CS / GI To PE Fittings (I.e. Transition Fittings of Sizes 20 MM To 63 MM)
CS / GI To PE Fittings (I.e. Transition Fittings of Sizes 20 MM To 63 MM)
1 PE PIPELINE
1.1 PE Pipe Laying in any unprepared surface by open trench method in all kind of soft soil and weathered rock.
Receipt, Loading, unloading, storing, reloading, transportation, unloading, stringing and laying of PE100, SDR11/17.6 line pipes of all sizes
including, proper stacking, identification, and supply of accessories of all sizes & thickness like PE Bends, Couplers, Endcaps, Tee,
Reducer, CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 63 mm), Warning Mat etc. Handling, Stringing / uncoiling, aligning
of the PE line pipe on the pipeline Right-of-Use/ route, laying / installation of PE line pipe along with required accessories as mentioned
above as per specification wherever required depending on site condition including execution of all works; Storage of material in
contractor's store, fabrication, access for construction procurement and supply of all materials, consumables, equipments, labour and other
inputs.
In the case of free issue items, the scope also includes, receiving and loading from Owner's designated store, transportation, unloading and
stacking of free issue items at Contractor's store
Carrying out all temporary, ancillary, auxiliary works required to make the PE pipeline ready for commissioning as per drawings.
Specifications, scope of work indicated in SOW and other provisions of Contract document and instructions of Engineer-in-charge,
including but not limited to carrying out the following works:
Surveying of route and detours required at the time of execution including marking the same in topographical sheet, preparation of
construction drawings showing survey details, and submit same to Owner for review / approval.
Carrying out preliminary activities such as preparation of drawings wherever required for crossing etc.
Preparation and getting approval of schedules, execution procedures, drawings/ sketches/ wherever required, making trial pits to determine
the underground utilities/ services etc., restoration of the abandoned trial pits to original condition.
Stacking and installation of construction markers, clearing, fencing, grubbing, cutting of trees, full filling all the requirements of various
statutory/ environment authorities to the entire satisfaction of concerned authorities, grading of work area.
Barricading the open pits work area as per local authorities norms & to the satisfaction of Owner/ Engineer -in- charge, installation of safety
signs.
Barricading the pipeline construction area prior to execution of the works as per drawing no. 1008-30-03-11 enclosed with tender document
and to the entire satisfaction of owner / engineer- in -charge.
Trenching to all depths by excavation in all types of soils including soft soil and weathered rock and different type of pavement / footpath /
roads etc. including rock breaking, chiselling or otherwise cutting etc. as required and storing excavated soil, reusable materials at
designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification
etc. [The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or
as per Specification/ OISD - 226 & PNGRB latest guidelines whichever is higher]. Dewatering of trenches / pits if required as per site
condition. Repairing of all damaged utilities if any, and payment of any compensation (if claimed by owner / other utility agencies)
Uncoiling/ stringing & aligning of PE pipes, clamping, jointing of the pipe ends/ fittings/ valves by qualified personnel using approved
electro-fusion techniques as per specification.
Installation / lowering the pipeline in trench to required depth as per Technical Specification & drawings, supply & placement of HDPE
Yellow colour warning mat over the pipeline along the complete route as per standard drawings, data sheets & technical specifications,
padding around pipeline (below & above) including supply of suitable padding material duly proved by EIC , backfilling to its original
condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area
of ROU, trench shall be backfilled & compacted and shall be made ready for motorable. All tiles/slabs/curb stones etc removed during
excavation shall be placed properly and no separate payment shall be admissible against this activity. Restoration shall be carried as per
separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
The scope of work against this item also include Electro-fusion jointing of valves, fittings wherever required and as directed by Engineer-in-
charge.
The scope of work of laying of PE pipe also includes works for padding in trench & soft soil covers over pipe before backfilling including
supply of soft soil..
Pneumatic testing, purging with nitrogen and commissioning as per specification and approved procedures providing all tools and
tackles, nitrogen, instruments, manpower and other related accessories and as per the instructions of the Engineer-in-charge.
Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of
debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner
and/or as directed by Engineer–in–charge.
Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of
completion of work) .
