Code Semester: Hydraulics 2
Code Semester: Hydraulics 2
HYDRAULICS 2
CODE
CIVIL 0018
SEMESTER
SUMMER-20
SUBMITTED BY
18S17731
STUDENT NO 03
Introduction
As we know that there is a complete circulatory process for water in this world. Water from the ocean get
evaporated and get rise to high level in the atmosphere and when get cool causes raining. Similarly, after
raining some of the water seep into to the soil and in this way water ground storage capacity of a earth
remain constant. The water quantity which does not seep become a part of runoff. The runoff generated
from an area depends on several condition of the site. For example, soil properties, topography of the
area, and development in the region, paved and unpaved area of the region. As we know that with the
development in an area the paved area will be increased, so the amount of runoff generated will also
increase in that area. Hence in order to cope with this situation there is a need of systematic system which
should be installed in the area to safely remove excess water generated to a particular place specified for
the water produced as a result of run off event. So, for designing such system there is need of calculation
the discharge generated from rain fall event. Hence to solve this situation several studies has been
conducted be civil engineers and as a result of study different methodology has been developed which can
be used to estimate the runoff generated from a rainfall event. Here in this report we will focus on
rationale method of calculating runoff for a region.
In rational method we used an equation consist of different parameters which purely depends on the
topography and environmental condition of the region. And depend on the rain fall pattern in the area. the
equation used for the calculation of runoff is given below. The rational formula is given below
Q=CiA
The catchment area can we calculate from the gis and also we can use google earth for the data. In the
rational equation the parameters are define below
The above parameter should be identified first for a region then based on the above data
runoff should be calculated. And based on the discharge calculated drainage system
should be designed. While designing each parameter should be considered for having a
sustainable design.
Task 1
Required:
I. Determine the peak runoff for the catchment area which is selected.
II. Design best hydraulic section for the given discharge(triangular, rectangular etc)
III. Differentiate or the feasibility between the two section
IV. In design consider the maximum and minimum velocity that does not cause erosion
Solution
Part(1)
The selected catchment area is given below, location(wadi Min’a, Oman)
RL2=2090 m
Rational Methode
Qmax=0.278 CAI
:
mm mm
i=16 =0.67
day h
The rainfall intensity from the above location is 12 to 20 mm/day so we take the average value which is
16mm/day
Qmax=0.278 x 0.15 x 2.1 x 0.67
Qmax=0.0586 m 3/sec
Part 2
Design the given discharge for the best hydraulic section
GIVEN DATA:
A=2100000 m2=2.1k m 2
P=6220m
R L2=2090 m
R L1=699 m
Solution:
Trapezoidal Section
Qmax =0.278 CAI
mm mm
i=16 =0.67
day h
C = 0.15
n=0.015
m3
Q=0.278× 0.15 ×2.1 ×0.67=0.0586
sec
S=¿)
2090−699
S= =0.32
4340
5
3
1 (A )
Q=
n ¿¿
5
2 1
1 (1.75 D ) 3 2
Q= (0.32)
n 2
(3.5 D)3
5
2 1
1 (1.75 D ) 3
0.0586= (0.32) 2
0.015 2
(3.5 D) 3
(1.75 D 2 )5
(0.0090)3=
(3.5 D)2
(1.75)5 10−2
0.0000007329= (D )
(3.5)2
D8=0.000000547
D=0.165 m
Triangular Section B
Q=0.34 cumecs(m3/sec)
S= 0.32
1
Z= = 0.707
√2
Required Data
Design most efficient hydraulic section
1
Z= = 0.707
√2
Solution:
1
A=2( zd×d)
2
A=ZD2
P=2 (ZD)2 + D 2
√
P=2 D √ 1+ Z 2
1
P=2D 1+(
√ √ 2
1
¿ ) ¿2
√
P=2 D 1+
P=2 D √ 15
2
P=2.449D
1 2/3 1/2
Q=R S
n
1 A
Q= ( ) 2/3 S1/2
n B
1 ZD 2/3 1/2
Q= ( ) S
n 2.499
1 D
Q= ( )2/3 S1/2
n 2
1 D 2/3 1
0.34 = ( ) (0.32) 2
0.015 2
Solving
D=0.171m
Part c
Feasibility study and cost analysis of two hydraulic sections
Ans
Part d
Consider the maximum and minimum velocity that wil cause erosion in design
Solution;
Now to determine the erosion velocity wee can determine from the following equation
Q= AV
Q max
V=
A
0.34
V=
12200000
Task 2
Part 01:
i. using the given data from excel and determine yo and also comment
ii. comment the type of flow. After the sluice gate(sub-critical or super-critical)
GIVEN DATA:
V = 0.015m 3
T=23 sec
y g= 12mm = 0.012m
t (cd) = 0.75
b=75mm = 0.075m
Required Data:
Solution:
Part (1)
Step 01 Determine Q
V
Q=
t
0.015
Q=
23
Q= 0.000652 m 3/sec
Step 02 Determine y c
1
Q2
( )
yc= 2
b g
3
y c =0.091 m
Part (1), Step 03
Determine y 0
We know that
a=cd . b . y . √2 g . y 0
V
= cd . b . y . √ 2 g . y 0
t
0.015
= 0.75 ×0.075 × 0.015 √ 2∗9.81 . y 0
23
0.7729=√ 2 × 9.81. y 0
( 0.7729)2
y 0=
2 ×9.81
y 0=0.030 m
y g < y c So the type of flow after the sluice gate is super critical flow
Part 02:
(I) Evaluate the friction factor
(II) Comment on the flow type
(III) Pressure variation from section 1 to 2
(IV) Kinetic energy variation from section 1 to 2
GIVEN DATA:
V= 0.005m3
T= 15.5sec
L=912 mm= 0.912m
D= 17 mm= 0.017m
h2 = 323mm = 0.323m
Required Data
Solution: (i)
For pipe flow we know for two section the Bernoulli’s equation is
P 1 v2 P 2 v2
+ +h1=¿ + +h +h
r 2g r 2g 2 e
h e=h1−hr
h e = 0.323 – 0.250
h e= 0.073m
Now from Doriy Equation
2 gD . he
f= (i)
LV 2
Vd
Q=
time
0.005
Q=
23
Q=0.000217 m3 / sec
π∗d 2
A=
4
3.1416∗( 0.017)2
A=
4
A=0.000227 m 2
Q 0.000217
V= =
A 0.000227
V =0.956 m/sec
Using equation
2× 9.81× 0.017 ×0.073
f= 2
0.912 ×(0.956)
f =0.0292
1. https://www.hydrocad.net/rational.htm
2. https://www.lmnoeng.com/Hydrology/rational.php
3. https://www.samsamwater.com/catchments/
4. http://www.fsl.orst.edu/geowater/FX3/help/8_Hydraulic_Reference/Open_Channel_Flow.htm
5. https://www.engineeringtoolbox.com/sluice-gate-flow-measurement-d_591.html
6. https://www.researchgate.net/figure/Rainfall-intensity-in-Oman-This-figure-is-available-in-
colour-online-at_fig7_230325195