0% found this document useful (0 votes)
306 views93 pages

Company-Profile 01 PDF

SINAMM Engineering Limited is a construction company based in Dhaka, Bangladesh. It was founded in 2004 by a team of engineers and professionals with experience in construction. The company has completed many projects including industrial buildings, power plants, apartments, offices, roads and highways. The management team includes the Chairman, Managing Director, and several Directors who have engineering or business backgrounds. The organization chart shows the company structure with directors leading divisions for construction, planning, logistics, and finance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
306 views93 pages

Company-Profile 01 PDF

SINAMM Engineering Limited is a construction company based in Dhaka, Bangladesh. It was founded in 2004 by a team of engineers and professionals with experience in construction. The company has completed many projects including industrial buildings, power plants, apartments, offices, roads and highways. The management team includes the Chairman, Managing Director, and several Directors who have engineering or business backgrounds. The organization chart shows the company structure with directors leading divisions for construction, planning, logistics, and finance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 93

SINAMM

ENGINEERING LIMITED

Company Profile

www.sinammengineering.com
P R O F I L E

TABLE OF CONTENTS.
SINAMM ENGINEERING LIMITED
TABLE OF CONTENTS

SECTION 1 OFFICEADDRESS

SECTION 2 MANAGEMENETTEAM

SECTION 3 ORGANIZATIONCHART

SECTION 4 FIELDOFSPECIALIZATIONOFMANAGEMENTTEAM

SECTION 5 WORKFORCE

SECTION 6 LISTOFPLANT&EQUIPMENT

SECTION 7 LISTOFCOMPLETEDPROJECTS

SECTION 8 LISTOFONGOINGPROJECTS

SECTION 9 LISTOFSISTERORGANIZATION

SECTION 10 ENGINEERINGSERVICES

SECTION 11 PROJECTMANAGEMENT

SECTION 12 WORKCERTIFICATIONLIST

SECTION 13 PHOTOGRAPHICPRESENTATIONOFSITEACTIVITY

SINAMM ENGINEERING LIMITED


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

ABOUT US

SINAMM ENGINEERING LIMITED named as SINAMM was conceived and formed in the year 2004 by a
teamofqualifiedEngineersandotherprofessionalspossessinglongstandingexperienceinvariousfields
of Constructional activities with a vision and mission and to play a significant role in development and
constructionsectorinnearfuture.

Construction, more than any industry, is indeed a serviceprofession, the lure of becoming a civil
engineeringcontractorattractsmany,butnotallcansurvivethischallenges.Manygiveupduetolackof
experience or inability to tackle the hazards involved. SINAMM has started the journey to take these
challengesandisdeterminedtoexistitsexcellenceinthefieldofconstructionsuchasbuildings,industry
andinfrastructureprojectsthroughinnovativeplanningandemployinglatesttechniqueswithcontinuous
advancement. We believe that our dedication, commitment, technical superiority, experienced human
resourcesandcollectivemanagementeffortswillensurequality,accuracyandtimelycompletionofwoks
fortheprospectiveclients.

The top management of SINAMM during the tenure of last 21 years played the key role in the field of
construction through Planning, Evaluation, Tendering,Monitoring, Supervision & Execution of industrial
building,Powerplants,HighriseApartments,Officebuildings,Commercialbuildings,RoadsandHighways
projects,Watersupply,SanitationandDeeptubwellprojects.

 Finally, keeping pace with rapid economical and technological changes, we are determined to put
ourselves in the front line of Construction sector through our works in future to build a planned,
productiveandhealthierenvironmentaroundus.SINAMMEngineeringLimitedbelievesinteamwork.We
feel proud to have a very strong team and we are confident to achieve our goals and objectives with
accuracy.WearededicatedtoprovidemostefficientandeffectiveskillsintheCountry.Weareworking
continuouslytoimproveoursystemtoprovidebestandefficientservicestoourclientsandalsotomatch
withtheupcomingdays.
P R O F I L E

SECTION 1
OFFICE ADDRESS.
SINAMM ENGINEERING LIMITED
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (hunting),9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

OFFICE ADDRESS
SINAMM ENGINEERING LIMITED PHONE :9103510(HUNTING)
      FAX :88029120031
Email :[email protected],[email protected]
WEB :www.sinammengineering.com

SINAMM ENGINEERING LTD


HOUSE # 57/C, ROAD # 15/A
DHANMONDI, R/A, DHAKA
P R O F I L E

SECTION 2
MANAGEMENT TEAM
SINAMM ENGINEERING LIMITED
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

MANAGEMENT TEAM

SINAMMEngineeringLimitedbelievesinteamwork.Wefeelproudtohaveaverystrongteamandweare
confidenttoachieveourgoalsandobjectiveswithaccuracy.Wearededicatedtoprovidemostefficientand
effective skills in the Country. We are working continuously to improve our system to provide best and
efficientservicestoourclientsandalsotomatchwiththeupcomingdays.

