1) The document outlines a preservation checklist for a quench water cooler heat exchanger with 13 initial preservation steps and 14 monthly preservation steps to be completed. 2) The initial preservation steps include delivering the item assembled and nitrogen pressurized, checking for damage, applying protective coatings, and pressurizing with nitrogen. 3) The monthly preservation steps include checking for damage, applying protective coatings, checking connections and insulation, and pressurizing with nitrogen.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
310 views

Preservation Check Sheet PROD

1) The document outlines a preservation checklist for a quench water cooler heat exchanger with 13 initial preservation steps and 14 monthly preservation steps to be completed. 2) The initial preservation steps include delivering the item assembled and nitrogen pressurized, checking for damage, applying protective coatings, and pressurizing with nitrogen. 3) The monthly preservation steps include checking for damage, applying protective coatings, checking connections and insulation, and pressurizing with nitrogen.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PACKAGE A1 OLEFINS

PRESERVATION CHECKSHEET
JOB CARD : HEPL-01-STD - Plate Heat Exchangers JOB PLAN TYPE : 1-INITIAL PRESERVATION

TAG : 10-E-2100C Description: QUENCH WATER COOLER Schedule Week : 39 2020

Subcontractor : PTSC Technician : Supervisor : Location : Site Work

NR STEP FREQUENCY ACTIVITY DUE DATE EXECUTED


1 IN_1 IN ITEM SHALL BE DELIVERED COMPLETELY ASSEMBLED AND PACKED, 9/22/2020 9/23/2020
UNDER NITROGEN PRESERVATION (0.5 BARG OR 0.2 BARG BY THE
DESIGN PRESSURE WHICHEVER IS SMALLER)
2 IN_2 IN ITEM SHALL BE LEFT IN SHIPPING PACKAGE UNTIL INSTALLATION. 9/22/2020 9/23/2020

3 IN_3 IN PACKAGE SHALL BE STORED IN WAREHOUSE OR UNDER SHELTER, 9/22/2020 9/23/2020


KEPT AWAY FROM WATER, HUMIDITY AND SUN.
4 IN_4 IN PACKAGE SHALL BE CHECKED FOR ANY DAMAGE OR WEAR. 9/22/2020 9/23/2020

5 IN_5 IN NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/23/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
6 IN_6 IN IF THE EXCHANGER HAS BEEN REMOVED FROM PACKAGE OR 9/22/2020 9/23/2020
PACKAGE HAS BEEN DAMAGED PERFORM THE FOLLOWING
CHECKS/ACTIVITIES:
7 IN_7 IN FOR ALL FLANGES: CHECK ANTI-RUST PROTECTION ON SEAL 9/22/2020 9/23/2020
SURFACES PROVIDED BY SUPPLIER/MANUFACTURER AND RENEW
ANY DAMAGED PROTECTION BY APPLYING A COAT OF PROTECTION
PRODUCT (DRY LAYER FOR EXTERNAL PARTS) AND PROTECT WITH
PLASTIC SHEETS OR WOODEN COVERS.
8 IN_8 IN WHERE A SPOT CHECK REVEALS SOME RUST FORMATION, PROVIDE 9/22/2020 9/23/2020
FOR THE FOLLOWING OPERATIONS DEPENDING BY THE PART
INVOLVED: - REMOVE ALL FLANGE COVERS OF THE NOZZLES,
CLEAN THE FLANGE FACES FROM RUST BRUSH AND AFTER WITH
SOLVENT AND APPLY RUST PREVENTIVE PRODUCT. - REMOVE RUST
BY MECHANICAL OR MANUAL BRUSH AND RESTORE PAINTING
ACCORDING TO PAINTING PROCEDURE.
9 IN_9 IN CHECK THAT ALL OPENINGS AND CONNECTIONS ARE TIGHTLY 9/22/2020 9/23/2020
CLOSED.
10 IN_10 IN ITEM SHALL BE PROTECTED FROM DUST, SAND, LIGHT, HUMIDITY 9/22/2020 9/23/2020
AND WEATHER CONDITIONS
11 IN_11 IN COAT WITH HEAVY GREASE OR PROTECTIVE PRODUCT 9/22/2020 9/23/2020
BOLTS/THREADED CONNECTIONS AND FLANGES AND ALL
EXPOSED MACHINED SURFACE.
12 IN_12 IN NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/23/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
13 IN_13 IN ANCHOR BOLTS THAT ARE NOT OTHERWISE PROTECTED WHEN 9/22/2020 9/23/2020
RECEIVED AT JOB SITE, SHALL BE CLEANED FROM RUST, AND SHALL
BE COATED WITH RUST PREVENTATIVE (DRY LAYER AND SOFT
LAYER FOR EXTERNAL OR INTERNAL PARTS).
14 IN_14 IN REMOVE AND STORE FRAGILE ACCESSORIES/INSTRUMENTS. 9/22/2020 9/23/2020

