0% found this document useful (0 votes)
30 views

Government College of Technology Mingora Swat: Networking Among All The Computers in Labs & Offices

The document discusses two topics: 1) Networking among all the computers in labs and offices at the Government College of Technology in Swat is being established. Networking has been completed in one lab, while the other two labs are delayed due to class schedules but will be finished by the end of February. 2) A survey found some CCTV cameras at the college were not working. As the cameras cannot be repaired, new cameras have been purchased and will be installed by the end of the week.

Uploaded by

Naveed Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views

Government College of Technology Mingora Swat: Networking Among All The Computers in Labs & Offices

The document discusses two topics: 1) Networking among all the computers in labs and offices at the Government College of Technology in Swat is being established. Networking has been completed in one lab, while the other two labs are delayed due to class schedules but will be finished by the end of February. 2) A survey found some CCTV cameras at the college were not working. As the cameras cannot be repaired, new cameras have been purchased and will be installed by the end of the week.

Uploaded by

Naveed Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

GOVERNMENT COLLEGE OF TECHNOLOGY

MINGORA SWAT
Ph: # 0946-9240198; Fax: # 0946-9240202, E-mail: [email protected]

No.GCT/Mng/PF/__ ____ Dated: ___ /____ /2020

To

Deputy Director ICT,

KP-TEVTA.

Subject: NETWORKING AMONG ALL THE COMPUTERS IN LABS & OFFICES

In response to letter No. KP-TEVTA/ICT/NW/439(1-3) dated on 29-01-2020, it is to

inform that the work has been initiated on the subjected matter. Networking has been

established in one of the labs. The other two labs were delayed due to the tough schedule of

DIT classes.

Currently, networking of 2nd lab is in progress and by the end of the February the

above subjected task will be accomplished.

Principal

Govt. College of Technology, Swat.

Dated:
GOVERNMENT COLLEGE OF TECHNOLOGY
MINGORA SWAT
Ph: # 0946-9240198; Fax: # 0946-9240202, E-mail: [email protected]

No.GCT/Mng/PF/__ ____ Dated: ___ /____ /2020

To

Deputy Director ICT,

KP-TEVTA.

Subject: REPAIR/ MAINTANANCE OF CCTV CAMERA SYSTEM

In response to letter No. KP-TEVTA/ICT/R&M/400(1-4) dated on 29-01-2020 it is to

inform that a complete survey of the system was conducted to identify the issues in the CCTV

Camera system. Some of the cameras were found out of order.

As per recommendation of the expert form the local market the cameras are

beyond repair. Therefore, new cameras have been purchased and it will be installed by the end

of this week.

Principal

Govt. College of Technology, Swat.