UNIT 5 DOMESTING WIRING NOTES As On 3rd Aug
UNIT 5 DOMESTING WIRING NOTES As On 3rd Aug
5. DOMESTING WIRING
5.1 Introduction
A network of wires drawn to connect the meter board to the various energy-consuming
loads (lamps, fans, motors etc) through control and protective devices for efficient
distribution of power is known as electrical wiring.
Electrical wiring done in residential and commercial buildings to provide power for lights,
fans, pumps and other domestic appliances is known as domestic wiring.
The distributor line runs (usually on overhead distribution lines) on the poles by the side
of the streets. The cable that connects the distributor to the consumer terminals is
commonly referred to as the service mains. The service mains terminates at the
consumer premises in what is called the service fuse or service cutout. Such cutouts
and several meters are the supplier property. In other words, these represent the
farthest point from the supplier’s responsibility.
The point at which the consumer’s wiring is connected into the cutout is known as the
point of commencement of supply or consumer terminals. From the consumer terminal
onwards, the cables are entirely under the control of the consumer and are laid-out as
per the consumer’s needs. Figure 5.1 shows the concept of service mains.
Unit-5 1
Department of EEE, RVCE Elements of Electrical Engineering
The input to the energy meter (or kWh meter, represented as EM) in the consumer
premises comes from the service mains. It consists of the phase (P) and neutral (N)
wires. The other two terminals of the energy meter are connected through a fuse or an
MCB or a switch to the main distribution board (MDB) or meter board of the owner
as shown in figure 5.2.
An MDB is a panel or enclosure that houses the fuses, circuit breakers and ground
leakage protection units where the electrical energy, which is used to distribute
electrical power to numerous individual circuits or consumer points, is taken in from the
distribution system. An MDB typically has a single or multiple incoming power sources
and includes main circuit breakers and residual current or earth leakage protection
devices. Panels are assembled in a systematic manner such as incomer section and
outgoing section.
The two output terminals from the main distribution board is then connected to sub-
main distribution boards (SMDBs) which are connected to the various parts of the
house. The SMDB is installed generally at the point where a large distribution cable
terminates and several smaller sub-circuits start. The number of SMDBs depends on
the loads present in the house. For example, one SMDB may connect the supply to
three lights and two fans of the living room and a bedroom, while another SMDB might
be used to connect the supply to four lights and two fans of the other bedroom and the
backyard and so on. Each part of the circuit connected to one SMDB forms one sub-
circuit. SMDBs are generally used in large buildings, where several points would be at a
considerable distance if only one distribution board were used.
Unit-5 2
Department of EEE, RVCE Elements of Electrical Engineering
5.2 Wire
A wire is a single, usually cylindrical, flexible strand or rod of metal. Wires are used to
bear mechanical loads or electricity and telecommunications signals. Wire is commonly
formed by drawing the metal through a hole in a die or draw plate.
Wire gauges come in various standard sizes, as expressed in terms of a gauge number.
The term wire is also used more loosely to refer to a bundle of such strands, as in
"multistranded wire", which is more correctly termed a wire rope in mechanics, or a
cable in electricity.
Wire comes in solid core, stranded, or braided forms. Although usually circular in cross-
section, wire can be made in square, hexagonal, flattened rectangular or other cross-
sections, either for decorative purposes, or for technical purposes such as high-
efficiency voice coils in loudspeakers.
aluminum. Various insulating materials like PVC, TRS, and VIR are used. The wires
may be of single strand or multi strand. Wires with combination of different diameters
and the number of cores or strands are available.
For example, the VIR conductors are specified as 1/20, 3/22,….7/20 etc.
The numerator indicates the number of strands while the denominator corresponds to
the diameter of the wire in SWG (Standard Wire Gauge). SWG 20 corresponds to a
wire of diameter 0.914mm, while SWG 22 corresponds to a wire of diameter 0.737 mm.
A 7/0 wire means, it is a 7-cored wire of diameter 12.7mm (0.5 inch). The selection of
the wire is made depending on the requirement considering factors like current and
voltage ratings, cost and application.
The enamel coating (on the individual strands) mutually insulates the strands and the
wire on the whole is provided with PVC insulation. The current carrying capacity
depends on the total area of the wire. If cost is the criteria then aluminum conductors
are preferred. In that case, for the same current rating much larger diameter of wire is
to be used.
