Project Engineering Deliverables: Functional Responsibility Description Type of Deliverable Cost (L.E.)

The document outlines engineering deliverables for a project including project controls, general engineering, mechanical engineering, and piping deliverables. It lists 17 specific deliverables such as a project controls plan, work breakdown structure, piping design criteria, piping calculations, and piping isometric drawings. The total estimated cost for all deliverables is 30,500 L.E. Additional information is requested including a project execution plan, fire hazard zone drawing, HAZOP study, PFDs, P&IDs, and plant layout drawings.

Uploaded by

MJ Magdy
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
265 views

Project Engineering Deliverables: Functional Responsibility Description Type of Deliverable Cost (L.E.)

The document outlines engineering deliverables for a project including project controls, general engineering, mechanical engineering, and piping deliverables. It lists 17 specific deliverables such as a project controls plan, work breakdown structure, piping design criteria, piping calculations, and piping isometric drawings. The total estimated cost for all deliverables is 30,500 L.E. Additional information is requested including a project execution plan, fire hazard zone drawing, HAZOP study, PFDs, P&IDs, and plant layout drawings.

Uploaded by

MJ Magdy
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project Engineering Deliverables 

Functional Responsibility Description Type of Cost


Deliverable (L.E.)
       
       
 Project Controls 
 
  *Project Controls Plan  *Document  500 
*Project Cost Reports *Report  500 
 

  *Work Breakdown Structure  *Chart  1500 


*Schedule  2000 
  *Project Schedule 
   
 
 
       
     
 Engineering ‐ General *List of Codes, Standards, &  * List  1000 
 

Regulations     
*Design Philosophies  *Document  2000 
   
 
       
       
Mechanical Engineering *Mechanical Equipment Design     
  *Document  1000 
Criteria  
   
*Mechanical Equipment  *Document  3000 
Specifications     
*Mechanical Equipment List  * List  2000 
   
       
       
Piping    *Piping Design Criteria  *Document  1000 
 
   *Piping Calculations  *Document  3000 
   *Tie‐In List  * List  1000 
 *General Arrangement     
* Drawings  5000 
Drawings 
   
*Pipe Support Standard 
* Drawings  2000 
Drawings 
   
 *Piping Isometric Drawings  * Drawings 
 

5000 
 
Total Cost = 30500 L.E
Information needed 
Project Execution Plan 

Fire Hazard Zone Drawing 

Hazard and Operability Analysis (HAZOP) 

Process Flow Diagrams (PFD's) 

Piping and Instrumentation Diagrams (P&ID's)

Plant Layout, Site and Plot Plans 

Line Designation Tables 

 
 