PRC-0002 Current PDF
PRC-0002 Current PDF
Engineering Directorate
May 2020
Page 1 of 27
PRC-0002 Rev. D
Page 2 of 27
PRC-0002 Rev. D
REVISI
ONS
VERSIO DESCRIPTI DATE
N ON
-- Original version 6/1/95
Formatting, changed process owner, rewrite
numerous sections for clarification, deleted
A requirement for WIR, deleted section 8.2 on audits, 07/07/99
added section 8.3 on WPQ, deleted mil specs for
NDE, added PRCs for
NDE.
Comprehensive rewrite to combine PRC-0002 and
PRC-0004 and make editorial changes. PRC-0004 12/30/200
B will be cancelled with this change. Include 3
requirements for precision cleaned hardware (ref.
JPG 5332.1).
Updated the review and approval signature blocks;
added definitions of flight and non-flight hardware in
2.0; added NAS 410, NASA-STD-5009, PRC-5010,
PRC-6510 and AWS G2.4 to 4.0; deleted PRC-6504
from 4.0; revised 6.5 to allow mechanical repairs and
restrict welded repairs to one attempt; revised 7.0 10/10/201
C through 7.3 to add separate inspection requirements 2
for flight hardware and require NAS 410 certification
for NDE personnel inspecting flight hardware;
revised the WPS, PQR and WPQ requirements in
8.0 to include a provision found in 6.1.1; and revised
Appendix A in its entirety.
Rewrite numerous sections for clarification, added
Appendix B (hardware classifications), modified
Class B and C weld definitions, added JPG 8500 to
references, removed PRC-0008 and TI-0000-01 from 05/15/202
D references, rewrote section 5.0, added more 0
emphasis on using ELI grade filler metals, require
MTR for filler procurement, restructured list in section
6.6, added definitions as section 10.0, align format
and content with PRC-0015.
Page 3 of 27
PRC-0002 Rev. D
1.0 SCOPE
This process specification provides the minimum requirements that govern the
manual arc welding of titanium alloy flight and non-flight hardware. Procedural and
quality assurance requirements are given. All work instructions and Welding
Procedure Specifications (WPS) used during welding shall satisfy the requirements
of this process specification and its applicable documents.
2.0 APPLICABILITY
This process specification applies to arc welding of titanium and titanium alloy
hardware that is fabricated under the authority of NASA/Johnson Space Center
(JSC) by the following welding process: Gas Tungsten Arc Welding (GTAW) and
Plasma Arc Welding (PAW).
The Gas Metal Arc Welding (GMAW) process is not considered an acceptable
process for welding titanium alloys under this process specification.
3.0 USAGE
Page 4 of 27
PRC-0002 Rev. D
of service intended for the joint by design and governs the extent to which quality
assurance provisions are applied to the weld joint as specified herein.
In addition to the above weld class definitions, the following requirements shall also
apply to weld classifications:
Page 5 of 27
PRC-0002 Rev. D
Work instructions shall be used for implementing this process specification. The
work instructions shall contain enough detail to ensure that the manufacturing
process produces consistent, repeatable results that comply with this specification.
At JSC, these work instructions are approved as Detailed Process Instructions
(DPIs) that describe in a detailed, step-by-step format the required procedures,
equipment, and materials to be used for conducting a given process. If this
manufacturing process is to be performed by an outside vendor, work instruction
development shall be the responsibility of the vendor.
3.3 DESIGN REQUIREMENTS
a. The design of welded joints (including weld sizes) shall utilize adequate
engineering analysis methods (e.g., stress analysis, fracture
mechanics/fracture control, finite element analysis, failure mode and
effects analysis, etc.) to ensure that the resultant connection strength is
capable of successfully transferring the maximum load expected to pass
between the interconnecting members and meet the required factors of
safety and design margins.
b. All engineering drawings shall depict welded joints using the applicable
symbols described in AWS A2.4.
c. The engineering drawing shall specify any additional or alternate testing
or inspection requirements. Where spot, intermittent, or other special
inspection requirements are specified that deviate from those stated
herein, it shall be detailed on the drawing as a note or by using the
applicable symbology described in AWS A2.4. For Class A welds,
alternate or reduced NDE requirements shall not be allowed.
e. Except for titanium alloy 6Al-4V welded with 6Al-4V filler metal,
hardware will be delivered in the “as welded” condition unless otherwise
specified on the engineering drawing. If required, the engineering
drawing shall include notation that will specify an appropriate heat
treatment process, referencing SAE AMS-H- 81200. For welds in alloy
6Al-4V welded with 6Al-4V filler metal, a stress relief heat treatment at
1100o F for 2 hours (vacuum or inert gas atmosphere) shall be required.
f. Intermittent welding (skip welds) shall not be allowed for Class A joints.
g. Intermittent welds shall not be allowed for butt welds (square or groove
design) unless the unwelded portions of the joint are adequately
Page 6 of 27
PRC-0002 Rev. D
supported to prevent one member from coming out plane with the
adjoining member.
h. Weld filler material shall be specified on the engineering drawing in the parts
list.
