9 HYDRAULICALLY Plumbing System - Shop
9 HYDRAULICALLY Plumbing System - Shop
DESIGN ANALYSIS:
A. DRAIN FIXTURES
1.1 Calculate total Drain Fixtures Units Loading serving branch lines
1.2 Equate D.F.Us. to GPM demand curve and convert to cu. ft. / sec. discharge 1.3 Substitute to
MANNING’S FORMULA
Q = 1.486 / n x A R 2/3 s1/2 ;where n = 0.012 for pvc or 0.15 for C.I
R = hydraulic radius = ratio of the flow area divided by the wetted perimeter
d = 0.7812 Q 3/8 Q in cu ft / sec, d in ft total drain fixtures unit to demand gpm to cu ft / sec
2.1 Calculate total drain fixtures units serving the soil stack
2.2 Equate the total Drain Fixtures unit serving the stack to an equivalent gpm demand
Q = 27.8 r 5/3
d 8/3
Q in gpm , d in inches r is the ratio the sheet area of flow to the cross sectional area of pipe, r = 7/24
(RNPC used) = 0.29
d=0.609 Q 3/8
rule of thumb vent stack is to be sized one standard pipe size lower, or refer to RNPC Table 7.5 p 88
If R = 10 5 , f = 0.8
S=slope
if s = 1 % , half bore
FOR PVC PIPE
d= 0.609 Q 3/8
H is the Total Dynamic Head = static head +headloss + residual pressure head at the discharge
9.1.1 compute total demand gpm vs water fixtures unit of the last three (3 ) floors
Qm water stockings volume and set pressure cut in and cut off to 25psig to 40 psig
p2 = 40 + 14.74
9.1 allow 70 psig max setting ( for flexibility of pressure adjustment) and with the calculated load
demand gpm( from gpm vs. water fixtures unit demand curve) for 3 floors , substitute to the formula
10.1 Recommended Formula use is Hazen Williams 6 ft / 100 ft head loss for steel pipe
Q = 0.468 Q0.38
11.1 Calculate group of floors to be serve demand gpm base on total fixtures unit at the demand curve
11.2 Size the Feeder pipe using Hazen Williams Formula for 6 ft / 100 ft head loss ( steel)
12.1 utilize 60 psi output pressure for the selection of pressure reducing valve ( prv)
12.2 select (prv ) capacity that will not starve if full demand gpm for group of floors are demanded
( proper sizing shall be based on manufacturer’s catalogue of prv )5
13.1.3 compute hoop stress capacity for riser pipe, sch 40 or sch 80 selection of design for pipe, valves
and etc.