2. Loop-In System
Unit-5 4
Department of EEE, RVCE Elements of Electrical Engineering
Advantages:
ii. No joint is concealed (in roof spaces). Hence, fault location is easy.
Limitations:
i. Length of cable required is relatively more. This causes higher voltage drops and
losses.
Unit-5 5
Department of EEE, RVCE Elements of Electrical Engineering
i. Cleat wiring
v. Conduit wiring
Cleat wiring is recommended only for temporary installations. The cleats are made in
pairs having bottom and top halves. The bottom half is grooved to receive the wire and
the top half is for cable grip. Initially the bottom and top cleats are fixed on the wall
loosely according to the layout. Then the cable is drawn, tensioned and the cleats are
tightened by the screw. Cleats are of three types, having one, two or three grooves, so
as to receive one, two or three wires. Cleat wiring is one of the cheapest wiring
considering the initial cost and labor, and is most suitable for temporary wiring. This
wiring can be quickly installed, easily inspected and altered. When not required, this
wiring could be dismantled without damage to the cables, cleats and accessories.
Unit-5 6
Department of EEE, RVCE Elements of Electrical Engineering
Advantages:
1) Easy installation.
4) Relatively economical.
Disadvantages:
Advantages:
Unit-5 7
Department of EEE, RVCE Elements of Electrical Engineering
Disadvantages:
1. The clips used to fix the cables on battens should not react with the sheath.
2. Lead sheath should be properly earthed to prevent shocks due to leakage currents.
3. Cables should not be run in damp places and in areas where chemicals (may react
with the lead) are used.
Unit-5 8
Department of EEE, RVCE Elements of Electrical Engineering
Advantages:
2. Highly durable.
3. Suitable in adverse climatic conditions provided the joints are not exposed.
Disadvantages:
2. Very expensive.
Advantages:
2. Provides good isolation as the conductors are placed apart reducing the risk of short
circuit.
Unit-5 9
Department of EEE, RVCE Elements of Electrical Engineering
4. Since the wires are not exposed to atmosphere, insulation is less affected by dust,
dirt and climatic variations.
Disadvantages:
1. Highly inflammable.
Advantages:
2. The lead and return wires can be carried in the same tube.
7. Aesthetic in appearance
Unit-5 10
Department of EEE, RVCE Elements of Electrical Engineering
Disadvantages:
4. Risk of short circuit under wet conditions (due to condensation of water in tubes).
The size in case of copper conductor is specified in terms of number of strands and the
gauge of each strand. British Standard Wire Gauge is a set of wire sizes given by BS
(British Standard) and is generally abbreviated SWF. It is also called Imperial Wire
Gauge and is used in India. A list of SWG and the thickness in mm is given in table 5.1.
Unit-5 11
Department of EEE, RVCE Elements of Electrical Engineering
SWG mm
0 8.230
1 7.620
2 7.010
3 6.401
6 4.877
9 3.658
12 2.642
14 2.032
16 1.626
18 1.219
20 0.914
Table 5. 1: SWG and thickness in mm
Note: A copper wire of 3/20 means the number of strands are 3 and the gauge of
each strand is 20 SWG.
2. Tappings are not allowed except in ceiling rose, boards and junctions.
4. Separate circuit should be drawn for lighting and heating from mains
5. For lighting, each circuit should not consists of more than 10 points or 800 watts.
Unit-5 12
Department of EEE, RVCE Elements of Electrical Engineering
The domestic lighting circuits are quite simple and they are usually controlled from one
point. However, in certain cases it might be necessary to control a single lamp from
more than one point (Two or Three different points).
Switches S1 and S2 are two-way switches with a pair of terminals A & B, and A’ & B’
respectively. When the switch S1 is in position A and switch S2 is in position B’, the
circuit does not form a closed loop and there is no path for the current to flow and hence
the lamp will be OFF. When S1 is changed to position B the circuit gets completed and
hence the lamp glows or is ON. Now if S2 is changed to position A’ with S1 at position 2
the circuit continuity is broken and the lamp is off. If S1 is in position B and S2 is in
position A’, the circuit is open and the lamp is OFF. Thus, the lamp can be controlled
from two different points.
Unit-5 13
Department of EEE, RVCE Elements of Electrical Engineering
1. A A’ ON
2. A B’ OFF
3. B A’ OFF
4. B B’ ON
Figure 5. 12: Illustration of two-way control of lamp for staircase lamp control
a) Straight connection
b) Cross connection
In case of straight connection, the terminals or points CD and EF are connected as
shown in figure 5.13 while in case of cross connection, the terminals CE and FD are
connected as shown in figure 5.14. As explained in two –way control the lamp is ON if
the circuit is complete and is OFF if the circuit does not form a closed loop.
Unit-5 14
Department of EEE, RVCE Elements of Electrical Engineering
1. A A’ ON
2. A B’ OFF
Straight
3. B A’ Connection OFF
4. B B’ (CD, EF) ON
5. A A’ OFF
Cross
6. A B’ ON
Connection
7. B A’ (CE, FD) ON
8. B B’ OFF
1. Plate earthing
2. Pipe earthing
Unit-5 16
Department of EEE, RVCE Elements of Electrical Engineering
the earth plate. A cement masonry chamber is built with a cast iron cover for easy
regular maintenance. Figure 5.15 shows the detailed diagram.
Unit-5 17
Department of EEE, RVCE Elements of Electrical Engineering
Earth electrode made of a GI (galvanized) iron pipe of 38mm in diameter and length of
2m (depending on the current) with 12mm holes on the surface is placed upright at a
depth of 4.75m in a permanently wet ground. To keep the value of the earth resistance
at the desired level, the area (15cm) surrounding the GI pipe is filled with a mixture of
salt and coal.. The efficiency of the earthing system is improved by pouring water
Unit-5 18
Department of EEE, RVCE Elements of Electrical Engineering
through the funnel periodically. The GI earth wires of sufficient cross- sectional area are
run through a 12.7mm diameter pipe (at 60cms below) from the 19mm diameter pipe
and secured tightly at the top as shown in the figure 5.16.
Note: When compared to the plate earth system the pipe earth system can carry larger
leakage currents as a much larger surface area is in contact with the soil for a given
electrode size. The system also enables easy maintenance as the earth wire
connection is housed at the ground level.
Fuse is a safety device used in any electrical installation, which forms the weakest link
between the supply and the load. It is a short length of wire made of lead / tin /alloy of
lead and tin/ zinc having a low melting point and low ohmic losses. Under normal
operating conditions it is designed to carry the full load current. If the current increases
beyond this designed value due any of the reasons mentioned above, the fuse melts
(said to be blown) isolating the power supply from the load as shown in the following
figures 5.12 and 5.13.
a. Permissible temperature rise of the contacts of the fuse holder and the
b. fuse material
c. Degree of deterioration due to oxidation
2. Fusing current: The minimum current at which the fuse melts is known as the
fusing current. It depends on the material characteristics, length, diameter, cross-
sectional area of the fuse element and the type of enclosure used.
3. Fusing Factor: It is the ratio of the minimum fusing current to the rated current. It
is always greater than unity.
This time-current characteristic chart (figure 5.19) shows how fast the fuse responds to
different levels of overcurrent condition. The fuse does not open if the current is within
the limits (i.e. less than the fuse rating). The current at which the fuse starts melting is
called the fusing current. All fuses have an inverse time/current characteristic. As
overcurrent increases, time-to-open the fuse decreases. Put more simply, the fuse will
open faster when the overcurrent problem is severe.
Unit-5 21
Department of EEE, RVCE Elements of Electrical Engineering
Whenever continuous over current flows through MCB, the bimetallic strip is heated and
deflects by bending. This deflection of bimetallic strip releases mechanical latch. As this
mechanical latch is attached with operating mechanism, it causes to open the miniature
circuit breaker contacts. But during short circuit condition, sudden rising of current,
causes electromechanical displacement of plunger associated with tripping coil or
solenoid of MCB. The plunger strikes the trip lever causing immediate release of latch
mechanism consequently open the circuit breaker contacts.
Unit-5 22
Department of EEE, RVCE Elements of Electrical Engineering
i. It automatically switches off the electrical circuit during abnormal condition of the
network means in over load condition as well as faulty condition. The fuse does
not sense but miniature circuit breaker does it in more reliable way. MCB is
much more sensitive to over current than fuse.
ii. Another advantage is, as the switch operating knob comes at its off position
during tripping, the faulty zone of the electrical circuit can easily be identified. But
in case of fuse, fuse wire should be checked by opening fuse grip or cutout from
fuse base, for confirming the blow of fuse wire.
iii. Quick restoration of supply can not be possible in case of fuse as because fuses
have to be rewirable or replaced for restoring the supply. But in the case of MCB,
quick restoration is possible by just switching on operation.
iv. Handling MCB is more electrically safe than fuse.