 We

EDUCATION:

Bachelor of Science in Civil Engineering


Graduated from Bangladesh University of Engineering & Technology (BUET) in 1984

ENGR.MATIURRAHMAN.Chairman

EDUCATION:

Bachelor of Science in Civil Engineering


Graduated from Bangladesh University of Engineering & Technology (BUET) in 1984

ENGR.NASIMAHMED.ManagingDirector

EDUCATION:

M .Com . (Accounting)
Dhaka University in 1988

MD.IMTIAZHOSSAIN.Director

EDUCATION:

B.sc (Hons.) & M.sc in Applied Physics & Electronics


Rajshahi University
MBA in Marketing
Mid-West Missouri University, USA
Scholastic Group, Bangladesh Centre

SARWARAHMED.Director

EDUCATION:

Bachelor of Science in Civil Engineering


Graduated from Bangladesh University of Engineering & Technology (BUET) in 1983


ENGR.A.N.M.IRSHAD.Director
P R O F I L E

SECTION 3
ORGANIZATION CHART.

SINAMM ENGINEERING LIMITED


House#75,Road#7/A,DhanmondiR/A,Dhaka–1209.Tel:9128256,8143583,8141434,8143675.Fax:88029120031Email:[email protected]

ORGANIZATION CHART

BOARD OF DIRECTORS

DIRECTORS DIRECTORS DIRECTORS DIRECTORS DIRECTORS


CONSTRUCTION (I) CONSTRUCTION (II) PLANNING LOGISTICS FINANCE

01 02 03 04 05 06 07 08 09 10 11 12 13
ASHUGANJ225MWCOMBINEDCYCLE
POWERPLANTATASHUGANJ(PILING
WORKS,TEMPORARYWORKS,CIVIL&
TENDERING&COSTANALYSIS

BUILDINGANDC.W.INTAKESYSTEM
EQUIPMENTMAINTAINANCE
GENERALADMINISTRATION

MATERIALSPROCUREMENT
SCHEDULING&REPORTING

WORKS)
DESIGN&DRAWING
SAFETY&CONTROL
QUALITYCONTROL
ESTIMATING

ACCOUNTS
PLANNING

BILLING

STORE



























P R O F I L E

SECTION 4
FIELD OF SPECIALIZATION OF
MANAGEMENT TEAM
SINAMM ENGINEERING LIMITED
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

FIELD OF SPECIALIZATION OF MANAGEMENT TEAM


Aprojectisconsideredasagroupofactivitieshavinginterrelationswhichmayincludetheroleofspecialistsandspecialized
workusingthelatestknowledgeandskillavailabletobeundertakeninthemostsystematicmanner.Wehavewideexperience
in construction management and project implementation in last 22 years. In past two decades we achieved the followings
successfullywithoptimismcourageandgoodjudgment.

 Architecture,Engineering,Planning,Designing,Costestimation&workexecution.
 Planning,Programming,Organizing,Staffing,Scheduling,Monitoring&ControllingofProject.
 Architectural,Structural,Sanitary&PlumbingandElectroMechanicalDesignwork.
 SubsoilInvestigationwork.
 Planning,Design&ImplementationofCentralAirConditionPlant&FireFightingSystem.
 Planning,Design&ImplementationofHighVoltageTransmissionLine.
 ExecutionofGridSubstationwithEngineeringManagement.
 ExecutionofPowerPlantwithEngineeringManagement.
 Planning,Design,ProcurementofLandandexecutionofHighriseCommercialBuilding.
 3(Three),2(Two)&SinglelevelBasementconstructionworkwithtotalEngineeringsolution.
 FactoryBuildingConstructionwithArchitectural,StructuralDesignusingPreEngineeredsteelroofingsystem.
 ConstructionofDeepTubewell&Irrigationproject.
 ConstructionofRoad,HighwaywithtotalEngineeringManagement.
 Constructionofwatertreatment&effluenttreatmentplan.
 From6to25storiedApartmentBuildingConstructionwork.
 Joborganization,equipmentdeploymentandmaintenance,qualitycontrol,officeadministration,accountingtechniques,
legaluspect,employment&labourrelations,publicrelations,safetyrules&regulations,willingnesstoworkalmostround
theclock,abilitytoorganizeteamwork,delegate,responsibilityandgiveduetoimportancetothekeypersonnel.
 AmbassadorResidenceconstructionworkunderforeignmission.
 Form site hunting to BASE TRANSCEIVER SWITCH (GTS) including telecommunication tower erection work under mobile
phoneserviceprovider.
 Interiordesignandexecutionworkforbothresidentialapartmentandcommercialbuilding.
P R O F I L E

SECTION 5
WORK FORCE.
SINAMM ENGINEERING LIMITED
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (hunting),9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

WORK FORCE :

