0% found this document useful (0 votes)
84 views

SCH Project Management Dashboard 0410 Week 10

The document is a project management dashboard for the construction of a junction for Schlumberger facilities. The project is delayed, with actual progress at 44.6% compared to the scheduled progress of 51.75%. Several work packages have not yet started according to the work breakdown structure. The budget consumed so far is $33,961 against a planned budget of $225,672, with $110,333 accounted for as the actual cost to date and $5,300 in pending items.

Uploaded by

Samir Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
84 views

SCH Project Management Dashboard 0410 Week 10

The document is a project management dashboard for the construction of a junction for Schlumberger facilities. The project is delayed, with actual progress at 44.6% compared to the scheduled progress of 51.75%. Several work packages have not yet started according to the work breakdown structure. The budget consumed so far is $33,961 against a planned budget of $225,672, with $110,333 accounted for as the actual cost to date and $5,300 in pending items.

Uploaded by

Samir Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT MANAGEMENT DASHBOARD

PROJECT NAME Construction of Junction for Schlumberger Facilities 20.000 100.000


18.000 90.000
16.000 80.000
REPORT DATE 04-10-20
14.000 70.000
12.000 60.000
PROJECT STATUS DELAYED 10.000 50.000
8.000 40.000
6.000 30.000
PROGRESS % (SCHED.) 51.75%
4.000 20.000
2.000 10.000
PROGRESS % (COMP.) 44.60% 0.000 0.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

WBS Summary Start End STATUS 12‐07‐20 01‐08‐20 21‐08‐20 10‐09‐20 30‐09‐20 20‐10‐20 09‐11‐20 29‐11‐20

Preliminaries 13-Jul-20 13-Oct-20 IN PROGRESS Preliminaries

Construction 25-Jul-20 17-Nov-20 IN PROGRESS Construction

Mobilisation 25-Jul-20 7-Aug-20 COMPLETE Mobilisation

Earthworks 6-Aug-20 8-Oct-20 IN PROGRESS Earthworks

Asphalt works 11-Oct-20 3-Nov-20 NOT STARTED Asphalt works

Road Appurtenances & Others 9-Nov-20 14-Nov-20 NOT STARTED Road…

Other Miscellaneous works 22-Aug-20 17-Oct-20 IN PROGRESS Other works

Handover 15-Nov-20 17-Nov-20 NOT STARTED Handover

Budget Vs. Actuals Budget Consumed (As per LPO) Pending Items
33,961 
5

4
Actual 110,333
3
13,847 
2
10,555 
Planned 225,672 1
15,896 
5,300 
1,472  0
Decisions Actions Variations
0 50,000 100,000 150,000 200,000 250,000 1 2 3 4 5 6 Requests

PROJECT CONTROL DEPT. Week‐10

You might also like