Comments For The Misconceptions About KV Line
Comments For The Misconceptions About KV Line
Prepared by:
Existing users Existing Travel Future Travel Time by Travel Time Saving
Time KV Line (min) (min)
(min)
Train 68 26 min
Car 113 42 71 min
Bus 130 88 min
• The limited stop train between Maradana and Homagama travel time is 25 min for the
modernized KV line.
• The 26 min saving for existing users but they are only 30,000 train passenger trips on KV line
• Therefore, majority of future users are transferred from Car or Bus therefore having either a
71 min or a 88 min saving based on current travel time.
• However, with the passengers moving out to railway, the roads will be faster, therefore the
effective travel time saving will be less for passengers transferring from cars and buses.
2. People will not use the Railway as they are not using even now
• Its true that there are only 30,000 passengers using the KV line as of 2018 Ticket sales data.
• There is already an advantage to use the Trains over car or bus if only travel time is
considered. (Car 113min, bus -130 min and Trains 68 min in evening peak)
• The reason the people don’t use it now is because
o They can’t even if they want. The trains are already at full capacity. The single track
and the signal system and does not allow even a single train to be added to the
schedule to provide more supply of trains
o The trains in current KV line are very unreliable, the delays data shown above shows
that they have delay close to 20-30 minutes
o The connectivity to the train stations are poor, if a breakdown happens in an isolated
station then it is hard to get to an alternate transport mode.
o The conditions of the trains, stations, services are very poor.
• However, with the modernization of the track and system the number of trains will increase
to
trips
Maximum section
o
The Cost
1. The cost was Initially estimated as 2.5 USD Billion and then reduced to 1.5 USD Billion
• The Project cost of 2.52 USD billion was estimated on the Draft Report Submitted to the
Steering Committee on 9th September 2018.
• The cost above was an initial cost based on initial estimates not based on detailed costing
• The ADB, the PMU and then IESL all commented that the cost was too high and that it needs
to be reassessed
• The project completed the detail design and the final project cost was reported in the final
report 11th April 2019 as 1.424 USD Billion.
o Construction Cost – 1.245 USD Billion
o Construction Supervision – 49 Million USD
o Contingency – 65 Million USD
o Price Escalation – 65 Million USD
• The reason for 2.52 USD Billion and reduction to 1.424 Billion
o The price estimated in LKR and at 150 LKR/USD. When the final price corrected at 179
LKR/USD the cost reduced.
o Once the detail cost estimations were done refining the estimated costs the cost
reduced
• The current alignment has many curves. In the 35 km from maradana to Padukka have 115
curves and total curve length is 16 km.
• The rail stations are located very close to each other. There are 24 stations in 35 km length
between Maradana and paduka. The distance between the stations vary from 0.6 to 1.9kms
• Two options for horizontal alignment were considered
o Option 1: (proposed development. The curves to be straightened as much as possible
within the existing ROW with minimum curve radius at 120m. Minimizes additional
acquisition. The land Acquisition cost is USD 8.5 million
o Option 2: maximum speed up o 70km/h and minimum curve radius of 300m. Cause
considerable land acquisition. The land acquisition cost is USD 32 million.
• The current speed of 23.5 km/h is increased to 35.2km/h in the current proposed design.
There is no notable speed gain even with straightening the curves with option 2 with speed
gain up to 37.5km/h due to station been close to each other and thereby not been able to
gain the maximum speed.
• The Travel time from homagama to maradana in proposed alignment is 42min while by
straightening the curves the travel time is only reduced by 5 min.
• The cost of reducing travel time by 5 min by going to a option that requires high acquisition
cost is not viable
• Therefore Option 1 with proposed alignment was selected.
Freight Movement
1. Freight movement is not possible by elevation and loading unloading cannot be done.
• Less than 2% of Sri Lanka good transport done with rail, where Freight traffic has declined
since 2010
• 98% of the freight handles by rail is for cement inputs and oil products
• There is no current demand for freight movement along the KV corridor except for parcel
delivery and there is no demand projected for future as well
• The short distance fright hauling is anyways more economical by trucks
• There is no need to provide loading unloading provisions at elevated section. If a need arises
then a ramp down or a separate design can be made
• The freight connection towards Avisawella is planned in the masterplan through Kelaniya
Kosgama Aviasswella which is a direct connection to the port. In case of freight to be
considered the above option is also available
Annex 1