Because of the many advantages of MCB over fuse units, in modern low voltage
electrical network, miniature circuit breaker is mostly used instead of backdated fuse
unit.
Only one disadvantage of MCB over fuse is that this system is more costlier than fuse
unit system.
Unit-5 23
Department of EEE, RVCE Elements of Electrical Engineering
Electric shock occurs when the body becomes part of an electrical circuit. Shocks can
happen in three ways.
A person may provide a path between an ungrounded conductor and the ground.
A person may provide a path between the ground and a conducting material that
is in contact with an ungrounded conductor.
The severity of the shock received when a person becomes a part of an electric circuit
is affected by three primary factors:
The amount of current flowing through the body
The path of the current through the body
The length of time the body is in the circuit.
Unit-5 24
Department of EEE, RVCE Elements of Electrical Engineering
1. Avoid water at all times when working with electricity. Never touch or try repairing
any electrical equipment or circuits with wet hands. It increases the conductivity
of electric current.
2. Never use equipment with frayed cords, damaged insulation or broken plugs.
3. If you are working on any receptacle at your home then always turn off the
mains. It is also a good idea to put up a sign on the service panel so that nobody
turns the main switch ON by accident.
4. Always use insulated tools while working.
5. Electrical hazards include exposed energized parts and unguarded electrical
equipment, which may become energized unexpectedly. Such equipment always
carries warning signs like “Shock Risk”. Always be observant of such signs and
follow the safety rules established by the electrical code followed by the country
you are in.
6. Always use appropriate insulated rubber gloves and goggles while working on
any branch circuit or any other electrical circuit.
7. Never try repairing energized equipment. Always check that it is de-energized
first by using a tester. When an electric tester touches a live or hot wire, the bulb
inside the tester lights up showing that an electrical current is flowing through the
respective wire. Check all the wires, the outer metallic covering of the service
panel and any other hanging wires with an electrical tester before proceeding
with your work.
8. Never use an aluminium or steel ladder if you are working on any receptacle at
height in your home. An electrical surge will ground you and the whole electric
current will pass through your body. Use a bamboo, wooden or a fibreglass
ladder instead.
9. Know the wire code of your country.
10. Always check all your GFCIs once a month. A GFCI (Ground Fault Circuit
Interrupter) is a RCD (Residual Current Device). They have become very
common in modern homes, especially damp areas like the bathroom and kitchen,
Unit-5 25
Department of EEE, RVCE Elements of Electrical Engineering
Unit-5 26
Department of EEE, RVCE Elements of Electrical Engineering
Unit-5 27
Department of EEE, RVCE Elements of Electrical Engineering
The Energy Rating Label provides an estimate of how much energy (in kilowatt-hours or
kWh) the appliance will use over a year. This is based on assumptions about 'average
usage' and allows consumers to estimate how much it will cost them to run that
appliance. However, actual energy consumption will depend on how an appliance is
used and how often it is used. Factors like climate can also have a big influence on
energy consumption (and efficiency) for some appliances.
The more stars on the Energy Rating Label, the more energy efficient the appliance is.
Efficient appliances use less electricity to achieve the same level of performance of
similar models with the same size or capacity. The more energy efficient a model, the
less energy it will use and the less it will cost you to run.
The domestic consumer is billed for the energy consumed. An industrial consumer is
billed both for the load as well as for the energy consumed. Table 5.4 shows a few
common appliances and calculate the energy they consume.
Unit-5 28
Department of EEE, RVCE Elements of Electrical Engineering
1 Incandescent 15 - 100
Lamp
2 Tube Light 30 - 50
3 CFL 3 – 30
4 Ceiling Fan 30 - 70
5 AC(Room) 1000 -
1500
6 AC(Central) 2000 -
5000
7 CD Player 15 - 20
8 TV 60 - 300
9 Laptop 50 -75
10 Desktop 80 - 250
11 Washing 500 -
Machine 1000
12 Refrigerator 50 - 300
13 Geyser 1000 -
3000
Unit-5 29
Department of EEE, RVCE Elements of Electrical Engineering
Example 1: Estimate Total Daily Energy Requirement for the following loads.