CIVILGRADUATEENGINEER   =48
  ELECTRICALGRADUATEENGINEER   =03
  MECHANICALGRADUATEENGINEER  =03
  CIVIL/ELECTRICAL/MECHANICAL(DIPLOMAENGR.) =94
  SURVEYOR      =11
  CADOPERATOR     =03
  EQUIPMENTANDVEHICLEOPERATOR  =65
  MECHANIC/ELECTRICIAN/WELDER/FITTER  =50
  PROCUREMENTTEAM    =18
  ACCOUNTSTEAM     =32
  OTHERS      =159

TOTAL=486
P R O F I L E

SECTION 6
LIST OF PLANT & EQUIPMENT.
SINAMM ENGINEERING LIMITED
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting) , 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

COMPANY OWNED EQUIPMENT/TOOLS LIST


SL NO NAME OF EQUIPMENT QUANTITY
1 Concrete Batching Plant – 30 m3/hr 6 Nos
2 Transit Mixture – 6 m3 Capacity 8 Nos
3 Wheel Loader 2 Nos
4 Vibro Hammer – FAV 418L 1 Nos
5 Power Pack – FAV 400 1 Nos
6 Excavator – CAT 320 N – 0.7 m3 7 Nos.
7 Dump Track – 9 m3 15 Nos.
8 Pump Car – 30 m Boom 1 Nos
9 Crane – 20 ton 1 Nos
10 Dozer –D6 2 Nos
11 Tower Crane-50 m boom, 1.25 ton tip load 1 Nos.
12 Dozer –D7 1 No.
13 Concrete Pump Stationary 5 Nos
14 Road Roller (Capacity : 10 ton to 3.5 ton) 4 nos.
15 Sub soil investigation Equipment set 4 sets
16 Cast-In-Situ Pile Driving Equipment 25 sets
17 Static Pile Driver-340 TON 1 No
18 Pile Load Testing Equipment 3 sets
19 Mixture Machine with hopper 10 Nos.
20 Weigh Batcher 4 Nos.
21 Concrete Vibrator - Electrical 50 Nos.
22 Concrete Vibrator - Diesel 15 Nos.
23 Welding Set 40 Nos.
24 Shuttering/ Centering Materials 10,000 SQM
25 Scaffolding Materials 17,500 Pcs
26 Steel Props 25,000 Pcs
27 Water Pump Submersible Pump 30 Nos
28 Air Compressor 1 Nos.
29 Gondola/Passenger Hoist 1 set
30 Tower Hoist with 120’-0” Tower 1 set
31 Roof Hoist 5 nos
32 Diesel Generator (From 300 KVA to 50 KVA) 20 set
33 Laboratory Test Equipment 4 set
34 Rammer Machine 10 nos.
35 Plate type soil compactor 5 set.

36 Total Station 8 Nos.

37 Leveling Instrument 10 Nos.

38 Pipe Bending Machine 2 set

39 Personal Computer 35 Nos.


40 Tele fax 1 Nos.
41 Photocopier 10 Nos.
42 Truck 4 Nos.

43 Tractor with Trailor 3 Nos.


44 Pickup 3 Nos.
45 Motor Cycle 4 Nos.
46 Microbus 1 No.
47 Ampere Meter 3 Nos.
48 Car 10 Nos.
P R O F I L E

SECTION 7
LIST OF COMPLETED PROJECTS..
SINAMM ENGINEERING LIMITED
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF COMPLETED PROJECT

PROJECT DURATION
PROJECT NAME AND NATURE CLIENT WORK VALUE
(IN MILLION BDT) START FINISHED

DESIGN & BUILT OF SHOE FACTORY BUILDING. AT ADAMJEE SUPER PROTECTIVE SHOES (PVT.) LTD.
42.50 20 11 2007 15 09 2008
EPZ, NARAYANGONJ. MR. DANKO SERGIY

EARTH FILLING WORKS OF PANCHAGOR 132/33 KV CHINA NATIONAL ELECTRIC WIRE & CABLE IMP/EXP.
6.50 25 04 2008 15 09 2008
SUBSTATION. CORPORATION (CCC)

SHIKHALBAHA 150 MW POWER PLANTS, CHITTAGONG.


 Sub soil investigation work.
 Construction of Pile testing.
SINOHYDRO CORPORATION LIMITED 45.00 01 09 2008 01 03 2009
 Construction of 2nd level over existing BPDB rest
ZHOU XIAOLIN
house building.
 Construction of cast-in-situ R.C.C. Piling works
CONSTRUCTION OF 132/33 KV NEW SUBSTATION IN
CHINA NATIONAL ELECTRIC WIRE & CABLE IMP.
JAYPURHAT UNDER PGCB AGAINST CONTRACT NO: 51.20 01 05 2009 30 06 2010
/EXP. CORPORATION (CCC).
PGCB/SPSDP/SS/LOT-2.

