Microsoft CSS Case Study For OPM3 Material From The Forthcoming Book Using OPM3 ISBN 0071629645 / 9780071629645
Microsoft CSS Case Study For OPM3 Material From The Forthcoming Book Using OPM3 ISBN 0071629645 / 9780071629645
Outline
Introduction ........................................................................................................... 2
Background .......................................................................................................... 2
The Journey.......................................................................................................... 4
Conclusion .......................................................................................................... 17
Disclaimer........................................................................................................... 19
How does a large organization at a mature stage of growth preserve the best of
environment? One way is for strategy to be set at the top but enacted bottom-up. Front-
line teams closest to the external business environment are empowered to collaborate
through lean processes that prevent complexity from degrading into chaos while
maximizing freedom of action. At Microsoft, the Customer Service and Support (CSS)
division has made this link between Strategy Management and customer-facing teams
by transforming its portfolio management capability. This case study will describe
several phases of this transformation, including how this transformation aligns with
Background
focused on helping customers and partners maximize the use of their technology
investments. Serving millions of customers around the globe, in more than forty
languages and 75 locations, the organization supports all customer segments from
consumer, developer, and IT Pros to partners and the enterprise. Through direct contact
with customers and partners, CSS is a core driver of the Customer Partner Experience
On an ongoing basis, CSS provides service and support for all of Microsoft’s
products, using the model shown in Figure 1. Using this model, CSS is constantly
seeking to improve the overall service and support experience for the customer, by
improving their support delivery or even through driving improvements to the product
itself to avoid the need for support altogether. Because of this challenge, CSS needs to
As CSS evolved a more holistic view of support their mission and goals were
refined. They coalesce around the three goal areas of Customer Partner Experience
(CPE), fiscal efficiencies, and employee satisfaction, and became more strategic about
improving these.
With these shared goals, CSS has needed to grow into a more global
organization, and internal initiatives have become larger, more complex, and of greater
management processes to meet this challenge and drive significant business value for
Microsoft.
changing, which poses unique challenges and opportunities when institutionalizing and
maintaining processes. Any process improvement must serve a direct business goal,
and the need for it must be clear to the business. At the same time, the business can
absorb rapid change, if the business case for it is evident and well-understood. While
averse to adopting processes for the sake of processes, Microsoft pushes accountability
process capability on empowering individuals and teams to act in the interests of the
company within a flat organization structure. Microsoft has a very strong model of
Commitments are set at the organization level and the individual level for
everyone in the organization at annual and midyear reviews, and meeting these
forward together, towards larger goals. These cultural norms and organizational
structure were key drivers for the approach that was taken in this project.
The Journey
As described above, CSS set out to improve its ability to execute on business
commitments, and began a journey that transformed the way it performed strategic
This journey had a number of phases and cycles, shown in Figure 2 below, and
At the onset of this improvement cycle, CSS created a divisional PMO to support
high impact, strategic projects for the vice president of CSS and business segment
Centralize and grow a team of senior full-time project manager resources who
could be successful in Microsoft’s decentralized environment;
Develop standard project management tools and training, in order to
standardize delivery practices and leverage these across CSS including
outside of the PMO;
Create a project intake and review process with high level criteria to ensure
PMO resources where working on the right projects
Manage the PMO Project Inventory and Project Statuses
organization. By the end of the first year a great many projects had been successfully
delivered, project benefits were being realized, and the PMO project manager resources
became almost too popular. There was very high demand for limited resources, and it
became critical to develop a prioritization model to add to the intake and review process
to determine which projects would receive the resources. Without this process, and
given Microsoft’s entrepreneurial culture, people became very creative in securing these
resources. For example, in order to keep a high performing project manager assigned
even though the extension actually had nothing to do with the original project! When
this failed, typical organizational politics were tried, with predictable chaotic results and
an inability to ensure that maximum business value could be obtained through the
Initially, in the spirit of lean process and low overhead, a “simple model” was put
into place for managing a portfolio of divisional projects, and making decisions about
projects. High level information was collected about the portfolio and provided to the
governance group. However, the deficiencies in this model quickly became clear:
Because there were only high level details, with no supporting information,
the data could have been stronger;
The lack of standards and data definitions meant that many of the categories
used to describe the portfolio were insufficient to support decision-making;
This first phase, implementing the “simple model,” served as a foundation and a
learning experience, and led to the approval of a pilot to develop a more effective
approach that addressed these deficiencies, setting the stage for a virtuous cycle of
To address the shortfalls in the simple model the PMO agreed that they would
need to collect summary level data, but it had to be supported by details. The
initial approach of only collecting summary level data had not been sufficient, and had
created credibility issues. In addition, when more details were needed about a
particular project to make a decision, this created a delay while the data was collected.
