Quality Assurance of M.S. Pipeline SGS India Pvt. LTD
Quality Assurance of M.S. Pipeline SGS India Pvt. LTD
pipeline
By
Manoj Raghavan
SGS India Pvt. Ltd.
AHMEDABAD
QUALITY CONCEPT
QUALITY
Quality is closely allied to cost and customer needs.
“Quality” may simply be defined as fitness for the purpose at lowest
cost.
As per International Organization for Standardization (ISO), ‘Quality’
can be defined as the totality of feature and characteristics of a product
or services that bear on its ability to satisfy stated or implied needs.
INSPECTION
“Inspection is the process of measuring the quality of a product or
service in terms of established standards.”
2
OBJECTIVE OF INSPECTION
3
OUT COME OF INSPECTION
Conformance:
Conformance means judging whether the product conforms to
specification. Conformance decisions are taken by trained
inspectors/inspection team deputed on the job. Acceptable
products/stage of work is released for dispatch/further activities.
Non-conformance:
Non-conforming products may be fit or unfit for use.
Inspector/Inspecting team, on detecting a nonconforming product or
stage of work, prepares a report to that effect. This is marked as
“Hold” and is subjected to further investigation. Outcome of further
investigation can be of the following :
4
OUT COME OF INSPECTION
5
WHEN AND WHERE TO INSPECT
1. Where to inspect ?
2. When to inspect ?
3. How to inspect ?
4. How much to inspect ?
Quality Assurance Plan (QAP) is the document in which
all these detail are available.
6
QUALITY ASSURANCE PLAN
7
QA QC OF M.S. PIPE LINE PROJECT
INSPECTION
INSPECTION OFOF
M.S.
M.S. PIPELINE
PIPELINE
PROCUREMENT
PROCUREMENT SITE
SITECONSTRUCTION
CONSTRUCTION
INSPECTION
INSPECTION ACTIVITY’S
ACTIVITY’SINSPECTION
INSPECTION
•PUMPS
•PUMPS •TRANSFORMERS
•TRANSFORMERS PIPE
PIPELAYING
LAYINGAT
AT PUMPING
PUMPING
•EXPANSION
•EXPANSION •MOTORS
•MOTORS
• •PIPE SITE
SITE STATION
STATION
PIPE BELLOW
BELLOW •PANEL
•PANEL
MANUFACTURING
MANUFACTURING •EOT
•EOTCRANE
CRANE •CABLE
•CABLE
• •INSIDE
INSIDECOATING
COATING •FITTINGS
•FITTINGS
• •OUTSIDE •INSTRUMENTATI
•INSTRUMENTATI
OUTSIDE •FLANGES
•FLANGES ONS
ONS
COATING
COATING •SURGE
•SURGEVALVE
VALVE
•TRENCHING
•TRENCHING •PUMP
•PUMP&&MOTOR
MOTOR
•BEDDING
•BEDDING INSTALLATION
INSTALLATION
•PIPE
•PIPESTRINGING
STRINGING •HEADER
•HEADERPIPE
PIPE
•JOINT
•JOINTWELDING
WELDING •VALVE
•VALVE
•NDT
•NDT •SUB-STATION
•SUB-STATION
• •JOINT
JOINTCOATING
COATING
•VALVE/AIR
SETUP
SETUP
•VALVE/AIRVENT
VENT
INSTALLATION
INSTALLATION
•THURST
•THURSTBLOCKS
BLOCKS
•ENCASINGS
•ENCASINGS
•HYDROTEST
•HYDROTEST
8
PROCUREMENT INSPECTION
9
PROCUREMENT INSPECTION
CLIENT
Inspection Request Flow
TPI Ahmedabad
Report Flow
TPI Executing office
INSPECTION LOCATION
10
RAW MATERIAL TESTING
Raw Material : Coils - IS 10748 Plates - IS 2062
Check the Coils/ Plates
Physically for the Identification of the following details
Name of the Manufacturer
Thickness of the Plate
IS Specification No. & Grade
Heat No./ Cast No. or Coil No./Plate No.