KPM, CHANDRAGHONA. RANGAMATI HILL DISTRICT,


MARUBENI CORPORATION 81.00 25 09 2009 31 08 2010
BANGLADESH, CIVIL WORKS CONTRACT.

AIRTEL, ROBI, HUIWEI, GRAMEEN PHONE, BANGLALINK ERICSSON AB


667.50 01 03 2005 05 12 2010
TELECOMMUNICATION ROLLOUT PROJECT MR. AHSAN HABIB

CONSTRUCTION OF 6-STORIED FACTORY BUILDING AT PLOT BENGAL REMEDIES LIMITED, Paragon House (6th
80.90 16 08 2009 07-04-2011
# A-114, BSCIC INDUSTRIAL AREA, TONGI, GAZIPUR. Floor) , 5, Mohakhali C/A, Dhaka-1212, Bangladesh

Page 1 of 7
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF COMPLETED PROJECT

PROJECT DURATION
PROJECT NAME AND NATURE CLIENT WORK VALUE
(IN MILLION BDT) START FINISHED

CONSTRUCTION OF UNIT RESIDENTIAL BUILDING AT PLOT


RAJIB SAMDANI 50.00 05 01 2010 30 06 2011
NO-09/B, ROAD NO-12, GOLPO, GULSHAN-1.

BANGLADESH POWER DEVELOPMENT BOARD


CONSTRUCTION OF 70 MW PEAKING POWER PLANT, UNDER
324.01 30 06 2010 30 08 2011
UPAZILLA BERA, DISTRICT PABNA.[TOTAL CIVIL WORKS]
HYUNDAI HEAVY INDUSTRIES LTD.

CONSTRUCTION OF APATRMENT PROJECT


CIRCLE WIND FLOWER. AT PLOT -30, SECTOR-11, CIRCLE HOLDING LTD. 200.00 Jun 2009 Dec 2011
SONARGAON JANAPATH, UTTARA, DHAKA

GAS TRANSMISSION COMPANY LIMITED


COMPRESSOR STATION PROJECT. TEMPORARY FACILITY
57.30 01 07 2012 30 10 2012
WORKS ASHUGANJ
HYUNDAI ENGINEERING CO. LTD

GAS TRANSMISSION COMPANY LIMITED


COMPRESSOR STATION PROJECT. TEMPORARY FACILITY
58.80 01 07 2012 30 10 2012
WORKS ELENGA.
HYUNDAI ENGINEERING CO. LTD

DESIGN –BUILT OF TWO STORIED MULTI PURPOSE CYCLONE


MINISTRY OF EDUCATION
SHELTER (MPCS/SCHOOL) BUILDING AT PACHAPALLI SHAHID 27.50 14 12 2011 15 12 2012
US ARMY CORPS OF ENGINEERS, ALASKA DISTRICT
ZIA, NARAIL.
CONSTRUCTION OF GATE HOUSE, SCHOOL BUILDING,
DORMITORY, DINING & CLINIC, OVER HEAD WATER TANK,
BOUNDARY WALL AND LAND DEVELOPMENT WITH
UTSHO BANGLADESH 78.00 22 09 2011 26 02 2013
INTERNAL ROAD OF UTSHO VILLAGE INCLUDING SANITARY
AND ELECTRICAL WORKS AT KOPATIA PARA, JONAKI
CHOURASTA, SREEPUR, GAZIPUR

Page 2 of 7
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF COMPLETED PROJECT

PROJECT DURATION
PROJECT NAME AND NATURE CLIENT WORK VALUE
(IN MILLION BDT) START FINISHED

CONSTRUCTION OF UNIT RESIDENTIAL BUILDING HOUSE FARIDUR REZA SAGOR


140.00 17 07 2010 15 03 2013
NO-46, ROAD NO-23,BANANI,DHAKA CHANEL I

POWER GRID COMPNAY OF BANGLADESH LIMITED


CONSTRUCTION OF 132/33 KV GIS AT CANTONMENT,
49.23 01 04 2012 30 10 2013
DHAKA.
SIMENS BANGLADESH LTD
FAEL KHAIR PROGRAM : CONSTRUCTION OF SCHOOL –CUM-
CYCLONE SHELTER AT PIROJPUR & BARGUNA DISTRICTS LGED
340.70 01 08 2012 31 01 2014
UNDER CONTRACT NO BDT-17, PACKAGE -3, (TOTAL 10 NOS ISLAMIC DEVELOPMENT BANK
OF CYCLONE SHELTER)
DESIGN –BUILT OF TWO STORIED -6 NOS OF MULTI
MINISTRY OF EDUCATION
PURPOSE CYCLONE SHELTER (MPCS/SCHOOL) BUILDING AT 168.30 08 09 2012 31 03 2014
US ARMY CORPS OF ENGINEERS, ALASKA DISTRICT
JESSOR AND RANGPUR DISTRICT.