Handing over the completed works to Owner for their operation/ use, reconciliation of material area wise and obtaining "no objection
certificate" from Owner/ Consultant.
Preparation and submission of Daily progress report, Laying Graphs / PE line cards on daily basis.
On completion of gas charging of pipelines. Preparation and submission of As-built drawings, crossings details, termination, utility graphs
and deviation statements.
In case, the minimum required depth is not possible due to site condition, necessary mitigation measures shall be required to be
taken by contractor in consultation with EIC as per PNGRB Guidelines. No additional payment shall be admissible against the same.
Submission of all documents required for contract closure in numbers as mentioned in contract.
Any other activities not mentioned / covered explicitly above, but otherwise required for satisfactory completion / operation / safety /
statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within
specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
d) 125 mm PE 100 pipe (With Free issue Pipe supplied in 50 meter length) Meter 6100 380 2318000
For restoration of asphalt / concrete roads, the item for construction of asphalt top / concrete top / red stone / paver shall be paid separately
ii) 0
as per the rates quoted for the same elsewhere in the SOR.
In case, contractor prefers to lay the pipeline through HDD method in place of method as per SOR item-1.1, contractor shall be required to
iii) 0
lay the pipe upto a depth not more than 1.4 m. The payment shall however be made as per SOR item No.- 1.1 only.
This item includes prepading & post padding in rocky trench also however, rock breaking, rock cutting for hard rock for making trench
iv) 0
covered separately in item no 1.15, Bidder to quote accordingly.
1.2 Restoration 0
Restoration to original conditions of dismantled surface like Asphalted/Bituminous Road, Concrete Pavement, Agra /Kota Stones / Tiles
(Chequered/interlocking etc.), Dry Brick Pavement as per the technical specifications attached in the tender after laying of pipeline in Built-
Up surface, as per the directions of EIC / Site lncharge. Scope includes supply of the approved quality material, testing of materials by third 0
party agencies as per technical specification / CPWD / IRC Standards, submission of the restoration reports, obtaining no objection
certificates from the concern local authorities /land owners / third party inspection agencies designated by land owing agencies and Owner.
Pneumatic testing, purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles, 0
nitrogen, instruments, manpower and other related accessories and as per the instructions of the Engineer-in-charge.
Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of
debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner 0
and / or as directed by Engineer–in–charge.
Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of 0
completion of work) .
Handing over the completed works to Owner for their operation/ use, reconciliation of material area wise and obtaining "no objection 0
certificate" from Owner/ Consultant.
On completion of gas charging of pipelines. Preparation and submission of As-built drawings, crossings details, termination, utility graphs 0
and deviation statements.
Any other activities not mentioned/ covered explicitly above, but otherwise required for satisfactory completion/ operation/ safety/ statutory/
maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified 0
schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
1.4 Pipe laying using manual moling technique (with casing) for PE pipe sizes of : 0
Laying of all PE pipe ( PE 100 SDR11/17) ,Including supply of HDPE casing pipe, Couplers, End caps etc. (Ref. cl. 4.3 of Particular job 0
specification.)
Survey of under ground utilities, execution of the work as per specification, including excavation of pits moling with the hole size not
exceeding 20% of the pipe dia, jointing and insertion of carrier pipe with casing, testing & commissioning and restoration of the pits to 0
original condition, submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
a) 32 mm PE 100 pipe (in 75 mm dia. HDPE Casing Pipe, PE63/80 PN 6.0) Meter 300 410 123000
b) 63 mm PE 100 pipe (in 125 mm dia. HDPE Casing Pipe, PE63/80 PN 6.0) Meter 750 680 510000
c) 125 mm PE 100 pipe (in 250 mm dia. HDPE Casing Pipe, PE63/80 PN 6.0, With Free issue Carrier Pipe supplied in 50 meter length) Meter 200 1360 272000
1.5 Pipe laying using manual Moling Technique (without casing) for PE pipe sizes of : 0
Laying of all PE pipe (PE 100 SDR11/17.6), Including supply of Couplers, End caps etc.as required to complete the job (Ref. cl. 4.2 of 0
Particular job specification.)
Survey of under ground utilities, execution of the work as per specification, approved procedure, including excavation of pits moling with
the hole size not exceeding 20% of the pipe dia, jointing and insertion of carrier pipe, testing & commissioning and restoration of the pits to 0
original condition, submission of as-built graphs as per specifications and the instructions of EIC.
d) 125 mm PE 100 pipe (With Free issue Pipe supplied in 50 meter length) Meter 1800 420 756000
1.6 Pipe laying using Directional Drilling technique (with casing pipe) for PE pipe size of : 0
Laying of all PE pipe (PE 100 SDR11/SDR17.6), Including supply of HDPE casing pipe, Couplers, End caps etc. (Ref. cl. 4.2 of Particular 0
job specification.)
Survey of U/G utilities, submission of profile for approval, execution of the work as per specification, approved procedure, including
excavation of pits and subsequent backfilling compaction, jointing and insertion of carrier pipe in casing pipe, testing & commissioning, 0
restoration of the pits to original condition, submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
a) 32 mm pipe (in 75 mm dia. HDPE Casing Pipe, PE 63/80 PN6.0) Meter 200 450 90000
b) 63 mm pipe (in 125 mm dia. HDPE Casing Pipe, PE 63/80 PN6.0) Meter 500 750 375000
c) 125 mm PE 100 pipe (in 250 mm dia. HDPE Casing Pipe, PE63/80 PN 6.0, With Free issue Carrier Pipe supplied in 50 meter length) Meter 350 1500 525000
Survey of U/G utilities, submission of profile for approval, execution of the work as per standard procedure attached, including
excavation of pits and subsequent backfilling, compaction, jointing and insertion of PE pipe, testing & commissioning, restoration of the pits 0
to original condition, submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
c) 125 mm PE 100 pipe (With Free issue Pipe supplied in 50 meter length) Meter 200 500 100000
1.8 Railway Crossing (with Casing Pipe) by Trenchless method like Boring, HDD etc. 0
Laying of all PE pipe (PE 100 SDR11/SDR17.6) in plain/normal soil, Including supply of Carbon Steel 0
(CS) casing pipe, Couplers, End caps etc.
Survey of U/G utilities, submission of profile for approval, execution of the work as per specification, approved procedure, including
excavation of pits and subsequent backfilling compaction, jointing and insertion of carrier pipe in casing pipe, testing & commissioning, 0
restoration of the pits to original condition, submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
a) 63 mm PE 100 pipe (in Casing Pipe - 6", 6.4mm wall thk) Meter 100 6200 620000
b) 125 mm PE 100 pipe (in Casing Pipe - 10" , 6.4mm wall thk) Meter 200 10200 2040000
1.9 Supply of GI/ MS/ Concrete Sleeves (wherever required as a Special Case as per instructions of the Engineer-in-charge) 0
Supply, installation of sleeve, insertion of pipe, sealing the annuals, firm fixing of Sleeves with concrete mix. Breaking through any
obstructions and their subsequent restoration, as per specifications and instructions of the Engineer-in-charge. 0
GI/MS Pipes shall be Heavy (C-Class) as per IS-1239
a) GI Sleeves (in Nos.) 0
b) MS Enamel Coated 0
Supply of isolation valves (as per data sheet) and installation of valves in the valve pits as per typical drawing and specification enclosed
and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR item No: 1.12 On supply of valves 70 % 0
shall be paid, on installation of valves-20% shall be paid and on completion of testing and commissioning -10% shall be paid.
Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material
1.12 including Steel Cover (as per given drawing & specifications) along with locking arrangement, shuttering, reinforcement, labour, 0
curing etc. as per the drgs, specification and instruction of EIC.
a Type-1 having Internal size of Minimum 1000 x 1500mm Nos. 44 23500 1034000
Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference 0
tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
Supply, fabrication and installation of RCC route markers as per the attached drawings, along the route including all associated civil works
Nos. 800 510 408000
such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
Supply, fabrication and installation of plate markers as per the attached drawings including all associated civil works such as
Nos. 150 2800 420000
excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let
Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter
Nos 2000 150 300000
cutting of lettering, numbers, direction, etc. as per the attached drawings to be installed near regulator.
