLA
System No.: Condensate System Title: Export Pumps
Reference Drawing Numbers: MEL-CON-EXP-DWG-001

The Managing Contractor advises that the above plant system comprising the mechanical equipment and piping (within the system) as per the
attached AS Built engineering drawings and specifications and is considered to be "mechanically complete".

The mechanical equipment and piping are complete;


Painting have been completed, as applicable;
All Category 1 punch items have been signed-off;
Hand marked-up, as-built drawings have been provided;
All QA/QC information relevant to the equipment within the Condensate system has been provided, as per project requirements
ADVISED BY RESPONSIBILITY NAME & SURNAME SIGNATURE DATE
AGREED BY
MELS TECHNICAL REP

MELS MECHANICAL REP

ACCEPTANCE OF MECHANICAL COMPLETION (MC) FOR OFF LOADING GANTRY


Client confirms acceptance that the above plant system is mechanically completed and hence accepts transfer of care, custody and control for the
system. Client, as employer/user of machinery, becomes legally responsible for the system under the Mozambique Safety Regulator.

Attachments: - list of signed-off checkout forms;


- list of signed-off equipment box-up certificates;
- marked-up ISOMETRIC’s showing scope of system;
- signed-off Category 1 punch lists;
- Category 2 punch list (correction by sub-section RFC);
- Category 3 punch list (correction by sub-section RFO).

RESPONSIBILITY COMPANY NAME & SURNAME SIGNATURE DATE

OPERATIONS MANAGEMENT PETROMOC - MATOLA

TECHNICAL MANAGEMENT PETROMOC - MATOLA

RFC – Ready for Commissioning


RFO – Ready for Operation