The document provides a unit price breakdown for a 6m wide asphalt road that is 1 meter in length. It lists the unit rates and percentages of the total unit price of AED 981 for various components including completion of the sub granular base (37.1% of cost), granular base (23.85%), bitumin base (24.87%), and asphalt layer (14.17%). The total unit price to complete a 1 meter section of the 6m wide asphalt road is AED 981.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
254 views
Unit Rate % Breakdown For Asphalt Road
The document provides a unit price breakdown for a 6m wide asphalt road that is 1 meter in length. It lists the unit rates and percentages of the total unit price of AED 981 for various components including completion of the sub granular base (37.1% of cost), granular base (23.85%), bitumin base (24.87%), and asphalt layer (14.17%). The total unit price to complete a 1 meter section of the 6m wide asphalt road is AED 981.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1
A Asphalt Road 6m Wide = AED 981.
00 per MTR Length Unit Price Breakdown
S.No Descriptions Unit Rate per (6m Wide x 1m Length)
% of Unit Price A-1 Completion of Sub Granular Base Qty Unit Unit Rate Sub Total Unit Price a) Marking & Setting out 1 MTR 44.00 b) Cutting of Existing Ground Level & Disposal 1 MTR 40.00 c) Grading & Leveling of Sub Surface 1 MTR 40.00 d) Compaction 1 MTR 50.00 e) Sub Granular Base & Compaction 1 MTR 180.00 f) Test & Completion 1 MTR 10.00 364.00 37.10%
A-2 Completion of Granular Base
a) Marking & Setting out 1 MTR 44.00 b) Sub Granular Base & Compaction 1 MTR 180.00 c) Test & Completion 1 MTR 10.00 234.00 23.85%
A-3 Completion of Bitumin Base
a) Marking & Setting out 1 MTR 44.00 b) Bitumin Base & Compaction 1 MTR 190.00 c) Test & Completion 1 MTR 10.00 244.00 24.87%
A-4 Completion of Asphalt Layer
a) Marking & Setting out 1 MTR 44.00 b) Asphalt Layer & Compaction 1 MTR 85.00 c) Test & Completion 1 MTR 10.00 139.00 14.17%