Pipeline Laying Liasioning (including Crossings) and getting permission from the statutory authorities. 0
Submission of applications as per approved drawing provided by owner / owner's representative (Initial Route survey, preparation of
drawing, measuring and providing details of surface type shall be in scope of contractor with approval from owner / owner's representative),
obtaing and submission of demand note, coordination , Liaisoning, obtaing written permission from land owing agencies like UIT, Nagar
i) Meter 18000 40 720000
Nigam, NHAI, Indian Railways, irrigation and any other government agencies who maintains the public lands (all fee paid to authorities shall
be reimbursed against documentary evidence). This rates are not applicable for Private lands i.e. Apartments etc. Permissions required
from various authorities like UIT, Nagar Nigam, NHAI/ Railways/Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate.
Rock cutting encountered while excavation of trenches for item 1.1 of SOR MDPE P/L laying), not exceeding "dia. of PE Pipe +
1.15 0.350 meter in width", and lift upto 1.5 meter, including rock breaking, chiselling or otherwise cutting etc. as required and storing Cu. Meter 2500 1450 3625000
excavated soil and disposal of excavated soil as directed within a lead of 5 Km.
Receiving and taking over, handling, loading, transportation and unloading of DRS/MRS/ Metering Skid from Owner's designated
stockyards to site, installation at foundation (including supply of all structural items) and hooking up with PE pipe including all works as
required to complete the job as per the drawings and specification, scope of work mentioned in tender document. The scope includes
supply of transition fittings and other MDPE and CS fittings as per requirements and various associated works (including steel welding, if
required) to commission DRS / MRS / Skid
0
Note:
1) Amount towards civil work shall be payable as per related SOR items.
2) Rate to include cost of all labour, tools, tackles, equipment, hire charges (this rate not in duplicacy with clause no. 3.4).
3) Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate
quoted. These items shall not be separately measured and paid.
a DRS (Maximum weight of single DRS shall be about 6.0 T) Nos. 1 180000 180000
b MRS / Metering Skid (Maximum weight of single MRS / Metering skid shall be about 4.0 T) Nos. 2 120000 240000
Note :- I) The quantities mentioned are indicative only. ii) For all the supply items mentioned above , procurement shall be made as per 0
specification after due approval of engineer- in - charge.
3 CIVIL WORKS 0
3.1 Laying of Brick layer/ Concrete 0
Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the
laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, 0
equipment, hire charges & supply of all materials, etc.)
a) Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.) Sq.m 400 500 200000
b) Concrete for width of PE pipeline trench as per drawing (80 mm thk.) Sq.m 80 600 48000
Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for
Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing
and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface,
3.2 excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, 0
breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified
Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications
and directions of Engineer-in-charge.
(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., 0
as applicable with all bye works and sundry works).
Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like
foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, cable trench inlcuding constrcution joints,
M3 23 8500 195500
bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes etc. at all depths and
heights complete as per drawings, specifications and direction of the Engineer-in-charge.
Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including
sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, 0
stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of
concrete, curing etc. with all bye works and syndry works.
Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load
bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings M3 27 6500 175500
with all bye-works and direction of the Engineer-in-charge.
(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks,
finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and 0
sundry works).
4 Structural Works 0
Supply of erection of single leaf mild steel gate 2.5m high with mesh upto 2m height and barbed wire fencing and 2m wide
4.1 complete in all respect including painting as per TS on all MS items, all works as per specification and drawings excluding No. 2 32500 65000
foundations and RCC beams.
Supply of all materials, fabrication and erection of chain link fencing 2.5m high with mesh up to 2m height and barbed wire
4.2 fencing complete in all respects including painting as per TS on all MS items, all works as per specification and drawings RM 100 4000 400000
excluding foundation and RCC beams.