15 MP_1 4W PACKAGE SHALL BE CHECKED FOR ANY DAMAGE OR WEAR. 9/22/2020 9/23/2020

16 MP_2 4W NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/22/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
PACKAGE A1 OLEFINS

PRESERVATION CHECKSHEET
JOB CARD : HEPL-01-STD - Plate Heat Exchangers JOB PLAN TYPE : 1-INITIAL PRESERVATION

TAG : 10-E-2100C Description: QUENCH WATER COOLER Schedule Week : 39 2020

Subcontractor : PTSC Technician : Supervisor : Location : Site Work

NR STEP FREQUENCY ACTIVITY DUE DATE EXECUTED


17 MP_3 4W ANY WATER DEPOSIT SHALL BE REMOVED 9/22/2020 9/23/2020

18 MP_4 4W IF THE EXCHANGER HAS BEEN INSTALLED OR REMOVED FROM 9/22/2020 9/22/2020
PACKAGE PERFORM THE FOLLOWING CHECKS/ACTIVITIES:
19 MP_5 4W CHECK THAT ALL OPENINGS AND CONNECTIONS ARE TIGHTLY 9/22/2020 9/23/2020
CLOSED.
20 MP_6 4W CHECK LEAKAGES ON CONNECTIONS. TIGHTEN COUPLINGS AND 9/22/2020 9/22/2020
FLANGES IF NECESSARY.
21 MP_7 4W NITROGEN PRESSURIZATION SHALL BE CHECKED (0.5 BARG OR 0.2 9/22/2020 9/22/2020
BARG BY THE DESIGN PRESSURE WHICHEVER IS SMALLER) AND IN
CASE RESTORED.
22 MP_8 4W CHECK PAINTING AND IF NECESSARY REPAINT. 9/22/2020 9/23/2020

23 MP_9 4W CHECK INSULATION AND IF NECESSARY REPAIR. 9/22/2020 9/22/2020

24 MP_10 4W CHECK AND DRAIN CONDENSATE FROM LOW POINTS. 9/22/2020 9/22/2020

25 MP_11 4W CHECK GREASE/PROTECTIVE PRODUCT COATING AND, IF 9/22/2020 9/22/2020


NECESSARY, REFURBISH ON BOLTS/THREADED CONNECTIONS,
FLANGES AND ALL EXPOSED MACHINED SURFACES.
26 MP_12 4W ITEM SHALL BE PROTECTED FROM DUST, SAND, LIGHT, HUMIDITY 9/22/2020 9/23/2020
AND WEATHER CONDITIONS
27 MP_13 4W CHECK STATUS OF TARPAULINS COVERING THE EQUIPMENT (IF 9/22/2020 9/22/2020
ANY). REPAIR IF TEARS FOUND.

REMARKS
Accepted by Supervisor CONTRACTOR/CLIENT
Accepted by Supervisor SUBCONTRACTOR
W □ M □ R □
Entered in
Name: Name:
Database

Signature: Signature: □
Date: Date:

You might also like