Final Assignment - BBA 2020 Opm
Final Assignment - BBA 2020 Opm
Assignment # 1:
Q#1: The assembly line involves only 13 work elements and must handle 20 cars per hours.
Work-element data are as follows: 10 points
Assignment 2:
Q#1: A supplier for Cure Hospital has introduced quantity discounts to encourage larger order
quantities of a special catheter. The price schedule is as follows: 3 points
Q#2: The average demand for sweaters is 100 per week. The production facility has the capacity
to sew 400 sweaters per week. Setup cost is $351. The value of finished goods inventory is $40
per sweater. The annual per unit inventory holding cost is 20 percent of the item’s value. 6
points
Q#3: A company begins a review of ordering policies for its continuous review system by
checking the current policies for a sample of SKUs. Following are the characteristics of one
item. 6 points
Assignment #3:
Activity Optimistic Time Most Likely Time (days) Pessimistic Time (days) Predecessors
(days)
A 10 22 22 None
B 20 20 20 None
C 4 10 16 None
D 2 14 32 A
E 8 8 20 B, C
F 8 14 20 B, C
G 4 4 4 B, C
H 2 12 16 C
I 6 16 38 G, H
J 2 8 14 D, E
Assignment #4:
Activity Normal Time Normal Cost Crash Time (weeks) Crash Costs Predecessors
(weeks) ($) ($)
A 5 2000 3 4,000 None
B 8 5000 7 8,000 None
C 10 10,000 8 12,000 A
D 4 3,000 3 5,000 A, B
E 3 4,000 2 5,000 B
F 9 8,000 6 12,000 D
G 2 2,000 2 2,000 E, F
H 8 6,000 5 9,000 G
I 9 7,000 7 11,000 C, F
There is a $1000 per-week penalty for each week the project is delayed beyond week 25. In
addition, your project team determined that indirect project costs are $2,500 per week. 5 points
GOOD LUCK