5 Electrical 0
Supply, Installation and testing of Galvanized iron earth electrode with 3mts long 65mm dia GI perforated pipe Class B, Complete
5.1 Nos. 2 12000 24000
with GI earth bus, test link in RCC/Brick earth pit, charcoal, salt, funnel and earth pit cover as per IS:3043, (as per drg. enclosed)
Supply, loading, storing, unloading and laying of GI pipes , including supply of GI fittings/accessories including Anaconda, Fittings of all
sizes & thickness like Elbows, Tees, unions, sockets, reducers, GI plugs, Sleeves etc., installation of GI line (along with installation of
required accessories as mentioned above) of following sizes, including fabrication with supply of all materials , consumables, labour and 0
other incidental works. The scope of work also includes installation of Regulators (4/6 bar to 21 m bar) which shall be provided as free issue
item. Carrying out all temporary, ancillary, auxiliary works required to make the GI line ready for commissioning as per drawings
specifications.
Scope of work indicated in SOW and other provisions of Contract document and instructions of Engineer- in-charge, including but not
limited to carrying out the following works: 0
Preparation and approval of schedules, execution procedures, sketches.
Finalisation of optimum route with consent of customer, from transition fitting to cooking oven/ appliance. 0
Making temporary but stable platforms/ scaffolding/ rope ladders and all other safety measures including safety belts wherever required. 0
Drillings of holes through walls (Brick, RCC) , Granite, Marble, Glass Cutting with proper heavy duty hammer drill machine tools and
tackles, using proper sealant /grout material colors to match the original replacement of damages during drilling, restoring the area to 0
original condition.
Supply & Fixing of approved clamps, Dowell Plugs with screws, grout material, suitable thread sealant i.e. Teflon Tape/ lock tight, drilling of
holes through tiles/ wood/ marble/ Granite etc. jointing of PE to above Ground service GI pipes, testing, purging with Nitrogen and 0
commissioning of the complete installation as per specification.
Painting of entire length of pipe along with fittings after proper surface finish by one coat of approved primer paint and two coats of 0
approved synthetic enamel paint complete as per specification & direction of EIC. Restoring the wall surface to origin
All above activities to be carried out as per specification to the complete satisfaction of consumer & as desired by Engineer-in-charge. 0
Handing over the completed works to RSGL for operation/ use, reconciliation of material area wise and obtaining "no objection certificate" 0
from RSGL / Consultant.
Any other activity not mentioned/ covered, explicitly above, but otherwise required for satisfactory completion/ safety/ statutory/ 0
maintenance of works shall also be covered under scope of work and has to be completed by contractor within specified schedule time.
a) ½” All floors (Including connectivity from TF to regulator.)- with supply of GI Pipes by Contractor Meter 7500 300 2250000
b) ¾” All Floors (Including Installation of Risers)- with supply of GI Pipes by Contractor Meter 39000 310 12090000
c) 1" Dia All Floors ((for Riser Installations & For Commercial Connections)- with supply of GI Pipes by Contractor Meter 2500 320 800000
Note:- 0
The quantity measurement shall be from the outlet of the Transition Fitting (TF) upto the Meter. All intermediate GI fittings (excluding
ii) 0
Flexible hose/Anaconda, valves and regulator) shall be considered while measuring length of GI Pipes.
iii) Supply and installation of isolation Ball Valves shall be paid as a separate SOR Item. 0
Supply and installation of copper tubing as per Consultant TS and associated fittings including brass fittings at the outlet of the meter and at
the entry of appliance valve as per satisfaction of EIC. The copper tube and fittings shall be procured from approved vendors who have 0
supplied these items for similar application earlier and with prior approved of Client / Consultant.
Copper tube shall be installed from the downstream of meter upto the isolation valve before the customers' appliance as per
requirement and to the satisfaction of EIC. The Contractor to provide all equipment, tools and material necessary to execute the work in an 0
efficient manner by cutting, cleaning, flux application, soldering and lacquering. The work includes supply of all tools, tackles and
consumables including clamps for fixing the tubes.
i) Supply and installation Appliance Ball Valves shall be paid as a separate SOR Item. 0
Installation & fixing of meters with associated inlet and outlet connections/ fittings, valves, regulators (100 m bar to 21 m bar), approved
a. meter brackets and other supports by proper scaffolding/ grouting, Restoring the area to original completer as per specification. (Meter and Nos. 3000 700 2100000
Regulator will be issued as free issue Item.)