COMPRESSOR STATION PROJECT. ELECTRICAL & GAS TRANSMISSION COMPANY LIMITED


30.50 01 03 2013 31 03 2014
INSTRUMENT WORKS AT ELENGA. HYUNDAI ENGINEERING CO. LTD

CONSTRUCTION OF FOUR STORIED SINGLE FAMILY KISWAR JAHAN


150.00 14 02 2010 30 04 2014
DWELLING AT PLOT-67, ROAD NO. 5, D.O.H.S, BANANI EPYLLION GROUP

Page 3 of 7
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF COMPLETED PROJECT

PROJECT DURATION
PROJECT NAME AND NATURE CLIENT WORK VALUE
(IN MILLION BDT) START FINISHED
CONSTRUCTION OF NEW HARIPUR 360 MW POWER PLANT
PROJECT- BUILDING WORKS
 Gas Turbine Building
 Gas Turbine Foundation
 Steam Turbine Building & Foundation ELECTRICITY GENERATION COMPANY OF
 Chemical dosing Shelter BANGLADESH LIMITED 421.13 25 12 2009 30 05 2014
 Service Gas Shelter HYUNDAI ENGINEERING & CONSTRUCTION CO. LTD
 Watch tower
 Fuel gas compressor
 Electrical Building

CONSTRUCTION OF FACTORY BUILDING OF DEKKO


KNITWEARS LTD AT EPYLLION GROUP AT KUTUBPUR, EPYLLION GROUP. 270.00 24 12 2012 31 05 2014
NARAYANGANJ.

CONSTRUCTION OF CIVIL FINISHING WORKS, NINAKABBO,


EPYLLION GROUP 105.00 15 07 2011 30 06 2014
PLOT # 227/A, TEJGAON INDUSTRIAL AREA, DHAKA

FAEL KHAIR PROGRAM : CONSTRUCTION OF SCHOOL –CUM-


CYCLONE SHELTER AT BHOLA DISTRICTS UNDER CONTRACT LGED
503.40 10 02 2013 11 08 2014
NO BD1-23, PACKAGE -7, (TOTAL 11 NOS OF CYCLONE ISLAMIC DEVELOPMENT BANK
SHELTER)

MSC -3 & DATA CENTER AIRTEL BANGLADESH LTD 187.20 10 03 2013 31 12 2014

Page 4 of 7
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF COMPLETED PROJECT

PROJECT DURATION
PROJECT NAME AND NATURE CLIENT WORK VALUE
(IN MILLION BDT) START FINISHED
SERVANSINGH JADAV AND PARTNERS
CONSTRUCTION OF PHASE 2A BUILDING AND EFFLUENT CONSULTING ENGINEERS LTD
TREATMENT PLANT IN BANGLADESH FOR DIGNITY TEXTILE 7 REMY OLLIER STREET 25 03 2012 31 12 2014
MILLS LIMITED BEAU BASSIN 535.03
MAURITIUS
BPDB-RPCL POWERGEN LIMITED
CONSTRUCTION OF KODDA 150 MW POWER PLANT
CHINA NATIONAL ELECTRIC WIRE & CABLE IMP. 521.80 28 01 2014 28 01 2015
PROJECT, GAZIPUR . [TOTAL CIVIL WORKS]
/EXP. CORPORATION (CCC).
FAEL KHAIR PROGRAM : CONSTRUCTION OF SCHOOL –CUM-
LGED
CYCLONE SHELTER AT PATUAKHALI DISTRICTS UNDER
306.10 01 02 2014 28 02 2015
CONTRACT NO BD1-11, PACKAGE -2, (TOTAL 11 NOS OF
ISLAMIC DEVELOPMENT BANK
CYCLONE SHELTER)
BHERAMARA 360 MW COMBINED CYCLE POWER PLANT .[ BANGLADESH POWER DEVELOPMENT BOARD
INTAKE SYSTEM WORKS, CIVIL WORKS & DEEP TUBWELL 256.80 01 03 2015 30 06 2015
WORKS], BHEREMARA. LARSEN & TOUBRO LIMITED

POWER GRID COMPNAY OF BANGLADESH LIMITED


CONSTRUCTION OF 132/33 KV GIS AT DHAKA UNIVERSITY
80.3 01 01 2013 02 07 2015
(NEW LOCATION SATMOSJID ROAD), DHAKA.
SIMENS BANGLADESH LTD

CONSTRUCTION OF EFFLUENT TREATMENT PLANT OF EPYLLION


FABRICS LTD.OF EPYLLION GROUP AT BANGLABAZAR, RAJENDRAPUR, EPYLLION GROUP 62.50 01 01 2015 31 07 2015
GAZIPUR

ASHUGANJ 225 MW COMBINED CYCLE POWER PLANT AT ASHUGANJ POWER STATION COMPANY LIMITED
ASHUGANJ (PILING WORKS, TEMPORARY WORKS, CIVIL & (APSCL) 01 06 2013 15 12 2015
BUILDING AND C.W. INTAKE SYSTEM WORKS) HYUNDAI ENGINEERING CO., LTD
1,030.00

Page 5 of 7
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF COMPLETED PROJECT

PROJECT DURATION
PROJECT NAME AND NATURE CLIENT WORK VALUE
(IN MILLION BDT) START FINISHED

COAST GUARD BOAT MAINTENANCE FACILITY,


NAVFAC PACIFIC OF THAILAND 57.30 01 01 2015 31 12, 2015
CHITTAGONG, BANGLADESH.