4.0 REFERENCES
The standards listed below shall be considered a part of this specification to the
extent specified herein. Unless otherwise indicated, the revision that is in effect on
the date of invitation for bids or the date of request for proposals shall apply.
e. Federal Documents
BB-H-1168 Helium Federal Specification
Verify correct version before use.
Page 7 of 27
PRC-0002 Rev. D
f. Military Documents
MIL-A-18455 Argon, Technical
g. NASA/JSC Documents
JPG 5322.1 Contamination Control Requirements Manual
h. NASA Headquarters
NASA-SPEC-5004 Welding of Aerospace Ground Support Equipment
and Related Nonconventional Facilities
All base materials used in the welding of hardware per this process specification,
shall meet the requirements of an applicable commercial specification (e.g., AMS,
ASTM, etc.). Alternatively, a manufacturer's specification may be used but it must
be approved by the responsible materials and processes (M&P) organization. Filler
and electrode materials used shall conform to the applicable American Welding
Society (AWS) specification. Filler metals shall be extra low interstitial (ELI) grade
wherever possible. Interstitial elements include but are not limited to, oxygen,
Page 8 of 27
PRC-0002 Rev. D
Allowable shielding gases (including purge gases) are listed in Table I. Gases
purchased to alternate specifications shall be allowed provided they meet the
minimum requirements of the specifications listed herein. Mixtures of these gases
are allowed, and the nominal mixture used for the qualification welding shall be that
used for production and shall be listed on the WPS. All shielding and purging gases
and nominal gas mixtures shall be treated as an essential procedure qualification
variable and shall be subject to the AWS B2.1 requirement for these variables. In
addition:
a. All gases used for welding and purging shall be delivered through clean,
non- volatile residue (NVR) tubing with known low permeability (e.g.
stainless steel, polyethylene).
b. Nitrogen, oxygen, carbon dioxide, or hydrogen gas in any concentration,
shall not be used for shielding or purging in any welding operation
governed under this specification.
c. All gases used for shielding or purging shall have a dew point of -60°F
(-51 °C) or better and oxygen content shall not exceed 50 ppm.
A protective weld atmosphere shall be freely accessible to all portions of the joint.
The weld atmosphere for inert gas chambers, and gas supplies for trailing shields
shall be monitored for moisture or oxygen content. Dew points shall be -60°F (-51
°C) or better and O2 content shall not be greater than 50ppm. All gas shielding must
be checked to ensure that a positive flow exists all times, so that a stagnant
atmosphere does not exist during welding or when the base metal is at an elevated
temperature. Shielding and purging flows shall not be disengaged until the substrate
is below 600°F (~316°C).
5.1.2 Weld Atmosphere Purity Test
Page 9 of 27
PRC-0002 Rev. D
Filler metals shall be selected based on specific base metals being welded, service
conditions, design requirements (load conditions, etc.), and other design or service
factors. The specific selection must be approved by the responsible M&P
organization prior to use. In addition, the following shall apply:
a) Filler and electrode materials used shall conform to the applicable AWS
specifications listed herein. Filler metals and electrodes purchased to
alternate specifications shall be allowed provided they meet the
minimum requirements of the specifications listed herein. Filler metals
shall be procured with delivery of a valid material test report (MTR).
e) Weld filler metals shall be called out on the engineering drawing in the parts
list.
f) Non consumable tungsten and tungsten alloy electrodes for GTAW and
PAW shall be selected according to the process being used at the
direction of the responsible M&P organization. The electrode type and
size shall be specified on the WPS.
5.2.1 Control and Storage
Page 10 of 27
PRC-0002 Rev. D
Welding electrodes and filler metals shall be stored in a clean, dry, and controlled
area that provides protection from contamination, physical damage, commingling of
alloys and loss of identification/traceability. Any form of electrodes or weld filler metal
which is damaged, dirty, exhibits oxidation/corrosion or has been contaminated with
water, oil, grease or any form of hydrocarbons shall not be used and shall be
disposed of in accordance with an appropriate disposal procedure. For JSC
operations, welding electrodes and filler materials shall be controlled in accordance
with SOP-004.5. Outside vendors shall provide control and storage according to the
applicable material specification or manufacturer's recommendation, whichever is
more rigid.
5.3 MECHANICAL PROPERTIES
When an inert gas or vacuum chamber is used for welding or trailing torch shields
and/or a trailing or fixed gas purge assemblies are used, the specific equipment and
method shall be considered an essential variable during qualification of the WPS
and personnel qualifications.
Prior to welding, all weld joint surfaces within a minimum of ½” of the weld line shall
be cleaned in a manner shown to be adequate and repeatable in producing a surface
cleanliness level conducive to producing sound welds by a given weld process. The
specific process and procedural steps to carry out the process shall be part of the
procedure qualification activities and shall be appropriately detailed on the
qualification and procedure specification (PQR and WPS) documentation as well in
the production work instructions. Personnel shall be trained in these same methods
and process techniques.
Applicable to all processes, unless otherwise specified, weld joints that are specified
Verify correct version before use.
Page 11 of 27
PRC-0002 Rev. D
for intermittent welding shall have the ends of the parts, or departure from a straight
weld line (e.g., square corner, etc.), welded regardless of the interval of the weld.
Temporary (includes the term “tack” welding) welding in areas of the hardware not
planned for welding or where the temporary weld will not be totally consumed by the
final weld, shall not be allowed. All temporary welds placed at or in a weld joint shall
be ground or feathered by welding appropriately to accommodate the final welding
process to achieve the expected deposit of sound weld metal. All temporary and
tack welding shall only be performed by a welder(s) whose qualifications are current
and applicable.
Equipment (e.g., power supplies, positioners, flowmeters, etc.) used for manual
welding operations need not have calibrated instrumentation (dials, gauges,
indicators, meters, etc.). However, reference indicating instrumentation (e.g., dials,
meters, gauges, etc.) shall be fully functional (i.e., useful output) and in good working
order. The equipment shall be capable of being used by a qualified welder, using a
qualified procedure, to produce sound and contaminant free welds. At the discretion
of the responsible M&P organization, specific equipment instrumentation and
metering devices may be calibrated to ensure repeatability of the process.
6.1.6 Welding Precision Cleaned Hardware (including tube preparation for
welding)
Page 12 of 27
PRC-0002 Rev. D
Tube cutters shall use a sharp blade, changed frequently. Cutting shall be performed
with minimal cutter pressure to aid in preventing particle generation. Tube facing
operations shall use vacuum to remove particulate. Facing operations shall be
performed away from the weld assembly area, to reduce particulate contamination
of the welding work area. Tube facing shall be performed without the use of cutting
oils, other fluids, lubricants or coolants. Abrasives, including sandpaper or abrasive
pads, shall not be used inside tubes or when unprotected internal surfaces are
exposed. After each tube preparation, and prior to welding, a high-velocity gas purge
shall be performed. The purge gas velocity shall be the maximum attainable using a
90-psig (minimum) source. The purge gas used during facing and welding shall meet
the hydrocarbon and particulate requirements for the system under assembly. The
purge gas shall be supplied in accordance with Section 5.1.
6.2 PROCESS SPECIFIC REQUIREMENTS
Additional filler metal shall be used with the PAW process unless it can be
demonstrated by weld qualification that weld cracking and other undesirable
metallurgical conditions will not exist in the finished weld made without filler metal
(autogenous weld). This method of welding shall be specified on an approved WPS.
6.2 PREHEATING
Preheat shall not exceed 600°F (~316°C) and shall be specified on the WPS. Actual
welding shall begin immediately after preheating has reached the temperature
specified on the WPS. Temperature indicating crayons (markers) shall not be used
to measure base or weld metal temperature.
6.3 INTERPASS TEMPERATURE
a. In weld joints between different base metal types and thickness, the higher
of the preheat requirements of the joint members shall apply.
Post-weld heat treatment shall be applied only when specified by the engineering
drawing and/or WPS and shall be performed after completion of welding. All PWHT
shall be performed according to SAE AMS-H-81200. Vibratory techniques shall not
Page 13 of 27
PRC-0002 Rev. D
be used in place of thermal treatment. All weld inspections shall be applied as soon
as practical following all post weld heat treatment activities.