Cleaning and performing minor maintenance, greasing etc. of appliance, testing/ showing performance to the customer ,signing of Joint 0
Meter Records (JMR) and instructing customer on use & safety norms, complete as per specifications & to satisfaction of customer
6.4 Installation of Commercial regulators, Metres including Conversion Nos. 65 3500 227500
Installation & fixing of Commercials regulators and meters with associated inlet and outlet connections/ fittings, valves approved meter
brackets and other supports by proper scaffolding/ grouting, Restoring the area to original completer as per specification. (Meter and 0
Regulator will be issued as free issue Item.).including supply of all types of burner nozzles/jets and associated controls etc.
Supply and installation of Isolation & Appliance Ball Valves as per Technical Specification and as directed by EIC 0
a) Isolation Ball Valve 1/2 " max. 6 bar (g) Nos. 2000 250 500000
b) Isolation Ball Valve 3/4 " max. 6 bar (g) Nos. 4000 430 1720000
c) Appliance Ball Valve 1/2 " max. 35 mili Bar (g) Nos. 3000 280 840000
d) Isolation Ball Valve 1 " max. 6 bar (g) Nos. 25 740 18500
6.6 Installation of Service Regulator: Installation & Fixing of regulator with associated inlet and outlet 0
a Service Regulator installation as per sketch attached - (4/6 bar to 100 mbar) Nos. 8 3500 28000
Regulator Boxes: Supply & Installation including painting of approved make regulator boxes and installing them firmly by
6.7 grouting using approved bracket /clamps as per drawing enclosed & as per specifications and cleaning the area complete to Nos 2 9200 18400
the satisfaction of EIC.
The work shall include identification and tracing of existing pipeline network from As-built drawings (to be provided by EIC)/ Trial Pits or any
other established methods (As-built drawing of some part of network may not be available). Final As-built drawing of the laid network
shall be submitted by Contractor which shall include all the gas assets such as valve, pipeline sizes, fittings etc. The scope of work shall
also include Final clean-up of right-of-use or area disturbed by contractor during their construction/repair activities for laying of Km 10 1300 13000
pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the
same as per satisfaction of Owner and / or as directed by Engineer–in–charge. (Pipe lengths required for the purpose shall be provided on
free issue basis).
The work shall include carrying out pneumatic test @ 6 Bar at every section of about 1 km length and identification of leaks. The scope of
work shall include isolation of section, carrying out the testing and restoring the network. The cost towards supply and installation of
i). section 10 2100 21000
required PE fittings etc. shall be inclusive in the item rate.
Note: The length of section shall be finalised by EIC
Repair of leaks (of various sizes) found and to make various sections ready for commissioning. All consumables, fittings or any other
material required for successful completion of work shall be arranged by contractor. The scope of work shall also include Final clean-up of
ii). right-of-use or area disturbed by contractor during their construction/repair activities for laying of pipeline works and disposal of debris and 0
surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as
directed by Engineer–in–charge.
Flushing and cleaning of pipeline, Pneumatic testing (if required any) as per specification and approved procedures providing all tools and
a) tackles, instruments, manpower and other related accessories and as per the instructions of the Engineer-in-charge. Pressurising and Km 10 2100 21000
keeping the pipeline under 4kg/cm2 with compressed air.
De pressurising the pipeline, purging with nitrogen and commissioning as per specification and approved procedures providing all tools
b) Km 10 3150 31500
and tackles, nitrogen, instruments, manpower and other related accessories and as per the instructions of the Engineer-in-charge.
Pre-commissioning activities and precommissioning checks as per specifications, making the entire pipeline segments system ready for
commissioning , providing assistance during the complete duration of commissioning operations, supply of all
equipment,manpower,consumables (including pigs and required quantity of nitrogen for purging) materials for all temporary works and
performing all associated works, complete as per relevant specifications, other provisions of contract document and instructions of Km 12 30000 360000
Engineer-in Charge
Total Price ( inclusive of all applicable taxes, duties & other levies [if any] payable by the Contractor under the Contract, or for any 53889251
other cause except final GST) for complete scope of work