DESIGN –BUILT OF TWO STORIED -11 NOS OF MULTI


MINISTRY OF EDUCATION
PURPOSE CYCLONE SHELTER (MPCS/SCHOOL) BUILDING AT 285.00 06 06 2015 31 12 2015
US ARMY CORPS OF ENGINEERS, ALASKA DISTRICT
DHAKA AND SYLHET DIVISION.

BANGLADESH POWER DEVELOPMENT BOARD


SHIKALBAHA 360 MW COMBINED CYCLE POWER PLANT
86.00 01 11 2015 30 04 16
PROJECT, CHITTAGONG
LARSEN & TOUBRO LIMITED
CONSTRUCTION OF TEMPORARY JETTY & TEMPORARY YARD
CONSTRUCTION AT GUMTI BRIDGE FOR PROJECT TITLED THE ROADS & HIGHWAYS DEPARTMENT
ND 100.10 10.04.2016 25 08 2016
CONSTRUCTION OF KANCHPUR, MEGHNA & GUMTI 2 OSJI JV.
BRIDGES & REHABILITATION OF EXISTING BRIDGES.
BIBIYANA SOUTH 400 MW COMBINED CYCLE POWER PLANT
CONSTRUCTION PROJECT (SOIL IMPROVEMENT & EARTH
BANGLADESH POWER DEVELOPMENT BOARD
MOVING WORKS, MONITORING SYSTEME INCLUDING
249.50 28 07 2015 27 10 2016
INSTALLATION OF PIEZOMETER, DISCHARGE WATER ROUTE,
ISOLUX INGENIERIA S.A
TEMPORARY SLOPE PROTECTION WORK), NABIGANJ,
HABIGANJ, SYLHET
BIBIYANA III, 400 MW GAS BASED COMBINED CYCLE POWER
PLANT CONSTRUCTION PROJECT , NABIGANJ, HABIGANJ,
SYLHET(INSTALLATION & TESTING OF 14 NOS. TEST PILE, BANGLADESH POWER DEVELOPMENT BOARD
SAND FILLING OF 2 M HEIGHT & SLOPE PROTECTION, SITE 113.6 15 12 2015 26 11 2016
OFFICE ON TURNKEY BASIS, SUPPLY , INSTALLATION, LARSEN & TOUBRO LIMITED
OPERATION & MAINTENANCE OF 80 TON WEIGH BRIDGE ON
RENTAL BASISFOR 20 MONTHS)

Page 6 of 7
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF COMPLETED PROJECT

PROJECT DURATION
PROJECT NAME AND NATURE CLIENT WORK VALUE
(IN MILLION BDT) START FINISHED

CONSTRUCTION OF STEEL STRUCTURE CANTEEN & AMPHITHEATRE


BUILDING OF SOFTWARE TEHCNOLOGY PARK AT JESSORE (PACKAGE BANGLADESH HI TECH PARK AUTHORITY 205.04 18 03 2015 31 12 2016
NO.-JSTP-WD6)

CONSTRUCTION OF BUILDINGS & ROADWORKS FOR


CONSUMER KNITEX LTD 500.00 22 11 2015 22 03 2017
CONSUMER KNITEX LTD AT TRISHAL

CONSTRUCTION OF PERMANENT SITE OFFICE FOR COAL POWER GENERATION COMPANY BANGLADESH
EMPLOYERS & ENGINEERS FOR MATARBARI ULTRA SUPER LIMITED 118.32 15 03 2016 31 03 2017
CRICATICAL COAL FIRED POWER PLANT AT MATARBARI. PENTA OCEAN COSTRUCTION CO., LTD.

TOTAL 8,643.06 IN MILLION BDT

Page 7 of 7
P R O F I L E

SECTION 8
LIST OF ON GOING PROJECTS.
SINAMM ENGINEERING LIMITED
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting), 9128256, 8143583, 8141434. Fax: 88-02-9120031, E-mail:[email protected]

LIST OF ONGOING PROJECT

PROJECT DURATION
WORK VALUE
PROJECT NAME AND NATURE CLIENT
(IN MILLION BDT) WORK
START
COMPLETION
CONSTRUCTION OF CIVIL WORKS FOR SOIL IMPROVEMENT,
LAND DEVELOPMENT AND RETAINING WALL FOR ADVANCE DHAKA MASS RAPID TRANSIT COMPANY LIMITED
990.7 15 08 2016 15 10 2017
WORKS OF LAKE 9 AT UTTARA DEPOT MRT LINE-6 [ METRO TOKYU CONSTRUCTION LTD
RAIL PROJECT]
WELL FIELD CONSTRUCTION PROJECT AT TETULZHORA-
DHAKA WASA
BHAKURTA AREA OF SAVAR UPAZILLA IRP STRUCTURE & 879.90 01 09 2016 21 08 2017
HYUNDAI ROTEM COMPANY
BUILDING WORKS
CONSTRUCTION OF PACKAGE B & C CIVIL & ARCHITECTURAL
WORKS & CONSTRUCTION OF RIVER INTAKE,JETTY,PUMP
BANGLADESH POWER DEVELOPMENT BOARD
HOUSE & ROADS OF BIBIYANA-III 400 MW COMBINED 661.00 20.05.2016 30 11 2017
LARSEN & TOUBRO LIMITED
CYCLE POWER PLANT, NABIGANJ, HABIGANJ,
SYLHET.BANGLADESH

PILING WORKS & SUPER STRUCTURE WORKS AT EPYLLION


EPYLLION GROUP 486.50 15 03 2016 31 03 2018
KNITWEARS LTD (HW) UNIT AT MODONPUR, NARAYANGANJ

A 413.792 MW (GAS) / 333.02 MW (FUEL OIL) (NET) DUAL


SEMBCORP NORTH-WEST POWER COMPANY LTD
FUEL FIRED POWER GENERATION FACILITY AT SIRAJGANJ, 1,600.00 13 03 2017 18 12 2018
SDCI (BANGLADESH) LIMITED
BANGLADESH (PACKAGE 2A & 2B)

TOTAL 4,618.1 IN MILLION BDT

Page 1 of 1
P R O F I L E

SECTION 9
LIST OF SISTER ORGANIZATION CHART
SINAMM ENGINEERING LIMITED
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

SISTER ORGANIZATION



  CIRCLEHOLDINGSLIMITED
   ARealEstateCompany

House#75(2mdFloor)Road#7/A
DhanmondiR/A,Dhaka–1209
Tel028127192,8130752Ex604
Fax029120361Email[email protected]


  SINAMGLOBALLIMITED
   ATradingCompany

nd
House#75(2 Floor)Road#7/A
DhanmondiR/A,Dhaka–1209
Tel028127192,8130752Ex604
Fax029120361Email[email protected]


  JSECONSORTIUM
   AnOrganizationforTeleCommunicationSectorWorks

nd
House#75(2 Floor)Road#7/A
DhanmondiR/A,Dhaka–1209
Tel028127192,8130752Ex604
Fax029120361Email[email protected]

P R O F I L E

SECTION 10
ENGINEERING SERVICES
SINAMM ENGINEERING LIMITED
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

ENGINEERING SERVICES :



SINAMMwithhisassociateshavetheopportunitiesandfacilitiestoprovideawiderangeofengineeringservices
raining from individual residential building high rise multistoried commercial building, from factory building to
communitybuilding,frompowerplanttotransmissionlineconstructionwork.SINAMMalwaysbelieveinquality
andtimelycompletionofprojectwithclientssatisfaction.



P R O F I L E

SECTION 11
PROJECT MANAGEMENT
SINAMM ENGINEERING LIMITED
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PROJECT MANAGEMENT :

SINAMM believe in adoption of techniques in a systematic manner to control the project activities
within the time frame maintaining highest quality of works. A dynamic and experience management
team are working continuous and constantly adopting new techniques and methods in construction
works with the aid of Planning, Scheduling, Plans and machinery to make construction easier, well
within time schedule and of high quality. The application of computer software in construction
managementtechniques,theuseofplantsandmachinery,fixingalternativesolutionsandselectingthe
possiblesolutionhavemadeourprojectactivitiesmoresmartandscientific.

P R O F I L E

SECTION 12
WORK CERTIFICATION LIST
SINAMM ENGINEERING LIMITED
P R O F I L E

SECTION 13
PHOTOGRAPHIC PRESENTATION OF SITE
ACTIVITY
SINAMM ENGINEERING LIMITED
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting),9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 SANDFILLINGWORKSATBIBIYANASOUTH400MWCCPPPROJECT.

 SANDFILLINGWORKSATBIBIYANASOUTH400MWCCPPPROJECT.
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting),9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 PILING&LOADTESTWORKSATBIBIYANAIII,400MWCCPPPROJECT.

 PILING&LOADTESTWORKSATBIBIYANAIII,400MWCCPPPROJECT.
House # 57/C, Road # 15/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9103510 (Hunting),9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 SOILIMPROVEMENTWORKSATBIBIYANAIII,400MWCCPPPROJECT.