6.5 WELD REPAIRS AND WELDED REPAIRS TO BASE METAL
Two attempts shall be allowed to make a weld repair. If after the second attempt a
defect still exists, the condition shall be documented on an appropriate non-
conformance report (NCR) or discrepancy report (DR) form. All repair and rework
shall be performed using the WPS used for the original weld, a specific qualified
WPS for that repair. Rework and repairs shall meet all of the requirements of the
original drawing and any additional requirements documented in the WPS. Weld
rework and repair does not include the correction of dimensional or other
deficiencies of the groove/bevel preparation of weld joints by “buttering” or build up
provided the area corrected by welding is fully consumed in the final weld. Also, the
following requirements shall apply in the weld repair activity:
a. Mechanical Repairs. Defects shall be repaired by routing or machining the
weld metal to the extent needed to completely remove the defects.
Thermal gouging and cutting shall not be used. For groove welds, the
reinforcement shall not be machined past flush to the base metal. For fillet
welds, the final machined weld profile shall meet the applicable profile and
size requirements. In both cases, the repair shall be blended smoothly into
the unrepaired weld metal. All repairs shall be subjected to the same
visual, surface and subsurface inspections as the unrepaired weld.
Repairs requiring liquid penetrant inspection shall be etched in
accordance with PRC-5010 prior to inspection.
d. Base Metal Repairs. Repairs to base metal anomalies shall be brought to the
attention of the responsible M&P organization for consideration of cause,
prior to repair activities.
6.6 SURFACE DEGRADATION FROM CONTAMINANTS
Page 14 of 27
PRC-0002 Rev. D
To prevent surface contaminants that can induce liquid and solid metal embrittlement,
stress corrosion, hydrogen embrittlement, or reduce fracture toughness from coming in
contact with the base material, the use of these substances on or with titanium is
prohibited:
1. Mercury
2. Cadmium
3. Silver
4. Gold
5. Hydrochloric Acid
6. Chlorinated Cutting Oils and Solvents
7. Fluorinated Hydrocarbons
8. Methyl Alcohol
9. Methylene Chloride
a) The welding operator is certified for the specific welding operation prior to
welding.
b) The fit-up is in accordance with the engineering drawing prior to welding for
Class A and B Pressure Containing Components.
d) Compliance with the WPS for essential variable ranges during welding.
Page 15 of 27
PRC-0002 Rev. D
Personnel performing acceptance inspections of flight hardware (Class I, II, IIIW and
GSE – see Appendix C) shall be qualified and certified, at a minimum, to Level 2 in
accordance with NAS 410. Personnel performing acceptance inspections requiring
Special Non-Destructive Evaluation (NDE) shall also be qualified and certified for
Special NDE in accordance with NASA-STD-5009.
Personnel performing acceptance inspections of non-flight hardware (Class III,
STE/D, mockup, and facility hardware – see Appendix C) shall be qualified and
certified in accordance with either NAS 410 or SNT-TC-1A. Personnel making
accept/reject decisions shall, at a minimum, be certified to Level 2. Level 3 personnel
making accept/reject decisions shall have successfully completed a hands-on
practical examination equivalent to the examination required for Level 2. Level 1
personnel may perform acceptance inspections under the direct supervision of a
Level 2 but shall not make accept/reject decisions.
Formal qualification and certification is not required for personnel performing
engineering evaluation inspections.
Unless otherwise specified, all welds in a structure shall be subjected to the required
inspections for the applicable weld class or classes. All unconsumed temporary or
tack welds shall be placed where consumed by final weld and subjected to the level
of inspection required by the highest weld class specified in the design
documentation.
7.2.1 General
Welds shall be visually inspected for conformance to the drawing requirements and
acceptance shall be in accordance with the applicable Class A, B or C acceptance
criteria in Appendix A or B.
7.2.3 Liquid Penetrant
Page 16 of 27
PRC-0002 Rev. D
7.2.5 Ultrasonic
7.3.1 Class A
Class A welds require visual, surface and subsurface inspections. Surface
inspections shall be accomplished using the liquid penetrant method. Subsurface
inspections shall be accomplished using the radiographic method. In cases where
the weld configuration renders adequate radiographic inspection impractical, an
alternate inspection method shall be utilized as approved by the responsible M&P
Engineering authority. When ultrasonic inspection is selected and approved as an
alternate to radiographic inspection, the ultrasonic inspection shall be performed as
specified in section 7.2.5. When liquid penetrant is the only available option for
inspection and is selected and approved as an alternate to radiographic inspection,
the liquid penetrant inspection shall be performed as specified in section 7.2.3. For
multi- pass welds, inspections shall be performed on every pass.