CFL 12 6 3
Fan 50 8 2
TV (21”) 150 2 1
Computer 250 3 1
Solution:
CFL 12 6 3 216
Fan 50 8 2 800
Hence Monthly Energy Requirement = Daily Energy Required X Days per Month
= 2066 X 30
= 61980 Wh
= Rs.371.88 /-
Unit-5 30
Department of EEE, RVCE Elements of Electrical Engineering
Rs.6/- per unit for the first 20 units, Rs.4/- per unit for the next 30 units and Rs.2/- per
unit for the next 50 units.
______________________________________________________________________
Example 2: A geyser is rated at 3kW, 230V, 50Hz. If it is switched ON for one hour
daily, what would be the energy cost saving, at the rate of Rs. 2.50 per unit if it is
replaced by a solar water heater?
Solution:
Solar water heaters use energy from the Sun. Though their initial investment is high, the
running cost is very low and are environmental friendly.
A 3kW geyser running for 1 hour daily would consume 3 units daily. The energy
consumed per month is 3 units X 30 days = 90 units per month. The cost of energy per
month is 90 units per month X Rs. 2.50 per unit = Rs. 225.
This would be the saving in electricity bill if solar water heater replaces the electric
geyser.
______________________________________________________________________
Exercise 2: Find out the wattage of the appliances in your house, their average use per
month and estimate the electricity bill of your house based on the BESCOM tariff.
Unit-5 31
Department of EEE, RVCE Elements of Electrical Engineering
Figure 5. 23: (a) External and (b) Internal views of a three-pin plug
These plugs have three round pins arranged in a triangle (figure 5.23), with the larger
top pin being the earthing pin. Plugs are non-interchangeable between current ratings.
Introduced in 1934, they are also called as Type-D plugs.
This 5A plug has three round prongs that form a triangle. The central earth pin is 20.6
mm long and has a diameter of 7.1mm. The 5.1mm line and neutral pins are 14.9mm
long, on centres spaced 19.1 mm apart. The centre-to-centre distance between the
grounding pin and the middle of the imaginary line connecting the two power pins is
22.2 mm. Type M, which has larger pins and is rated at 15 amps, is used alongside type
D for larger appliances in India, Sri Lanka, Nepal and Pakistan. Some sockets can take
both type M and type D plugs.
Unit-5 32
Department of EEE, RVCE Elements of Electrical Engineering
The use of a 3-pin socket in house wiring is as shown in figure 5.25. The detailed
connection of a 3-pin plug is as shown in figure 5.26.
Unit-5 33
Department of EEE, RVCE Elements of Electrical Engineering
The phase wire from the supply is connected to one terminal of the switch. The other
terminal of the switch is connected to one terminal of the bulb. The other terminal of the
bulb is connected to neutral of the supply. This is shown in figure 5.28. The figure
shows a CFL but the connection remains the same regardless of the light type
(incandescent, fluorescent, CFL, etc.)
The phase wire from the supply is connected to one terminal of the switch. The other
terminal of the switch is connected to one terminal of the dimmer. The other terminal of
the dimmer is connected to one of the supply terminals in the motor of the ceiling fan.
Finally, the other terminal of the motor is connected to the neutral of the supply. This
has been shown in figure 5.29.
Unit-5 34
Department of EEE, RVCE Elements of Electrical Engineering
The neutral and phase wires for the room are first drawn from the distribution
board.
Then the neutral wire from the supply is connected to one terminal of the outlets,
one terminal of each bulb and one terminal of ceiling fan as shown figure 5.30.
These wires are represented in black.
Then the phase wire (hot wire/ live wire) from the supply is connected to the one
terminal of every switch and to the other terminal of the outlets as shown in the
figure 5.27.
Unit-5 35
Department of EEE, RVCE Elements of Electrical Engineering
Next connections are made form the other terminal of the first switch to one bulb
and form the other switch to the second bulb. Then the open terminal from the
third one-way switch is connected to the regulator and then the other terminal of
the regulator is connected to the ceiling fan as shown.
If the base body of the board is made of metal, then it is necessary to connect
the earth wire (green wire) to board base body.
The power outlet / three-pin socket connection is made as shown in the above
room wiring diagram.
Such a scheme is followed to connect all the sockets, switches and lights in the
entire house.
***************************************************************************************************
Unit-5 36