They realized that they would need to collect and maintain the details about all
proposals and projects, and then would need the ability to summarize and roll up this
(1) Standards and processes needed to be defined and enforced for the
across projects.
(2) They would need to develop a technical solution for the capture of the data,
suite, which included Microsoft Office Project Portfolio Server 2007. This tool was
developed to address these challenges exactly and brought some additional thinking to
the table as the tool’s capabilities were explored. The PMO began to work with groups
across CSS to develop these standards, model it in the pilot, and develop the solution.
In addition, soon after this proof of concept was approved a new Strategy
Management Group was formed and the PMO became part of this group. This created
an opportunity to further extend and improve the pilot, modeling strategic definition and
alignment for the portfolio that now extended across CSS and not just within the PMO.
The following section describes the improvements that were undertaken in the next
phases.
The newly formed Strategy Management Group and the CSS Leadership Team
refined the goals and strategies and set commitments for the organization. They
acknowledged that they had to tie the portfolio to business commitments, and
manage those. Given the strong Microsoft culture of managing business commitments,
every project needs to directly support a business commitment, or it will quickly become
abandoned. It was critical to make this business commitment relationship explicit and to
document it in the portfolio details. The CSS PMO did this in a number of ways, but one
outcome was the development of a detailed framework for representing project impacts
shown below:
Next, leadership realized that they would need to manage the portfolio, not just
the projects. While the individual business leaders were responsible for driving
successful delivery of their individual projects, given the number of global projects, the
interdependencies, and the breadth of change management needed for these larger
initiatives, this in itself was no longer sufficient to ensure success across the
organization. Microsoft CSS executives and the PMO realized that they would need to
Third, the PMO identified that they would need to put governance in place for
the portfolio, at the right level. In order to be meaningful, this portfolio would need to
be reviewed by executive managers regularly and used to make decisions about project
priorities. Managers needed to realize that this was happening and receive feedback
that reinforced this governance. The PMO made sure that there was early
communication to the project leads so that they could update their portfolio data.
However, the best motivator for them and their teams came at the first meeting. As the
portfolio was reviewed by the executive team, many e-mails were sent during the
meeting with additional requests for data, and validation of the data that was there.
