SECTION 4: Form of Tender Part A: Non-Price Criteria: Tenderer Name Proposed Solution (Method and Approach)
SECTION 4: Form of Tender Part A: Non-Price Criteria: Tenderer Name Proposed Solution (Method and Approach)
Weighting: 15%
Proposed Solution (Method and Approach)
Describe the Tenderer’s (your) proposed method/approach for satisfactorily delivering the
Contract Works including the following:
preliminary quality plan describing procedures for meeting the quality
requirements of the Proposed Contract
allocation of resources to work activities
construction methods
site establishment, contractors’ facilities and security
utilities and connections
defects management
your systems and processes
coordination/management of subcontractors
any innovation you wish to propose
the key benefits of your Tender
if relevant, how your proposed solution will beneficially exceed the requirements.
[Answer]
Provide (as a 1 x A3 page appendix to your Tender) a preliminary works programme for
satisfactorily delivering the Contract Works by the Due Date for Completion including:
critical path
phasing/staging
procurement lead in times
milestones.
Provide a supporting statement outlining:
key dependencies and risks
opportunities and options for completing the works earlier if feasible.
[Answer (supporting statement)] [Append preliminary Works programme to your Tender]
Describe how the relationship between with the Principal/Engineer will be managed during
the Works Contract including:
contact points and availability
accountabilities
regular progress reporting
issue resolution and escalation process.
[Answer]
List what you consider to be the key risks for the Contract Works and outline your proposed
treatment for each.
[Answer]
Confirm that you operate a documented health and safety policy and system that aligns with
AS/NZS 4801:2001 and the requirements set out at Property projects: contractor health and
safety.
If confirmed, state how long your organisation has operated its health and safety
policy and system. If not confirmed, provide an explanation.
[Confirmed: [state how long your organisation has operated its health and safety policy and
system] / Not Confirmed: [Explanation]]
Append a draft SSSP for this Works Contract or a previous example of a SSSP that includes
the management of the site specific safety hazards and associated critical risks listed at
Section 2.2d.
[Append a draft/example SSSP]
Site Forman:
[name of nominated person]
[level of commitment]
[potential constraints]
[contingency]