7.3.2 Class B
Page 17 of 27
PRC-0002 Rev. D
7.3.3 Class C
The WPS, PQR, and WPQ shall be prepared and retained as a permanent record
and made available upon request to the responsible M&P organization for review.
These procedures must contain, at a minimum, all of the essential welding variables
(procedure qualification variables, etc.), an identification of the welding equipment,
the pre-weld cleaning procedure (refer to Section 6.1.1) and include any pertinent
tooling information. One copy of the WPS shall be maintained in the vicinity of the
welding station and shall be readily accessible by the welders, inspectors,
supervision, and engineering.
8.1 PROCEDURE QUALIFICATION VARIABLES
Applicable to all processes, the process variables considered “essential” and
applicable to qualification of a welding processes/procedure shall be all those as
required by AWS B2.1 and to include the following:
a. A change from vertical downhill welding to vertical uphill or vice versa,
b. A change from a stringer to a weave bead and vice versa,
c. A change from multiple passes per side to a single pass per side, and vice
versa,
d. As deemed necessary by the responsible M&P organization, an
increase or decrease in any one or more of the variables considered
integral to the calculated heat input (i.e., current, voltage, and travel
speed) beyond that which was qualified. Where necessary, the
procedure shall include weld tests that define the tolerance ranges of
specifically identified variables,
e. For keyhole welding techniques, a change from keyhole to non-
keyhole and vice versa.
f. WPSs qualified outside of a weld chamber using trailing shields and
gas purge assemblies may also be used for welding in a weld
chamber, but not vice versa.
g. Any deviations or waivers regarding the use of this process specification shall
be requested in writing. This request shall be directed to the responsible M&P
organization with the appropriate justification and rationale. A written
response will be provided upon such a request.
Page 18 of 27
PRC-0002 Rev. D
to use in production. If a qualified WPS does not exist prior to welding of production
parts, one shall be qualified according to AWS B2.1 “Standard Test Weldments” at
a minimum. “Prequalified” or “Standard Welding Procedure Specifications” shall not
be permitted for production use on Class A or B welds made on flight hardware.
8.3 PROCEDURE QUALIFICATION RECORD
Any deviations or waivers regarding the use of this process specification shall be
requested in writing by the outside vendor. This request shall be directed to the
responsible M&P organization with the appropriate justification and rationale. A
written response will be provided upon such a request.
9.1 TRAINING
Welder training (when necessary) should consist of practice using the facility
welding equipment and a specific WPS to demonstrate proficiency, under the
supervision of a qualified/certified welder. Specific development of an appropriate
training program shall be the responsibility of the vendor.
When qualifying personnel for titanium welding, the welding setup shall be
considered an essential variable. When qualifying personnel for titanium welding by
the guided bend test method, titanium alloys not listed in AWS B2.1, Appendix C1
or C2, the plunger diameter (dimension “A” in Annex II of AWS B2.1) shall not
Verify correct version before use.
Page 19 of 27
PRC-0002 Rev. D
exceed 20T (10T radius). For the alloys listed in Appendix C, use the bend radiuses
shown in the table.
10.0 DEFINITIONS
The following definitions (and associated acronyms) shall apply to this entire
document:
Page 20 of 27
PRC-0002 Rev. D
Appendix A
WELD ACCEPTANCE CRITERIA
A1.0 GENERAL
If any of the acceptance criteria given below conflict with the engineering drawing
requirements, then the stricter criteria shall apply. The symbol ‘T’ shall equal the
nominal base metal thickness of the thinnest component in the welded connection.
The weld length shall be the distance from end to end of the weld deposit or to a
sharp change in weld direction where the angle of change in any direction is greater
than 30° with a radius of less than 1/2”. Unless otherwise stated, the criteria in this
Appendix shall apply to all weld classes. Alternate and/or additional acceptance
criteria, when applicable, shall be specified in the design documentation.
Brushing of titanium welds is not allowed prior to visual and surface inspection.
Page 21 of 27
PRC-0002 Rev. D
Page 22 of 27
PRC-0002 Rev. D
Page 23 of 27
PRC-0002 Rev. D
Note: Convexity of a weld or individual surface bead with dimension Width shall not exceed the value of the following table.
(4) Acceptable Groove Weld Profiles in Butt Welds Note: Reinforcement shall not exceed 1/8”.
Page 24 of 27
PRC-0002 Rev. D
Appendix B
Hardware Classification
Hardware
Classificatio
n
Page 25 of 27
PRC-0002 Rev. D
Page 26 of 27
PRC-0002 Rev. D
Appendix C
Page 27 of 27