Status of Major Materials S.no Description Make Status

This document provides a status update on major materials for a project. It lists 11 items including pipes, fittings, insulation, supports, valves, and hoses. The status for most items is "Received", while filter elements and super insulated hoses are still waiting for quotes from suppliers with orders placed in February 2020 and anticipated receipt.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views

Status of Major Materials S.no Description Make Status

This document provides a status update on major materials for a project. It lists 11 items including pipes, fittings, insulation, supports, valves, and hoses. The status for most items is "Received", while filter elements and super insulated hoses are still waiting for quotes from suppliers with orders placed in February 2020 and anticipated receipt.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

STATUS OF MAJOR MATERIALS

S.no Description Make Status


1 Pipes Shublaxmi Received
2 Fitiings Dynamic / Hilton Received
3 Insulation Ruag Received
4 Anchor G10 Supports Permawallace Received
5 Valves Stohr Received
6 Safety Valves Tyco Received
7 Filter Body VRV Received
8 Metal Bellows Witzermen Received
9 Filter element Cryogenmash / Johncrane Waitng for the quote from supplier
Order Placed to US agent, Feb 2020 it
10 Bayonet CPC Cryolab
will be recived
11 Super insulated Hose Witzermen / Bergonfer Waitng for the quote from supplier