0% found this document useful (0 votes)
233 views

MEP Payment Breakup Desired - AP

The document outlines the breakdown of milestone payments for MEP tunnel services in an infrastructure project with a total cost of 2745 Crore. It allocates 1884.99 Crore (68.67% of total) for tunnel works. MEP costs are estimated at 284.45 Crore (15.09% of tunnel costs). The MEP costs are further broken down into percentages and amounts for different subsystems - electrical (73.82 Crore), ELV (16.1 Crore), firefighting (81.6 Crore), TVS (20 Crore), substations (31.64 Crore), fire pump rooms (54.4 Crore), and work stations (3.45 Crore

Uploaded by

balabhavini
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
233 views

MEP Payment Breakup Desired - AP

The document outlines the breakdown of milestone payments for MEP tunnel services in an infrastructure project with a total cost of 2745 Crore. It allocates 1884.99 Crore (68.67% of total) for tunnel works. MEP costs are estimated at 284.45 Crore (15.09% of tunnel costs). The MEP costs are further broken down into percentages and amounts for different subsystems - electrical (73.82 Crore), ELV (16.1 Crore), firefighting (81.6 Crore), TVS (20 Crore), substations (31.64 Crore), fire pump rooms (54.4 Crore), and work stations (3.45 Crore

Uploaded by

balabhavini
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Milestone payment Break up for MEP Tunnel services

Overall project cost (Contract Price) as per agreement (Crore) 2745


Weightage as % for Tunnel as per Schedule- H, addendum-5 68.67
( Head Tunnel)

Alloted cost for Tunnel 1884.99

Weightage as % of Tunnel systems) 15.09

MEP cost as per the weitage of the overall contract price (Crore) 284.45

Percentage
S.no Item % of the total cost Amount in Crore Bifurcation of activities weightage of
subheads
Support supply & installation
Supply & Installation of containment
supply and installation of wiring for lighting and small power
1 Electrical 70 73.82 supply and installation of Light fixture
supply and installation of MV/LV cable
supply and installation of HT/LT switchgears in inside tunnel substation
Testing & commissioning
Support supply & installation
Supply & Installation of containment
supply and installation of Support fixing for linear heat detector cable
supply and installation of linear heat detector cable installation
supply and installation of ELV Cable pulling for CCTV,emergency telephone and push button,PA
2 ELV system 70 16.10 system,A75 ohm leaky feeder cable, SCADA/PLC
Scope in
Tunnel supply and installation of ELV equipment installations
supply and installation of VMS at inside tunnel (Pictorial Tunnel )Advisory Display Board
supply and installation of Traffic Sign "Overtaking Prohibition" TYPE-A@ 500 mtr
Testing & commissioning of ELV system
Integration system with cause n effect
supply and installation of Support Installation for hydrant system
supply and installation of Hydrant pipe
supply and installation of Fire house cabin arrangement
3 Firefighting System 60 81.60
supply and installation of Support Installation for mist system
supply and installation of Mist system pipe and accessories installation
Testing & commissioning
Support supply & installation
4 TVS system 100 20.00 supply and installation of Jet fan
Testing & commissioning
supply and installation of DG sets
supply and installation of Transformers
North portal supply and installation of HT/LT Switchgear
5 Substation 15 15.82 supply and installation of UPS and associate equipments
(Electrical) Support & Tray supply and installation
Internal electrification of wiring
Testing & commissioning
supply and installation of DG sets
supply and installation of Transformers
South portal supply and installation of HT/LT Switchgear
6 Substation 15 15.82 supply and installation of UPS and associate equipments
(Electrical) Support & Tray supply and installation
Internal electrification of wiring
Testing & commissioning
Supply & Installation of support and containment
Supply and installation of Hydrant system Main Header and associate piping arrangement
material
Scope of North portal Fire Supply and installation of Pump and diesel engine
7 support 30 40.80
pump room (FFFS) Supply and installation of Mist system Main Header and associate piping arrangement
Tunnel
services supply and installation of mist system pumps
from portals supply and installation of Control panel
Testing & commissioning
Supply and installation of Mist system Main Header and associate piping arrangement
South portal Fire supply and installation of mist system pumps
8 10 13.60
pump room (FFFS) supply and installation of Control panel
Testing & commissioning
supply and installation of Servers (SCADA/PLC )for MEP service
supply and installation of BTS for telephone communication system
North porta Work supply and installation of Video wall system to monitor
9 15 3.45
station (ELV) supply and installation of Traffic control system equipment's
Testing & commissioning
Integration the system
supply and installation of Servers (SCADA/PLC )for MEP service
supply and installation of BTS for telephone communication system
South portal Work supply and installation of Video wall system to monitor
10 station (ELV) 15 3.45
supply and installation of Traffic control system equipment's
Testing & commissioning
Integration the system