 BRL, CONSTRUCTION OF 6-STORIED FACTORY BUILDING
KPM, CIVIL WORKS, RANGAMATI HILL DISTRICT

 SOILIMPROVEMENTWORKSATBIBIYANAIII,400MWCCPPPROJECT.
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PH OT OGRAPH I C PRESENT AT I ON OF SI T E ACT I V I T Y

◙ 

      

◙ 

      
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PH OT OGRAPH I C PRESENT AT I ON OF SI T E ACT I V I T Y

◙ 
        

◙        


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 PILINGWORKSATASHUGANJ225MWCCPPPROJECTATASHUGANJ.

 EXCAVATIONWORKSATASHUGANJ225MWCCPPPROJECTATASHUGANJ.
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 FOUNDATIONWORKSATSTG&GTGSTRUCTUREATASHUGANJ225MWCCPPPROJECTATASHUGANJ.

 INTAKEWORKSATASHUGANJ225MWCCPPPROJECTATASHUGANJ.
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION

 CIVILWORKSATASHUGANJ225MWCCPPPROJECTATASHUGANJ.

 CIVILWORKSATASHUGANJ225MWCCPPPROJECTATASHUGANJ.
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 KODDA
 150 MW POWEROFPLANT AT KODDA.
 BRL, CONSTRUCTION 6-STORIED FACTORY BUILDING
KPM, CIVIL WORKS, RANGAMATI HILL DISTRICT

 PILE LOAD TEST WORK AT KODDA 150 MW POWER PLANT AT KODDA.


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 KODDA 150 MW POWER PLANT PROJECT, KODDA.


 NINAFUTURESTICK

 KODDA 150 MW POWER PLANT PROJECT, KODDA.


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 NEW HARIPUR 360 MW POWER PLANT PROJECT.

 NEW HARIPUR 360 MW POWER PLANT PROJECT.


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 132/33 KV GIS SUBSTATION AT CANTONMENT.

 132/33 KV GIS SUBSTATION AT CANTONMENT.


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY


 70NINAFUTURESTICK
MW PEAKING POWER PLANT, BERA , PABNA

 70 MW PEAKING POWER PLANT, BERA , PABNA


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 JOYPURHAT 132/33 KV SUBSTATION

 JOYPURHAT 132/33 KV SUBSTATION


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY


 BRL,
KPM,
CONSTRUCTION OF 6-STORIED FACTORY BUILDING
KPM, CIVIL
CIVIL WORKS,
WORKS, RANGAMATI
RANGAMATI HILL
HILL DISTRICT
DISTRICT

 KPM, CIVIL WORKS, RANGAMATI HILL DISTRICT


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 150 MW PEAKING POWER PLANT AT SHIKALBAHA, CHITTAGONG

 150 MW PEAKING POWER PLANT AT SHIKALLBAHA, CHITTAGONG


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 SUPER PROTECTIVE SHOE FACTORY ADAMJEE EPZ, NARAYANGANG.

 SUPER PROTECTIVE SHOE FACTORY ADAMJEE EPZ, NARAYANGANG.


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

ETPSTRUCTUREATDTMLPROJECTATGAZIPUR.
 UTSHOVILLAGEATGAZIPUR
DEKKO KNIT WEARS FACTORY BUILDING, KUTUBPUR, NARAYANGANJ.

 BRL, CONSTRUCTION OF 6-STORIED FACTORY BUILDING
NINAFUTURESTICK
KPM, CIVIL WORKS, RANGAMATI HILL DISTRICT

 DEKKO KNIT WEARS FACTORY BUILDING, KUTUBPUR, NARAYANGANJ.


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 ETPSTRUCTUREATDTMLPROJECTATGAZIPUR.

 2ASTRUCTUREATDTMLPROJECTATGAZIPUR.
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 UTSHOVILLAGEATGAZIPUR 

 USARMYCROPSOFENGINEERS(USARMY)PROJECTSATNARAIL.
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 ISLAMICDEVELOPMENTBANK(IDB)PROJECTSATBORGUNA&PIROJPUR.

 ISLAMICDEVELOPMENTBANK(IDB)PROJECTSATBORGUNA&PIROJPUR.
House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 EARTH FILLING WORKS OF PANCHAGOR 132/33 KV SUBSTATION

 EARTH FILLING WORKS OF CANTONMENT 132/33 KV SUBSTATION


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 CIRCLE WIND FLOWER

 CIRCLE BELL FLOWER


House # 75, Road # 7/ A , Dhanmondi R/A, Dhaka – 1209. Tel : 9128256, 8143583, 8143675, 8141434, Fax:9120031, E-mail:[email protected]

PHOTOGRAPHIC PRESENTATION OF SITE ACTIVITY

 TELE COMMUNICATION PROJECT :

 TELE COMMUNICATION PROJECT :


57 / C 1st

15/A

Telephon e: 8 1 4 3 5 8 3
91 2 8 2 5 6 , 8 1 4 1 4 3 4
Fax. 88 - 02 - 9 1 2 0 0 3 1
[email protected]

You might also like