Based on this reinforcement, there was a significant effort prior to the following
The greatest value of this solution became more apparent over the next year. As
Because these benefits were directly tied to the business commitment for the
management team, they were very interested in ensuring that these benefits were
realized in the projected timeframe. A process was put in place for the managers and
their teams to update the projected benefits for the projects as they completed analysis
and planning. These benefits rolled up into the overall portfolio benefits, which also
met. These portfolio benefits were reviewed quarterly in the Executive Team meetings,
At the first meeting after the portfolio was approved, there were a number of
updates to the project benefits, and it was clear that several of the proposed benefits
had been adjusted downward as measurements and processes improved. This trend
continued throughout the next quarterly meeting, as the executives and their teams
strove to ensure that the benefits here were achievable in the projected timeframe. The
downward trend in benefit projections is shown in Figure 4 below, for the first two
reviews (the blue column represents the projected benefits for the portfolio; the yellow
line represents the business targets that had been set). By the middle of the third
quarter it became clear that the business unit was in critical danger of not meeting their
projections (and thus their commitments) for the following year. While this was a major
concern, it was soon enough to adjust to keep their commitments on track – which is
exactly what they did. Working quickly together and with their teams, additional projects
were identified that could provide the value needed, and projects that had become
uncertain were halted. The portfolio was adjusted, and the projected benefits began to
increase. Ultimately, the benefit projections actually exceeded the target, and the
Forecasted Benefits
Target (Committed) Benefits
Actual Benefits
Q1 Q2 Q3 Q4 Q1
Q2
YearReview
Portfolio 1 Year 2
Schedule
The high point for this Executive team came when there was a very senior review with
Steve Ballmer, CEO of Microsoft. He was energized by the approach, and the fact that
they could so confidently predict that that they were on target. His statement at the time
As CSS began to share with other groups their success and lessons learned,
they gained even greater insights into their own journey. One insight came by learning
more about OPM3 and seeing how their story aligned to the OPM3 model and
their current maturity mapped to this framework, and to gain additional insights into
areas for growth. As of the writing of this case an OPM3 benchmark assessment for
Management have not yet been assessed).i This assessment has validated
improvements to date and also identified areas of opportunities for improving some
current processes and adopting the few processes that have not been adopted.
are being used to set future direction with our leadership team. This completes the
discussion of the journey, and the next section will provide additional analysis of the
At the onset of the pilot, we realized that this was a serious initiative, and this
became a global project in its own right. We identified three foundational areas that we
(1) Ensuring we were integrating this solution into the governance of the
organization;
(2) Carrying this governance through development of processes and people; and
Figure 5 describes these three building blocks of success, along with the
cycle of identifying an area of improvement, aligning it to the business strategy for the
year in order to address it, and using the outcome of that to make the case for the next
across the organization. Given the Microsoft culture, this approach was much more
successful than attempting to get approval for an enterprise project and portfolio
management initiative. Figure 6 below shows how this cycle of improvement evolved
over time, with improvements to one area providing visibility and momentum for an
There were a number of additional wins from bringing in this new process and
solution. One win was achieved when extending this process out to a supporting
organization. The first step was to collect the entire project list for their global group.
Simply by looking at the projects on the list, this Executive team cut the size of the
portfolio by 20%. This organization immediately saw the value of this solution, and
began to reinforce and extend the processes required to maintain this information.
On the other hand, trying to bring more mature portfolio processes (such as
tried to perform a portfolio review, but the information in the inventory was inaccurate
and incomplete. This created doubt about the process and solution overall, and the
approach was rapidly abandoned. Mature processes were needed to build an inventory
this experience reinforced previous lessons learned about the ways that improved
Conclusion
initiative into one that enjoyed sponsorship top-down. In turn this initiated the
actions taken within Strategic, Portfolio and Project Management throughout were a
direct result of business decisions and direction set by the CSS Leadership team, yet
we knew that transformation is a journey, not a destination. CSS had realized significant
organization.
transformation have moved into other positions of leadership in the company. The
management capabilities has underscored the value of standards like OPM3 to support
The information contained in this document represents the current view of Microsoft Corporation on the issues
discussed as of the date of publication. Because Microsoft must respond to changing market conditions, it should
not be interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any
information presented after the date of publication.
This White Paper is for informational purposes only. MICROSOFT MAKES NO WARRANTIES, EXPRESS,
IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS DOCUMENT.
Complying with all applicable copyright laws is the responsibility of the user.
Microsoft may have patents, patent applications, trademarks, copyrights, or other intellectual property rights
covering subject matter in this document. Except as expressly provided in any written license agreement
from Microsoft, the furnishing of this document does not give you any license to these patents, trademarks,
copyrights, or other intellectual property.
© 2010 Microsoft Corporation, © 2010 OPM Experts LLC. All rights reserved.
Microsoft and Project Portfolio Server are trademarks of the Microsoft group of companies.
i
Microsoft’s OPM3 assessment was led by OPM Experts LLC. See http://opmexperts.com