ISI Mark ( If required as per the Tender)
Review of Results of MTCs for chemical and physical properties.
Three Samples for test drawn from a lot of 500 MT in the presence of
Client and tested for tensile test, bend test and chemical analysis.
Sample No.1 to be tested in the Laboratory approved by Engineer- In-
charge
Sample No.2 will be kept by the Dept for record.
Sample No.3 will be Kept by the Contractor for Record
11
12
INSPECTION OF WELDING
13
WPS
Joint detail
Base material & its thickness
Process / processes employed
Consumables employed
Positions of welding
Preheat, interpass temp & preheat maintenance
Post weld heat treatment
Type of machines employed
Welding parameters selected
Method of initial & interpass cleaning
Back gouging methods
14
WPS
15
16
WELD DEFECTS
17
JOINT DESIGN
18
JOINT DESIGN
19
INSPECTION OF PIPE
20
COATING INSPECTION
Upon the receipt of pipes in coating yard, the inspectors check the
inspection document of the pipes.
Sand blasting is done as surface preparation prior to applying
coating. Its checked with a comparator.
Outside coating: Coaltar tape; continuity of coating is checked by
Holiday test and bonding by Peel of test. Thickness by Elcometer.
Inside coating: Black epoxy paint; continuity is checked by Holiday
test and bonding by adhesion test. Thickness by Elcometer.
Release note issued for all accepted pipes.
21
THIRD PARTY INSPECTION FOR QA & QC OF
SITE CONSTRUCTION WORK
Preparation of Quality Assurance plan for construction
Review of test certificate, equipments, etc.
Physical Verification at Site w.r.t to approved drawings
Periodic quality audit of how the system is functioning
Quality records and Inspection and Test Plans.
Quality control of the material used during the construction
Calibration of equipments, measuring and testing devices against
certified standard procedures.
Check for non-conformities with contract technical requirements,
technical specifications or deviation from approved submittals
(drawings or material), help contractor to close them and appraise
the client about the deviation on immediate basis.
22
CONTRACTOR’S AUDIT
REVIEW OF CONTRACTOR’S/PROJECT
DOCUMENT
RE- INSPECTION
HIGHLIGHTING THE DEVIATION FOR DEVIATION
AND INSTRUCT FOR RECTIFICATION
CLIENT’S APPROVAL
FOR DEVIATION (IF ANY)
CLEARNACE OF UNIT/ITEM/PART
23
INSPECTION ON PIPE LAYING
24
Inspection of fixing of surge equipment, gate valves, air vent valves,
miters, flow meters.
Supervision of concrete chambers, encasing and thrust blocks.
Hydrostatic test of pipeline.
Supervising backfilling and stage wise soil compaction.
Surveillance of day-to-day activities at site and review of the
documents to achieve quality at site. And reporting the same on
weekly basis to client.
Highlighting the quality issues to client and issuing letter to
contractor if required.
Review of contractor’s documents prior to any Statutory authority’s
visit.
Preparing Punch list / Check list for the completed activities .
25
CONSTRUCTION SUPERVISION OF PUMPING
STATION
Supervision of construction of sump, pumping station and sub station.
Laboratory Tests on Building Materials such as Cement, Aggregate,
Brick, Block, Rebar, Structural section, Wood, Tile, etc as per
relevant Indian Standards.
Concrete mix design for strength, workability & durability of concrete
for various requirements.
Tests to evaluate performance of Construction aids/ Chemicals such
as Admixtures, Modified Mortars, Epoxies, Grouts, Sealants etc.
Tests on water for assessment of its suitability for concreting
Facilities for various Non-Destructive Test such as Rebound Hammer
test, Ultrasonic Pulse Velocity tests, Core Extraction test.
Installation of pump motors, valves, instruments and header pipes.
Commissioning of pumping station.
26
COMMISSIONING OF THE PROJECT
27
THANK YOU
28