Unit 2 Network Techniques in Project Management
Unit 2 Network Techniques in Project Management
By:
Dr. Jitendra Singh Yadav
Assistant Professor, Dept of Civil Engineering
National Institute of Technology Hamirpur
Oval
9/14/202 Prepared By: Dr. Jitendra Singh Yadav 5
0
The activates and event are connected logically and sequentially to form a network.
Ex:
Activity oriented
Limitations to CPM/PERT
•Clearly defined, independent and stable activities
•Specified precedence relationships
•Over emphasis on critical path
•It is difficult to estimate accurate time & cost of various activities involved in a project.
•Errors in estimation makes the PERT charts unreliable as a control aid.
9/14/202 Prepared By: Dr. Jitendra Singh Yadav 1111
0
Comparing CPM and PERT
Both CPM and PERT provide the user with project management tools to plan , monitor and update their project
as it progress.
Similarities between CPM and PERT
•Both follow the same steps and use network diagrams.
•Both are used to plan the scheduling of individual activates that make up project.
•They can be used to determine the earliest/ latest start and finish times for each activity.
Differences between PERT and CPM
•PERT is probabilistic whereas CPM is deterministic
•In CPM, estimates of activity duration are based on historical data
•In PERT, estimates are uncertain and we talk of ranges of duration and probability that an activity duration will
fall into the ranges.
•CPM concentrates on Time/cost trade off.
• Head Event: All activates have ending i.e again a specific point of time and is marked by an event.
Events which has only incoming arrows.
Logical Purpose: Dummy is required to establish relation in a network having activity common to
two sets of operations running parallel to each other.
Redundancy exists when, among the predecessor set of any job, one of the jobs is a predecessor for
some other job in the same set.
4. There must not be any dead end left except the final node.
5. No activity can start until its tail end event has occurred.
7. Representation of the network should be such that every activity is completed to reach the end
objective
8. All constraints and interdependencies should be shown properly on the network by use of
appropriate dummies.
9. Logical Network- arrow heads point correct way to indicate the true control situation.
10. It is usual practice to show the time flow from left to right.
9/14/202 Prepared By: Dr. Jitendra Singh Yadav 37
0
ERRORS TO BE AVOIDED IN CONSTRUCTING A NETWORK
•Two activities starting from a tail event must not have a same end event. To ensure this, it is absolutely
necessary to introduce a dummy activity.
•Looping error should not be formed in a network, as it represents performance of activities repeatedly in
a cyclic manner.
•In a network, there should be only one start event and one ending event.
• The direction of arrow from left to right. Avoid mixing of the direction.
Q- A project consists of six activities(jobs) designated from A to F, with the following relationships
I. A is the first job to be performed.
II. B and C can be done concurrently, and must follow A.
III. B must precede D.
IV. E must succeed C but it cannot start until B is complete.
V. The last operation F is dependent on the completion of both.
Draw the network diagram.
•A project to be planned by network technique should consist of well specified and clearly definable
jobs Operations or activities.
•A project is broken down into activities in order to draw the network.
•The decomposition of project into activities is necessary for performing the basic calculations
required for scheduling and analysis purpose.
•Listing each of activities and predecessor-successor relationship amongst them will be our major
concern.