CBTI Phase 2 Construction Task Report 10092020
CBTI Phase 2 Construction Task Report 10092020
TO: JERRY/JEROME
FROM: ENGR. DONATO/ENGR.JERICK/ENGR.ANTON
SUBJECT: Checking of Ongoing Works at CBTI PHASE 2 Chemical Storage Facility Plant
Foundation at Tank #7,#8,#9,#12,#13 ,#15,#16. DONE
(Previously turned over to Toughstar)
Foundation at Tank # 17 - ongoing backfilling of base course temporarily stops due to
rain not yet ready for turned over to Toughstar
The area is still unworkable at this point in time due to continuous rain Oct.6,7 &8 . While waiting for
the area to dry up we come up to an idea to just assemble the rebar of footing foundation on the
vacant space near Tank #9 as shown. Then later on once they finish the rebar works on footing we
shall laid it on the excavated foundation using mobile crane and backhoe. As of this moment rebar
works of footing foundation still ongoing.
We have just backfilled second layer of base course but due to rain last Oct. 6 7 & 8 the work
temporarily stops. Backfilling will resume once the area is dried up. Regarding the starter of road
roller, according to the supplier the flywheel needs to be reversed because the other side of
flywheel gear teeth was already worn out.
Tank #8 - Installation of monkey ladder and touch up done. Balance of work - waiting for radiographic
testing; waiting for flange connection; Scaffolding installation inside tank. Ready for radiographic test.
Vacuum test. Hydro test. Dye penetrant test at roof plate and air leak test and installation of roof
nozzle. (situation as is)
TANK#8
TANK#8
Tank #9 - Installation and full welding of step ladder is ongoing. waiting for radiographic testing;
waiting for flange connection; Scaffolding installation inside tank. Ready for radiographic test.
Vacuum test. Hydro test. Dye penetrant test at roof plate and air leak test and installation of roof
nozzle. Ongoing scope of work-welding of stair.(as is)
TANK#9 TANK#9
Tank #11- (Status: the area is still flooded and unworkable. Rebar works ongoing near tank #9.)
Tank # 10 - As a preventive measure due to very near setback to Holcim (weighing scale) and
potential to hazard, the tank is finally deleted on site by Sir Jerome.
Tank #12 – Full welding of doubler plates at two nozzles. waiting for radiographic testing; waiting for
flange connection; Scaffolding installation inside tank. Ready for radiographic test. Vacuum test.
Hydro test. Dye penetrant test at roof plate and air leak test and installation of roof nozzle. Ongoing
scope of work -installation of bridge support done.
TANK#12
TANK#12
Tank #13-. Full welding of doubler plates at two nozzles - waiting for radiographic testing; waiting for
flange connection; Scaffolding installation inside tank. Ready for radiographic test. Vacuum test.
Hydro test. Dye penetrant test at roof plate and air leak test and installation of roof nozzle.(situation
as is)
Tank#14
Tank #15
Tank #15
Tank #16- Full welding of 4th course shell plates vertical.
Manpower-1welder
Tank#17- We have just backfilled second layer of base course and performed compaction inside
ringwall foundation but unfortunately heavy rain fell last Oct.6,7 & 8 2020.Right now the area is
flooded and unworkable. We will resume backfilling works and compaction once the area is dried up.
NOTE:
Tank#8-pressure leak test of lug support done.
Tank#12-pressure leak test of lug support done.
Tank#13-pressure leak test of lug support done.
Tank#14-pressure leak test of lug support done.
IN HOUSE: Sandblasting operation- blasting and painting shell plates and primary rafter.
Included also the sandblasting and painting of piping 4”diameter.
Installation of monkey ladder at tank #8 and tank#7 done.
Touch up is ongoing at the tank#7
@ done & tank#7
EQUIPMENT STATUS: