Chapter I - Introduction PDF
Chapter I - Introduction PDF
3. Preparation of Detailed Estimate: Cost of items; Transportation cost, other expenses and overheads; Contingency.
4. Types of Estimate: Approximate estimate, Detailed estimate, Revised Estimate, Supplementary Estimate, Annual repair or Annual
maintenance estimates; Extension and improvement estimates; Complete estimates; Split up of cost of building works.
5. Analysis of Rate: Introduction, Purpose of rate analysis, Importance of rate analysis, Requirements of rate analysis, Factors affecting the
rate analysis, Procedure of rate analysis.
6. Detailed estimate: Estimate of walls, Estimate for a single room building, Estimate for a two room building; Estimate of earthwork by
three methods, Estimate of an Aqueduct, Estimate of RCC slab culvert, Estimate of RCC T beam Decking, Estimate of Septic tank and Soak
pit,
7. Valuation: Introduction, Purpose of valuation; Principles of valuation; Terms used in valuation; Methods of determining the value of
property; Methods of valuation report writing.
References:
• Estimating, Costing, Specification and Valuation in Civil Engineering. Monojit Chakraborti, R.K. Printers, 1963
• Civil Estimating Quantity Surveying and Valuation. Amarjit Aggrawal, Katson Publishing house, Ludhiana, 1985
• Estimating and project management for small construction firms” Seymour Berger and Jules B.Godel, Van Nosttradn Reinhold Publishing
company, Network, 1977.
Mode of Evaluation
• Active Class Participation (30%)
– Interaction in classes (online)
– Interaction in discussion forum (offline)
An estimate for any construction work may be defined as the process of calculating the quantities and costs of the various
items required in connection with the work.
What is an Estimate?
In case the funds available are less than the estimated cost the
work is done in part or by reducing it or specifications are altered.
2. Estimate gives an idea of time required for the completion of the work.
5. Estimate decides whether the proposed plan matches the funds available
or not.
NEED OF ESTIMATION AND COSTING
6. Estimates are required in order to obtain administrative approval,
allotment of funds and technical sanction. (For public construction works)
• All expenses for all probabilities can be known after the completion of the
project
– Long and thin work shall be taken in linear or running units, and
linear measurement shall be taken. (viz. running meter, rm.)